conceptual design of alternatives for the use of free ......• ozone as an intermediate oxidant...
TRANSCRIPT
COPYRIGHT
Conceptual Design the Use of Free Chlorine in the
Poughkeepsie’s Water Treatment
Poughkeepsie Joint Water
COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
F ina l
Conceptual Design of Alternatives for the Use of Free Chlorine in the
Distribution System Poughkeepsie’s Water Treatment
Poughkeepsie Joint Water Project
F ina l Repor t
of Alternatives for the Use of Free Chlorine in the
Distribution System for Poughkeepsie’s Water Treatment
Facility
Prepared for
Project Board
March 2012
Contents
Section Page
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL III COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
1 Introduction ...................................................................................................................................... 1-1
1.1 Project Background.......................................................................................................................... 1-1
1.2 Bench-Scale Testing Results ............................................................................................................ 1-1
2 Existing Conditions ............................................................................................................................ 2-1
2.1 Raw Water Quality ........................................................................................................................... 2-1
2.2 WTP Overview ................................................................................................................................. 2-2
2.2.1 Liquid Treatment Processes ............................................................................................... 2-2
2.3 Residuals Treatment Processes ....................................................................................................... 2-3
3 Alternatives for Disinfection By-Product Control ................................................................................ 3-1
3.1 Introduction ..................................................................................................................................... 3-1
3.1.1 Alternative 1 Chlorine Dioxide with Enhanced Coagulation Design ................................... 3-1
3.1.2 Alternative 2 Enhanced Coagulation with Intermediate Ozone Design ............................. 3-4
3.1.3 Alternative 3 MIEX Design .................................................................................................. 3-7
4 Residuals Impacts from DBP Control Alternatives ............................................................................... 4-1
4.1 Solids Generation............................................................................................................................. 4-1
4.2 Impact of Increased Solids Generation ............................................................................................ 4-1
4.3 MIEX Residuals ................................................................................................................................. 4-2
5 Cost Evaluation of Alternatives .......................................................................................................... 5-1
5.1 Introduction/Assumptions ............................................................................................................... 5-1
5.2 Capital Costs .................................................................................................................................... 5-2
5.3 Operating and Maintenance Costs .................................................................................................. 5-2
6 Recommendations and Implementation Plan ..................................................................................... 6-1
6.1 Assessment of Compliance Reliability ............................................................................................. 6-1
6.2 Phased Implementation .................................................................................................................. 6-2
6.3 Recommendations ........................................................................................................................... 6-4
Tables
2-1 Raw Water Quality
2-2 Residuals System Design
3-1 Alternative 1 – Basis of Design
3-2 Alternative 2A/2B Basis of Design
3-3 Alternative 3A/3B MIEX Basis of Design Table
4-1 Projected Solids
4-2 Thickener Capacity/Loading
4-3 Centrifuge Capacity/Loading
5-1 Capital Cost Markups Used for Estimates
5-2 Operation and Maintenance Cost Assumptions
5-3 Capital Costs
5-4 Operating and Net Present Cost
6-1 Phased Approach Costs
CONTENTS, CONTINUED
IV PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
Figures
2-1 Frequency plots for flow and turbidity
2-2 Frequency plots for flow and turbidity
2-3 PWTF Process Flow Diagram
3-1 Purate Process Schematic
3-2 Alternative 1 – Basis of Design
3-3 Alternative 2A/2B Site Plan
3-4 Alternative 3A/3B MIEX Site Plan
6-1 Total Trihalomethane (TTHM) Formation Estimate
6-2 Haloacetic Acid (HAA5) Formation Estimate
6-3 Flowchart of Phased Implementation Approach
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 1-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
SECTION 1
Introduction
%.% Project Background The Poughkeepsie Joint Water Project Board (PJWPB) supplies water to the City of Poughkeepsie, the Town of
Poughkeepsie, and the Village of Wappingers Falls. From 2004 through 2009, chloramines were utilized as the
disinfectant to maintain chlorine residual in the distribution system and to minimize disinfectant byproduct
formation. Due to unintended consequences and water quality issues in the distribution system with chloramines,
the PJWPB decided to return to free chlorine for the distribution system disinfectant in 2009. With the return to
free chlorine disinfection, reduction of chlorinated DBPs must to be addressed at the WTP by the reduction of
precursors, such as total organic carbon (TOC), for the PJWPB to be in compliance with the upcoming Stage 2
DBPR in October 2013. Sampling for the Stage 2 DBPR at the required sites in the distribution system must begin
in October 2012. For each of the alternatives developed, use of ultraviolet light will be maintained for primary
disinfection at the WTP.
The purpose of this report is to identify the estimated size, design criteria, budgetary capital, and additional
operating costs for alternatives for treatment process upgrades, on a conceptual level to enable comparison of
alternatives. The PJWPB can use this report to make an informed decision on the treatment processes to install to
continue to maintain free chlorine disinfection while meeting the upcoming Stage 2 DBPR.
%.' Bench-Scale Testing Results Bench scale testing in the summer 2010 (September) and spring of 2011 (May) was completed to assess multiple
treatment improvement options, including:
- Enhanced Coagulation with Ferric Chloride, Alum, and Polyaluminum chloride
- Oxidation using chlorine dioxide and ozone
- Organics removal using magnetic ion exchange (MIEX)
These processes were tested alone or in conjunction with one another to assess DBP formation potential at
various detention times.
