conceptual proposals evaluation response - pwcsa · pdf fileconceptual proposals evaluation...
TRANSCRIPT
E-MERGE SYSTEMS, WHITMAN REQUART AND ASSOCIATES, WESTIN ENGINEERING, AND ICSE
Conceptual Proposals Evaluation Response
Responses to Questions from the Prince William County Service Authority
RFP SA 2113 – Distribution and Collection SCADA Replacement
Due Date/Time: March 27, 2013, 12.00 PM
Prepared For: Prince William County Service Authority
Purchasing Department 4 County Complex Court Woodbridge, VA 22192
Attn: Angela White
E-Merge Systems, Inc. 1314 East Cary Street
Richmond, Virginia 23219 Tel: (804) 344-3511 Fax: (800) 608-6039
www.emergesystems.com
March 27, 2013
Prince William County Service Authority – RFP SA2113 2 Follow-up Questions and Answers
Question 1
Please describe in detail the programming role of each firm on this project.
Programming will be performed in “Phase 2 – Pilot Sites Construction and Configuration” and “Phase 4 –
Full System Construction”. In our proposal – Section 2 Project Characteristics, iii, Proposed Project Team
Organization, illustrates the key team members and their roles. Our proposal Section 2 Project
Characteristics, iv, Key Project Team Members included resumes. In the resumes we identified the roles
of our personnel including their experience.
We understand that in “Phase 2 – Pilot Sites Construction and Configuration” - All programming and
configuration will be conducted on-site (Service Authority facilities) in close cooperation with the Service
Authority SCADA Program Manager.
E-Merge as the project lead will develop the SCADA system architecture and will coordinate the
development of HMI and PLC programming standards with Westin and WR&A. Emerge will also be the
lead Networking and Telemetry developers. Westin’s senior software engineer will be the lead System
Platform development and E-Merge’s senior software engineer will be the lead the development of the
PLC programming. The table below lists the specific programming functions and assignments required for
the project and the role of each personnel/firm assigned.
Table 1 - Team Programming Functions
Programming Function Name Company Years of
Experience
Project Manager Jim Lester E-Merge 15
System Architect Jim Lester E-Merge 15
System Platform Developers
(HMI Screens, Objects and Templates)
Uri Papukchiev
Kevin Cooke
Anand Dixit
Westin
Westin
E-Merge
16
8
15
Networking/Telemetry Janardan Lal
Chris Murray
E-Merge
Westin
20
12
PLC Developer Andrew Jackson
Greg Horn
E-Merge
WR&A
10
8
March 27, 2013
Prince William County Service Authority – RFP SA2113 3 Follow-up Questions and Answers
Question 2
Please list up to three (3) projects where this team has worked together and describe the roles
and responsibilities of each team.
E-Merge and Westin
Westin and E-Merge have worked together to successfully complete several projects for Henrico County,
VA and City of Norfolk, VA.
Henrico County, DPU: The original Water Treatment Facility (WTF) SCADA system was constructed
through a low-bid process and had several functional (programming related) issues. Westin/E-Merge
reviewed the existing hardware and software, developed a system baseline, and then came up with a
transition plan to upgrade the SCADA system HMI and historical database software. E-Merge worked
closely with Westin, Henrico County Utilities, IT and Purchasing to identify all computer hardware, SCADA
software and networking components that were required for the upgrade. We upgraded the SCADA
application to GE Proficy iFIX v4.0 for the plant’s redundant SCADA servers and fifteen View Clients, ten
of which were migrated to a Terminal Services environment.
Henrico County DPU: The WTF purchased an ozone optimization software program used by the
operators to make adjustments to the ozone system for peak performance, but required manual entry of
SCADA data. The project involved linking the SCADA realtime server database to the ozone optimization
software program. Westin was the prime and E-Merge was a subcontractor to Westin on this project.
Henrico County DPU: Developed scheduled regulatory and production reports for the WTF operations
using SyTech XL Reporter. This system provides plant-wide “Read Only” access to reports from within
iFIX SCADA application. Westin was the prime and E-Merge was a subcontractor to Westin on this
project.
City of Norfolk: Westin developed the SCADA Master Plan for the Moore’s Bridges WTP. E-Merge, which
also has a services contract in place with the City, leveraged the guidelines identified in the Master Plan
and came up with a Design/Build approach to upgrade the SCADA System (from an obsolete GE
XL/SCADA) with an open architecture Supervisory Control layer consisting of GEIP Cimplicity and
Historian and redundant Modicon Quantum PLCs. Moore’s Bridges is a 108 MGD plant.
E-Merge and WR&A
E-Merge has a long working relationship with WR&A and we have successfully executed projects for
Chesterfield County, VA, Spotsylvania County, VA and the City of Norfolk, VA.
Chesterfield County: WR&A and E-Merge worked together as the design engineer and Systems
Integrator, respectively for the following projects: Bailey Bridge SPS (Large 10MGD WWPS), Sunnybrook
SPS, Turner Road SPS, Upper Swift Creek SPS, and Countywide Radio propagation study.
Spotsylvania County: WR&A and E-Merge worked together as the design engineer and Systems
Integrator, respectively for the Countywide SCADA System for Sewer PS Collection. In coordination with
WR&A and the County Engineer, E-Merge built and programmed the radio telemetry, SCADA system
specified by WR&A. We are currently working with WR&A and the County to upgrade the Stonewall SPS.
City of Norfolk: E-Merge has worked with WR&A on the Western Branch Pump Station (WTWA
Improvements). In addition, E-Merge is working with WR&A to build the SCADA system for the City’s
Sedimentation Basins 7 and 8 at the Moore’s Bridges WTP. Note: E-Merge has a multi-year services
contract with the City of Norfolk with sole responsibility for SCADA implementation projects.
E-Merge and ICSE
E-Merge and ICSE have worked together for over ten years. ICSE has been our subcontractor on many
March 27, 2013
Prince William County Service Authority – RFP SA2113 4 Follow-up Questions and Answers
projects and has provided electrical contracting and panel fabrication support. Customers have included
Spotsylvania County, Hanover County, Chesterfield County, Appomattox River Water Authority, New Kent
County, Infilco Degremont, and several industrial customers.
Given the fact that E-Merge has worked with Westin, WR&A and ICSE on several large initiatives, we
innately understand each other’s capabilities and work closely together to deliver excellent services and
solutions to our customers. E-Merge shall be the prime on this initiative and the E-Merge Project Manager
will be the point of contact for all project management activities for the Service Authority. Each member of
the team brings unique skills and qualifications to the table. The unified teams’ collective experience is
greater than the sum of the individual company’s experience. We believe this team provides an
unmatched combination of depth of knowledge and breadth of experience, technical capabilities and
professional competence to enable the Service Authority to achieve its goals in the design and build of a
state of the art D&C SCADA System.
March 27, 2013
Prince William County Service Authority – RFP SA2113 5 Follow-up Questions and Answers
Question 3
Please provide a list of projects of similar size and complexity where E-Merge was the Prime
Contractor.
E-Merge has provided design/build SCADA/PLC systems for many Water/Waste Treatment/Distribution
plants in Virginia and Delaware of similar size (in I/O and $ value) and complexity (from a technology
perspective). Subsequent to our implementations, we strive to maintained long-term relationships with our
clients and some of them include:
Hanover County, VA
City of Norfolk, VA
City of Richmond, VA
Chesterfield County, VA
Henrico County, VA
Spotsylvania County, VA
New Kent County, VA
Appomattox River Water Authority, Petersburg, VA
South Central Waste Water Authority, Petersburg, VA
United Water, Newark, DE
Below is a matrix of sample projects that E-Merge has successfully executed as a Prime and that
illustrate the complexity and size:
March 27, 2013
Prince William County Service Authority – RFP SA2113 6 Follow-up Questions and Answers
Table 2 - Emerge Sample Projects Matrix
Technology City of Norfolk New Kent County Chesterfield County
Spotsylvania County
Hanover County
Project Overview Design/Build project. Reverse engineering of a 108 MGD Water Treatment Plant. DCS to Open Architecture Migration. Converting GE XL/SCADA DCS to Cimplicity for HMI and replacing the PCUs with redundant Modicon Quantum PLCs.
SCADA System for WW collection system with 120+ RTUs
Design/Build. Implemented SCADA for over 65 well sites, water tanks and sewage pumps stations. Additionally, provided ground up large SCADA system for Nutrients removal at WWTP and integrated water/wastewater distribution system. Automation of several well sites and Reclamation facilities.
