comprehensive project report for … · “medley ” at survey no’s ... movements from and to...
TRANSCRIPT
COMPREHENSIVE PROJECT REPORT FOR RESIDENTIAL APARTMENT PROJECT
“MEDLEY”
At
Survey No’s. 222, 223, 226 & 227, Kambipura Village, Kengeri Hobli,
Bangalore South Taluk, Bangalore.
Submitted By
M/s. Good Earth Eco Communities Private Limited, Tarana No. 9, 10, & 11, Good Earth Malhar, Survey No. 193, 226 & 227, Kambipura Village,
Kengeri Hobli, Bangalore South Taluk, Bangalore – 560 074.
Submitted to
SEIAA, Karnataka.
ENVIRONMENTAL CONSULTANTS
M/s. SAMRAKSHAN, F- 4, I Floor, Swastik Manandi Arcade,
S. C. Road, Sheshadripuram, Bangalore - 560 020. Phone : 080 23460102
Email: [email protected]
INDEX
SL. NO
DESCRIPTION PAGE NO.
1 APPLICATION IN FORM I 1-14
2 APPLICATION IN FORM I A 15-25
ANNEXURE TO APPLICATIONS
A COMPREHENSIVE PROJECT REPORT
26 - 30
B WATER REQUIREMENT DETAILS FOR THE PROJECT
31 – 32
C
SEWAGE GENERATION, UTILITY OF TREATED SEWAGE & DESIGN DETAILS OF SEWAGE TREATMENT PLANT
33 - 42
D WATER BALANCE CHART
43
E
WATER REQUIREMENT & SEWAGE DISPOSAL DURING CONSTRUCTION PHASE
44
F
SOLID WASTE GENERATION & MANAGEMENT DETAILS
45 - 46
G (CONSTRUCTION & OPERATION PHASE)
ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN (EMP) FOR
47 – 58
H RAIN WATER MANAGEMENT SCHEME
59 – 60
I DISASTER MANAGEMENT PLAN FOR PRE-CONSTRUCTION PHASE
61
J RISK ASSESSMENT & MANAGEMENT PLAN
62
K TRAFFIC MANAGEMENT MEASURES
63
L
M
N
SAVINGS IN ELECTRICAL POWER CONSUMPTION
SOIL INVESTIGATION REPORT
PROJECT RELATED DRAWINGS/PLANS
64
65
MEDLEY ANNEXURES TO APPLICATION
26
Annexure &
Details to Application in
Form 1 and Form 1A
MEDLEY ANNEXURES TO APPLICATION
27
ANNEXURE – A
COMPREHENSIVE PROJECT REPORT
PROJECT AT GLANCE
PROPOSED PROJECT Residential Apartment project with 119 flats.
LOCATION “MEDLEY”
Survey No’s. 222, 223, 226 & 227, Kambipura Village, Kengeri Hobli,
Bangalore South Taluk, Bangalore.
TOTAL PLOT AREA 15,849.48 sq m (3 Acres 36.66 Guntas)
TOTAL BUILT UP AREA 23,785.74 sq m
TOTAL COST OF PROJECT
Rs. 73,00,00,000/-
(Rupees Seventy Three Crores Only)
PROJECT PROFILE The project consisting of 2 Blocks and club house
1) Block 1 consisting of 8 Buildings with configuration as under;
a) 3 Wings consisting of G + 1F
b) 3 Wings consisting of G + 2F
c) 1 Wing consisting of 1B + G + 1F
d) 1 Wing consisting of 2B + G + 2F
2) Block 2 consisting of 2B + G + 4F
CAR PARKING DETAILS 139 cars
WATER SUPPLY The water supply is from Kumbalagodu Grama Panchayat/Bore well
sources.
PROPOSED SANITATION Under Ground Sanitary System Facility for conveying the wastewater to
the Sewage Treatment Plant
SOLID WASTE
MANAGEMENT
Collection & Segregation at source of generation and Organic waste will
be composted through Vermi Composting method and the Inorganic
waste will be sent for recycling.
AIR POLLUTION / NOISE
GENERATION SOURCE
2 X 250 kVA capacity DG sets
MEDLEY ANNEXURES TO APPLICATION
28
BACK GROUND OF THE PROPOSED PROJECT:
M/s. Good Earth Eco Communities Pvt. Ltd., Tarana No. 9, 10, & 11, Good Earth Malhar, Survey No. 193,
226 & 227, Kambipura Village, Kengeri Hobli, Bangalore South Taluk, Bangalore – 560 074 intend to
construct Residential Aprtment Building “MEDLEY” at Survey No’s. 222, 223, 226 & 227, Kambipura
Village, Kengeri Hobli, Bangalore South Taluk, Bangalore. The source of water is through Kumbalagudu
Grama Panchayat/Borewell Sources and power is from BESCOM/KPTCL. The project has been designed
in accordance with the regulations/bylaw of Bangalore Development Authority (BDA).
LAND USE FOR THE PROJECT:
Sl
No
Particulars Area
sq m Acres %
1 Total Plot area 15,984.24 3.94 -
2 Road widening (1.5 m for 2015 RMP road widening
and 4.5 m for 2031 RMP road widening)
134.76 0.03 -
3 Total Plot area considered for development 15,849.48 3.91 100
4 Ground Coverage area 6,184.46 1.53 39.02
5 Paved area 4,434.68 1.09 27.98
6 Landscape area 5,230.32 1.29 33.00
COMBINED AREA STATEMENT FOR THE PROJECT:
Sl
no
Floor Built up area in sq m
Block 1 Block 2 Club house
1 Basement 1 3,213.89 - -
2 Basement 2 3,993.30 - 99.82
3 Ground Floor 5,237.31 947.73 -
4 First Floor 4,677.28 925.3 -
5 Second Floor 2,020.54 915.38 -
6 Third Floor - 915.39 -
MEDLEY ANNEXURES TO APPLICATION
29
7 Fourth Floor - 839.8 -
TOTAL 19,142.32 4,543.6 99.82
Total built up area of the project = 19,142.32 + 4,543.6 + 99.82
= 23,785.74 sq m
CAR PARKING STATEMENT:
Sl. No. Description Parking spaces
1 Basement 2 72 cars
2 Basement 1 62 cars
TOTAL 139 cars
AIR POLLUTION SOURCES & ITS MANAGEMENT:
The anticipated power required for the project will be augmented from BESCOM which is about 595 kVA.
The primary sources of air pollution from the establishment are from the operation of diesel generator sets,
which are used as an alternative source of power supply during the emergencies of power failure from
KPTCL/BESCOM. The proposed project will be provided with DG set of following capacity and is installed
to serve as an alternative back up source of power supply in the event of break down power supply
BESCOM. The details of capacities & fuel consumption for the DG sets are given below.
Air Pollution Sources for the Proposed Project:
No Stack Details Stack Attached to
Physical Details D.G Set
1 Capacity 2 X 250 kVA capacity DG set
2 Fuel quantity 52.5 L/hr for each DG set of 250 kVA capacity
3 Fuel used Ultra Pure Low Sulphur Content Diesel
4 Stack height Chimneys (Above ground level) of 3 m for each DG sets
5 Stack diameter 500 mm
Emission Details
MEDLEY ANNEXURES TO APPLICATION
30
1 Sulphur dioxide 0.01667 g/s for each DG set for 250 kVA
2 Suspended Particulate
Matter (SPM)
0.01667 g/s for each DG set for 250 kVA
3 Oxides of Nitrogen 0.51111 g/s for each DG set for 250 kVA
NOISE GENERATION SOURCES:
Major noise producing sources of the proposed project is expected to be from DG set, Vehicular
movements from and to the proposed project. The DG sets will be provided with acoustic enclosures to
control the noise levels in such a way that the noise levels are within the permissible limits specified for
ambient noise levels. More over the DG set is operated only during the emergencies in power failure.
PROJECTED COST OF THE PROJECT:
The total projected cost of the project is presented as below:
No. Particulars Cost in Rupees
1 Land Cost Rs. 21,54,07,500/- (Sale deed value) Rs. 21,54,07,500/-
2 Construction Cost @ rate of Rs. 2,000/sft Rs. 51,18,69,124/-
TOTAL Rs. 72,72, 67,624/- or say
Rs. 73,00,00,000/-
Rupees Seventy Three Crores Only
MEDLEY ANNEXURES TO APPLICATION
31
ANNEXURE: B
SOURCE OF WATER FOR THE PROPOSED PROJECT:
The most important aspect under the water supply scheme is the selection of source of water, which should
be reliable and potable. The source of water supply to the proposed project is through Kumbalagodu
Grama Panchayat/Borewell Sources.
DETAILS OF WATER CONSUMPTION OF THE PROJECT:
The water requirement in the project is for domestic purpose, public uses and firefighting purposes. It
includes the quantity of water required in the houses for drinking, bathing, cooking, washing etc., the
quantity of water required for domestic purposes depends on the habits, social status, climatic conditions
and customs of the people. In India on an average the domestic water consumption under normal
conditions is about 135 litres/capita/day as per NBC, the details of domestic consumption is as follows:
Sl
No
Utility Consumption in Litres Per
Capita Per Day (LPCD)
1 Drinking 5
2 Bathing 55
3 Cooking 5
4 Washing of clothes 10
5 Utensils washing 10
6 Washing of floor 5
7 Flushing of Toilets 45
Total 135
The anticipated water demand is worked out by taking into consideration that the project is fully developed
and occupied. The total domestic water demand of the project is worked based on 135 LPCD of domestic
water requirement details are as under.
