Confidential and proprietary
NPAC Application Server Migration
2/17/05
![Page 2: Confidential and proprietary NPAC Application Server Migration 2/17/05](https://reader035.vdocuments.us/reader035/viewer/2022071807/56649e425503460f94b34a3f/html5/thumbnails/2.jpg)
Confidential and proprietary 2
Proposed Schedule
• Regression Testing from 4/11/05 to 5/6/05.• Group and Fail Over Testing from 5/9/05 to 5/20/05.• First Region Deployed on Sunday 5/22/05• First Region Burned in for 4 Weeks.• Regions 2, 3, 4 and 5 Deployed on Sunday 6/19/05.• CA Deployed on Sunday 7/10/05.• Regions 6, 7 and SOW 34 Deployed on Sunday
7/17/05.• May Require Extended Maintenance Windows.
![Page 3: Confidential and proprietary NPAC Application Server Migration 2/17/05](https://reader035.vdocuments.us/reader035/viewer/2022071807/56649e425503460f94b34a3f/html5/thumbnails/3.jpg)
Confidential and proprietary 3
FAQs - 1
Q - When do SPs need to submit their IP addresses to NeuStar?A - Unless an SP is also simultaneously changing their IP address there is no
need to submit this information.
Q - When will SPs receive IP addresses from NeuStar?A – For production systems, 8 weeks prior to going into production. March 25th
per current schedule.For Regression Test bed next Thursday 2/24/2005
Q – Are new IP addresses required for Regression Testing?A – Yes. Will be provided 2/24/05.
Q – Will SPs be able to test the new IP addresses before conversion?Y – All production systems will be available on 4/25 to allow “pinging” through
the firewall.The Regression Test bed will also be available for “ping” testing on 3/28/05
![Page 4: Confidential and proprietary NPAC Application Server Migration 2/17/05](https://reader035.vdocuments.us/reader035/viewer/2022071807/56649e425503460f94b34a3f/html5/thumbnails/4.jpg)
Confidential and proprietary 4
FAQs - 2
Q – What is the environment for Regression Testing?A – NeuStar will provide a new Test environment specifically for this purpose.
This Test bed will be used for Regression, Group and fail over testing. This is in addition to the SOW 34 test bed.
Q – What steps must the SPs take to participate in Regression testing?A – SPs will be required to submit Profile information by 3/28/05. SPs will also
need to schedule their participation in Regression testing via the CCS Testing coordinator starting on 2/24/05. Finally, key exchange will take place when an SP is ready to start testing.
Q – Do SPs need to stop SMG NPAC Gateway during the maintenance window
A – To be specified
![Page 5: Confidential and proprietary NPAC Application Server Migration 2/17/05](https://reader035.vdocuments.us/reader035/viewer/2022071807/56649e425503460f94b34a3f/html5/thumbnails/5.jpg)
Confidential and proprietary 5
FAQs - 3
Q – How will the IP change be coordinated between SPs and the NPAC?
A – An e-mail will be sent out on March 1st defining the process. This will be followed up with a conf call on March 10th. Finally, the steps that need to be followed during the actual maintenance window will be defined by March 22nd.
Q – Is an extended maintenance window going to be required?
A – At this time it is not expected that an extended window will be required.
Q – Will SPID migration be allowed during these maintenance windows?
A – For those regions undergoing the transition, SPID migration will not be allowed. For other regions, it will be a usual maintenance window, and SPID migration will be allowed.
![Page 6: Confidential and proprietary NPAC Application Server Migration 2/17/05](https://reader035.vdocuments.us/reader035/viewer/2022071807/56649e425503460f94b34a3f/html5/thumbnails/6.jpg)
Confidential and proprietary 6
FAQs - 4
Q – Will there be conference calls to discuss the migration?
A – The Industry Testing calls will resume on a weekly basis starting in March
Q – How can SPs get more information about the scope of the Regression testing?
A – SPs can review the contents of the Regression Test Suite located at the NPAC web site. SPs can also ask questions during the weekly Industry Testing conf calls.
Q – Will there be another fail over test this year to test the new hardware?
A – Yes. Probably in late fall – like last year.