The processes identified that could allow the PJWPB to meet the Stage 1 and Stage 2 DBP regulations in the future
with free chlorine as the distribution disinfectant include:
• Chlorine dioxide as a pre-oxidant with enhanced coagulation
• Ozone as an intermediate oxidant after enhanced coagulation and clarification
• MIEX applied to the raw water ahead of the current treatment units without changing coagulation.
These treatment processes are the basis of this conceptual design evaluation in the sections below. Details of the
bench scale evaluation and results can be found in the reports titled “Treatment Alternatives for Reducing
Disinfection Byproducts, Dec 2010 and September 2011”.
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 2-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
SECTION 2
Existing Conditions
'.% Raw Water Quality
Raw water values from 2006 to 2010 were used to develop a raw water profile to be used for this design. For
plant flow, turbidity, pH, alkalinity, and DOC, histograms with cumulative frequency plots were developed. These
graphs were used to determine the sensitivity of the data and to help select the proper maximum and design
conditions. Figures 2-1 and 2-2 demonstrate the frequency plots for flow and turbidity.
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
20
40
60
80
100
120
140
160
180
200
25 50 75 100 125 150 175 200 225 250 275 300
Fre
qu
en
cy
Turbidity (NTU)
Frequency
Cumulative %
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
50
100
150
200
250
6 6 7 9 10 11 12 13 14 15 16 17 18 More
Fre
qu
en
cy
Raw Water Flow (MGD)
Frequency
Cumulative %
FIGURE 2-1 Frequency Plot For Influent Flow
FIGURE 2-2 Frequency Plot For Influent Turbidity
EXISTING CONDITIONS
2-2 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
Table 2-1 presents a summary of the raw water quality used in this investigation. This water quality data set was
used to establish values for chemical doses and residuals quantities in the conceptual design discussed later in this
report.
TABLE 2-1
Raw Water Quality
April 2006 to October 2010
# of Data
points Average
10th
Percentile
90th
Percentile
95th
Percentile
99th
Percentile
Standard
Deviation
Raw Water (MGD) 699 9.3 7.5 11.0 11.3 12.6 1.44
Turbidity NTU 549 49.4 13.2 96.3 120.0 217.8 41.5
Temp C 518 14.9 2.2 25.5 26.2 27.2 8.6
pH: 551 7.65 7.45 7.85 7.91 8.03 0.18
Alkalinity (mg/L): 537 63.6 51.2 74.6 76.9 79.0 9.1
Calcium (mg/L): 528 26.5 21.2 32.6 35.4 41.8 4.9
Hardness (mg/L): 527 81.1 65.6 97.9 101.0 112.4 12.8
UV 254: 542 0.13 0.10 0.17 0.18 0.23 0.05
TOC (mg/L): 517 4.18 3.02 5.57 6.35 8.21 1.44
DOC (mg/L): 513 3.77 2.90 4.80 5.32 6.09 0.87
Fe (mg/L) 49 0.07 0.01 0.10 0.18 0.66 0.13
Mn (mg/L) 33 0.01 0.003 0.011 0.012 0.014 0.003
Bromide (ug/L) 228 6.8 N/A N/A 19.4 N/A N/A
Note: Percentile denotes the value at which X% of valves are below that number.
Based on the analysis presented above, the minimum flow was considered as the 10th percentile flow, and the
peak was assumed as 99th percentile flow. This number is below the rated plant flow of 19.3 MGD. For
development of chemical doses and solids generated, the 90th percentile turbidity and Dissolved Organic Carbon
were used along with the following flows:
• Minimum flow of 5.5 mgd
• Average flow of 9.3 mgd
• Peak flow of 12.6 mgd
• Maximum flow of 19.3 mgd
'.' WTP Overview
The Poughkeepsie Water Treatment Facility (PWTF) is a conventional WTP that was last upgraded in 2001 to meet
new regulations and water quality goals. A description of the liquid unit processes and solids unit processes are
detailed below. Figure 2-3 shows the overall PWTF process flow diagram.
'.'.% Liquid Treatment Processes
In the liquid treatment process, raw water is pumped from the Hudson River. At the intake, potassium
permanganate is added for manganese oxidation. At the rapid mix tank, seasonal carbon is added. Also at the
rapid mix tank, polyaluminum chloride and a flocculation/ sedimentation polymer are added. Following Rapid mix,
flow is directed to three (3) solids contact clarifiers. Effluent from the contact clarifiers flows into rectangular
sedimentation basins for additional settling time.
EXISTING CONDITIONS
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 2-3 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
Chlorine is added to the settled water upstream of the filters. There are six (6) filters, dual media sand/anthracite
design. Individual filter effluent is disinfected utilizing ultraviolet (UV) disinfection. The individual filter effluent is
combined into a single pipe and flows to a clearwell to backwash supply water, and to the equalization chamber
for pumping via high lift pumps to the distribution system. Prior to pumping, phosphoric acid, fluoride, and pH
adjustment (caustic) is added.