MEDLEY ANNEXURES TO APPLICATION
32
WATER CONSUMPTION OF THE PROPOSED PROJECT:
No. Water requirement
1.1 No. of flats 119
Total contributing population from the project,
considering 5 person per flat
5 X 119 = 595
1.2 Water requirement for the Residential Apartment by
considering water demand of 135 LPCD
595 X 135
80,325 LPD or say 80 KLD ---- A
1.4 Water requirement for the visitors/club house
(considering 10% of total water requirement)
8 KLD ---- B
TOTAL WATER REQUIRED FOR PROPOSED PROJECT: A + B = 80 + 8
= 88 KLD
WATER DISTRIBUTION SYSTEM:
The water supply scheme to cater to the public and domestic water requirement of the project consists of
sourcing pretreated potable water from Public supply into a common collection facility known as the Raw
Water Sump. The Raw Water Sump will be constructed in RCC. The water from the UG sump will be
distributed to individual houses through Hydro Pneumatic System.
MEDLEY ANNEXURES TO APPLICATION
33
ANNEXURE: C
SEWAGE GENERATION AND DISPOSAL SYSTEM:
Wastes of different type such as spent water from bath rooms, water closets/pans, house and street
washings, semi liquid waste of human excreta, dry refuse of house and street sweepings, broken furniture,
crockery etc., are produced daily. If proper arrangement for collection treatment and disposal of all the
wastes produced are not made, unsanitary conditions will develop and it will become impossible for the
public to live. Therefore, it is most essential to collect, treat and dispose all the sanitary waste produced.
Generally, it has been observed that about 80 - 90 % of the water supplied comes out as sewage.
Therefore, the total quantity of wastewater generated from the project is worked out as below.
Water required for the project = 88 KLD
Wastewater generation = 88 X 0.90 = 80 KLD
(Assuming 90% of the water supplied comes out as wastewater)
The domestic wastewater generated from the proposed project will be conveyed to Sewage Treatment
Plant of capacity 90 KLD for treatment and disposal.
TREATED SEWAGE DISPOSAL:
The treated sewage will be disposed as under:
a. Toilet Flushing:
Total contribution population from the proposed project is 595 persons.
Total flushing water requirement @ rate of 45 LPCD
= 595 X 45 = 26,775 L/day or say 27 KLD
b. Gardening:
Treated water used for gardening @ rate of 5 L/sq m/day
Area available for landscape development is 5,230.32 sq m
= 5,230.32 X 5 = 26,151.16 L/day or say 26 KLD
b. 28 KLD of treated sewage will be reused for domestic purpose after providing necessary pre-
treatment.
MEDLEY ANNEXURES TO APPLICATION
34
DESIGN DETAILS OF PRPOSED SEWAGE TREATMENT PLANT:
Treatment plant for treating sewage in the campus has been proposed for a capacity of 90 cum/day.
Stream No Qty KL/day Peak flow TSS mg/l TDS mg/l COD mg/l BOD mg/l
1 90 KLD 8 <366 <660 <800 <400
WASTEWATER TREATMENT SYSTEM:
The design concept is as per the annexed flowchart (Refer: Wastewater treatment Process Flow chart -
Figure 2). The wastewater from all the sources is combined and is applied with a treatment appropriate to
it. Total 90 KLD would be treated to tertiary levels at a standard fit for toilet flushing. The discharge effluent
would meet the criteria stipulated by the Karnataka State Pollution Control Board (KSPCB)
DECENTRALIZED WASTEWATER TREATMENT SYSTEM (DTS)
The wastewater stream is conveyed to a DTS unit comprising of a settler integrated with an anaerobic up
flow to secondary module and a tertiary module with a combined retention time (HRT) of 50 hours.
The design detail of T1 is as given in table below:
DESIGN DETAILS OF DTS & TERTIARY
Total waste water –90 KL/day Peak hours – 8
Inlet COD – 800mg/l Inlet BOD – 400 mg/l
Outlet COD-< 100 mg/l Outlet BOD – <20 mg/l
Dimensions of the treatment modules are
Primary Module – (6,3) Length x 2.5 m Width x 1.8 m Depth
Secondary Module – 1 m Length x 4 m Width x 1.8 m Depth – 9 Nos
1.4 m Length x 4 m Width x 1.8 m Depth – 4 Nos
Tertiary Module – Aeration tank = 1.5 m Length x 3 m Width x 1.8 m Depth PSF
1.2 m dia x 0.9 m height
ACF 1.2m dia x 0.9m height & Chlorination 6 lph
MEDLEY ANNEXURES TO APPLICATION
35
REUSE OF TREATED WATER
About 90 KLD of treated wastewater undergoes further treatment and polishing through activated carbon
filter and sand filters before being used for toilet flushing and irrigation. Post treatment chlorination is done
to ensure complete disinfection.
The calculations are presented in later sections of this report. The polished water with BOD less than 10
mg/l shall be recycled for toilet flushing and gardening requirement.
Sludge
The DTS system is de-sludge once in 24 months and the digested sludge disposed off through BWSSB.
The annual quantity of sludge accumulation is estimated to about 33 KL. The sludge is harmless and can
be converted to organic compost.
Biogas
The DTS Unit would generate approximately 8 cum of gas per day as a result of the anaerobic treatment.
This would be used to heating purposes.
WASTEWATER TREATMENT FLOW CHART
DTS PROCESS FLOW CHART
S
E
T
T
L
E
WASTEWATER FROM
SOURCE
SETTLER
AERATION TANK & DUAL MEDIA
FILTER (ACF & PSF)
COLLECTION TANK- ONLINE
CHLORINATION
MEDLEY ANNEXURES TO APPLICATION
36
WASTEWATER TREATMENT PROCESS FLOW CHART
DECENTRALIZED WASTEWATER TREATMENT SYSTEM (DTS)
DTS water treatment solution is based on the principle of making effective use of natural processes like
gravity, microbiological activity and temperature. This results in a system which can work without wasting
scarce energy resources and needs only minimal maintenance. In fact the system produces energy in form
of methane/biogas. DTS is economically viable compared to conventional wastewater management
solution. DTS enables maximum reuse of the contents of the wastewater (water, nutrients and energy) and
can therefore be considered as a viable option for ecological/sustainable sanitation. The solution is also
designed to meet environmental laws and reduce carbon.
Key attributes of the DTS solution:
Provide treatment for both - domestic and industrial sources are reliable, long lasting and tolerant
towards shock loads and inflow fluctuation
Simple operation and low maintenance
MEDLEY ANNEXURES TO APPLICATION
37
The DTS core system generally consists of four treatment steps:
Step 1: Primary treatment and sedimentation
Step 2: Secondary treatment
Step 3: Tertiary treatment in aerobic/anaerobic media filters
The treatment steps are however designed to suit specific reuse requirements
STEP 1: PRIMARY TREATMENT AND SEDIMENTATION
This step is achieved using the biogas settler which can be considered as a gas tight septic tank with low
hydraulic retention times. Two main treatment processes take place in the biogas settler:
The mechanical treatment retains contaminants by sedimentation/flotation, and the wastewater from the
clarified layer flows through the outlet.
Biological treatment through anaerobic microorganisms which partially decompose the organic pollutants.
The digestion process ensures that the accumulated sludge is reduced and stabilized. Storage volume for
sludge is provided for 18 to 24 months, defining the desludging period.
SETTLER
Average reduction of organic content (BOD, COD) is between 25 and 40 % at this stage. The biogas
produced is captured and used as an energy source (direct thermal application or electricity production via
gas-generator).
MEDLEY ANNEXURES TO APPLICATION
38
STEP 2: SECONDARY MODULE
Secondary module consist two modules: The first reactor consists of a series of chambers, in which the
wastewater flows up-stream. Activated sludge is located at the bottom of each chamber. The inflowing
effluent is mixed with the sludge and is inoculated with bacterial mass which decompose the Pollutants. At
this stage the BOD reduction rate is 90 %. The pathogen reduction is in the range between 40 – 75 %.
FLUIDIZED BED REACTOR
SECOND REACTOR
The secondary reactor has anaerobic filter which has a similar up-stream flow. Filter materials such as
gravel, rocks or specially formed plastic components are used to provide additional surface area for
bacteria to settle. Non-settleable and dissolved solids are treated by bringing them in close contact with a
surplus of active bacterial mass fixed on filter material. The BOD removal rate at this stage is in the range
of 70-90%. The surplus of activated sludge produced has to be removed in intervals of 1 to 3 years.
FIXED FILM REACTOR
MEDLEY ANNEXURES TO APPLICATION
39
SLUDGE GENERATION AND DISPOSAL
Sludge will be produced in the primary and secondary module. The design provides integrated storage
volume for a period of 18 to 24 month.
Disposal: Regular disposal through BWSSB every 18 to 24 months. An onsite processing through the
installation of drying beds attached to the DTS could be an alternative option due to the fact that the sludge
produced will be harmless and rich in plant nutrients.
