Page 1: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONSSCAP Biosolids Committee Meeting

August 2, 2012

Page 2: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 2

AGENDA

• Facility Siting Considerations• Composting Technologies• Permitting• Regulatory Compliance• Process Control• Compost Quality

Page 3: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 3

FACILITY SITING CONSIDERATIONS

• Location, Location, Location!– Regulations– Nearby Compost Market– Sensitive Receptors

• Public Education/Politics– Education Begins Early– Keep it Simple– Remember the Benefits

• Diversion• Soil Enhancement• Erosion Control

– Don’t ignore the public/politics

Page 4: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 4

COMPOSTING TECHNOLOGY

• Windrow• Negative Aerated Static Pile with

Biofiltration• In-vessel

Page 5: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 5

COMPOSTING TECHNOLOGY: Negative Aerated Static Pile Composting

Page 6: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 6

COMPOSTING TECHNOLOGY: Negative Aerated Static Pile Composting

Page 7: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 7

PERMITTING

• Local Conditional Use Permit• CEQA• CA Solid Waste Facility Permit

– Report of Compost Site Information– Odor Impact Minimization Plan

• Regional Water Quality Control Board• Local Air District Permit• U.S. EPA Registration

Page 8: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 8

REGULATORY

• Inbound Materials Monitoring– Biosolids– Carbon Feedstocks

• Process Water Management• Ground Water Monitoring• Special Occurrences• Source Testing

• Compost Sampling – C.C.R. Title 14, Chapter 3.1, Article 7

• Metals Concentrations (max)• Pathogen Reduction (PFRP) • Sampling Requirements

Page 9: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 9

PROCESS CONTROL PARAMETERS

• Control Points– Feedstock Handling– Mix Ratios– Moisture– Aeration Rates– Temperature/PFRP

Page 10: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 10

THE COMPOSTING PROCESS

Feedstocks

Microorganisms

Oxygen

Water

Compost

CO2Water

Odors?

Heat

Page 11: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 11

COMPOST FACILITY FEEDSTOCK-PROCESS-MARKET

Identify and quantify

Feedstocks

Analyze Markets

Develop and adjust recipes

Collect or receive feedstocks

Process:Grind, Mix, Compost,

Cure, Screen, etc.

Market and distribute

AssessCompost Facility

Start here or

here

Page 12: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 12

THE KEY PROCESS VARIABLES for Control of the Composting Process

1. Initial feedstock mix

2. Pile moisture

3. Pile aeration

4. Pile shape and size

5. Pile temperature

6. Composting retention time

Page 13: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 13

FEEDSTOCKS: YOUR RAW MATERIAL

• Chemical Composition– Organic Matter, Nutrients, Degradability

• Physical Characteristics– Moisture, Bulk density, Heterogeneity

• Other– Contamination, Cost, Availability, Regulations

Page 14: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 14

FEEDSTOCK SUMMARY

• Each feedstock has certain attributes• The RECIPE is how feedstocks are combined• Composting system designed for feedstocks• Regulations are always partly based on feedstock

Page 15: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 15

OTHER CONSIDERATIONS

• Health & Safety• Initial Mix Ratios• Moisture• Aeration• Temperature• Time• Curing/Maturity• Testing

Page 16: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012

page 16

SUMMARY: Key Initial Parameters for Composting

Condition Reasonable range Preferred range Moisture % 40 — 65 50 — 60 C:N 20:1 — 60:1 25:1 — 40:1 Oxygen % Greater than 5 Greater than 10 Temperature oF oC

113 — 160 45 -- 71

120 — 150 49 -- 66

pH 5.5 — 9.0 6.5 — 8.0 Particle size 1/8 to 2 inches

.3-5 cm Depends on feedstocks

and use for compost

Porosity: Bulk density lbs/ yd3

(kg/l)

Free Air Space %

Less than 1200

(.7) 40-60

800-1000 (.45-.6) 50-60

Page 17: COMPONENTS FOR SUCCESSFUL COMPOST FACILITY OPERATIONS SCAP Biosolids Committee Meeting August 2, 2012