'.1 Residuals Treatment Processes
The Alum Sludge Treatment Facility (ASTF) provides for dewatering and disposal of solids generated at the water
treatment facility. The treatment process is depicted in Figure 2-3 and includes:
- Waste Backwash Equalization
- Waste Backwash Treatment with Plate Settlers
- Gravity Thickening for Settled Solids
- Thickened Sludge Storage Tank
- Centrifuges for Dewatering
Dewatered solids are taken off-site for landfill disposal. Supernate from the waste backwash treatment system is
recycled to the head of the plant upstream of rapid mix. Other liquid flow streams, such as the gravity thickener
supernate, and the centrate from dewatering, are directed back to the waste backwash equalization tank. Table
2-2 lists the design basis for each of the processes.
TABLE 2-2 Residuals System Design
Unit Process Design Criteria Notes
Backwash Equalization Tank 270,000 gallons
Clarifier Sludge Pumps Three, each at 350 gpm capacity
Plate Settler Feed Pumps Three, each at 200 gpm
Plate Settlers (waste backwash treatment) Two inclined plate settlers; 400 gpd/sf
loading rate each
Settled Sludge Pumps from BW Treatment Two @ 80 gpm each
Sludge Thickener One, 2500 lbs/day dry solids 1995 design memo
Sludge Thickener Underflow Pumps Two @ 80 gpm capacity each
Thickened Sludge Storage Tank 84,000 gallons
Centrifuge Feed Pumps Two @ 20 gpm each
Centrifuge Two, 5,000 lb/day at 3.5% inlet solids Units over 20 years old, backdrives replaced
in 2001. 1995 design memo information.
EXISTING CONDITIONS
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 2-4 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 2-3 PWTF Process Flow Diagram
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
SECTION 3
Alternatives for Disinfection By-Product Control
1.% Introduction Several alternatives were developed as a part of this study, based upon the results of previous bench-scale
testing. The design parameters developed for these alternatives will be discussed in this section. The alternatives
include:
• Alternative 1- Chlorine Dioxide: Preoxidation with chlorine dioxide; enhanced coagulation with alum and
sulfuric acid
• Alternative 2A – Ozone Enhanced Coagulation: with alum and sulfuric acid; intermediate ozone
• Alternative 2B – Ozone Enhanced Coagulation: with alum and CO2; intermediate ozone
• Alternative 3A – MIEX with Alum: pretreatment with alum coagulation; MIEX at 600 Bed Volumes
• Alternative 3B – MIEX with Alum: pretreatment with reduced alum coagulant dose, MIEX at 1000 Bed
Volumes
For each of the alternatives above, conceptual level footprint requirements were developed. These footprints all
included re-use of existing facilities/areas to maximize plant space when applicable. Location sketches were
developed for each alternative and the points of interconnection for new processes were identified.
1.%.% Alternative % Chlorine Dioxide with Enhanced Coagulation Alternative 1 includes enhanced coagulation with alum followed by organics oxidation by chlorine dioxide gas. In
order to optimize organics removal, the pH needs to be depressed. In Alternative 1, sulfuric acid will be used to
depress pH. Since sulfuric acid is also a component in the on-site generation of chlorine dioxide, carbon dioxide
gas was not evaluated for pH depression.
Currently, the plant has approximately 15,200 gallons of coagulant storage. In order to have thirty days of
storage at average flow 9.3 MGD and average alum coagulant dose of 60 mg/L, 25,800 gallons of storage are
required for Alternative 1. Since this exceeds the current coagulant storage, new storage facilities will need to be
constructed. Additionally, new chemical metering pumps and a day tank
are required.
Chlorine dioxide is generated using sulfuric acid and Purate®. Purate® is a
blended chemical consisting of approximately 40% Sodium Chlorate and
approximately 7.5% Hydrogen Peroxide. When Purate® and sulfuric acid
are combined, salt, chlorine dioxide, oxygen and water are produced. The
chlorine dioxide system will consist of 300 gallon Purate® storage totes, a
sulfuric acid storage tank, and a chlorine dioxide generator, an educator,
and a booster pump. The educator and booster pump will allow for the
chlorine dioxide gas to be dosed into a liquid stream.
The Purate® storage area and the chlorine dioxide generation system will
be installed in the existing chemical building. Since the existing
coagulation tanks will be replaced with a new alum storage system and the existing fluosilicic tank is no longer in
use- the existing PACL and Fluosilicic Acid area will be converted into Purate® storage and chlorine dioxide
generation area.
Sulfuric acid will be required for pH adjustment and for chlorine dioxide generation. One tank will be provided for
acid storage. This tank will be sized for average dose and flow required for pH adjustment and for the chlorine
dioxide generation. The doses required were determined using a WaterPro model based on raw water conditions.
The maximum dose is to be used for conditions where alkalinity and pH in the raw water are high. The average
dose is to be used when raw water pH and alkalinity are average. The sulfuric acid dose will depress the pH to 6.2
FIGURE 3-1 Purate Process Schematic
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
3-2 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
for optimal organics removal with alum. During time of low raw water pH and alkalinity, no sulfuric acid is
required; the pH reduction due to alum addition alone will drop the pH to 6.2. The new sulfuric acid tank will
replace the existing ammonia storage tank in the chemical storage area.