DESIGN COMPUTATIONS OF DTS TREATMENT MODULES
The characteristics of each wastewater stream are extrapolated based on the data submitted by MEDLEY.
Wastewater Stream Characteristics
Stream No Qty KL/day Peak Flow hrs TSS mg/l TDS mg/l COD mg/l BOD mg/l
1 60 8 <366 <660 <800 <400
DECENTRALIZED TREATMENT SYSTEM FOR WASTEWATER
Treatment scheme:
The wastewater is conveyed to a DTS unit with a hydraulic retention time (HRT) of 34.75 hours
The design parameters assumed are
Total waste water – 90 cum/day
Peak hours – 8
Inlet COD – 800mg/l
Outlet COD < 100 mg/l
Inlet BOD – 400 mg/l
Outlet BOD < 10 mg/l
Primary Module:
Desludging intervals = 12 months
Sludge production rate = 0.00416 l/g BOD
Hydraulic retention time = 4 hours
Corresponding COD removal rate = 32.4%
BOD removal rate = 34.4%
Outlet COD = (1-0.324) x 800
MEDLEY ANNEXURES TO APPLICATION
40
= 540.8 mg/l
Outlet BOD = (1-0.344) x 400
= 262.4 mg/l
Secondary Module:
Fluidized Bed Reactor:
Hydraulic retention time = 27 hours
Corresponding COD removal rate = 90%
BOD removal rate = 92%
Outlet COD = (1-0.9) x 540.8
= 54.08 mg/l
Outlet BOD = (1-0.92) X 262.4
= 20.99 mg/l
Fixed Film Reactor:
Hydraulic retention time = 3.75 hours
Corresponding COD removal rate = 42%
BOD removal rate = 44%
Outlet COD = (1-0.42) x 54.08
= 31.36 mg/l <266 mg/l
Outlet BOD = (1-0.44) x 20.99
= 11.75 mg/l <20 mg/l
DESIGN OF TERTIARY TREATMENT
Treated effluent Quality:
Flow : 90 KLD
Outlet COD : 28.22 mg/L
Outlet BOD : 11 mg/L
Operation hours : 8 hours
Expected Parameter after Polishing:
BOD : <10 mg/L
Quality parameters assumed for design of tertiary treatment Assuming factor of safety of 1.5
MEDLEY ANNEXURES TO APPLICATION
41
Designed BOD = Expected BOD X FOS
= 11 mg/l X 1.5
= 16.5 mg/L (0.0165 kg/m3)
Designed Flow = 90 KLD
Total BOD flow in aeration tank = Designed BOD x Designed Flow
= 0.0165 X 90
= 1.5 Kg/d
= 0.187 Kg/h (assuming 8 hours aeration)
Oxygen required = 1.8 kg of O2 /Kg of BOD removal
= 1.8 x 0.187
= 0.3366 kg of O2 /hr
Air required = O2 required / (density of Air) x (% of O2 in air by weight) x (α) x (β) x O2 transfer
efficiency at the respective aeration tank depth
= 0.3366/ (1.2 x 0.232 x 0.65 x 0.95 x 0.2)
= 9.7 m3/hr ~ 10 m3/hr
So, blower capacity will be = 10 m3/hr @ 0.35 kg/cm2
Provide one standby additional
Diffuser details:
Diffuser type - Fine bubble tubular diffuser
Adopt Dia 90 mm x 1000 mm long with throughput rate of 10.0 cum
No. of diffusers required = 2 nos.
Aeration Tank:
MLSS = 3000 mg/l
F/M = 0.12
Volume of aeration tank = Flow x BOD/ (F/M x MLSS)
= 90 x 11/ (0.12 x 3000)
= 2.75 cum
Provide 1.5 m (L) x 3 m (W) x 1.8 m (H) = 8 m3
MEDLEY ANNEXURES TO APPLICATION
42
Pressure Sand Filter:
Flow = 90 KL/day
Flow rate = 90/10
= 9 KL/ hr
Assuming filtration rate of 10 cum/sqm/hr
Area of filter = 1.13 Sqm
Hence pressure sand filter of 1.2 m dia and height 0.9 m is required.
Activated carbon Filter:
Flow = 90 KL/day
Flow rate = 90/10
= 9 KL/ hr
Assuming filtration rate of 10 cum/sqm/hr
Area of filter = 1.13 Sqm
Activated carbon sand filter of 1.2 m dia and height 0.9 m is required.
Chlorine dosing:
Provide a 6 L/h chlorine dosing pump with a 100 liters dosing tank. Storage tank dilution is 1 in 35.
MEDLEY ANNEXURES TO APPLICATION
43
ANNEXURE: D
WATER BALANCE CHART
Recycle for Toilet Flushing
Wastewater generated 80 KLD
Daily water Requirement after recycling
88 – 27 = 61 KLD 33 + 28 = 61 KLD
(Fresh & recycled water)
Total Raw Water demand (Start Up) 88
KLD
Toilet Flushing
27 KLD
STP designed for 90 KLD capacity
27 KLD or say 28 KLD to be recycled
Landscape Development
26 KLD
Water Drawn from Kumbalagodu Grama Panchayat/Borewell @ 55
LPCD = 119X5X55 = 33 KLD
Softener
Ultra-Filtration
UV
Potable water for judicious mixing
MEDLEY ANNEXURES TO APPLICATION
44
ANNEXURE: E
WATER REQUIREMENT & SEWAGE DISPOSAL: CONSTRUCTION PHASE
Domestic water requirements during construction phase
Total number of manpower required : 100
Water requirements @ of 100 LPCD : 100 x 100 = 10,000 L/day
Total domestic water requirement : 10 KLD
Wastewater generated: Considering 90% of the water consumed = 10,000 X 0.90 = 9,000 L/day
The wastewater generated from the construction site will be treated in Package of STP of 10 KLD capacity.
The treated sewage will be reused for dust suppression activities.
MEDLEY ANNEXURES TO APPLICATION
45
ANNEXURE: F
SOLID WASTE GENERATION & ITS MANAGEMENT
CONSTRUCTION PHASE:
The total manpower : 100
Considering solid waste generation @ 0.25 kg/capita/day
Total solid waste generation : 100 x 0.25 = 25 Kg/day
The domestic wastes will be composted and the product will be used as manure.
OCCUPANCY PHASE:
The wastes that are generated from the day to day activities which are in solid form are categorized as
solid wastes. Solid Wastes include dry refuse of house and street sweepings, crockery, Kitchen Wastes,
electronic wastes. Collection, disposal and management of Solid Wastes are very important to avoid the
nuisance and unhygienic conditions. The quantity of solid waste generated from project is calculated as
under.
No. Solid Waste Generation Details
1 Total no. of occupants considered: 595 persons
Assuming solid waste generation rate as 0.6 kg/person/day
Quantity of Solid Waste Generated = 595 X 0.6 = 357 Kg/day
a) Organic solid waste: 60% of the total waste: 214 Kg/day
b) Inorganic solid waste: 40% of the total waste: 143 Kg/day
The solid wastes generated will be segregated at its point of generation and collected separately in different
color coded Synthetic Bins depending upon the basis of its Bio Degradability at a common designated
point. Organic solid waste will be composted through Vermi Composting method and product will be used
as manure for Landscape development. The inorganic solid waste will be handed over to recyclers.
MEDLEY ANNEXURES TO APPLICATION
46
SECONDARY SLUDGE FROM STP:
The solid waste generated from the STP of secondary settling is in the form of stabilized secondary sludge.
Then is passed through the Plate & Frame filter press, the solids obtained as semi solid cakes are used as
organic manure for the development of plantations within the premises. The quantity of secondary sludge
from the secondary settling units of the treatment
* Total capacity: 90 m3/day and sludge: 33 Kgs/Day
HAZARDOUS WASTE:
The Hazardous waste generated from the project is waste oil of about 100 Litres/annum which will be
stored in closed barrels and disposed to KSPCB approved and CPCB register waste oil re-processors.
Authorization will be obtained from KSPCB as per Hazardous & Other Waste (Management &
Transboundary Movement) Rules, 2016.
BIO MEDICAL WASTE:
The Bio Medical Waste generated from the project will be collected and segregated at source based on
their categorization as per the Biomedical Waste (Management and Handling) Rules in containers and will
be disposed as per the guidelines. Common designated place will be earmarked for the storage of bio
medical waste and will be disposed scientifically.
e - WASTE:
The Electronic Waste (e-waste) such as CD’s, Pen drives, computer and its components, used batteries,
etc., from the project will be segregated, collected and stored at a designated place and will be handed
over to authorized recyclers.
MEDLEY ANNEXURES TO APPLICATION
47
ANNEXURE – G
ENVIRONMENTAL MANAGEMENT PLAN:
INTRODUCTION:
The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project
and ensuring the existing environmental quality. The EMP converse all aspects of planning, construction
and operation of the project relevant to environment. It is essential to implement the EMP right from the
planning stage continuing throughout the construction and operation stage. Therefore the main purpose of
the Environmental Management Plan (EMP) is to identify the project specific activities that would have to
be considered for the significant adverse impacts and the mitigation measures required.
The construction phase impacts are mostly short term, restricted to the plot area and not envisaged on the
larger scale. In the operational phase the environmental impacts are due to continuous operation of the
project, hence, the emphasis in the Environment Management Plan (EMP) is to minimize such impacts.