Multi-year and multi-phased SCADA Controls and RTU upgrades including WWTPS, and over 65 SPS. Bailey Bridge PS, Sunnybrook PS, Falling Creek WWTP.
SCADA/RTU system consisting of 2 WTPs, 3 WWTPs, 56 SPS – Telemetry over radio, CDMA and satellite. Design/Build of Motts Run and Ni River WTPs SCADA/Controls upgrades.
Design/Build project. Baselined existing infrastructure over County. Developed SCADA Master Plan – implementation of Wonderware Technologies at multiple plants towards the aim of being consolidated under the System Platform. Upgraded Water Distribution System with Micrologix PLCs and CDMA/Pots.
Physical I/O 3500 3000 Over 5,500 3000 5000
SCADA Tags 7000 6000 7,500 4500 7500
Historized tags 2700 1500 1000 1000 1000
SCADA/HMI GE Proficy Cimplicity
GE Proficy iFIX GE Proficy iFIX FactoryTalk View Wonderware
System Architecture Redundant SCADA, Redundant PLCs, Redundant fiber network
Redundant SCADA, Redundant PLCs, Redundant fiber network
Redundant SCADA, Redundant PLCs
Redundant SCADA, Redundant Comms to RTUs
Redundant SCADA, Redundant Comms to RTUs
PLC/DCS Modicon Quantum AB ControlLogix, CompactLogix, MicroLogix, SLC 5/05
Modicon Quantum, Momentum, Compact, TCP Quickpanels
AB SLC 5/05, Redundant ControlLogix, CompactLogix, MicroLogix
AB CompactLogix, MicroLogix
Telemetry Yes (Radio) Yes (Radio, CDMA) Yes (Radio) Yes (Radio, CDMA and satellite)
Yes (CDMA, POTS, Radio)
Location Redundancy Yes – over Citywide WAN
No No Yes at different at different plants in County.
Yes at different physical locations across the County
Database/Historian Proficy Historian Proficy Historian Proficy Historian FactoryTalk Historian
Wonderware Historian
Microsoft Technologies AD Authentication AD Authentication AD Authentication AD Authentication AD Authentication
Terminal Services/Thin Client
Yes - Microsoft Yes – Microsoft Yes – Microsoft Yes - RDP Yes - RDP
Reporting/Data Analysis MS SQL Reporting Services, Proficy Portal
Proficy Portal Proficy Portal MS SQL Reporting Services, FactoryTalk VangatePoint
MS SQL Reporting Services, ActiveFactory
Virtualization No No No Yes – VMWare No
March 27, 2013
Prince William County Service Authority – RFP SA2113 7 Follow-up Questions and Answers
Technology City of Norfolk New Kent County Chesterfield County
Spotsylvania County
Hanover County
Process/Domain Water Treatment plant 108 MGD, WWTP, Collection Telemetry
D&C Distribution, Wastewater Nutrient Removal, Reclaim Facility
Wastewater and SPS
Water/Wastewater. D&C Distribution
Water Distribution, WTP and WWTP
References/Contact:
Mr. Scott Howerin City of Norfolk, Virginia DPU 6040 Waterworks Rd. Norfolk, VA 23502 Tel: (757) 441-5774 ext 235
Mr. Harold Jones Utility Supervisor County of New Kent 12007 Courthouse Circle New Kent, VA 23124 Tel : (804) 966-2676
Ms. Anne Wright Department of Utilities Chesterfield County Chesterfield, VA 23832 Tel: (804) 768-7582
Mr. Chris Edwards County of Spotsylvania 600 Hudgins Road Fredericksburg, VA 22408 Tel: (540) 507-7304
Mr. Charles Smith County of Hanover, Virginia Hanover County DPU 7516 County Complex Rd Hanover, VA 23069 Tel: (804) 365-6738
$ Value (Cumulative to Date)
$3.1MM $2.4MM $1.95MM $2.8MM $1.1MM
Please feel free to contact any and all of our references.
March 27, 2013
Prince William County Service Authority – RFP SA2113 8 Follow-up Questions and Answers
Question 4
Please list any SCADA implementations in the past 5 years that included an access control and/or
IP camera component.
E-Merge has successfully provided SCADA implementations in the past 5 years that have included an
access control and/or IP camera component for the following clients:
Spotsylvania County – Longwatch Video Surveillance Software (Active X embedded in
FactoryTalk View SCADA) with IP Cameras (PTZ), card access system, intercom, physical gate
control – StrongArm 30 MPH crash gate and loop detector. Such systems have been
implemented at multiple locations over the County.
Hanover County - Longwatch Video Surveillance Software (Active X embedded in Wondwerware
InTouch SCADA) with IP Cameras (PTZ) and gate access control.
Appomattox River Water Authority - Longwatch Video Surveillance Software (Active X embedded
in Wondwerware InTouch SCADA) with IP Cameras (PTZ) and gate access control.
Longwatch Video Surveillance System supports multiple communication protocols include: TCP, UDP,
RTSP/RTP, HTTP, VAPIX, and Pelco-D. Supported video formats include: MJPEG, MPEG-4, and
MXPEG.
We have additionally executed several high-end security systems for VDOT for their mission critical
infrastructure including:
Hampton Roads Bridge Tunnel Surveillance Project
Monitor Merrimac Bridge Tunnel Surveillance Project
Jamestown Scotland Ferry Surveillance Project
Chesapeake Expressway Network Upgrade Project
At the Hampton Roads and Monitor Merrimac Bridge Tunnels, E-Merge needed a way to track intruders
once they came ashore while disregarding any other events such as boats in the water passing by, birds
flying onto the island, and workers that were already on the island. Sightlogix software has the ability to
set alarm zones with alarming restrictions as to size of intruder and direction of motion; a bird moving
inland would be too small to set off the alarm, and a worker in the inner alarm section on land would not
set off the alarm. Pairing the Sightlogix fixed IR camera with a typical imaging PTZ camera allowed for
detailed tracking of any alarm situation; as the intruder crosses the view of the IR camera, the PTZ
camera is able to zoom into the location and follow the movement of the intruder, gathering higher
resolution images that can be used as evidence. With the SightLogix Surveillance System, E-Merge was
able to accomplish everything that was needed to provide a strong solution for our customer.
The Jamestown Scotland Ferry Project needed a radio network that was both reliable and weather-proof.
In the original security system, the video clarity was poor and would drop out during certain weather
conditions. With the Firetide Network (High Bandwidth Mesh Network Radios), E-Merge was able to
provide a stronger Radio Network that made the video stream cleaner and stronger to the point that video
loss and clarity was a non-issue. Please note that the system provides “live” video feed (Pelco and Axis IP
cameras) from moving ferries to the headend. There is DVR capability both at the ferries and at the
headend.
At the Chesapeake Expressway Toll Plaza, Axis fixed and PTZ cameras were installed. Low-profile fixed-
directional cameras with high resolution were installed within toll booths to record currency exchange and
monitor customer interaction. The high-resolution recording ability was required due to video being
admissible into courts of law. PTZ cameras were placed on roadway fixtures to allow for full 360° pan to
March 27, 2013
Prince William County Service Authority – RFP SA2113 9 Follow-up Questions and Answers
view incoming and outgoing toll plaza traffic and easily monitor accidents and roadwork. Barix devices
were installed at the Chesapeake Expressway Toll Plaza to replace an outdated and failing intercom
system. They required an independent system, IP based system that did not require a dedicated server.
One head-end master station and individual remote clients located at each install location make up a half-
duplex intercom system controlled from the control room by the master station in a one-to-many
configuration. They were used in conjunction with AiPhone door panels.
Westin - As part of a pilot project for HRSD’s Interceptor SCADA Upgrade project, Westin interfaced card
access readers using the card readers Wiegand protocol to the SCADA RTU, which allowed an operator
to swipe in and out when on site. The swipe out presented the operator with a list of items to check before
leaving the site, which helped eliminate return trips.
WR&A – WR&A’s Security Protective Design Group has completed numerous designs and
implementations of high profile access control systems and CCTV monitoring systems. WR&A serves a
variety of confidential secure government clients by developing designs for full-scale force protection
systems including perimeter intrusion detection systems, facilty intrusion detection systems and access
control systems using the industry’s state of the art technologies including access card badging system,
voice activated and biometric acces control systems.
In the previous 5 years, WR&A has successfully compled more than 10 separate CCTV system projects
using over 150 wired and wireless networkded video cameras integrated into graphical user interface
systems.