Table 3-1 summarizes the design criteria for Alternative 1. Figure 3-2 shows the proposed site plan for this
alternative.
TABLE 3-1
Alternative 1- Chlorine Dioxide with Enhanced Coagulation - Basis of Design
Parameter Value
Plant Flow (min/ avg/ max) 5.50 MGD/ 9.3 MGD/ 19.3 MGD
Alum Dose (avg/ max) 60 mg/L/ 100 mg/L
Bulk Alum Storage Required 25,800 gallons
Bulk Alum Tank Number and Size 3 Tanks. 10’ Diameter, 18’ Height
Alum Day Tanks 1 Tank. 7’ Diameter, 14’ Height
Chlorine Dioxide System Purate® based system, 10 lb/hr maximum capacity
Sulfuric Acid for CLO2 Design Feed Rate 2.50 gph
Purate® Feed Design Rate 2.41 gph
pH Control Sulfuric Acid Dose (min/ avg/ max) 0 mg/L / 6.5 mg/L /15 mg/L
Number of Sulfuric Acid Feed Pumps 2 (1 duty and 1 standby)
Bulk Sulfuric Acid Provided 3,000 gallons (sized for one bulk delivery plus 10%)
Bulk Sulfuric Acid Tank Number and Size 1 Tank. 9’ Diameter, 8’ Height
Sulfuric Acid Day Tanks 1 Tank. 3’ Diameter, 6’ Height
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-3 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 3-2 Alternative 1-Chlorine Dioxide with Enhanced Coaguation Site Plan
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-4 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
1.%.' Alternative ' Enhanced Coagulation with Intermediate Ozone
Alternative 2 includes enhanced coagulation with alum followed by ozonation for organics removal. As in
Alternative 1, the pH will need to be depressed for organics removal. Two different sub-alternatives were
evaluated for pH depression:
• Alt 2A – Ozone Enhanced Coagulation: with alum and sulfuric acid; intermediate ozone
• Alt 2B – Ozone Enhanced Coagulation: with alum and CO2; intermediate ozone
Alternative 2A will utilize the same coagulation and sulfuric acid system as described above for Alternative 1. In
Alternative 2B, carbon dioxide is used for pH adjustment. Carbon dioxide consumes less alkalinity than sulfuric
acid. At times of high raw water alkalinity and pH, conditioning with sulfuric acid will result in a settled water
alkalinity 36 mg/L. With carbon dioxide, settled water alkalinity would be 49 mg/L.
In Alternative 2 A/B, clarified water will be ozonated. By adding ozone to the water, the organic material in the
water will be oxidized. The new ozone system will require ozone generation, liquid ozone storage, ozone
destruction, and an ozone contact basin.
The organics will be oxidized into assimilable organic carbon (AOC). AOC can be easily removed by biologically
activated filters (BAF). If AOC is not removed, it will lead to biological instability in the distribution system. BAF is
achieved by removing the pre-chlorine feed to the filters. Once the chlorine feed is removed, naturally occurring
biologic growth will develop and the organisms will consume the AOC.
Table 3-2 summarizes the design criteria for Alternative 2A/2B. Figure 3-3 shows the proposed site plan for this
alternative.
TABLE 3-2
Alternative 2A/2B- Enhanced Coagulation with Intermediate Ozone - Basis of Design
Parameter Value
Plant Flow (min/ avg/ max) 5.50 MGD/ 9.3 MGD/ 19.3 MGD
Alum Dose (avg/ max) 60 mg/L/ 100 mg/L
Bulk Alum Storage Required 25,800 gallons
Bulk Alum Tank Number and Size 3 Tanks. 10’ Diameter, 18’ Height
Alum Day Tanks 1 Tank. 7’ Diameter, 14’ Height
Applied Ozone Dose (avg/max) 1.0 mg/L/1.5 mg/L
Ozone Generator 240 lbs/day capacity, 1 duty, 1 standby
Ozone Contact Time 10 minutes
LOX Tank Vertical Tank, 9’ tall, 8’ diameter
LOX Vaporizers 1 duty, 1 standby. 24 sf footprint
Ozone Destructors 1 duty, 1 standby
Alternative 2A
pH Control Sulfuric Acid Dose (min/ avg/ max) 0 mg/L / 6.5 mg/L / 15 mg/L
Bulk Sulfuric Acid Provided 3,000 gallons (sized for one bulk delivery plus 10%)
Bulk Sulfuric Acid Tank Number and Size 1 Tank. 9’ Diameter, 8’ Height
Sulfuric Acid Day Tanks 1 Tank. 3’ Diameter, 6’ Height
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
3-5 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 3-2
Alternative 2A/2B- Enhanced Coagulation with Intermediate Ozone - Basis of Design
Alternative 2B
pH Control Carbon Dioxide Dose (min/ avg/ max) 0 mg/L / 8.0 mg/L / 30 mg/L
Feed System Gaseous into sidestream flow to feed location
Storage Size 14 Tons, horizontal tank
Feed Rate Maximum 200 lbs/hr
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-6 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 3-3 Alternative 2A/2B – Enhanced Coagulation with Intermediate Ozone - Site Plan
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-7 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
1.%.1 Alternative 1 MIEX
Alternative 3 include MIEX ion-exchange resin for organics removal followed by alum coagulation for turbidity
removal. The MIEX process is a magnetic ion exchange resign specially formulated for organics removal. Prior to
coagulation, the raw water will enter a basin where it will be mixed with the MIEX resin. The resin will remove the
organics and be separated from the main process flow. Once separated, the resin will be regenerated using a salt
solution. The regenerated resin will then be recalculated back to the main process stream.
