Configuration & Persistency Service R7
USE CASE KEY INFORMATIONBUSINESS DRIVERROADMAPPROPOSALSDEVELOPMENT STATUS (R6 Extension)DEVELOPMENT STATUS (R7 as New Project)Use Case DiagramUse Case Functional DefinitionsConfiguration Persistence Service Information ElementWeekly Meetings - Recordings & Discussion LogSUPPORTING FILESTesting
Current StatusEnd to End flow to be TestedTest Cases and Status
For R7 GuiLin release the Data Persistency Service
USE CASE KEY INFORMATION
Topic Description Wiki
Contacts
Requirements Tracking Project Management requirements Jira Ticket (clone++ of REQ-1)
- REQ-322 Getting issue details... STATUS
OOF SON PCI for NFR - REQ-345 Getting issue details... STATUS
Architecture Sub-committee Jira tracker
Link to Architecture Jira for Architecture sub-committee w/ presentation link
- ONAPARC-575 Getting issue details... STATUS
R7 Functional Requirements Page
Guilin release - functional requirements proposed list#Configuration&PersistencyServiceProject
Base Project Page CONFIGURATION & PERSISTENCY SERVICE R6
Meetings Register Configuration & Persistency Service Meeting Notes & Recordings
PoC Jira REQ Model Driven C&PS PoC - REQ-384 Getting issue details... STATUS
High Level Design PoC Page for the High Level Design of the Model Driven C&PS PoC (R7)
High Level Design (PoC)
High Level Design PoC Issues decisions & assumptions for the C&PS PoC (R7)
Issues decisions and assumptions
C&PS Portal Page Configuration & Persistency Service Portal Page
R7 COMPONENT DESCRIPTION ARC Configuration & Persistency Service (CnPS) Component Description - Guilin (R7) Release
BUSINESS DRIVER- The Data Persistency Service is a new platform component that is designed to serve as a data repository for Run-time data that EXECUTIVE SUMMARY
needs to be persistent. As a stand-alone ONAP component, this project provides data layer services to other ONAP platform components and use cases that require persistent configuration or operational data. The R6 development will be enhanced as well.
- The ability for service operators to visualize and manage data in a RAN network (PNFs, VNFs, and logical constructs) with ONAP is BUSINESS IMPACTa critical business function because they are key Life Cycle Management (LCM) and OA&M operations. The project has business impacts to enhance the operation of data-handling within ONAP by providing efficient data layer services.
- This project applies to any domain (wireless, transport, optical, and wireline) that ONAP may manage. It is not a market or BUSINESS MARKETSgeographical specific capability. It is expected that scaled ONAP installations such as Edge & Core ONAP deployments will also deploy the database across each installation.
- This project represents a large potential Operating Expense (OPEX) savings for operators because of the ability to FUNDING/FINANCIAL IMPACTSconfigure networks saving time and expenses.
- There is no additional organizational management or sales strategies for this use case outside of a ORGANIZATION MGMT, SALES STRATEGIESservice providers "normal" ONAP deployment and its attendant organizational resources from a service provider.
ROADMAPThe roadmap for CPS and what will be delivered in the upcoming releases:
Updated C&PS ROADMAP 26 Jun 2020
- This is the evolution of ConfigDB in the CC-SDK / SDN-C. this solution was initially coded in R3 for the OOF/SON/PCI Use Case and was C&PS 1.0referred to as "ConfigDB" using a MariaDB ITDM solution. Because in R7 GuiLin planning, there is some clarity needed to identify the different tracks of development, the notation is introduced here, "C&PS 1.0" to allow people to have a common "language" to refer to a body of work. This was done in the R6 time frame.
- This is the continuation of the C&PS 1.0 solution (see above). Updates will involve schema and interface changes for additional data C&PS 1.1supported in the C&PS database. This will be introduced in the R7 Guilin time frame. Thus, when someone refers to C&PS, in the R7 time frame they are referring to the C&PS 1.1 solution. Additionally, there are two C&PS related PoC going on the Model-Driven C&PS and State Management PoC (Bell Canada) and when referring to R7 C&PS, work done in these PoC are also included.