The following mitigation measures are recommended in order to synchronize the economic development of
the project area with the environmental protection of the region.
The emphasis on the EMP development is on the following;
Mitigation measures for each of the activities causing the environmental impact.
Monitoring plans for checking activities and environmental parameters and monitoring
responsibilities.
Role responsibilities and resource allocation for monitoring; and
Implementation of the Scheduled plan.
Environmental management plan has been discussed in the following sections separately for Construction
phase and Operational phase.
EMP DURING CONSTRUCTION PHASE:
During Construction phase the activities which need to be monitored and managed from the point of
pollution are detailed in the subsequent sections.
MEDLEY ANNEXURES TO APPLICATION
48
LEVELLING AND SITE CLEARANCE:
The proposed building is Residential Apartment project with 2 Basement floors and earth excavation is
necessary. The total quantity of excavated soil is about 16,000 cum. About 4,800 cum will be used for
backfilling, about 5,300 cum will be used for landscape development, about 4,400 cum will be used for
paved area and about 1500 cum will be used for formation activities and preparation of soil – cement
blocks (Used for compound wall and construction workers sheds construction).
Basement area = 3993.3 sq m
Basement Height = 6 m
Project site is undulating and level difference considered is 2 m
Therefore, earth excavation necessary is 4 m
Earth excavation required = 3,993.3 X 4
= 15,973.2 cum or say 16,000 cum
Soil reused for landscape development =5,300 cum
(Landscape area 5,230.32 sq m x 1 m filling for landscape development)
Soil reused for backfilling = 30% of excavated soil i.e., 4,800 cum
Soil reused for Paved area = 4,400 cum
(Total paved area in the project is 4,434.68 sq m x 1 m considered as filling height)
About 1500 cum will be used for formation activities and preparation of soil – cement blocks which will be
used for compound wall and labor shed construction.
Environmental Management during Leveling and Site Clearance:
Environmental
Impacts
Mitigation Proposed Remarks
Noise generation:
Caused due to
Excavators and
Bulldozers
Most optimum no. of operation by the heavy equipment.
Selection of equipment with less noise generation.
The earth moving equipment will be periodically checked
and maintained for noise levels. Since the site is more or
less even use of these earth moving equipments may not
be necessary.
The workers will be provided with PPE such as ear plugs.
To reduce
noise level,
Equipment will
be provided
with noise
control
devices.
MEDLEY ANNEXURES TO APPLICATION
49
Dust generation:
Leveling operations
results in the
emission of dust.
The site cleared will be periodically watered to reduce dust
emissions.
Barricades like metal sheets will be provided all round the
premises to avoid fugitive dust emission in to the
neighboring area apart from water sprinkling.
The workers will be provided with PPE such as nose
masks and goggles to reduce impact.
Tertiary treated
water will be
used.
TRANSPORTATION OF CONSTRUCTION MATERIALS:
During the Transportation of construction materials, minimum number of vehicles will be used. Most
optimum route is planned to reduce the impact of transportation activity on the environment.
Environmental Management during Transportation
Environmental Impacts Mitigation Proposed
Noise generation
Quality fuel will be used.
Vehicles will be periodically maintained.
Dust generation
Quality packaging of the construction materials.
Construction materials will be covered with tarpaulin sheet to prevent them
from being air borne.
The vehicle speed will be regulated.
The workers transporting materials will be provided with PPE such as nose
masks to reduce impact of air borne dust on their health.
Vehicular emissions Periodic emission check for vehicles will be done.
Clean fuel will be used for vehicles.
CONSTRUCTION ACTIVITIES:
During the construction work, the following impacts are identified to monitor and mitigate the level of
impact.
Environmental Management during Construction
Environmental Impacts Mitigation Proposed Remarks
Noise generation Less noise generating equipment. Implementation
MEDLEY ANNEXURES TO APPLICATION
50
Personnel Protective Equipment (PPE) such as ear
plugs and helmets will be provided for workers.
The working hours will be imposed on the
construction workers.
responsibility:
Contractor - Civil
Works
Dust generation PPE in the form of nose masks will be provided for
construction workers.
Use of water sprays to prevent dust from being air
borne.
Barricades like metal sheets will be provided all
around the premises to avoid fugitive dust emission
in to the neighboring area apart from water
sprinkling.
Implementation
responsibility:
Contractor
Water discharge
(construction works)
Sewage generated will be treated in package STP. Implementation
responsibility:
Contractor
Air Emissions from
Construction
machinery
Periodic check and regular maintenance of
construction machinery for emissions will be done.
Clean fuel will be used in equipments.
Implementation
responsibility:
Contractor
WASTEWATER DISCHARGE:
The sewage generated from the labors during construction is estimated to be about 10 KLD. The sewage
will be treated in package STP.
LABOUR CAMPS:
Environmental Management for Labor Camp:
Environmental Impacts Mitigation Proposed Remarks
Wastewater generation Provision of adequate sanitation facilities.
Responsibility:
Contractor
Usage of water Water for labor camps will be supplied in required Responsibility:
MEDLEY ANNEXURES TO APPLICATION
51
quantities. Contractor
Solid waste generation Segregation of Dry Waste and Wet Waste.
Adequate facilities to handle solid wastes will be
composted through Vermi Composting method.
Implementation
responsibility:
Contractor –
maintenance.
DISPOSAL OF EXCAVATED EARTH:
The proposed building is Residential Apartment project with 2 Basement floors and earth excavation is
necessary. The total quantity of excavated soil is about 16,000 cum. About 4,800 cum will be used for
backfilling, about 5,300 cum will be used for landscape development, about 4,400 cum will be used for
paved area and about 1500 cum will be used for formation activities and preparation of soil – cement
blocks (Used for compound wall and construction workers sheds construction).
PERSONNEL SAFETY SYSTEM:
It is planned to adopt the safe working practices which shall govern all construction works undertaken
throughout the project. Following Safety Aids to all laborers will be provided:
Safety Helmets, Safety Belts, Safety Shoes, Hand gloves.
Gumboots while concreting.
Safety Goggles while welding/ Stone dressing etc.,
Facemasks and full body kit while Pest control.
Implementation of Safety procedures such as:
• Using proper lifting techniques.
• Using Safe Scaffolds.
• Hot work permits for Fabrication and Welding.
MEDLEY ANNEXURES TO APPLICATION
52
FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS
(CONSTRUCTION ASPECTS)
Sl.
No.
Description Financial Provision in Rs.
Capital Cost Recurring Cost
1 Environmental Management Plan construction phase:
Tertiary treated water for
• Sprinkling to control fugitive dusts
• Construction & curing purposes
• Flushing
1,00,000
1,00,000
50,000
50,000
50,000
25,000
2 Potable water requirement for the construction workers 50,000 25,000
3 Sewage Treatment Plant 30,00,000 -
4 Maintenance of Vehicles and equipments - 1,00,000
5 Top Soil Conservation 1,00,000 -
6 Temporary Storm Water Drains 3,00,000 1,00,000
7 Personal protection safety gadgets and health care 50,000 25,000
8 First aid facilities for workers 50,000 25,000
9 Plantation of Saplings 1,00,000 1,00,000
10 Environmental Monitoring Plan (Air, Noise, Water and Soil). - 50,000
11 TOTAL 39,00,000 5,50,000
Contingency at 10 % 3,90,000 55,000
TOTAL 42,90,000 6,05,000
EMP DURING OPERATION PHASE:
Following are the identified operational phase activities in the impact assessment, which may have impact
on the environment.
1. Air quality
2. Water quality
3. Noise quality
4. Solid waste disposal
5. Green belt development
6. Storm water Management
MEDLEY ANNEXURES TO APPLICATION
53
AIR QUALITY MANAGEMENT:
The pollutants envisaged from the project are SPM, SO2, NOx, HC and CO mainly due to burning of liquid
fuel (HSD) in DG. Exhaust from DG set will be emitted from stack of adequate height for dispersion of
gaseous pollutants. The following Table presents the EMP for air quality management during operation
phase.
Air Quality Management during Operation Phase
Environmental Impacts Mitigation Proposed
DG set Equipment selected will ensure the exhaust emission standard as
prescribed as per the latest amendments from the MoEF.
DG will be used as stand-by unit
Periodic check and maintenance
Ambient air quality Ambient air quality monitoring as per the prescribed norms at regular
interval.
WATER QUALITY MANAGEMENT:
Water requirement of project will be met through Kumbalagodu Grama Panchayat/Bore well Sources.
Details of water requirement and Water balance is presented in Annexure B & D respectively.
The sewage generated from the proposed building will be treated in STP. Treated water will be reused for
flushing, gardening etc., and the following Table presents the EMP for water quality.
Water Quality Management during Operation Phase
Environmental impacts Mitigation Proposed
Wastewater Sewage will be treated in Sewage treatment plant to produce tertiary treated
water which will be reused for secondary purposes such as flushing
landscaping development, irrigation etc.,
Water conservation measures will be encouraged
NOISE MANAGEMENT:
High noise generating units such as DG set will be provided with acoustic enclosures. Green belt on the
project boundary will further act as noise barrier and helps in attenuation of noise. The Table presents the
EMP for noise level.