The waste stream for the MIEX process is the organics laden brine stream that results from the regeneration of
the resin. The removal of organics will be based on the duration of time the resin has with the raw water with
varies inversely with Bed Volumes, or BV. The lower the BV’s the higher organics removal and the higher quantity
of brine produced. A small amount of resin will be carried over into the flocculation and clarification process, and
this resin will need to be replaced over time.
Since the organics will be removed prior to coagulation, flocculation, and clarification, the coagulation system can
be designed for turbidity removal. Thus, downward pH adjustment and higher coagulant doses for enhanced
coagulation are not required with Alternative 3. Lower coagulant doses can be used, resulting in fewer residuals
being created. Also, no new coagulant facilities will be required and the current PACL tanks and pumps can be
reused.
If MIEX is selected, then piloting of the process is required to determine precise organics removal projections and
operating conditions. The basis of design used for costing purposes is presented below.
Two sub-alternatives were evaluated:
• Alt 3A – MIEX with Alum: pretreatment with alum coagulation; MIEX at 600 Bed Volumes
• Alt 3B – MIEX with Alum: pretreatment with reduced alum coagulant dose, MIEX at 1000 Bed Volumes
Table 3-3 summarizes the design criteria for Alternative 3A/3B. Figure 3-4 shows the proposed site plan for this
alternative.
TABLE 3-3
Alternative 3A/3B - MIEX Basis of Design Table
Parameter Value
Plant Flow (min/avg/ max) 5.50 MGD/ 9.3 MGD/ 19.3 MGD
Average Alum Dose
Alternative 3A 40 mg/L
Alternative 3B 25 mg/L
Bed volumes of Resin Service in Contactor
Alternative 3A 1000 BV
Alternative 3B 600 BV
Number and Size of MIEX Contactors Two at 31ft x 31ft
Upflow Clarifier Rate 8 gpm/sf
High Rate Contractor Resin Concentration 200 mg/L
Loss of Resin 2 gallons per MG treated
Resin Contact Time 6 minutes
Tank Facility Footprint (includes salt storage) 35 ft x 65 ft
Resin Recirculation Tank Volume 4 tanks at 2,380 Gallons
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
3-8 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 3-3
Alternative 3A/3B - MIEX Basis of Design Table
Parameter Value
Virgin Resin Tank Volume 1 tank at 560 Gallons
Salt Saturator Volume 1 tank at 11,650 Gallons
Brine Tank Volume 1 tank at 5,000 Gallons
ALTERNATIVES FOR DISINFECTION BY-PRODUCT CONTROL
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 3-9 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 3-4 Alternative 3A/3B - MIEX Site Plan
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 4-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
SECTION 4
Residuals Impacts from DBP Control Alternatives
Each of the DBP control options presented in Section 3 will have an impact on the type of residuals produced, the
amount of residuals produced, and thereby affect the capacity of the residuals systems (Section 2) and may
require capital or operating improvements to address limitations. The sections below discuss the details of these
additional impacts.
5.% Solids Generation
Existing plant production data, raw water quality information, and plant records were used to examine the
existing solids treatment facilities and their current capacity with PACL as the coagulant. Future solids generation
utilized this same plant data but used the coagulant doses during bench testing to achieve the DBP reduction
results. Table 4-1 is the resultant average and peak dry solids generated per day under various alternatives. For
most alternatives more solids will need to be treated and handled than under current conditions.
TABLE 4-1 Projected Solids
Alternative Average Coagulant Dose
(mg/L)
Average Solids (dry lbs/day) Peak Solids (dry lbs/day)
Chlorine Dioxide with Alum EC 60 6785 17,032
Intermediate Ozone with Alum EC 60 6785 17,032
MIEX at 1000 BV, 40 ppm Alum 40 6103 15,414
MIEX at 600 BV, 25 ppm alum 25 5591 14,720
2010 PACL Coagulation 55.7 5443 15,387
2011 PACL Coagulation 65 6099 15,246
PACL with Ozone 100 6832 15,813
2010 PACL Coagulation 55.7 5443 15,387
5.' Impact of Increased Solids Generation
The existing plate settler system is not affected by the increase in solids generation from coagulation.
Under current and most future conditions, the existing gravity thickener is adequate for handling the projected
solids generated (Table 4-2). Currently the plant views the thickener as one of the potential bottlenecks in the
residuals handling system. The projected loading rates compared to typical design parameters are within
acceptable ranges. To run at higher solids or hydraulic loading rates than currently practiced, more optimization
and polymer usage may be required.