WR&A’s Secruity Protective Design Group consists of professional engineers, ASIS board certified
protection and physical security professionals and CCTV specialists trained and certified by major
manufactures of CCTV surveillance equipment.
March 27, 2013
Prince William County Service Authority – RFP SA2113 10 Follow-up Questions and Answers
Question 5
Please describe your method for simulation of HMI and PLC programming.
Developing and testing of HMI and PLC code is a critical part of any SCADA project. We have therefore
developed a methodology that allows our clients to provide feedback at critical milestones as well as
thoroughly testing the programs before being deployed in the field. This has significantly reduced
commissioning time, and field changes. Our methodology is as follows:
A. PLC
a) After the process control narratives and P&IDs have been completed, we will identify what
repetitive code will be required and develop a functional description for code development. We
will also develop test scripts for each functional description identified. Examples of repetitive
functions requiring code development are pump alternation and signal conditioning (instrument
out of range alarm, dead band, etc.).
b) The functional descriptions will then be used to develop a library of code modules. The preferred
method would be to develop these code modules as function blocks (FBs) (UDTs and AOI in the
RS Logix 5000 world). Each code module (FB) will then be thoroughly tested. Our preferred
method of testing is to bench test the code module (FB) using an actual RTU hardwired to a test
panel, but in some cases we may use emulation software.
c) Once all the code modules have been developed and approved by the Service Authority we will
begin programming of a particular site. Test scripts will be developed and the program will be
tested using emulation software.
B. HMI
a) HMI programming will begin with the identification specific scripts, animations, screens, and
reports required for the project. A functional description and test procedure will then be
developed. Testing will be completed using virtualization which is a methodology we have very
successfully employed for simulation. Standard object development and testing will also be
performed.
b) In this scenario we would replicate the proposed solution in a test environment. For the purposes
of simplification, we would have the Wonderware HMI application on a Virtual Machine (VM) with
a RSLinx Gateway (OPC Server and/or I/O Server). On another VM, we would install RSLogix
5000 Professional, which includes RSLogix Emulate 5000. The Rockwell emulator is a very solid
product. We would load the developed PLC
program/s into the emulator. Theoretically,
you could test your HMI application against
multiple controllers in the emulator. We would
follow the Control Narratives and thoroughly
and completely test the HMI application and
the PLC program(s). This allows you to check
out all features including animation, trending,
data logging, alarms and events, etc. We shall
also simulate normal modes of operation as
well as failure modes.
Figure 1 - HMI PLC Emulation
March 27, 2013
Prince William County Service Authority – RFP SA2113 11 Follow-up Questions and Answers
C. Factory Acceptance Testing (FAT)
a) A witnessed FAT will be conducted with all of the hardware and software associated with the pilot
sites. This will include the HMI servers, WAN communications equipment and RTUs. The RTUs
will be hardwired to a test panel for testing. A complete test will be conducted including the
following:
i) I/O check out from RTU input to proper display on HMI.
ii) Functional test to verify proper operation of equipment and various operations including
automatic, remote manual, local manual, etc.
iii) Failure testing or sometimes called what ifs testing will be conducted. This testing will verify
proper operation in the event of an equipment failure or loss of communications. Example of
equipment failures includes primary pump failure, loss of wetwell level signal, etc.
iv) Trends and reports will also be verified at this time.
b) We recommend that operators and maintenance personal be involved in the FAT. This allows for
feedback on how the system is to operate and gives them an introduction to the new system.
March 27, 2013
Prince William County Service Authority – RFP SA2113 12 Follow-up Questions and Answers
Question 6
Please describe your approach for ensuring the SA staff is fully engaged in this project and will be
self-supportive at completion.
It is our team’s desire and goal to maximize the participation of the Service Authority’s (SA) technical staff
members in the development of standards, standards compliance, and implementation to ensure that the
constructed SCADA system is reflective of your requirements and that SA staff are system experts, not
just at the end of the project, but at each phase of the project. Achieving these objectives requires the
creation of an integrated project delivery team that is comprised of both SA technical team members and
E-Merge team members.
During the standards development and Pilot Project phases, our senior software team members will be
co-located with the Service Authority’s Project Manager and software team, at your facilities. This co-
location will enhance communication, team building, and cooperation, which are essential elements to
understanding the SA’s needs, knowledge transfer between team members, and building consensus on
project direction and approach.
Our team recognizes that SA staff members have the added responsibility to maintain operational
continuity while they’re managing and participating in capital delivery projects. The first step in
establishing the integrated project delivery (IPD) team will be defining the level of effort required by SA
technical staff to support the existing SCADA system. Typically the role of a technical support team is to
maintain, recover, and enhance existing systems. Building the new SCADA system should eliminate the
need for most enhancements but we anticipate that there may still be a need to free-up technical staff to
participate actively in the upgrade project. A potential strategy for freeing-up SA staff is to leverage E-
Merge team members (or an alternate contractor) to provide support for the existing system during the
SCADA upgrade.
The next step involves identifying the project phases and tasks which are critical for SA staff to
participate. Based on SA staff availability and their priorities for participation a work-plan and resource
loaded project schedule will be developed in Microsoft Project for the IPD that identifies participation of
the SA’s technical team members. This will identify resource utilization for all team members so that we
can identify when additional support may be required by the Service Authority.
We believe it is critical that the SA’s SCADA staff actively participate in the Pilot Project and the
development of project standards. Well defined, documented and proven SCADA Software Standards
and Modules (Objects) are the cornerstone to implementing a system that is reliable, maintainable and
consistent in its “look-and-feel.” Utilizing an integrated project delivery (IPD) team (comprised of both
Service Authority (SA) staff and senior E-Merge team members) for standards development and
validation not only ensures high-quality standards, it also supports knowledge transfer and ensures the
creation of a software leadership team with “hands-on” experience. This will enable our Software Task
Leaders to mentor other implementation team members and manage their compliance with the SA’s new
SCADA Software Standards.
As a minimum, the SCADA Software Standards and Modules developed in this phase would cover the
following: software delivery methodology and test standards, Process Control Narratives, program
structure and object development, I/O and device objects (both HMI and PLC), intelligent alarming,
equipment KPIs and historical data capture. The standard developed for Process Control Narratives
(PCN) will provide a consistent presentation of the control strategy to support the conversion of existing
control software. In addition, the data management plan will define data requirements for each defined
asset class and will architect the necessary software “hooks” for integrating future operations optimization
applications.
March 27, 2013
Prince William County Service Authority – RFP SA2113 13 Follow-up Questions and Answers
Applying proven standards will significantly reduce system delivery risk and optimize operator acceptance
and satisfaction. It is recommended that the standards be validated on a select number of representative
facilities. The E-Merge team has a full understanding of the benefits of a Pilot Project, which go beyond
validation of design and software standards and include:
Develop and validate re-useable Software Modules for common equipment and unit processes.
When executed effectively, the risk and effort associated with implementing the following sites will
be significantly reduced.
Validate migration strategies and methods for transitioning from the old to the new SCADA
system. Testing these strategies on a Pilot Project minimizes the possibility of widespread service
disruption.
Identify any unanticipated issues and validate constructability.
Provide Operations staff with operating experience on the new SCADA system so that they can
provide operational feedback on the system configuration early in the project. It also provides the
Operations staff with a training tool to ease the transition on future phases.
In addition to actively participating in the Pilot Project design and implementation, we expect that SA staff
will leverage that experience to witness Factory and Site Acceptance Tests (FAT and SAT) performed by
E-Merge team members. If possible, we encourage the Service Authority to reverse these traditional roles
whereby SA staff program a group of sites and senior E-Merge team members witness their FAT/SAT
tests for compliance with standards.
March 27, 2013
Prince William County Service Authority – RFP SA2113 14 Follow-up Questions and Answers
Question 7
Please list all projects containing a SCADA programming component performed for a Water/Wastewater Utility in the past 5 years.
Table 3 - SCADA Programming (E-Merge)
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iFix
/Cim
pli
cit
y
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Vie
w
Ro
ck
we
ll A
lle
n-B
rad
ley
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
City of Norfolk, Moore’s Bridge Water Treatment Facility
108 MGD WTP SCADA/Controls Upgrade, WW SCADA System
Design/Build project. Reverse engineering of a 108 MGD Water
Treatment Plant. DCS to Open Architecture Migration. Converting GE
XL/SCADA DCS to Cimplicity for HMI and replacing the PCUs with
redundant Modicon Quantum PLCs. Also, provided SCADA System for
WW collection system with 120+ RTUs
New Kent County Department of Public Utilities
County-wide SCADA Upgrade and SCADA design/install for Nutrients Removal System at Parham Landing WWTP
Design/Build project. Implemented SCADA for over 65 well sites, water
tanks and sewage pumps stations. Additionally, provided ground up
large SCADA system for Nutrients removal at WWTP and integrated
water/wastewater distribution system. Automation of several well sites
and Reclamation facilities.