MEDLEY ANNEXURES TO APPLICATION
54
Noise Management during Operation Phase
Environmental Impacts Mitigation Proposed
Noise from DG set area Acoustic enclosures will be provided for DG set.
DG set will be installed in an area (utility section) where the access will
be restricted.
The use of PPE (ear plugs) will be mandatory in this area.
Selection of equipment to ensure that the residual noise level of < 55
dB(A)
Noise levels will be checked periodically using a noise pressure level
meter.
SOLID WASTE MANAGEMENT:
The solid wastes generated during operation phase can be categorized under
Three types: Domestic/Residential Waste
Wet Garbage: Food waste, Lawn mowing wastes etc.
Dry Garbage: Paper, Plastic, Bottles, etc.
Sludge from Sewage Treatment Plant (STP)
The solid waste generated and its management is detailed in Annexure – F.
The various mitigation measures to be adopted during collection and disposal of wastes are as follows:
It is preferable that the container and bins used for collection of waste should be of closed type and
waste is not exposed thus possibility of spreading of disease through flies and mosquitoes is
minimized.
Collection system should be properly supervised so that quick and regular removal of waste from
the dustbin is practiced.
Door to door collection shall be done in each building to collect the solid wastes.
STORM WATER MANAGEMENT:
As the project location is blessed with fairly good rainfall, it is planned to collect the storm water at different
gradients of the location. There will be rainfall runoff from building roof-tops, roads and pavements and
greenbelt area. Necessary provision will be made to collect the quantity of rainfall runoff during the most
MEDLEY ANNEXURES TO APPLICATION
55
rainy day of season. Necessary rain harvesting pit/recharge pit at every 30 m centre to centre have been
envisaged. 32 recharge pits are proposed in the project. A storm water drain with 600mm wide with RCC
precast perforated cover and 1800 mm dia RCC precast Ring soak pit will be provided around the
periphery of property and designed as per building by-law (schedule 12). The details of the rain water
harvesting facilities can be interpreted in the layout plan.
LANDSCAPE DEVELOPMENT:
About 200 trees of native indigenous species will be proposed to be planted at site.
Sl
No
Proposed Trees Numbers
Botanical Name Common Name
1 Magnolia champaka Sampige Tree 56
2 Azadirachta indica Neem Tree
3 Bambusa balcooa Indian bambo Tree
4 Mangifera indica Mango Tree
5 Cassia fistula Christmas Tree 62
6 Delonix regia Ornamental Tree
7 Bombax malbaricum Cotton Tree
8 Butea monosperma Bastard teak Tree 82
9 Lagestroemia speciosa Queen’s crape-myrtle Tree
10 Pongamia pinnata Karanj Tree
Total 200
MANAGEMENT OF SOCIO-ECONOMIC ISSUES:
1) Schools for laborer’s children
Temporary education centers (Crèche) will be provided for education of the children of the laborers.
2) Health camp for laborer’s family
Periodical health camps will be organized to monitor and facilitate the occupants of the labor camps.
MEDLEY ANNEXURES TO APPLICATION
56
HEALTH RISK AND DISASTER MANAGEMENT:
Public health and safety:
Since all the construction related activities are confined to the project site, minimal health related impacts
are envisaged within the project influenced area during the construction stage.
At the project site on an average of 100 no. of persons will be engaged, who face direct exposure to dust
and noise generated from the construction activity. This is likely to cause health related affects such as
asthma, bronchitis etc. and hearing impairments respectively.
To minimize these anticipated impacts, suitable actions like
Use of water sprinklers to prevent dust from being air borne.
Providing suitable personal protective equipments (PPE) like mouth mask with filters, noise mask,
helmets etc.
Periodic health check up camp for the laborers will be arranged.
Provision of safety belts.
In case of injury on site medical treatment and transport will be organized.
Due to operation of the project, there will be enhancement in public Health and safety.
Regular visit of resident medical officer to take care of the first aid and primary medication in case of
emergency for staff and office occupants and laborers.
First aid kit with primary medicines will always be available in the medical centre.
Display of action plan and preparedness measures during emergency situations.
EMP IMPLEMENTATION SCHEDULE:
Phased according to the priority, the implementation schedule is presented in the following table.
Implementation Schedule for EMP
No Recommendations Requirement
1 Air pollution control measures Before commissioning of respective units
2 Water pollution control measures Before commissioning of the project
3 Noise control measures Along with the commissioning of the project
4 Solid waste management During commissioning of the project
5 Green belt development Stage-wise implementation
MEDLEY ANNEXURES TO APPLICATION
57
The responsibility of EMP implementation lies with the project promoter.
FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS
(OCCUPANCY PHASE)
Sl
No
Description Financial Provision in Rs.
Capital Cost Recurring Cost
1 Operation of Sewage Treatment Plant - 3,00,000
2 Reclaimed Sewage Distribution Network 5,00,000 1,00,000
3 Rain water harvesting tanks and its facilities 5,00,000 1,00,000
4 Ground water recharging pits & its management 6,00,000 1,50,000
5 DG sets acoustic & Maintenance 5,00,000 1,00,000
6 Landscaping 3,00,000 1,00,000
7 Solid waste management per annum 6,00,000 50,000
8 Environmental Monitoring Plan per annum (Air, Noise, Water) - 1,00,000
9 TOTAL 30,00,000 10,00,000
Contingency at 10 % 3,00,000 1,00,000
TOTAL 33,00,000 11,00,000
ENVIRONMENTAL MONITORING ROUTINES:
A comprehensive monitoring program is suggested below:
Monitoring Schedule for Environmental Parameters
Sl
No
Particulars
Monitoring
frequency
Duration of
monitoring
Important parameters
for monitoring
I Air Quality
1. Ambient Air monitoring
Project premises Once in a month 24 hourly
sample
RSPM, SPM, SO2,
NOx
2. Stack monitoring
Once in a year if
required
Grab SPM, SO2, NOx, HC,
CO
II Water and Wastewater Quality
MEDLEY ANNEXURES TO APPLICATION
58
1. Water Quality
i. Groundwater at two locations (up-
gradient and down-gradient) of treated
effluent discharge area/land
Once in a month Grab As per KSPCB
requirements
2. Wastewater quality
i. Inlet into STP NA NA -
ii. Treated effluent prior to discharge NA NA -
III Soil Quality
1. Within project premises at 1 location on
effluent discharging area/land
Once in 6 month Composite
sample
As per KSPCB
requirements
2. Ecological preservation and up
gradation
Seasonal Visual
observations
Survival rate
IV Noise monitoring
1. Project premises Once in 6 month Day and night As per KSPCB
requirements
MEDLEY ANNEXURES TO APPLICATION
59
ANNEXURE: H
RAINWATER HARVESTING AND STORM WATER MANAGEMENT:
RAIN WATER HARVESTING:
The water collected from the terraces of the buildings will be collected in the rainwater collection sump and
reused for domestic purpose after necessary treatment.
VOLUME OF RAIN WATER HARVESTED:
The total quantity of water i.e., received in the form of rainfall over an area is called the rain water
endowment of that area, out of which the amount of water that can be effectively harvested is called the
rain water harvesting potential.
Rain Water harvesting potential = Intensity of Rainfall (m) x Roof Area x Impermeability Factor.
The collection efficiency accounts for the fact that all the rain water falling over an area cannot be
effectively harvested due to losses on account of evaporation, spillage or run off etc.,
According to the data available from Indian Meteorological Department, the
Average annual rainfall around month of September = 194.80 mm
Assuming that about 90 % Rainfall can be effectively harvested.
Number of Rainy Days = 9.3
Therefore the I.R = 194.80/9.3 = 20.94 mm/day or 0.02094 m/Day or 0.021 m/day
The Second Floor area of Block 1 and Fourth Floor area of Block 2 is about 840 sq m and 2021 sq m
respectively (Total – 2861 sq m).
For rain water harvesting consider 75 % of this total area is 2,146 sq m
Quantity of Rain Water that can be harvested from the building is as follows.
Rain water (Q) from Roof top = 0.021 x 2,146 x 0.9
= 40.55 cum/day or say 41 cum/day
Rain water storage sump of 90 cum capacity will be constructed to collect the rain water and will be reused
for domestic purposes.
MEDLEY ANNEXURES TO APPLICATION
60
STORM WATER MANAGEMENT:
Storm water disposal is divided into 2 Groups:
Terrace Storm water disposal: The entire rainwater from the terrace would be disposed through
suitable rain water pipes and collecting in the dedicated rain water collection sump, which is
proposed at site level. This water will be utilized for domestic purpose (as detailed in VOLUME OF
RAIN WATER HARVESTED).
Site (Paved and landscape area) Storm water disposal: The entire storm water from the site would
be disposed off through suitable RCC Box drainage system to the rainwater recharge pits and the
excess is diverted to external storm water drainage.
The quantity of storm water that the paved area will produce can be determined by considering the
impermeability factor to be 0.9.
Q = 0.021 x 4,434.68 sq m x 0.9
= 83.81 or say 84 cum/day -----A
The quantity of storm water that the landscaped area will produce can be determined by
considering the impermeability factor to be 0.3.