RESIDUALS IMPACTS FROM DBP CONTROL ALTERNATIVES
4-2 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 4-2
Thickener Capacity/Loading
Dry Solids (lbs/day)
Thickening (solids loading -
lbs/day/sqft)
Thickening (Hydraulic Loading -
gpm/sqft)
Design Capacity 2,500 1.6 -
Typical Design Values - 5 to 10 0.5 - 1.0
Solids Production (w/PACl) in 2010 5,443 3.4 0.28
Peak Day in 2010 13,375 8.4 0.64
Peak Week in 2010 11,971 7.5 0.38
Average Day at 19.3 MGD 12,252 7.7 0.58
Peak Day In Future (max) 17,000 10.7 0.80 (estimated)
For the centrifuges, the system appears to be undersized based on current and future solids generation as shown
in Table 4-3. The values shown in red are above the solids loading rate for a single unit. The original design of the
system was for a single centrifuge to be run during average conditions, and two only during peak conditions, and
only for one or two shifts per day. Recent operational experience at the PWTF demonstrated that the centrifuges
are undersized when both units had to be run on all three shifts to process the solids being generated in the plant.
Additionally, these units are over 30 years old and have reached the end of their useful life.
TABLE 4-3
Centrifuge Capacity/Loading
Dry
Solids
(lbs/day)
Throughput (lbs/hr)
based on 1 shift 7 days
week, single centrifuge
Throughput (lbs/hr) based on
two shifts, 7 days/week, single
centrifuge
Throughput (lbs/hr) based on
three shifts, 7 days/week, single
centrifuge
Current Design Capacity 5,000 625
Solids Production
(w/PACl) in 2010 5,443 778 363 247
Peak Day in 2010 13,375 1,911 892 608
Peak Week in 2010 11,971 1,710 798 544
Average Day at 19.3
MGD 16,136 2,305 1,076 733
5.1 MIEX Residuals
The MIEX process utilizes an ion exchange process inside of a mixed reactor. Periodically after a certain amount
of usage, or bed volumes, the media needs to be regenerated to renew its exchange capacity. Typically, sodium
chloride (brine) is utilized as the regenerant. The waste brine contains TDS, organic compounds, and other
contaminants adsorbed by the media. Alternately, sodium bicarbonate can be utilized to reduce the chloride
loading in the waste stream.
The brine residuals require disposal, this is typically accomplished directly via sewer to a publically owned
treatment works (POTW). Other options include additional brine treatment on-site for volume minimization, and
then either to the POTW or trucked for disposal.
RESIDUALS IMPACTS FROM DBP CONTROL ALTERNATIVES
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 4-3 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
For the PWTF to send to the sewer would require equalization and a small lift station to direct flow to the sewer
on the Marist University campus. Additionally, approval would be required from the City of Poughkeepsie’s
WWTP. Preliminary discussions with the City have indicated they would be hesitant to accept that flow.
To complete volume reduction would entail installing new equipment that would cost $500,000 to $1,000,000 in
capital costs. Additionally, some new solids would be added to the existing plant residuals, at approximately 20 to
40 lbs per million gallons of water produced. This concept was not pursued further in this study.
The estimated volumes of brine waste:
- 600 Bed Volumes – 3225 gallons/day
- 1000 Bed Volumes – 5100 gallons/day
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 5-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
Section 5
Cost Evaluation of Alternatives
7.% Introduction/Assumptions
The CH2M HILL Parametric Cost Estimating System (CPES) was used for estimating the costs of the various
alternatives. CPES is a proprietary conceptual design and cost estimating tool that generates quick, accurate, and
detailed cost estimates at the conceptual stage of a water treatment project
CPES construction and life cycle (O&M) cost models were developed for each of the alternatives and sub-
alternatives presented in Section 3 of this report. The cost estimates were prepared using a variety of cost data
including vender quotation, unit cost line items, and parametric estimating tools. The cost estimates are
considered to be consistent with Class 4 estimates as defined by the Estimate Classification system of the
American Association of the Advancement of Cost Engineering International (AACE International), formerly known
as the American Association of Cost Engineers (AACE). The estimates were developed without detailed
engineering data and are considered approximate. Class 4 estimates are normally expected to be accurate within
minus 30 percent to plus 50 percent. This range implies that there is a high probability that the final project cost
will fall within the range.
A contingency has been included in these cost estimates as a provision for unforeseeable, additional costs within
the general bounds of the project scope; particularly where experience has shown that unforeseeable costs are
likely to occur. The contingency is used as a means to reduce the risk of possible cost overruns.
Table 5-1 lists the markups applied within the capital cost model. Table 5-2 lists the assumptions for operating
costs used in the cost development.