March 27, 2013
Prince William County Service Authority – RFP SA2113 15 Follow-up Questions and Answers
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iFix
/Cim
pli
cit
y
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Vie
w
Ro
ck
we
ll A
lle
n-B
rad
ley
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Chesterfield County Department of Public Utilities
County-wide SCADA Controls and
RTU Upgrade
Multi-year and multi-phased SCADA Controls and RTU upgrades
including WWTPS, and over 65 SPS. Bailey Bridge PS, Sunnybrook
PS, Falling Creek WWTP. Collaborated with WRA on several of these
projects.
Spotsylvania County Department of Public Utilities; Motts Run and Ni River WTPs.
SCADA Controls and RTU Upgrade
SCADA/RTU system consisting of 2 WTPs, 3 WWTPs, 56 SPS –
Telemetry over radio, CDMA and satellite. Design/Build of Motts Run
and Ni River WTPs SCADA/Controls upgrades. Technologies include
Rockwell FactoryTalkView and ControlLogix PLCs and VMWare.
Hanover County Department of Public Utilities; Doswell WTP
SCADA Master Plan Development
and Upgrade
Design/Build project. Baselined existing infrastructure over County.
Developed SCADA Master Plan – implementation of Wonderware
Technologies at multiple plants towards the aim of being consolidated
under the System Platform. Upgraded Water Distribution System with
Micrologix PLCs with CDMA/POTS.
March 27, 2013
Prince William County Service Authority – RFP SA2113 16 Follow-up Questions and Answers
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iFix
/Cim
pli
cit
y
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Vie
w
Ro
ck
we
ll A
lle
n-B
rad
ley
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Washington Gas Light Company, D.C.
Integration of Disparate Platforms via
Virtualization, System Upgrades, and
Alarm Management.
Upgraded and enhanced HMI graphics within the current iFIX SCADA
system to achieve 49 CFR compliance through the development of an
Alarm Response Management (ARM) System. System used
Wonderware ArchestrA System Platform and Workflow to manage
alarm information. VMWare virtualization used to host iFIX and
Wonderware applications.
Appomattox River Water Authority, VA
50-95 MGD Plant Expansion; E-
Merge awarded “Sole Source.”
Expansion for long-term client (since 1998!). System consisted of a
Modbus Plus process LAN with over 25 Modicon 984-145/Quantum
PLCs and 18 RTU sites with Modicon Momentum PLCs
communicating over CDMA. Redundant InTouch Wonderware SCADA
nodes provided operators monitor and control capability.
City of Richmond Department of Public Utilities WTP, VA
Maintenance and Support
Provided engineering, maintenance, and controls support including
instrument calibration, PLC programming, panel wiring, and
workshops.
March 27, 2013
Prince William County Service Authority – RFP SA2113 17 Follow-up Questions and Answers
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iFix
/Cim
pli
cit
y
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Vie
w
Ro
ck
we
ll A
lle
n-B
rad
ley
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Henrico County, DPU
SCADA Upgrade, Ozone system
optimization, Regulatory Reporting
Westin/E-Merge reviewed the existing hardware and software,
developed a system baseline, and then came up with a transition plan
to upgrade the SCADA system HMI and historical database software.
Upgraded the SCADA application to GE Proficy iFIX v4.0 for the
plant’s redundant SCADA servers and fifteen View Clients, ten of
which were migrated to a Terminal Services environment. E-Merge
also helped optimize the Ozone system and provided regulatory
reporting with SyTech XL Reporter.
Infilco Degremont, Inc. AquaDAF® Control System
Turnkey Solution
AquaDAF® Control System was responsible for monitor and control of
over 900 field I/O. Built upon the GE Intelligent Platforms (GE-IP)
Max-ON RX3i Hot Standby Redundancy configuration for the
PACSystems™ RX3i Programmable Automation Controllers (PACs).
E-Merge also responsible for development of a standalone
HMI/SCADA application.
South Central Wastewater Authority
SCADA Services and Support
E-Merge provided SCWAA with SCADA and PLC support and to
replace the existing chlorination system with a new Sodium
Hypochlorite Storage and Feed Facility.
March 27, 2013
Prince William County Service Authority – RFP SA2113 18 Follow-up Questions and Answers
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iFix
/Cim
pli
cit
y
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Vie
w
Ro
ck
we
ll A
lle
n-B
rad
ley
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
United Water, Newark, DE
30 MGD plant migration from Bristol
Babcock 33xx RTUs to A-B
CompactLogix PLCs and GEIP iFIX
5.x and Historian
Collaborative” design/build SCADA Filter/Rest of the Plant Upgrade
project. Had to reverse engineer all the logic in the Bristol Babcock
33xx RTUs. Developed new control narratives. Provided new NEMA
4x SS Filter Consoles with AB PanelView Plus OITs and
CompactLogix PLCs. Completed the 8-month duration project in 6
months - 2 months ahead of schedule!
March 27, 2013
Prince William County Service Authority – RFP SA2113 19 Follow-up Questions and Answers
Table 4 - SCADA Programming (WR&A)
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
Sie
me
ns W
in C
C
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
Sie
me
ns T
IA P
ort
al
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Anne Arundel County, MD
Broadneck WRF Plant Upgrade
PLC and HMI programming for new plant-wide control system installed
as a part of the ENR upgrade and expansion of the facility. Project
includes programming and interface to 8 new Siemens S7/300 PLCs
with redundant HMI server system with 5 clients. Plant-wide
communications using Ethernet and Profibus network protocols.
Arlington County, VA
Water Distribution SCADA System
Provide continuing programming support for new SCADA System
functions, system upgrades, troubleshooting and training to operations
and maintenance personnel for County-wide SCADA System. The
system uses Ethernet, dial-up and leased telephone line
communications.
James City Service Authority
James City County, VA
Water/Wastewater SCADA System
County’s designated PLC and HMI programming Engineer for all new
and upgraded facilities. Work with County to develop revised controls
strategies and implement into processes. Maintain the Service
Authority’s SCADA standards, work closely with County SCADA
personnel during all phases. System uses ISDN telephone network
communications to approximately 120 county-wide facilities. Starting
pilot program to convert communications to cellular based network.
March 27, 2013
Prince William County Service Authority – RFP SA2113 20 Follow-up Questions and Answers
HMI
Programming
PLC Programming Other
Client
Project/Utility Services
Sie
me
ns W
in C
C
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
Sie
me
ns T
IA P
ort
al
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
City of Suffolk, VA
Wastewater Pump Station Standards
Developed City’s standard PLC and OIT programming for new and
revised wastewater pumping stations. Serve as the City’s designated
programming Engineer for new PLC control systems. Work with City
personnel to train, trouble shoot and maintain the system functions.
March 27, 2013
Prince William County Service Authority – RFP SA2113 21 Follow-up Questions and Answers
Table 5 - SCADA Programming (Westin)
HMI
Programming PLC Programming Other
Client
Project/Utility Services G
EIP
Pro
fic
y i
Fix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
City of Ottawa Water
SCADA Replacement
Water Treatment/Distribution
Population 883,000
SCADA Master Plan, Standards, Governance Plan, Workflow
Modeling, Smart Alarming, Plant/Remote Network, HMI Upgrade,
Rockwell Logix PLC Programming, OO Software Modules, Operations
Data Management, Business Intelligence, Cyber Security, and
Continuity of Operations Plan for a $12M Automation and SCADA
Program.
Durham Region
Water SCADA Upgrade and
Integration
Water Treatment and Distribution
Region of Durham operates 14 water supply systems located
throughout the Region involving the operation and control of 65
individual treatment and distribution sites. This phase involves detailed
design; procurement and project management of site upgrade
services; HMI and PLC programming; system startup and post-
implementation support. Westin is also performing the HMI and PAC
programming and integration.