Q = 0.021 x 5,230.32 sq m x 0.3
= 32.95 or say 33 cum/day-------B
The Total quantity of storm water (A+B) = Paved area + Landscaped area
= 84 + 33 cum/day = 117 cum/day
The project proponents shall also Provide Recharging Pits along the inner periphery of the boundary wall
with recharging pit of size 1.2 m dia x 2.5 m deep spaced at 30 m center to center. 32 recharge pits are
proposed in the project. These recharging pits are filled with graded media comprising of Boulder at bottom
and with coarse aggregates to facilitate percolation of harvested rain water to Recharge Ground Water
table. The Recharge Pits are interconnected in such a way that the rain led to the first recharge pit is also
led to the next pit. The excess rain water shall be drained off to the storm water drain.
MEDLEY ANNEXURES TO APPLICATION
61
ANNEXURE: I
DISASTER MANAGEMENT PLANS FOR PRE CONSTRUCTION PHASE:
RISK AND DISASTER MANAGEMENT PLAN:
Disaster is an unexpected event due to sudden failure of the system, external threats, internal
disturbances, earth quakes, fire and accidents. Thus an appropriate management plan shall be
incorporated.
Precautions:
Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the
project in-charge.
Conditional maintenance of equipments, materials, and expertise for use during emergency.
The electrical systems shall be provided with automatic circuit breakers activated by over current.
Proper escape routes are planned and displayed in the public domain.
Selected representatives are given proper training to guide other inhabitants during Fire accidents.
Periodic awareness program is conducted for the workers on their roles during emergency situations.
Important telephone numbers like police authorities, fire department and hospitals etc., of use during
emergency situations will be made available.
MEDLEY ANNEXURES TO APPLICATION
62
ANNEXURE: J
RISK ASSESSMENT & MANAGEMENT PLAN:
a. Construction Phase:
Sl. No. Potential Mitigation
1 Accidental fire Fire safety gadgets.
2 Fall of objects Use of personal protection devices-helmets
3 Working at great heights Protection to prevent fall with life safety belts and nets.
4 Accidents from machinery Personal protection gadgets
5 Electrical mishap Adopting safety measures to prevent any act of negligence and
providing electrical safety measures like fire extinguishers.
b. All necessary measures will be taken to avoid accidents and mishaps during operation phase.
Precautions for Risk and Disaster Management Plan:
Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the
project in-charge.
Conditional maintenance of equipments, materials, and expertise for use during emergency.
The electrical systems shall be provided with automatic circuit breakers activated by over current.
Fire extinguishers are provided at pre-notified locations inside the building.
Proper escape routes are planned and displayed in the public domain.
Selected representatives are given proper training to guide other inhabitants during Fire accidents.
Periodic awareness program is conducted for the occupants on their roles during emergency
situations.
Important telephone numbers like police authorities, fire department and hospitals etc., of use during
emergency situations are made available.
MEDLEY ANNEXURES TO APPLICATION
63
ANNEXURE: K
TRAFFIC MANAGEMENT MEASURES
Merging of vehicles will be performed only to left traffic from the exit gates, this ensures safety.
To establish smooth entry & exit of vehicles, bell mouth shape geometry is provided at the gates. This
ensures smooth transition for merging of vehicles.
Yellow paint junction boxes are painted at the locations to create psychological barrier for through
drivers to control the speed.
Rubber humps are introduced for the outgoing vehicles at the exit gate drive way. All gates are manned
with efficient security who can guide the entry and exit of vehicles.
Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress).
Road marking, STOP lines, parking lanes, slot numbers etc.,
Must be clearly painted so as to guide the vehicles.
MEDLEY ANNEXURES TO APPLICATION
64
ANNEXURE: L
SAVINGS IN ELECTRICAL POWER CONSUMPTION
ENERGY CONSUMTION AND SAVINGS DETAILS:
Description Quantity
of fitting
Optg.
Time/ day
(Hrs)
Total energy
consumed per
annum (kWh)
Energy cost/
annum @ Rs.
4.00/unit
Total energy
consumed per
annum (kWh)
Energy
cost/annum @
Rs. 4.00/unit
A COMMON AREA
BASEMENT ETC
WITH 1X40 W USING COPPER POLYFILL
BALLAST
WITH 2X18 W USING
ELECTRONIC BALLAST
Total Apartment
internal common
area, lift lobby,
basement area
lighting using CFL
lamps & electronic
ballasts
310 12.00 64,254.60 257,018.40 59,257.02 237,028.08
B. EXTERNAL LIGHTING = 15 kW
Power saving due to use of Digital Timer Controller & CFL with Electronic ballast based light fittings for
External security, Landscape lighting against Flourcent fittings & street lighting with Metal Hallide is
assumed to be 30%
1.00 12.00 65,700.00 262,800.00 45,990.00 183,960.00
C. LIFTS
Total lift load (Conventional Lift motor without VFD) = 15 kW
Total Lift load (Machine room less, Gear less, belted lift motor with VFD = 12.37 kW
LIFTS LOAD 8.00 12.00 525,600.00 2,102,400.00 433,444.80 1,733,779.2
D. SOLAR WATER
HEATERS
68.00 2.00 49640.00 198,560.00 12,240.00 48,960.00
E.
TRANSFORMER
FOR ALUMINIUM WOUND TRANSFORMER FOR COPPER WOUND
TRANSFORMER
500 kVA Trafos 2.00 24.00 175,200.00 700,800.00 136,656.00 546,624.00
Grand Total 880,394.00 3,521,578 687,587.82 2,750,351.28
TOTAL ENERGY SAVED IN kWh @ % 22.90 %
MEDLEY ANNEXURES TO APPLICATION
65
ANNEXURE: M
SOIL INVESTIGATION REPORT
MEDLEY ANNEXURES TO APPLICATION
66
ANNEXURE: N
PROJECT RELATED DRAWINGS / PLANS
PROJECT SITE
LOCATION MAP:
GOOGLE MAP:
CDP MAP:
PROJECT SITE
TRANSFO
RM
ER
YARD
RAM
P D
OW
N T
o BA
SEM
ENT
SLO
PE 1
:10
-
2
.1
5
-
1
.1
5
+1.05
+
2
.1
8
+
2
.5
1
+3.18
+3.95
+4.35
+3.65
+3.55
+3.30
+3.30
+
0
.3
5
+3.30
+
3
.3
0
-
0
.4
5
CU
TO
UT
+1.30
+2.30
C
U
T
O
U
T
C
U
T
O
U
T
5.00
5.00
P
athw
ay
P
a
th
w
a
y
P
a
th
w
a
y
P
a
t
h
w
a
y
Path
way
P
a
th
w
a
y
P
a
t
h
w
a
y
P
a
t
h
w
a
y
P
a
t
h
w
a
y
P
a
th
w
a
y
Path
way
P
a
th
w
a
y
Pathw
ay
R.W.HPIT
R.W.HPIT
R.W.HPIT
R.W.HPIT
R.W.HPIT
R.W.HPIT
LANDSCAPEDAREA LANDSCAPEDAREA
L
A
N
D
S
C
A
P
E
D
A
R
E
A
2.00
3.35
3.06
3.00
3.00
3.06
2.94
3.87
3.05
3.02
5.00
5.00
5.00
L
A
N
D
S
C
A
P
E
D
A
R
E
A
L
A
N
D
S
C
A
P
E
D
A
R
E
A
BLO
CK
-1
PRO
POSE
D R
ESID
ENTIA
L BU
ILDIN
G
G.F
& F
.F
BLD
G/.
HT/.
=7.0
0M
BLOCK -1PROPOSED RESIDENTIAL BUILDINGBasement 1, Basement 2G.F ,F.F & SFBLDG/.HT/.=10.00M
BLOCK-1PROPOSED RESIDENTIAL BUILDINGG.F & F.F &SFBLDG/.HT/.=10.00M
5m se
tbac
k
5M SETBACK LINE
5m se
tbac
k5m
setb
ack
5m setback
5m setback
Basement Extent
5.00
5.00
5.00
3000mmØ
30
0m
m
30
0m
m
30
0m
m
60
00
mm
75
3
0
0
0
m
m
Ø
X X
20
00
mm
VA
RIE
S
11
00
mm
10
0m
m
RCC 1:2:4 PRECAST TOP COVER
SLAB 600MM WIDE WITH 10MMØ
TOR BARS AT 100MM C/C BOTH
WAYS.
CRUSHED
STONE
900mmØ x 50mm THICK x 300mm
DEPTH RCC PRECAST RINGS
WITH
50mmØ HOLES ALONG DIA
(8NOS)
COMPACTED EARTH
SURFACE
RCC 1:2:4 TOP COVER SLAB
WITH 10MMØ TOR BARS AT
100MM C/C BOTH WAYS.