- C&PS 2.0 is the stand-alone project. In R8 Honolulu, the goal is to have C&PS become its own stand-alone project. Thus, a presentation to C&PS 2.0the Architecture S/C and TSC will be made again to petition for a stand-alone project.
Updated Roadmap:
RELEASE CONTENT WIKI
R6 Frankfurt CONFIGURATION & PERSISTENCY SERVICE
R7 Guilin Store Real-Time Configuration Data
Update Data
Access Control
Guilin release - functional requirements proposed list#RunTimeConfigurationDatabase/DataPersistencyServiceProject
Management framework (not mgmt policy to run network, ONAP mgmt policy)
Network Elements (config info, policy for NE, A1 for NE)
R8 Honolulu Data Recovery
Model Adaptation (Dynamic Schema)
R-Future Data Auditing
Topology Traversal
Data History
Roll-Back
Data Syncing
Performance Optimization (Scaling)
PROPOSALS
PROJECT PROPOSAL Target for R7 Guilin
DPS Project Proposal Configuration Persistency Service Project Proposal (Oct 25 2019)
COMPONENT DESCRIPTION ARC RunTime DB Component Description - R6 Frankfurt
ARCHITECTURE FLOWS ARCHCOM: InfoFlow - RunTime Config DB Information Flow
MEETINGS REGISTER Configuration & Persistency Service Meeting Notes & Recordings
DEVELOPMENT STATUS (R6 Extension)PROJECT PTL User Story / Epic Requirement
A&AI James Forsyth
AAF No Active PTL
APPC Takamune Cho
CLAMP Gervais-Martial Ngueko
CC-SDK (incl. CDS) Dan Timoney Epic #1 - OOF SON PCI U/C
(possible) MariaDB/Yang Model/Schema
Epic #2 - E2E Network Slicing
DCAE Vijay Venkatesh Kumar
DMaaP Mandar Sawant
External API Adrian OSullivan
MODELING Hui Deng
Multi-VIM /
Cloud
Bin Yang
OOF Shankaranarayanan Puzhavakath Narayanan
POLICY Pamela Dragosh
PORTAL Manoop Talasila
SDN-C Dan Timoney
SDC Ofir Sonsino
SO Seshu Kumar M
VID Ittay Stern
VNFRQTS Trevor Lovett
VNF-SDK Kanagaraj Manickam
DEVELOPMENT STATUS (R7 as New Project)PROJECT PTL User Story / Epic Requirement
A&AI James Forsyth
AAF No Active PTL
APPC Takamune Cho
CLAMP Gervais-Martial Ngueko
CC-SDK (incl. CDS) Dan Timoney
DCAE Vijay Venkatesh Kumar
DMaaP Mandar Sawant
External API Adrian OSullivan
MODELING Hui Deng
Multi-VIM /
Cloud
Bin Yang
OOF Shankaranarayanan Puzhavakath Narayanan
POLICY Pamela Dragosh
PORTAL Manoop Talasila
SDN-C Dan Timoney
SDC Ofir Sonsino
SO Seshu Kumar M
VID Ittay Stern
VNFRQTS Trevor Lovett
VNF-SDK Kanagaraj Manickam
List of PTLs:Approved Projects
*Each Requirement should be tracked by its own User Story in JIRA
Use Case DiagramUse cases define how different users interact with a system under design. Each use case represents an action that may be performed by a user (defined in UML as an Actor with a user persona).
The R7 Model Driven C&PS PoC diagram:
Use Case Functional DefinitionsUse Case Title
Configuration Persistence SERVICE
Actors (and System Components)
SDC, A&AI, C&PS, Use Cases (PCI, E2E NS, A1E, Mirror), DBMS, TSDB, xNF, DCAE, DMaaP
1.
2.
3. 4.
Description Configuration Persistence Service is a platform component that is designed to serve as a data repository for Run time data that needs to be persistent. It is characterized by the following.
