Connecting NorthlandEconomicaly active | a resilient network | safer journeys
What we are building on
The 2015-18 NLTP in Northland
$460m forecast total investment, including…• $194m for local roads maintenance & operations, up 22% (all
NZ up 6%)• WDC 3rd highest increase in NZ, and FNDC 5th highest
• $117m for state highway maintenance & operations, up 24% (all NZ 6%)• 2nd highest regional increase
• $90m for state highway improvements (could be more)• $37m for local road improvements• $6m for public transport services and improvements• $5m for specific cycling and walking improvements• $5m for road safety promotion
A significant investment package to connect Northland:
• Appropriate levels of service = predictable journeys• Network resilience improvements = more reliable journeys• Network safety improvements = safer journeys• Network efficiency improvements = improved travel times
… which will deliver:
• Northland to its internal and external markets• Workers to their places of work• Communities to each others and required services
… which will contribute to Connecting:
The small print
Committed – under contract
Probable – going into contract
Proposed – in programme, but needs more development work
Status of projects in the investment business case process
The small print
Committed – under contract Probable – going into contractProposed – in programme, but needs more development work
Status of projects in investment business case process
Appropriate levels of service
Reliable Journeys
• Restoration and rehabilitation
• Prevention• Maintenance• Major works
• Mitigation • Preparedness
The four-part approach
Safer Journeys
Safety allianceRest area strategy• Loop Road• Springfield to
Mata• Akerama Curves• Whangarei• Brynderwyns
North
Managing higher density flows
• Improving the operation and relieving congestion of SH1 and at key intersections through Whangarei urban area
• Public transport services are growing• Urban cycleway fund• SH14 hospital access
The inland route
• Conditional
agreement to becoming… SH13?!
Next steps• Business case for Loop
Road intersection• Collaboration agreement• Secretary of Transport• Asset hand over• Contract changes• Corridor plan
Upper North Island connections
• Air • Rail• Road - SH1• SH 12 and SH16• SH14, Inland route
Freight efficiency
• 50 MAX routes• Inland freight route• Whangarei to Port• Dust mitigation
Getting ready for the next wave of investment….Corridor plans
Getting ready for the next wave of investment….Corridor plans
Tirohanga stream bridgeWaihou River bridgeTaheke bridge
Thanks you.