(150mm THICK)
230mm THICK BRICK WALL
BUILT IN CM 1:6
75mm THICK IN PCC 1:5:10
150mmØ HUME PIPE
(OUTLET AS PER DRG)
150mmØ HUME
PIPE
(INLET AS PER
DRG)
40mm GRAVEL
FILLING UP TO 300mm
40mm GRAVEL FILLING UP
TO 300mm CAMPACTED
EARTH FILLING
RCC PRECAST RING OF
3000mmØ x 50mm THICK x
300mm DEPTH 50mmØ
HOLES ALONG DIA (8NOS)
65mm GRAVEL
FILLING UP TO 300mm
BRICK BAT OF SIZE
50MM TO 80MM
FILLING UP TO 300mm
50mmØ HOLES 2 NOS. ON
OPPOSITE DIRECTION AT
300mm APART
50mmØ HOLES 2 NOS. ON
PERFORATED HOLES6
KGF/CM
OR TYPE-B
PLAN OF SOAK PIT
EXTERNAL RAIN WATER SOAK PITSECTION AT X X
RAIN WATER SOAK PIT DETAIL (3.0 M DIA X 6M DEEP)
TOTAL NO OF APARTMENT 119
NO OF SURFACE PARKING 0 CARSNO OF BASEMENT PARKING 139 CARS
563.00M
T
O
-
K
A
M
B
I
P
U
R
-
>
T
O
-
R
A
M
A
N
A
G
A
R
T
O
-
K
E
N
G
E
R
I
M
Y
S
O
R
E
R
O
A
D
1
2
.
1
9
m
t
r
w
i
d
e
r
d
(
P
r
o
p
o
s
e
d
r
o
a
d
i
n
o
w
n
e
r
's
p
r
o
p
e
r
t
y
)
LOCATION PLANNot to Scale
77.03 M
164.35
1
2
.
1
9
m
t
r
w
i
d
e
r
d
1
2
.
1
9
m
t
r
w
i
d
e
r
d
1
2
.
1
9
m
t
r
w
i
d
e
r
d
E
x
i
s
t
i
n
g
1
2
.
1
9
m
t
r
w
i
d
e
r
d
-
R
M
P
p
r
o
p
o
s
e
d
t
o
1
5
m
t
r
w
i
d
e
r
o
a
d
(
p
r
o
p
o
s
e
d
e
x
p
a
n
s
i
o
n
t
o
1
5
m
t
r
w
i
d
t
h
)
58.40 M
243.99
Survey No 228(p)4 A-19.8 G
SY No227(p)
37 G
SURVEY NO.-227
SURVEY NO.-222
SURVEY NO.-223
SURVEY NO.-226
SURVEY NO.-223
Basement Extent
5M SETBACK LINE
5m s
etba
ck
5m s
etba
ck
5m s
etba
ck
R.W.HPIT
SITE PLAN
SCALE - 1:400
A0 1:400
P
L +
3.35m
lv
l
PL +3.3
5m lv
l
PL -2.0
6m lv
l
PL +1.4
4m lv
l
P
L -0.70m
lv
l
PL-1.7
0m lv
l
P
L -1.70m
lv
l
PL +
0.0
5m
lvl
P
L +
1.50m
lv
l
PL +2.9
6m lv
l
P
L +
3.60m
lv
l
P
L +
8.35m
lv
l
P
L +
1.75m
lv
l
-2.0
0m lv
l
+3.15m
lvl
BLO
CK
-1PR
OPO
SED
RES
IDEN
TIAL
BUILD
ING
G.F
& F
.FBL
DG
/.HT
/.=7
.00M
S
T
P
- F
F
R
&
F
B
R
B
E
LO
W
RAIN WATER
TANK BELOW
RAIN WATER
TANK BELOW
Treated W
ater
T
ank belo
w
F
lush &
Irrig
atio
n
W
ater T
ank
belo
w
5.91
BLO
CK-
1PR
OPO
SED
RES
IDEN
TIAL
BUILD
ING
G.F
& F
.F &
SFBL
DG
/.HT
/.=1
0.00
MBLO
CK-
1PR
OPO
SED
RES
IDEN
TIAL
BUILD
ING
G.F
& F
.F &
SFBL
DG
/.HT
/.=1
0.00
M
BLOCK -1PROPOSED RESIDENTIAL BUILDINGG.F & F.FBLDG/.HT/.=7.00M
BLO
CK
-1
PRO
POSE
D R
ESID
ENTIA
L BU
ILDIN
G
Base
men
t 1, G
.F &
F.F
BLD
G/.H
T/.=
7.00
M
Basement Extent
Basement Extent
Basement Extent
5m s
etba
ck
5m s
etba
ck
5m s
etba
ck
-2.0
0m lv
l
-2.0
0m lv
l
-2.0
0m lv
l
-1.0
0m lv
l
PL -0.7
0m lv
l
-0.4
0m lv
l
+0.00m lvl
-0.4
0m lv
l
+1.20m
lvl
+4.10m
lvl
+0.50m
lvl
-1.5
0m lv
l
CU
TO
UT
+
1
.1
5
m
lv
l
PAN
EL R
OO
MBE
LOW
S
E
W
A
G
E
P
U
M
P
IN
G
T
A
N
K
B
E
L
O
W
Ramp DN
7.00
R.W.HPIT
R.W.HPIT
R.W.HPIT
R.W.HPIT
R.W.HPIT
7.68
Ram
p D
N
Ramp UP
1.54
BLO
CK-
2PR
OPO
SED
RES
IDEN
TIAL
BUILD
ING
Base
men
t 1, B
asem
ent 2
,G.F
, 1S
T , 2
ND ,
3RD
, 4T
H
BLD
G/.
HT/.
=14.
95M
13.0
0
7.02
Ramp UP
Ramp UP
Ramp UP
Ramp UP
Ramp UP
Ramp UP
SLOPE 1:12
SLOPE 1:12SLOPE 1:12
SLOPE 1:12
SLOPE 1:12
SLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UPSLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UPSLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UP
SLOPE 1:12
Ramp UPSLOPE 1:12
Ramp UP
SLOPE 1:12
2.01
2.10
BASE
MEN
T B
ELO
W@
-2.0
M L
VL
BASE
MEN
T B
ELO
W@
-2.0
M L
VL
OPE
N T
OSK
Y
OPE
N T
OSK
Y
OPE
N T
OSK
Y
OPE
N T
OSK
Y
OPE
N T
OSK
Y
OPE
N T
OSK
Y
3.69
C
olle
ctio
n
T
a
n
k
belo
w
7.54
7.53
7.50
SURVEY NO.-222
SURVEY NO.-227
SURVEY NO.-223
SURVEY NO.-226
SURVEY NO.-223
7.57
SLOPE 1:12
2.004.50
85.21
31.05
6.75
89.6
4
R.W.HPIT
ROAD
Relinquished area to BDA for Road Widening (134.76 SQM)
Centre line of Existing 12M Road
1.5M for 2015RMP Road Widening
4.5M for 2031 RMP Road Widening
5.00
12.18
1.504.50
40.24
20.75
3.00
50.2
7
5.85
6.00
5m setback
12.01
SURVEY NO.-227
GENERAL NOTES:-
ALL DIMENSIONS ARE IN METRES UNTIL
AND UNLESS SPECIFIED
AREA STATEMENT &
F.A.R CALCULATION( IN SQUARE METRES)
SITE AREA : 15849.48 SMT (3 ACRES -36.66GUNTAS)
COVERAGE ALLOWABLE = 50 %
COVERAGE =
PLINTH AREA (RES GF )
PLOT AREA
6185.03
15849.48
=
X 100 =39.02 %
PERMISSIBE F.A.R = 2.25
F.A.R =
TOTAL FLOOR AREA
PLOT AREA
=
16595.83
15849.48
= 1.05 < 2.25
HEIGHT OF THE BUILDING :-
PERMISSIBLE HEIGHT OF THE BUILDING :- 15 M
ACHIEVED HEIGHT OF THE BUILDING :- 14.95 M
CAR PARKING :-
TOTAL NO OF UNITS = 119 UNITS
FLATS LESS THAN 225 SMT
= 119 UNITSX1 CAR)
10 % OF VISITORS CARS FOR 119 UNITS = 12 CARS
CLUB HOUSE = 99.82 / 50 =2 CARS
10 % OF VISITORS CARS FOR CLUB HOUSE = 1 CARS
TOTAL NO OF CAR PARKING =134 CARS
=119 CARS
BASEMENT FLOOR-2 PARKING = 77 CARS
BASEMENT FLOOR-1 PARKING = 62 CARS
CAR PARKING REQUIRED = 134 CARS
CAR PARKING PROVIDED = 139 CARS
TYPE SIZE (LENGTH X HEIGHT) DESCRIPTION
ED FLUSH DOOR1.10X2.10
SCHEDULE OF OPENING
D1 FLUSH DOOR0.90X2.10D2 FLUSH DOOR0.75X2.10FD FRENCH DOOR2.40X2.10W WINDOW1.80X1.40V VENTILATOR0.60X1.20
PROJECT :PROPOSED RESIDENTIAL APARTMENT BUILDINGAT SY-NO: 222,223,226 & 227KAMBIPURA VILLAGE,KENGERI HOBLI,BANGALORE SOUTH TALUK
OWNERS SIGNATURE
ARCHITECTS SIGNATURE
DIRECTORGOODEARTH ECO COMMUNITIES PVT. LTD
SUBJECTS OF DRAWING
SANCTION DRAWING
SITE PLAN (BLOCK-1 & 2)SHEET NO : 01 OF 12
SCALE : 1 : 400 DATE : 12 JULY 2018
3.00
ENTRY
0.00 LVL
Pedestrian
Entry
ENTR