- The types of data that is stored in the Run-Time data storage repository for:DATA REPOSITORY
- These are configuration parameters that are used by xNFs during PnP, installation, CONFIGURATION PARAMETERScommissioning. - These are parameters that are derived, discovered, computed that are used by xNFs during OPERATIONAL PARAMETERSrun time AFTER the xNF becomes operational i.e. AFTER it has "booted up", been installed, configured. These operational parameters are Exo-inventory information, meaning it is information that doesn't belong in A&AI. - NE policy type information used by micro-service.NETWORK ELEMENT POLICY INFORMATION - Information related to operational parameter.APPLICATION INFORMATION
- Architecturally, the Configuration Persistence Service is designed to be a common services data layer which can serve DATA LAKEas a data lake to other run time entities (ONAP components or external tools).
- The Configuration Persistence Service enables functionality to be performed by other entities. It will ENABLE C&PS FUNCTIONSthe capability of another components or external tools within/or external to ONAP to perform the functions.
- Enables OSS configuration, optimization, and LCM operations.CONFIGURATION MANAGEMENT FUNCTIONS - The Configuration Persistence Service enables the ability to sync data between initial and delta changes ONAP & SYNCINGthe xNFs. - It will allow for the recovery of data once a source of truth is defined.DATA RECOVERY - It will allow for updates, delta changes, and incremental updates to be performed.UPDATES - See a history of changes in data including versioning of the data, updates, roll back, restoration, and time DATA HISTORYseries management. - Auditing of parameters against a "golden" template. It itself stores & provides the data for auditing. Consistency AUDITINGchecks. - It will allow for rollback back of entire DB to "save points" or recovery points.ROLL BACK RESTORATION - It will allow for the recovery and restoration of data records to a fall back point. - A security topic, which allows the definition of policies, of who and what they can update.ACCESS CONTROL - It will enable the ability for something to traverse the relationship between data elements.TOPOLOGY TRAVERSAL - Allows for the adaptation or transformation of models from other sources (e.g. ORAN or 3GPP models).MODEL ADAPTION
Points of Contact
Use Case Lead: Benjamin Cheung Tony Finnerty Joanne Liu Rudel
Key Use Case Members: Toine Siebelink Bruno Sakoto theodore johnson
Code Contributors: (same as above)
Preconditions
DEPLOYMENT - The C&PS container/project is deployed and up and running.
AUTHENTICATION - Authentication is performed by C&PS to allow access and interaction with other ONAP platform components.
Triggers / Begins when
(See "Flow Step" for Design Time Activities, and Initial Database Setup below in the Steps/flows)
Steps / Flows (success)
Steps in Basic Operation and setup of C&PS.
SETUP FLOW STEP SETUP STEP DESCRIPTION
DESIGN TIME ACTIVITIES (SD&C) (SETUP)
(Design time), (Setup DB) Yang Model development E.g.: ORAN specification Yang Model in line with 3GPP. SQL structure.
SDC CSAR LISTENER (SETUP)
The C&PS project listens for the Service CSAR packages which contain the schemas for resources associated with those services.
INITIAL DATABASE SETUP
(Run Time)
The C&PS Database is initially setup.
INITIAL A&AI GETALL (SETUP) Initial A&AI GetAll nodes is used to setup the existing xNFs that exist in the system
RUN-TIME OPERATION RUN-TIME DESCRIPTION
(1) STND DEFINED VES UPDATE
(1) Standard defined VES event comes in through VES event, VES listener.
This is then published onto DMaaP and C&PS get for that topic, namespace 3GPP_Configuration to write updates to the C&PS Database.
Information coming into the C&PS via Stnd-Defined VES need to be "mapped" to the appropriate xNF and record.
(2) A&AI SYNCHRONIZATION (2) A&AI Updates are made in order to update the existing xNF in the system
if a xNF is created or deleted the corresponding records in C&PS DB need to be created/deleted.
A&AI publishes onto DMaaP when an A&AI event occurs which updates the active xNFs available to the network.
(3) MICRO-SERVICE UPDATE (3) Micro-services can update information in C&PS DB
(4A) ONAP PLATFORM
COMPONENT INTERACTIONS
(4A) Other ONAP platform components such as the controllers might read or write information into the C&PS DB.