TABLE 5-1 Capital Cost Markups Used for Estimates
Item Value
Overhead 10%
Profit 5%
Mobilization/Bond/Insurance 5%
Contingency 30%
Local Adjustment Factor to Poughkeepsie NY 114
Escalation to Midpoint of Construction 1.10
In addition to the global markups provided above, the additional project costs were included in the capital cost
summary:
• Pilot Testing (estimated based on whether testing would be required or not, and expected effort to
complete)
• Engineering Design and SDC at 15% of construction costs
• Startup at 2% of total construction costs
COST EVALUATION OF ALTERNATIVES
5-2 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 5-2 Operation and Maintenance Cost Assumptions
Net Present Cost (NPC) Calculation Inputs
Annual Discount Rate (i) 3%
Number of Years (n) 20 years
Power Costs
Power Cost $0.062/kWhr
Facility Electrical 2 Watts/square foot of building area
Chemical Costs
Alum $390/ton
PACL $304/ton
Sulfuric Acid $271/ton
Carbon Dioxide $640/ton
Purate $1,900/ton
Liquid Oxygen (LOX) $125.67/ton
Salt $140/ton
MIEX Resin $60.57/ton
Residuals Disposal Costs
Solids Disposal $72/dry ton
Brine Disposal (via tanker truck) $0.1495/gallon
Brine Disposal (via sewer) $0.35/1000 gallons
Repair, Maintenance, and Contingency 20% of subtotal of O&M costs
7.' Capital Costs Table 5-3 presents a breakdown of capital costs by each alternative by treatment systems required in that
alternative.
7.1 Operating and Maintenance Costs
The O&M costs were based on annual average flow rate of 9.3 mgd. Consumption is based on average flow
condition. The O&M costs presented are the additional O&M costs above the current facility O&M costs that
would occur with the installation of the new processes, chemical addition, and residuals production.
In evaluating MIEX (Alternatives 3A/3B) it became apparent that direct discharge of brine waste to the sewer may
be difficult. Therefore, within the O&M component we have calculated the expected cost for hauling of liquid
residuals to a nearby wastewater plant that would accept the brine from tanker trucks. This cost, inclusive of
transportation and disposal, was $0.165/gallon based upon current liquid hauling costs paid at the PWTF. If sewer
disposal was permissible, then a lower disposal cost could be realized, shown as alternative 3C in Table 5-4.
COST EVALUATION OF ALTERNATIVES
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 5-3 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 5-3
Estimated Capital Costs of Alternatives
Individual Unit process Alternative 1A Alternative 2A Alternative 2B Alternative 3A Alternative 3B
Alum Storage and Feed $ 1,480,000 $ 1,480,000 $ 1,480,000 $ 100,000 $ 100,000
Chlorine Dioxide System $ 350,000 - - - -
New Sulfuric Acid System $ 190,000 $ 190,000 - - -
Carbon Dioxide System - - $ 530,000 - -
Ozone System and Contactor - $ 9,860,000 $ 9,860,000 - -
MIEX System - - - $ 17,320,000 $ 17,320,000
Pipelines $ 190,000 $ 380,000 $ 380,000 $ 1,712,599 $ 1,712,599
Centrifuges $ 1,810,000 $ 1,810,000 $ 1,810,000 $ 1,810,000 $ 1,810,000
Overall Construction Cost $ 4,020,000 $ 13,720,000 $ 14,060,000 $ 20,938,880 $ 20,938,880
Other Project Costs
Pilot Testing $ 300,000 $ 300,000 $ 500,000 $ 500,000
Engineering Design and SDCs (15%) $ 603,000 $ 2,058,000 $ 2,109,000 $ 3,140,832 $ 3,140,832
Startup (2%) $ 80,400 $ 274,400 $ 281,200 $ 418,778 $ 418,778
Total Project Cost $ 4,703,400 $ 16,352,400 $ 16,750,200 $ 24,998,490 $ 24,998,490
COST EVALUATION OF ALTERNATIVES
5-4 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 5-4
Operating and Net Present Cost of Alternatives
Alt Description Project Costs Additional O&M
Costs
NPC O&M Costs Total NPC Costs
1 Chlorine Dioxide with EC $4,704,000 $331,000 $4,924,000 $9,627,00
2A Ozone with EC with Sulfuric Acid $16,352,000 $222,000 $3,303,000 $19,655,000
2B Ozone with EC with CO2 $16,750,000 $279,000 $4,151,000 $20,901,000
3A MIEX – 1000 BV, truck disposal $24,999,000 $664,000 $9,879,000 $34,877,000
3B MIEX – 600 BV, truck disposal $24,999,000 $709,000 $10,548,000 $35,546,000
3C MIEX – 600 BV, sewer disposal $24,999,000 $376,000 $5,594,000 $30,592,000
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 6-1 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
SECTION 6
Recommendations and Implementation Plan
9.% Assessment of Compliance Reliability
Based on the information presented section 5, it would appear that chlorine dioxide with enhanced coagulation
would be the least expensive way to achieve DBP compliance. However, the results received during bench-scale
testing show there is some potential risk of not being able to achieve DBP compliance with this alternative. Figure
6-1 is the Total Trihalomethane (TTHM) formation from previous bench testing and Figure 6-2 is the Haloacetic
Acid (HAA5) formation. Each treatment process tested is shown for formation at 5, 7 and 10 days detention time.
From the figures below, we can see that chlorine dioxide with enhanced coagulation is up near the safety factor
(80% of the maximum contaminant level) for TTHMs and in the safety factor, approaching the actual MCL for
HAA5s. This safety factor is present to acknowledge the bench tests are just one snapshot in time, and there is
some experimental error associated with laboratory analysis of DBPs. This does not mean that chlorine dioxide
with enhanced coagulation could NOT meet DBP requirements, but that there is more risk associated with this
option than would be with Alternative 2, ozone with enhanced coagulation. Therefore if the PJWPB wanted to
ensure compliance for Stage 2 DBPR, the option that would need to be implemented in Alternative 2.