Y
EXIT
85.1
0
101.27
JAYAKUMAR.K.SCOA REG.NO-CA/2003/30607BCC/BL-3.6/A-2458/2013-14
5.91
85.21
31.05
6.75
89.6
4
40.2420.75
3.00
50.2
7
12.01
85.1
0101.27
AREA = 3Acre -36.66GuntasSurvey No-222,223,226 & 227
91
90
89
88
87
86
85
84
83
82
81
80
79
78
104
103
102
101
100
5.40
M W
IDE
DRIV
E W
AY
5.40
M W
IDE
DRIV
E W
AY
8.00 M WIDE DRIVE WAY
99
98
97
96
95
94
93
92117
116
115
114
113
112
111
110
109
108
107
106
105131
130
129
128
127
126
125
124
123
122
121
120
119
118
132133134135
136137138139
33.20
5.97
5.50
57.9
6
1.32
3.50
2.90
9.00
9.37
2.00
30.61
68.4
8
5.50
6.24
BASEMENT FLOOR-1 PARKING PLAN
KEY PLAN
SCALE=1:300
2.70
3.90
BLOCK-1
4.10
2.39
R
O
A
D
A1- 1:300
E
N
T
R
Y
/ E
X
IT
P
A
N
E
L R
O
O
M
A
C
C
L P
anel
M
etering P
anel 3 (30 M
eters)
M
etering P
anel 2 (30 M
eters)
M
etering P
anel 1 (42 M
eters)
M
e
te
rin
g
P
a
n
e
l 4
(3
0
M
e
te
rs)
1.00
R
A
M
P
U
P
T
o B
A
S
E
M
E
N
T
-2
S
LO
P
E
1:11
5.40
5.40
5.40
5.40
8.36
LIFT
BASEMENT 1-FLOOR PLAN
PARKING - 62 CARS
GENERAL NOTES:-
ALL DIMENSIONS ARE IN METRES UNTIL
AND UNLESS SPECIFIED
AREA STATEMENT &
F.A.R CALCULATION( IN SQUARE METRES)
SITE AREA : 15849.48 SMT (3 ACRES -36.66GUNTAS)
COVERAGE ALLOWABLE = 50 %
COVERAGE =
PLINTH AREA (RES GF )
PLOT AREA
6185.03
15849.48
=
X 100 = 39.02 %
PERMISSIBE F.A.R = 2.25
F.A.R =
TOTAL FLOOR AREA
PLOT AREA
=
16595.83
15849.48
= 1.05 < 2.25
HEIGHT OF THE BUILDING :-
PERMISSIBLE HEIGHT OF THE BUILDING :- 15 M
ACHIEVED HEIGHT OF THE BUILDING :- 14.95 M
CAR PARKING :-
TOTAL NO OF UNITS = 119 UNITS
FLATS LESS THAN 225 SMT
= 119 UNITSX1 CAR)
10 % OF VISITORS CARS FOR 119 UNITS = 12 CARS
CLUB HOUSE = 99.82 / 50 =2 CARS
10 % OF VISITORS CARS FOR CLUB HOUSE = 1 CARS
TOTAL NO OF CAR PARKING =134 CARS
=119 CARS
BASEMENT FLOOR-2 PARKING = 77 CARS
BASEMENT FLOOR-1 PARKING = 62 CARS
CAR PARKING REQUIRED = 134 CARS
CAR PARKING PROVIDED = 139 CARS
TYPE SIZE (LENGTH X HEIGHT) DESCRIPTION
ED FLUSH DOOR1.10X2.10
SCHEDULE OF OPENING
D1 FLUSH DOOR0.90X2.10D2 FLUSH DOOR0.75X2.10FD 2.40X2.10W WINDOW1.80X1.40V VENTILATOR0.60X1.20
PROJECT :PROPOSED RESIDENTIAL APARTMENT BUILDINGAT SY-NO: 222,223,226 & 227KAMBIPURA VILLAGE,KENGERI HOBLI,BANGALORE SOUTH TALUK
OWNERS SIGNATURE
ARCHITECTS SIGNATURE
DIRECTORGOODEARTH ECO COMMUNITIES PVT. LTD
SUBJECTS OF DRAWING
SANCTION DRAWING
SHEET NO : 07 OF 12
SCALE : 1 : 300 DATE : 12 JULY 2018
BASEMENT FLOOR PLAN-1
5.50
2.50
1.80
1.80
5.50
2.507.63
JAYAKUMAR.K.SCOA REG.NO-CA/2003/30607BCC/BL-3.6/A-2458/2013-14
2.70
FRENCH DOOR
O
TS
O
TS
O
TS
O
TS
O
TS
O
TS
O
TS
0405
06
9
07
11
13
18
17
15
21
20
19
01
0203
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
3738
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
64
7172
73 7475
76
77
61
62
08
10
12
14
16
63
6566 67
6869
5.40
M W
IDE
DRIV
E W
AY
5.40
M W
IDE
DRIV
E W
AY
7.17 M WIDE DRIVE WAY
TOILET1.35x1.45
STOREROOM
2.40x3.00
70
33.20
6.24
54.4
8
33.33
72.4
0
22.0
0
36.28
2.00
9.00
2.90
3.50
57.9
7
5.50
5.97
2.70
3.90
4.10
3.10
7.70 M WIDE DRIVE WAY
BASEMENT 2-FLOOR PLAN
PARKING - 77 CARS
A1- 1:300
BASEMENT FLOOR-2 PARKING PLAN
KEY PLAN
SCALE=1:300
TR
EA
TE
D
W
AT
ER
TA
N
K B
ELO
W
FLU
SH
&
IR
R
IG
AT
IO
N
W
AT
ER
TA
N
K
BE
LO
W
C
olle
ctio
n
Tank b
elo
w
9.37
R
AIN
W
AT
ER
TA
N
K
BE
LO
W
5.40
5.40
5.40
5.40
ve
h
icu
la
r
E
n
try
7.17
7.70
5.50
2.00
2.00
R
A
M
P
D
O
W
N
T
o
B
A
S
E
M
E
N
T
-2 S
LO
P
E
1:10
CLUB6.60x11.75
RAMP UP To BASEMENT-1SLOPE 1:13
up
E
N
T
R
A
N
C
E
E
X
IT
E
N
T
R
Y
BLOCK-1
LIFT
LANDSCAPED AREA
GENERAL NOTES:-
ALL DIMENSIONS ARE IN METRES UNTIL
AND UNLESS SPECIFIED
AREA STATEMENT &
F.A.R CALCULATION( IN SQUARE METRES)
SITE AREA : 15849.48 SMT (3 ACRES -36.66GUNTAS)
COVERAGE ALLOWABLE = 50 %
COVERAGE =
PLINTH AREA (RES GF )
PLOT AREA
6185.03
15849.48
=
X 100 =39.02 %
PERMISSIBE F.A.R = 2.25
F.A.R =
TOTAL FLOOR AREA
PLOT AREA
=
16595.83
15849.48
= 1.05 < 2.25
HEIGHT OF THE BUILDING :-
PERMISSIBLE HEIGHT OF THE BUILDING :- 15 M
ACHIEVED HEIGHT OF THE BUILDING :- 14.95 M
CAR PARKING :-
TOTAL NO OF UNITS = 119 UNITS
FLATS LESS THAN 225 SMT
= 119 UNITSX1 CAR)
10 % OF VISITORS CARS FOR 119 UNITS = 12 CARS
CLUB HOUSE = 99.82 / 50 =2 CARS
10 % OF VISITORS CARS FOR CLUB HOUSE = 1 CARS
TOTAL NO OF CAR PARKING =134 CARS
=119 CARS
BASEMENT FLOOR-2 PARKING = 77 CARS
BASEMENT FLOOR-1 PARKING = 62 CARS
CAR PARKING REQUIRED = 134 CARS
CAR PARKING PROVIDED = 139 CARS
TYPE SIZE (LENGTH X HEIGHT) DESCRIPTION
ED FLUSH DOOR1.10X2.10
SCHEDULE OF OPENING
D1 FLUSH DOOR0.90X2.10D2 FLUSH DOOR0.75X2.10FD 2.40X2.10W WINDOW1.80X1.40V VENTILATOR0.60X1.20
PROJECT :PROPOSED RESIDENTIAL APARTMENT BUILDINGAT SY-NO: 222,223,226 & 227KAMBIPURA VILLAGE,KENGERI HOBLI,BANGALORE SOUTH TALUK
OWNERS SIGNATURE
ARCHITECTS SIGNATURE
DIRECTORGOODEARTH ECO COMMUNITIES PVT. LTD
SUBJECTS OF DRAWING
SANCTION DRAWING
BASEMENT FLOOR PLAN-2SHEET NO : 06 OF 12
SCALE : 1 : 300 DATE : 12 JULY 2018
7.00
5.50
2.50
5.50
2.50
11.7
5
6.60
1.80
1.80
1.80
1.80
JAYAKUMAR.K.SCOA REG.NO-CA/2003/30607BCC/BL-3.6/A-2458/2013-14
FRENCH DOOR
S
T
P
- F
F
R
&
F
B
R
B
E
LO
W
R
AIN
W
AT
ER
TA
N
K
BE
LO
W
PU
M
P R
O
O
M
BE
LO
W
OTS
O
TS
O
TS
O
TS
O
TS
O
TS
O
TS
O
TS
O
TS
TOILET1.35x1.45
20.26
36.4
0