March 27, 2013
Prince William County Service Authority – RFP SA2113 22 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Duffin Creek Wastewater Pollution
Control Plant
SCADA System Upgrade
Wastewater Treatment
Duffin Creek WPCP is the 2nd
largest plant in Canada and needed to
replace its obsolete SCADA system to improve performance,
maintainability, and usability. Scope of services included: system
assessment, SCADA standards, design, bid, and construction
oversight including Plant-wide SCADA LAN (Ethernet/IP) design. In
addition, Westin performed GEIP HMI and PAC programming and
integration of operations data with other data sources. The strategies
developed for system testing and migration resulted in a very smooth
cutover with no operational disruptions.
Halton Region
SCADA Upgrade
The Halton Region has a high dependency on its SCADA System to
maintain its water and wastewater service levels. The Region’s
SCADA system is mission-critical and a failure of any part of the
system necessitates a prompt response by the SCADA group to
recover the system. In recognition of their operational dependency on
SCADA, Halton Region authorized the preparation, implementation
and maintenance of a SCADA disaster recovery and business
continuity (DR/BC) plan.
March 27, 2013
Prince William County Service Authority – RFP SA2113 23 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Waterloo Galt and Preston
WWTP SCADA Upgrade Wastewater
Treatment
Westin, as part of a consulting team, was contracted by Waterloo
Region to upgrade their Wastewater Treatment Plants to a uniform
and modern SCADA system. Westin’s scope of work included
planning, SCADA standards, site inventory, I&C and network design,
HMI and Rockwell Logix PACs programming, network configuration,
construction oversight, training and documentation.
City of Hamilton Water and
Wastewater Services
SCADA Standards and Upgrade
This project is providing the City with a SCADA System Master Plan
and a strong set of SCADA Standards based on industry best
practices, thus creating a road map for the future and for the
implementation phase to be undertaken as part of the project. The
project incorporates a number of key elements including a detailed
review of technology, piloting of the proposed solution, meeting
compliance requirements of the Ministry of Environment (MOE), the
development of the guiding documents for the future, and the detailed
design and construction administration required to implement the
City’s new SCADA system.
March 27, 2013
Prince William County Service Authority – RFP SA2113 24 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Wayne County, Michigan
Downriver Wastewater Treatment
Plant (DWTP)
SCADA System Upgrade
Wastewater Treatment
The DWTP is capable of treating over 225 million gallons of raw
sewage per day serving a combined population of approximately
415,000. Westin’s scope of services included: system assessment,
SCADA standards, I&C design, SCADA LAN design, bid, and
construction oversight. In addition, Westin’s team was responsible for
the programming of the SCADA HMI and Rockwell PLC’s.
Chicago Department of Water
Management
SCADA System Replacement
DWM selected Westin to design, configure and deliver a project to
replace their Pumping Station SCADA system. Through stakeholder
workshops, Westin determined DWM’s requirements, then customized
a solution to meet their unique needs. Control strategies, HMI
graphics, reports and components were carefully selected with DWM’s
input. The new system includes Allen-Bradley PLCs and both
centralized and remote GE Proficy iFIX operator interface systems.
The resulting state-of-the-art system and control rooms feature
multiple video wall displays that provide operators and management a
true supervisory view of their system.
March 27, 2013
Prince William County Service Authority – RFP SA2113 25 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Charles County Department of
Utilities
SCADA System Replacement
Water and Wastewater Treatment
Upgrade of Motorola Moscad SCADA system for remote unattended
operations for their treatment plants and 160 remote water and
wastewater facilities. Scope of services includes SCADA,
communications and I&C planning, standards, system design, bid, HMI
and PLC programming and construction oversight.
Rowland Water District
SCADA System and Telemetry
Network Needs Assessment, Design,
Implementation and Upgrade
The District issued Westin an emergency Purchase Order to replace
the server with new hardware and to transfer the system configuration
files. Westin satisfied the District’s urgent need on the server
replacement. The District requested Westin provide new PLCs and
associated telemetry for two new sites that were under construction.
The Needs Assessment defined a plan for upgrading the SCADA
application, PLCs and SCADA radio network. The District negotiated a
contract with Westin to prepare bid documents and perform the
SCADA and PLC program application upgrades.
March 27, 2013
Prince William County Service Authority – RFP SA2113 26 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
South Bayside System Authority
Enterprise SCADA Migration
Wastewater Treatment and
Collection
SBSA provides regional wastewater transmission and treatment for
three municipalities. Westin prepared a SCADA Master Plan, system
architecture and design for technology and automation improvement
projects including upgrades to the SCADA HMI, data Historian,
Ethernet fiber optic network and PLC control at the WWTP and four
main pump stations. Scope included E,I&C, control panels, Rockwell
PLC hardware and network design; PLC programming, HMI software
configuration, systems integration, training and start-up services;
migration of 10+ years of data from Classic Historian to the latest
Proficy Historian. SBSA has won CWEA’s “Large Plant of the Year”
award on two occasions in part because of the effectiveness of their
SCADA system
Pittsburg, City of
SCADA Assessment, Design, and
Implementation
Pittsburg selected Westin to develop a SCADA System Assessment
that described the overall SCADA System Upgrades for the City of
Pittsburg. This assessment defined four projects to improve the City’s
existing SCADA System over a 2-year timeframe. The projects
focused on defining the SCADA design framework, upgrading the
SCADA Master Station, designing and implementing improvements to
the SCADA Remote Sites, and revising the Water Treatment Plant
(WTP) controls. Each project adhered to consistency in SCADA
design, implementation, and documentation, so that the City could
maintain the SCADA system at minimum cost.
March 27, 2013
Prince William County Service Authority – RFP SA2113 27 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Inland Empire Utilities Agency
SCADA Master Plans
Northwest Recycled Water HMI
Upgrade
Wastewater Treatment and
Collection
Westin developed a SCADA Master Plan for the Reclaimed Water
System and subsequently for all of Wastewater Operations. The plans
set the architecture, vendor platforms, and roadmap for replacement of
the existing DCS. HMI and PLC software standards were developed
and a pilot project implemented. The pilot project at the Agency’s new
Reclaimed Water Pump Station included the configuration of a
Virtualized SCADA System that consists of Rockwell Automation’s
Factory Talk HMI, Vantage Point Historian, and View Point Portal.
Irvine Ranch Water District
Michelson Water Recycle Plant
SCADA System Migration
Water and Wastewater
Virtualized treatment/distribution system SCADA in array of virtual
machines under VMWare; merged ArchestrA graphics/ templates from
multiple galaxies into a single galaxy; implemented redundancy; and
prepared Disaster Recovery process. Commissioned RO WTP and
Well 21. Project included planning/code development for 36 PLCs and
Wonderware System Platform 3.0. Developed detailed design for
templates used in PACs, SCADA data objects (application objects),
and SCADA graphical objects.
March 27, 2013
Prince William County Service Authority – RFP SA2113 28 Follow-up Questions and Answers
HMI
Programming PLC Programming Other
Client
Project/Utility Services
GE
IP P
rofi
cy
iF
ix
Wo
nd
erw
are
Ro
ck
we
ll F
ac
tory
Ta
lk
Ro
ck
we
ll
Mo
dic
on
GE
IP
SC
AD
A P
ac
k
Co
mm
issio
nin
g a
nd
Sta
rtu
p
Tra
inin
g a
nd
Kn
ow
led
ge
Tra
ns
fer
Project Description
Trinity River Authority
Central Regional Wastewater
System (CRWS) SCADA
Wastewater Treatment
TRA’s goals for their upgraded SCADA system included migrating
from a multi-vendor approach to a uniform SCADA system that would
be easier to support and expand the level of plant control and
monitoring. Westin performed current system assessment, developed
an upgrade plan, SCADA standards and system design, and provided
construction management. Westin designed around a Rockwell PLC
platform and provided HMI configuration and programming.
March 27, 2013
Prince William County Service Authority – RFP SA2113 29 Follow-up Questions and Answers
Question 8
Describe in detail how you envision knowledge transfer taking place during the project. We do not
want formal training to be the only means of knowledge transfer.
The integration and knowledge transfer between the Service Authority’s core technical team and our team
was addressed in our response to Question 6. In our response to this question we have focused our
discussion on knowledge transfer between the SA’s Operations team and the Integrated Project Delivery
(IPD) team.
Knowledge transfer between the SA’s Ops team and the IPD team will be bi-directional and a process that
is continuous over the life of the project. However, the intensity and criticality of that knowledge transfer is
highest during the standards development and Pilot Project. To maximize the value of the SA’s new
SCADA system it is important that the design and implementation of the SCADA system be aligned with
your operating and control philosophy and that the constructed system provides Operators with the
information and control they require to operate the SA’s system in compliance with regulations and
efficiently.
