DESCRIPTION

This is the gist of erection sequence of condenser.

TRANSCRIPT

Page 1: Condenser Erection
Page 2: Condenser Erection

Outline of Condenser waterbox

Neck

N1

N2

side view front view

Tube water flow

hotwell

Tube module

Page 3: Condenser Erection

Facts1 pass 2 flowHeat transfer area 35500 sq. m32000 tubes

29900 0.711 mm thick2080 1 mm thick

Cooling water flow 64000 cu. m per hr P = 0.5MPa(g) or 0.01MPa(abs) T = 20-43 deg c

Page 4: Condenser Erection

ModulesCondenser is transported in 30 large size

assembly units Heaviest assembly unit 40 T

Page 5: Condenser Erection

N1 blockNeckN2 blockLPH 1HotwellCondenser tube moduleWaterboxConnection to condenser

Page 6: Condenser Erection

Resources Variablesneed 22 men

1fitter+(5rigger+8helper)+(4welder+4helper)

Duration 12-15 monthsConsumables welding rods 200 cases

5 box /case

Page 7: Condenser Erection

TestsLeak test

Hydro test

DPT 100%

Radiography of joints 10%

Page 8: Condenser Erection