FIGURE 6-1 Total Trihalomethane (TTHM) Formation Estimates
RECOMMENDATIONS AND IMPLEMENTATION PLAN
6-2 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 6-2 Haloacetic Acid (HAA5) Formation Estimates
9.' Phased Implementation
Understanding that the PJWPB may have limited capital to spend initially on this project, we have developed a
path forward for the PJWPB that will allow for continued reduction of DBP concentrations while assessing the
performance of different options. This approach will allow the PJWPB to judiciously utilize the capital dollars
available and not “waste” capital dollars on solutions that will not work the WTF and distribution systems towards
compliance with Stage 2 DBPR. The major steps of this approach include:
1) Implement Residuals Improvements to remove this bottleneck from the existing system and prepare for
enhanced coagulation
2) Implement enhanced coagulation first and evaluate system data for one full year. Implementing
enhanced coagulation is required for either Alternative 1 or 2 so this is work that would need to be
completed regardless of the final chose direction.
3) Develop a combined hydraulic model of the PJWPB distribution system to evaluate water age and
methods to reduce water age. Reductions in water age may reduce DBP formation at end points of the
system.
4) After initial results, make decision on whether to implement chlorine dioxide or intermediate ozone. This
approach has risk that the system will not be in compliance with Stage 2 DBPR by October 2013 and
therefore would require a 2-year extension from New York State Department of Health (NYSDOH) for
capital improvements.
The approach is demonstrated in a flow chart in Figure 6-3. Table 6-1 is a breakdown of the anticipated costs to
implement this phased approach.
RECOMMENDATIONS AND IMPLEMENTATION PLAN
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 6-3 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
FIGURE 6-3 Flowchart of Phased Implementation Approach
RECOMMENDATIONS AND IMPLEMENTATION PLAN
6-4 PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
TABLE 6-1
Phased Approach Estimated Costs ($M)
Cost Item pH adjustment Chlorine Dioxide Ozone MIEX
H2SO4 CO2 H2SO4 CO2 H2SO4 CO2
Centrifuges $ 1.81 $ 1.81 $ 1.81 $ 1.81 $ 1.81 $ 1.81 $ 1.81
pH adjustment $ 0.19 $ 0.53 $ 0.19 $ 0.53 $ 0.19 $ 0.53
Chemical Feed
Modifications $ 0.10 $ 0.10 $ 0.10
Chlorine Dioxide $ 0.35 $ 0.35
New Alum Facility $ 1.48 $ 1.48 $ 1.48 $ 1.48
MIEX $ 17.32
Ozone $ 9.86 $ 9.86
Pipelines $ 0.19 $ 0.19 $ 0.38 $ 0.38 $ 1.71
Construction Total $ 0.10 $ 2.44 $ 4.02 $ 4.36 $ 13.72 $ 14.06 $ 20.94
Pilot Testing $ 0.30 $ 0.30 $ 0.50
Engineering, SDCs
(15%) $ 0.32 $ 0.37 $ 0.60 $ 0.65 $ 2.06 $ 2.11 $ 3.14
Startup ( 2%) $ 0.04 $ 0.05 $ 0.08 $ 0.09 $ 0.27 $ 0.28 $ 0.42
Project Total $ 2.46 $ 2.85 $ 4.70 $ 5.10 $ 16.35 $ 16.75 $ 25.00
Costs shown in Millions
9.1 Recommendations
The following conclusions and recommendations can be drawn from this report:
1) Pursuit of MIEX as an option for DBP compliance is more expensive on both a capital and life cycle cost
basis than those of chlorine dioxide and ozone. MIEX should only be considered further if there is a need
for a higher quality water for industrial users (i.e. IBM)
2) Ozone with enhanced coagulation is the least expensive option that will reliability allow PJWPB to achieve
compliance with the Stage 2 DBPR using free chlorine as the distribution disinfectant.
3) Replacing existing centrifuges is critical for immediate operations and for the ability to implement
enhanced coagulation
4) A phased approach to manage the capital expenditures of the PJWPB can be applied. It requires the
following immediate steps:
a. Develop implementation plan to address NYSDOH concerns over elevated DBPs in the distribution
b. Develop final plan for implementing enhanced coagulation (in conjunction with centrifuge
replacement)
c. Develop distribution system model to refine water age estimates and identify areas in the system
where water age could be improved, or localized treatment could be considered
RECOMMENDATIONS AND IMPLEMENTATION PLAN
PJWB DBP CONCEPT DESIGN DRAFT REPORT 043012_FINAL 6-5 COPYRIGHT 2012 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
d. Obtain temporary 30-day chemical storage waiver from NYSDOH to use existing PACL tanks to
implement enhanced coagulation testing
e. Start sampling as soon as possible after enhanced coagulation is implemented to see what effects
it has in the system on DBP formation. Gather as much data as possible before October 2012
when compliance sampling for Stage 2 DBPR begins
f. Evaluate data and utilize decision flowchart to determine next steps to take to meet Stage 2 DBPR
if enhanced coagulation alone with distribution system improvements does not reliably meet the
regulations.