To assist Operations in understanding the potential of current SCADA systems, our team recommends
that the IPD team and representatives from the SA’s operations team visit a number of utilities that have
undergone recent SCADA upgrades. This will provide Operations with the opportunity to see first-hand
how other utilities are leveraging SCADA to optimize operations and the features and functionality most
appreciated by their Operators.
In addition to the design and review workshop topics listed on pages 17 and 18 of the RFP, our team has
recommended Operating and Control Philosophy workshop/s to gain a better understanding of the
SCADA goals and objectives for Operations as well as present and review current industry best practices
with the Operations team. Prior to this workshop/s, our Project Manager and Phase Leads will interview
SCADA stakeholders (primarily O&M staff) with respect to their perspectives on the current SCADA
system and desired improvements. Information gathered during the interviews, review of existing
documentation, site visits to other agencies, and current industry best practices will be presented and
reviewed during the workshop to drive consensus on desired SCADA functionality.
If feasible, E-Merge recommends that representatives from Operations be assigned to the Integrated
Project Delivery core team to follow the project through-out its life cycle, actively participate in all
workshops, and witness all Factory and Site Acceptance Tests. This will ensure that Operational needs
are represented at all key junctures and that Operations understands the underlying reason for technical
decisions. If it is not possible to assign dedicated Operations staff then we recommend that Operations
participate in all Process Control Narratives workshops as well as standards development workshops
relating to HMI configuration, alarm management, and reporting.
Implementing a smaller subset of the total system as a pilot (or test) project enables the delivery team to
prove out concepts, validate standards, and identify unforeseen integration issues. In addition to lowering
the risk and optimizing delivery for the larger system, Pilot Projects also provide Operations and SCADA
Support staff with the opportunity to gain experience with the new system early in the upgrade process. In
addition to Operations participating in the Factory and Site Acceptance Testing for the Pilot Project,
Emerge recommends the following additional knowledge transfer opportunities:
Training of O&M staff prior to deployment of the software to site. The simulator developed for
testing purposes would be used to provide staff with hands-on training. An overview of systems
standards, with an emphasis on operator interface standards, would be included in this first O&M
March 27, 2013
Prince William County Service Authority – RFP SA2113 30 Follow-up Questions and Answers
training session. Training sessions will be recorded so that O&M staff can revisit them at anytime
from their SCADA or training workstations.
O&M Manuals would be created and published prior to commissioning so that they are available
to O&M staff. Our team recommends that O&M manuals be incorporated into SCADA as context
sensitive help.
After the training, a single test system would be maintained for a number of weeks to provide
Operator’s with an opportunity to do self-study prior to commissioning. Our development team
would be available to answer questions and provide support as required. This test system could
become a permanent feature for ongoing self-study by Operators.
A post-implementation evaluation period would be facilitated for 14 days of continuous operation.
During this time Operators would be encouraged to log issues (both problems and
enhancements) to an Issues Log which the IPD team would monitor. At the end of the evaluation
period, we would facilitate a workshop with Operations to review their feedback and reach
consensus on desired changes.
For each of the remaining facilities (or groups of facilities), our team recommends that O&M staff
participate in the Process Control Narrative Workshop, review the submitted PCN and test plan,
participate in the FAT, pre-deployment training, and SAT. E-Merge commits to recording each training
session and ensuring that are development staff members are available to your O&M staff for ad-hoc
support and training.
March 27, 2013
Prince William County Service Authority – RFP SA2113 31 Follow-up Questions and Answers
Question 9
Explain in detail the method used to size the overall system defined in the Conceptual Drawing? Is
the size proposed typical for a water/wastewater utility with 125 sites?
The RFP identified the following technologies:
Wonderware System Platform 2012 or Current Version
VMware based application, historian, and terminal servers
Microsoft 2008 Server or current version
Allen-Bradley CompactLogix PLCs
RS Logix 5000 Enterprise PLC programming software
Local HMI displays, including thin clients and panel mounted Operator Interfaces with integrated
I/O
Additionally, the following ancillary systems were listed in the RFP:
Physical security and Access Control
Video Monitoring Systems – including IP Cameras
IP radios
IP cellular modems
Cyber Security
The RFP states that there are 3,000 separate data points representing monitor and control information
from 125 sites. If we assume that each data point represents a physical device (i.e. pump status or flow
measurement instrument), then we can assume that there an average of twenty-four (24) physical
devices per site that are required to be represented within the new PWCSA SCADA system.
The Wonderware System Platform software uses “Application Objects” to represent physical devices with
common attributes. For example, a simple Digital Alarm, like a Door Alarm, will really only have one
attribute – Alarm On or Off. However, a more complex device such as a Pump can be modeled with
several attributes – Run Command, Run Status, Alarm Status, Speed Command, Speed Feedback, and
Runtime. All of these attributes
are considered as an I/O point
within System Platform. So, in the
case of the Pump example we
would have one (1) Application
Object in System Platform with six
(6) separate attributes (or I/O
points). With these guidelines in
mind, we have assumed that we
will average twenty-four (24)
Application Objects representing
an average of sixty (60) I/O points
for each site, for a total Application
Object count of 3,000 and a total
I/O count of 7,500.
Figure 2- System Platform Application Object
March 27, 2013
Prince William County Service Authority – RFP SA2113 32 Follow-up Questions and Answers
We have built in application redundancy at the System Platform Device Integration (DI) Server for all I/O
communications, and at the Application Object Server (AOS) Server level for all Object scanning. If a
partner server fails for the DI Server or the AOS Server, then the remaining server will immediately
assume the failed server’s processing load. This design has been thoroughly vetted and approved by
InSource Solutions Application Engineers.
Based on the above, a starting point for the Wonderware System Platform would be sized as follows:
System Platform 2012R2, 25K IO/5K History - Application Server 25K IO with 4 Application Server
Platforms (comes standard with 4 Application Server platforms), Historian Server 5K Tag Enterprise
Edition, 2 Device Integration Servers. Depending upon the SA’s needs for historization – the Historian can
be scaled up to 12K, 25K, or 50K tags.
We have also built in redundancy and load balancing at the HMI level using the ACP ThinManager
software package. The ThinManager Redundancy technology provides normal runtime load balancing for
even distribution of client sessions across Terminal Servers. If one of the Terminal Servers becomes
unavailable, then all client sessions will automatically reconnect to the available Terminal Server. An
additional HMI Client Terminal Server was added to the “SCADA DMZ” for Corporate VPN access outside
of the trusted SCADA network. This approach was taken with Cyber Security best practices in mind. Our
design approach using InTouch for Terminal Services and ACP ThinManager is easily scaled to
accommodate more Terminal Servers as needed.
The beauty of the design we have proposed is that we can scale up (or down) as needed. This is because
of the modular SCADA software and Virtualization.
During the preliminary design phase, we shall use the information gathered during the workshops to
finalize the overall system architecture and right size it to address your needs.
Additionally, find attached architecture diagrams from Spotsylvania County that highlights a similar
architecture using virtualization and SCADA technologies (FactoryTalk View as the SCADA headend with
A-B ControlLogix PLCs). Also, attached are the architecture diagrams for New Kent County – which is a
“Unified” solution not only for the D&C distribution system, but also all Water and Wastewater Operations.
It consists of GE IP iFIX SCADA headend with A-B ControlLogix PLCs, SLC 5/05 and MicroLogix PLCs.
Please see Appendix A for Architectural Diagrams.
March 27, 2013
Prince William County Service Authority – RFP SA2113 33 Follow-up Questions and Answers
Question 10
Is there a warranty provided for any period from the date of beneficial use?
E-Merge proposes to provide standard warranty period of one year from substantial completion of a
facility for hardware and workmanship failures. Our warranty coverage will cover repairs or providing and
installing new equipment that has failed due to a manufacturer’s defect or due to workmanship (including
programming, configuration, etc.) faults. During the warranty period, E-Merge will respond within four (4)
hours to initial phone calls from the Service Authority and will provide personnel on-site within one (1)
business day if required to resolve the issue.
E-Merge’s warranty will be supplemented by the manufacturers’ extended warrantees as appropriate.
SCADA system hardware will be ordered with 3-year next business day on-site service. Software will be
purchased with the vendor’s customer support contracts which will be kept current by E-Merge throughout
Phase 4 of the project and will be extended for the year following completion. All on-going support
contracts will be transferred to the Service Authority at completion of the project.