(4B) EXTERNAL ENTITIES (4B) External entities can interact with the C&PS DB through External API
Post-conditions
SETUP OF C&PS - C&PS database is setup with initial schema
RUN-TIME OPERATION OF C&PS - the above run-time types of actions/operations (1) - (4A/B) above in the flow steps results in updates of C&PS or the interacting entity successfully retrieving information from C&PS DB.
Alternate / Exception Paths
The following describes error cases or conditions for each of the flow steps above:
SETUP FLOW STEP EXCEPTIONS / ALTERNATE / CORNER CASES / ERRORS
DESIGN TIME ACTIVITIES (SD&C) (SETUP) Problems in SD&C
SDC CSAR LISTENER (SETUP) If the SDC CSAR package is irretrievable from DMaaP.
If there is an Error in the SDC CSAR package
INITIAL DATABASE SETUP
(Run Time)
YANG models, schema setup problems
Setting up the C&PS DB errors.
INITIAL A&AI GETALL (SETUP) Inability to perform A&AI GetAll
Errors in A&AI GetAll
RUN-TIME OPERATION EXCEPTIONS / ALTERNATE / CORNER CASES / ERRORS
(1) STND DEFINED VES UPDATE Inability to get VES event from namespace DMaaP Bus
Errors within the Stnd-Def VES event
(2) A&AI SYNCHRONIZATION Inability to perform A&AI Event update
Errors in A&AI Event Update
(3) MICRO-SERVICE UPDATE Inability of micro-service to update C&PS DB
Errors in C&PS DB Update
(4A) ONAP PLATFORM COMPONENT Inability of component to update C&PS DB
Errors in C&PS DB Update
(4B) EXTERNAL ENTITIES Inability of entity to update C&PS DB
Errors in C&PS DB Update
Errors in API/interface interaction problem.
Related Use Cases
These are associated use cases or requirements depending on C&PS
Use Case Link or Description
OOF SON PCI Use Case The OOF SON PCI is a 5G RAN Wireless use case spanning R3 through R7 and beyond:
R7 OOF SON Use Case
End to End Network Slicing E2E Network slicing is a 5G RAN Wireless application
E2E Network Slicing Use Case in R7 Guilin
Assumptions
Describes any assumptions that are made for this use case
Tools / References / Artifacts
List of any tools or reference material associated with this Use Case as well as any JIRA trace-ability.
List of any associated diagrams or modelling artifacts associated with the Use Case
Configuration Persistence Service Information ElementInformation Element Name
Points of Contact Authors and maintainers of the Information Element
Information Element Main Contact (typically Use Case SME)
Information Modeling Contact
Schema Definition Contact
Related Use Cases Use Cases that have interactions using this Information Element.
Please provide a point of contact for each related Use Case.
Participating ONAP Components
The list of ONAP Components that are stakeholders for the Information Element
Related JIRA Please provide link to related JIRA item
Description How to inject model at onboarding.
Model-Driven Approach.
What's the minimum set that ONAP needs to know about a model in order to model & catalog.
Resource IM call and weekly C&PS
https://wiki.onap.org/download/attachments/84656758/CPS_PoC_IM_Support.pptx?version=1&modificationDate=1594025081000&api=v2
https://wiki.onap.org/display/DW/Support+for+CPS+Model+Driven+PoC
Related Standards & Industry Activities
Please refer to any standards or industry activities that should be taken into account when defining the Information Model related to this Information Element. Please provide links to relevant material.
Attributes Attributes: Name and describe each attribute of this Information Element. Please include the datatype of the attribute if possible. Is this attribute read-only, read-write? Are there any default values?
Relationships Relationships: Describe how this Information Element is related to other Information Elements. Also describe nature of the relationship: association, inheritance, dependency, etc. and multiplicity.
Originator Where does this information come from? (What component initially creates it)
Consumers Who uses this information inside & outside of ONAP? How do they use it?
Includes description of information consumed (whole class, specific attributes, etc.)
Producers Who updates this information inside & outside of ONAP? Under what conditions do they update it?
Includes description of information produced (whole class, specific attributes, etc.)