E-Merge will install software vendor’s recommended patches and upgrades for the HMI software and
operating systems. We will review new patches and software to be installed from these vendors on a
monthly basis and keep all systems up to date with recommendations. Software updates will be done in
cooperation with the Service Authority’s SCADA personnel for purposes of training and knowledge
transfers during this work.
If there are any other warranty requirements or extended warranty periods that the Service Authority
would like us to consider, we are open to discussing these as well.
March 27, 2013
Prince William County Service Authority – RFP SA2113 34 Follow-up Questions and Answers
Question 11
Based on the staff resource categories provided in your proposal, what percentage of the overall
budget for a project like this would each job likely require?
Our team takes the approach of ensuring the right staff members are brought into the project at the right
time and in the right mix to optimize both the quality of our deliverables and the overall project cost.
Our Project Manager Jim Lester and Team Leads - Dean Foote and Padraic Gray are
professionals with decades of experience planning and implementing SCADA migrations for
operating water and wastewater utilities. They understand and have developed strategies to
mitigate the operating impact and potential risk that each SCADA transition represents.
To leverage our team’s experience, developing SCADA design and software standards, we will
use our team’s most senior and skilled staff members for standards development and Pilot
Project. Having defined, validated and refined the standards for the project, these people will lead
future project phases to provide team oversight, support, and standards compliance.
Our highly skilled but less experienced and lower cost staff members will play a much larger roll
on project phases that follow the Pilot Project where they will be applying the standards
developed during the Pilot.
The table below provides an initial estimate of labor classifications, phases and the % involvement with
respect to the tasks.
Table 6 - Initial Labor Estimate
Labor Classification Phase 1
Pilot Site Design
Phase 2
Pilot Sites Construction Configuration
Phase 3
Full System Design
Phase 4
Full System Construction Configuration
Project and Quality Management
Project Manager 70% 70% 70% 70%
Phase Leader (DF, JL) 10% 10% 10% 10%
Quality Assurance 20% 20% 20% 20%
Total 100% 100% 100% 100%
System Architect Preliminary Design and Detailed Design
Design Task Lead 80% 25%
Design Engineer 20% 75%
Total 100% 100%
System and Software Design, Development, Test, and Commission
System Task Lead 85% 25%
System Engineer 15% 75%
Total 100% 100%
Construction Management
Phase Leader/Project Manager 20% 20%
Construction Admin Staff 80% 80%
Total 100% 100%
March 27, 2013
Prince William County Service Authority – RFP SA2113 35 Follow-up Questions and Answers
Question 12
Please describe your field data collection process for preliminary and final design in detail.
Our team will make the best use of time available at field locations to efficiently collect data while
minimizing the number of visits. Our team will use experienced Engineers familiar with SCADA, control
and instrumentation equipment while performing the site visits. These Engineers will use a customized
Site Inventory Checklist while performing the field visits to ensure all aspects of the facility are inspected
and evaluated. The site visit will also include the use of descriptive digital photography to supplement
information collected on the check list. This is a method that members of our team have successfully used
on previous projects involving SCADA system designs and installations for multiple types of facilities. We
have included a sample of the Site Visit Checklist similar to what would be used for this project, included
as Appendix B.
A general checklist will be used to collect preliminary data and record the general arrangement and
condition of the existing equipment. The specific final check list will be developed based on the
information gathered during the different workshops once we have a firm understanding of the existing
equipment to be demolished and new equipment to be installed. The checklist will help ensure that the
Engineer is able to effectively evaluate and collect data for the different aspects of the work and
equipment required for the installation.
March 27, 2013
Prince William County Service Authority – RFP SA2113 36 Follow-up Questions and Answers
Question 13
Please describe your approach/philosophy on alarm management.
Our team will work with PWCSA to develop and implement a set of alarm management best practices
using the steps outlined below. We have often seen systems developed by other where the operators are
in information overload mode, and therefore ignore all alarms. Ensuring that alarms are meaningful and
that operators are not overwhelmed with nuisance alarms is accomplished by classifying alarms based on
criticality and implementing “smart alarming” strategies. Condition-based alarming (“smart alarming”)
adjusts alarm properties based on the mode of operation. For example, a low-flow alarm is not activated if
the supply pump is not running. We want to provide an alarm management system such that the different
consumers of alarms (operators, maintenance, etc.) take the alarms seriously and perform appropriate
actions. Outlined is a structured methodology that we have successfully implemented:
Table 7 - Structured Alarm Management Methodology
Step Description
Step 1 Develop a standardized approach for the development, institutionalization, and
maintenance of alarms throughout the entire SCADA system (i.e. Water and
Wastewater Operations). Some examples of topics to be reviewed are configuration
of alarm priorities to ensure faster response times to critical alarms, alarm areas to
ensure proper routing to personnel, and alarm security to ensure acknowledgement
by authorized personnel.
Step 2 Create a document that will be used a guideline during development,
institutionalization, and maintenance of the new SCADA system to ensure all alarms
comply with the philosophies set forth in Step 1.
Step 3 Implement strict security and change management policies to ensure that the SCADA
system alarm properties do not deviate from the philosophies set forth in Step 1. This
step should also include implementation of periodic system audits to ensure
compliance.
Step 4 Develop and implement real-time alarm management techniques to support all
operational scenarios. An example would be disabling a field device’s alarm state
based on a failed PLC input channel, and subsequently displaying a unique animation
on the HMI screen that is adjacent to the device value to provide visual feedback of
the faulty input.
Step 5 Implement long term SCADA system alarm control and maintenance tools and
procedures:
a. Alarm History data collection and performance benchmarking to determine
strengths and deficiencies.
b. Identify “Bad Actor” alarms within the SCADA system, where the term “Bad
Actor” refers to an alarm (or subset of alarms) that can be associated with
operator overload (e.g. nuisance alarms or alarm floods).
(Note: This approach is an adaption of the guidelines set forth under American Petroleum Institute
Recommended Practice 1167 (API RP 1167), which was used by E-Merge to create the Alarm Response
Management system put in place at Washington Gas to meet the requirements set forth under 49 CFR
Part 192. Even though the API RP 1167 guidelines were designed for Natural Gas Pipeline operators, the
approach is sound for all industries, including Water/Wastewater Utility operators. Other Alarm-Event
standards include ISA-S18 and EEMUA 191).
March 27, 2013
Prince William County Service Authority – RFP SA2113 37 Follow-up Questions and Answers
Question 14
Please describe your approach to reporting, in reference to translating the historical data
collected by the SCADA system into useful information. The SA is interested in how data is turned
into useful information, both with on-screen and printed reports. The response should cover the
offeror’s approach to determining stakeholders’ needs, and describe the data presentation
packages they typically utilize.
Our team follows a structured approach to report development which starts with the creation of a Report
Narrative. The Report Narrative serves the same purpose for report development that a Process Control
Narrative/Strategy serves for the development and testing of control system programming.
The Report Narrative describes the purpose and function of a Report (or Dashboard) in plain English as
well as in a format that enables a programmer to build and test the report. The Report Narrative
documents the report owner and controls; report purpose, distribution, and frequency; report description;
data sources, data elements; calculations, and exception handling. The following are included with each
Report Narrative as appendices: formatted report or dashboard for final presentation of report data; and
procedures and test forms for performing a Client Acceptance Test.
The steps that we follow in developing and validating reports are as follows:
Step 1 – Inventory Existing Reports: Inventory existing reports in an Excel or Access database and
identify report name, description, owner, and frequency. Collect and organize existing reports in a single
location. We will submit the Report Inventory to the Service Authority (SA) for your review.
Step 2 – List of Required Reports: Workshop or meeting with report stakeholders to validate the Report
Inventory and determine the following: which reports will be retained?, which reports need to be
modified?, and new reports?, report priority?. We will update the Report Inventory based on SA feedback
to create a list of required reports and re-submit.
Step 3 – Report Narratives: We will write report narratives for the highest priority reports by reviewing
existing reports (if available) and interviewing the identified report owners. Draft report narratives will be
submitted to the Service Authority for review and we will meet with report owners (if necessary for
clarification). Report Narratives will be finalized based on feedback from SA report owners.
Step 4 – Report Development Standard: Prior to developing the first reports, we will develop a Report
Development Standard that documents: how reports are to be executed and distributed, the standard
structure of reports, file and variable naming convention, and define re-useable, common functions and
procedures.
Step 5 – Develop, Test and Deploy: We will develop the highest priority report to validate the standard
developed in Step 4. The report will be bench tested using the test procedure and forms documented in
the narrative. Following successful completion of the bench test, the report will be deployed to site and a
Client Acceptance Test will be performed with the report owner.
Notes:
A. The SA’s Core SCADA team will have an active participation in all steps but especially steps 4 and 5.
We anticipate that the SA’s Core SCADA Team will write and test a number of reports, with the
assistance of our report developers, to ensure that they are familiar with the reporting standard and
can support report enhancement and development post implementation.
B. Step 5 will be repeated for all reports. However, following the completion of the first report we
anticipate that reports will be grouped (probably by owner) for development and testing.
C. Issues identified during testing will be resolved and the final report will be released for use by SA
March 27, 2013
Prince William County Service Authority – RFP SA2113 38 Follow-up Questions and Answers
staff. A Report Issues Log will be started during the first Client Acceptance Test and maintained for the
development of all reports. If report problems are identified post implementation these will be
recorded in the Issues Log for resolution.
D. The Report Standard will be updated as report development progresses to capture any revisions or
enhancements to the standard.
E. The final step for reach report will be updating the Report Narrative to reflect the as-built state of the
final report.
Data Presentation Packages:
Wonderware technology is tightly integrated with Microsoft on Operating System, Database, Framework
and Web Technology levels. Connectivity to multiple data sources including those listed above (and many
more) is standard. Below is a sample (not meant to be an all-inclusive list) of different database or
database connectivity options available. Wonderware Historian, OSI Pi, Access, Excel, Text File, CSV,
Tableau Data Extract, Aster Data nCluster, Cloudera Hadoop Hive, Firebird, Greenplum, IBM DB2, MS
Analysis Services, Powerpoint, MSSQL, MapR Hadoop Hive, MySQL, Netezza, OData, Oracle, Oracle
Essbase, ParAccel, PostgreSQL, Progress OpenEdge, SAP NetWeaver Business Warehouse, Sybase
IQ, Teradata, Vectorwise, Vertica, Windows Azure Marketplace DataMarket, Other Databases (ODBC)
For Reporting.
Wonderware Historian
Client
Wonderware Historian Client
provides rich data analysis
and reporting capabilities to
maximize the value of
information stored in the
Wonderware Historian
database. Wonderware
Historian Clients are
integrated with Microsoft
Office components to deliver
data-trend and numerical
data analysis using
Microsoft Excel,
comprehensive data
reporting using Microsoft
Word, and the capability to
publish real-time and
historical plant information
to the Web or company
intranet site using
Wonderware Information
Server. We have deployed
reporting for several
customers using the
Historian Client, especially
for trending purposes.
Figure 3 - Wonderware Historian Connectivity
March 27, 2013
Prince William County Service Authority – RFP SA2113 39 Follow-up Questions and Answers
Key capabilities of Wonderware Historian Clients include:
Real-time and historical data trends and reports
Integrate diverse HMI and ArchestrA namespaces within a single interface
Simplified data queries which understand your process and information needs
Integration with and support for Microsoft Office® via Excel® and Word® add-ins
Integration with ArchestrA System Platform components including Wonderware Historian and
Wonderware Information Server
Figure 4 - Trend Chart Created with Historian Client
Wonderware Historian Client may or may not be adequate for the SA’s reporting needs. Wonderware has
recently acquired a new product called Dream Report: http://dreamreport.net/en/dream-report/dream-
report-product.html. It has a graphical and intuitive report designer – and one can create new reports from
previously saved templates. Additionally, the product has a built in web portal - distributing and sharing
reports over the Internet/Intranet. Users can easily browse and display PDF reports from the current
project running or generate new reports on demand. E-Merge has not used this product – but it does
appear to be promising.
Other reporting packages that we have successfully deployed include:
Crystal Reports.
Customized reporting via MS SQL Server Reporting Services.
ASP.Net frontend with MS SQL Server backend.
March 27, 2013
Prince William County Service Authority – RFP SA2113 40 Follow-up Questions and Answers
VB.Net frontend with Access/MS SQL Server backend.
XL Reporter from SyTech, Inc.
MS Excel Reports.
Rockwell FactoryTalk VantagePoint.
March 27, 2013
Prince William County Service Authority – RFP SA2113 41 Follow-up Questions and Answers
Appendix A – Architectural Drawings
This page was labeled proprietary by E-Merge and has been redacted.
This page was labeled proprietary by E-Merge and has been redacted.
This page was labeled proprietary by E-Merge and has been redacted.
This page was labeled proprietary by E-Merge and has been redacted.
March 27, 2013
Prince William County Service Authority – RFP SA2113 42 Follow-up Questions and Answers
Appendix B – Sample Site Visit Checklist
Date/Time:________________ Site Visit Checklist RTU/PLC Location
Facility Name/Address: _____________________________ Type: _____________________ GPS Coords: _____________________________________ Elev: ______________________ Type of Ex. Controls: _______________________________________________________________ RTU/PLC Manf. Name/ Model or Number: ______________________________________________ Communications/Ports (used & available): ______________________________________________ Process Area or Location: ___________________________________________________________ Number of Physical I/O AIs: ________ AOs: ________ DIs: ________ DOs: ________ Estimate Used/Spare: AIs: ____/____ AOs: ____/____ DIs: ____/____ DOs: ____/____ Type and Number of PLC Modules Power Supply Type: ________________________________ Quantity: _______ Analog Input Card Type: ________________________________ Quantity: _______ Card Type: ________________________________ Quantity: _______ Analog Output Card Type: ________________________________ Quantity: _______ Card Type: ________________________________ Quantity: _______ Discrete Input Card Type: ________________________________ Quantity: _______ Card Type: ________________________________ Quantity: _______
Discrete Output Card Type: ________________________________ Quantity: _______ Card Type: ________________________________ Quantity: _______ Other (Indicate Function) Card Type: ________________________________ Quantity: _______ Rack Arrangement: Indicate location of PLC/ Power Supplies, I/O Modules and Spare slots:
Type of Enclosure(s) – NEMA Rating, material, paint, general condition/UL Certified: ______________________________________________________________________ Communications Method: WAN/LAN Details: ______________________________________________ Radio Details: ______________________________________________ Other Details: ______________________________________________ Control Panels / Equipment: UPS/Battery Backup (Type, Manufacturer, Model): ______________________________ Power Supply (type, manufacturer, model #): __________________________________ Surge/Lightning Protection (type, manuf., model #): _____________________________ Power Supply (type, manufacturer, model #): __________________________________ Environmental Issues (A/C, Corrosive Gases, Dust, etc.): ________________________ _______________________________________________________________________
Description of Process Equipment, Operations and Local Controls (Pumps, VFDs/RVSS, Motor Control, Number/Type of Motors, OIT, local controller, switches, readouts, tanks, etc.): ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ Instrumentation/Devices:
Level Sensor: Float Switches
Pressure Sensor: Pressure Switches
Flow Meter: Analyzers:
Security Devices: Power Monitor:
Generator: ATS:
Surge Protection: Intrinsically Safe Barriers::
Intrinsically Safe Relays:
Intrinsically Safe Barriers::
Other: Other:
Current Problems or Issues Overheating Notes: ________________________________________ Corrosion Notes: ________________________________________ Surge/Lightning Prot. Notes: ________________________________________ Hazardous Area Notes: ________________________________________ Installation Issues Enclosures Notes: ________________________________________ Instruments Notes: ________________________________________ UPS Notes: ________________________________________
Other Notes: ________________________________________ Equipment Failures Notes: ________________________________________ Expansion Capacity Notes: ___________________________________________________ Communications Notes: ___________________________________________________ Antennas/Cables/Masts Notes: ___________________________________________________ Terminations/Splices Notes: ___________________________________________________ Wire Labels Notes: ___________________________________________________ Security/Intrusion Notes: ___________________________________________________ Locking Panel Notes: ___________________________________________________ Lighting (Area, Enc.) Notes: ___________________________________________________ Other Notes: ___________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ Photo Checklist:
Enclosure Label: ___________ RTU/PLC Label: ___________ I/O Cards Label: ___________ Terminals Label: ___________ Power Supply Label: ____________
Modem Label: ____________ OIT/Display Label: ___________ Network Eq. Label: ___________ Building/Facility Label: ___________
Other Label: ___________
Generator Label: ___________
ATS Label: ___________ Other Label: ___________ MCC/VFDs Label: ___________