Steward Where will this information stored and maintained in ONAP?
Impacted APIs & Schemas
Identify impacted ONAP schemas & APIs
Are there existing schemas be used or extended?
Information Modeling Status
What is the status of ONAP Information Modeling activities associated with this Information Element.
Please provide links to relevant wiki pages & JIRA.
Schema Definition Status
What is the status of ONAP Schema Definition activities associated with this Information Element.
Please provide links to relevant wiki pages & JIRA.
ONAP Release Priority Prioritization for ONAP Releases
Weekly Meetings - Recordings & Discussion LogLink to the team's weekly discussion, attendees & Recordings
Configuration & Persistency Service Meeting Notes & Recordings
SUPPORTING FILES
ITEM DESCRIPTION FILE
Project Proposal Presentation
TSC Project presentation
Present at TSC 09 Apr 2020
ConfigurationPersistencySvc_29Ap2020v5.pptx
Project Proposal Presentation
Answers discussion updates
( Version)15 May 2020
ConfigurationPersistencySvc_15My2020v5.pptx
C&PS Model Driven PoC
(Ericsson)
PoC demonstrating Model Driven management
using C&PS database
CPS POC Proposal.pptx
State DB (Bell Canada) PoC
Bell Canada Leading a PoC related to State management using the C&PS project.
state-db-swagger-overview-1.0.0.pdf
StateDB at Bell.pptx
Time series database mgmt
Time series database mgmt
Presented by theodore johnson
TimeSeriesStreamingDatabase_202006Jn18_TJ.pptx
VIRTUAL DDF Presentations
C&PS Overview Presentation 25 Jun 2020 ConfigurationPersistencySvcDDF_25Jn2020v8.pdf
VIRTUAL DDF Presentations
Model-Driven C&PS PoC Presentation 25 Jun 2020 DDF_CPS_PoC_202006Jn25.pdf
C&PS PoC Architecture Options
C&PS PoC Architecture Options CPSPoC_ArchOptions_202007Jy03.pdf
C&PS V-DDF C&PS Overview
C&PS Overview Update ConfigurationPersistencySvcDDF_10Jy2020v8a.pptx
ConfigurationPersistencySvcDDF_10Jy2020v8a.pdf
C&PS R8 Requirements C&PS R8 Requirements Sub-committee proposal for 17 Aug 2020 ConfigurationPersistencySvcR8_202008Ag17v9.pptx
ConfigurationPersistencySvcR8_202008Ag17v9.pdf
C&PS R8 Requirements C&PS R8 Requirements Sub-committee proposal for
17 Aug 2020 (updated 10:40 AM UTC)
ConfigurationPersistencySvcR8_202008Ag17v9.pptx
ConfigurationPersistencySvcR8_202008Ag17v9a.pdf
C&PS R8 requirements presentation
C&PS R8 Requirements sub-committee presentation made 17 Aug 2020 zoom_2020Aug17ReqSCPresentation.mp4
audio_only_2020Aug17ReqSCPresentation.m4a
C&PS R8 TSC Project proposal
C&PS presentation to present at the TSC to request for a new project status ConfigurationPersistencySvcR8TSC_202010Oc01v10.pptx
ConfigurationPersistencySvcR8TSC_202010Oc01v10.pdf
1. 2. 3. 4.
TSC Presentation C&PS presentation to present at the TSC to request for a new project status, updated after presentation 01 Oct 2020
ConfigurationPersistencySvcR8TSC_202010Oc01v11.pptx
ConfigurationPersistencySvcR8TSC_202010Oc01v11.pdf
Testing
Current Status
Testing BlockersHigh visibility bugsOther issues for testing that should be seen at a summary levelWhere possible, always include JIRA links
End to End flow to be Tested
**This should be a summary level Sequence diagram done in Gliffy**
Test Cases and Status
1 There should be a test case for each item in the sequence diagram NOT YET TESTED
2 create additional requirements as needed for each discreet step COMPLETE
3 Test cases should cover entire Use Case PARTIALLY COMPLETE
4 Test Cases should include enough detail for testing team to implement the test FAILED