completion report - asian development bank...i basic data a. loan identification 1. country 2. loan...

72
Completion Report Project Number: 35068 Loan Number: 1826 September 2008 India: Gujarat Earthquake Rehabilitation and Reconstruction Project

Upload: others

Post on 12-Feb-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Completion Report

Project Number: 35068 Loan Number: 1826 September 2008

India: Gujarat Earthquake Rehabilitation and Reconstruction Project

CURRENCY EQUIVALENTS

Currency Unit – Indian Rupee/s (Re/Rs)

At Appraisal At Project Completion 14 March 2001 14 June 2007

Rs1.00 = $0.021478 $0.0226398 $1.00 = Rs46.56 Rs44.17

ABBREVIATIONS

ADB – Asian Development Bank ADA – Area Development Authorities AIFC – Average Incremental Financial Cost AUDA – Ahmedabad Urban Development Authority BME – Benefit Monitoring and Evaluation COS – Country Operational Strategy DMMP – Disaster Management and Mitigation Program DSC – Design Supervision Consultant EA – Executing Agency EIA – Environmental Impact Assessment EMG – Extended Mission in Gujarat FIRR – Financial internal rate of return GEB – Gujarat Electricity Board GERI – Gujarat Energy Research Institute GSDMA – Gujarat State Disaster Management Authority GSDP – Gross State Domestic Product GUDC – Gujarat Urban Development Company GWIL – Gujarat Water Infrastructure Limited GWSSB – Gujarat Water Supply and Sewerage Board IA – Implementing Agency ICB – International competitive bidding IDA – International Development Association INRM – India Resident Mission JAR – Joint assessment report NCB – National Competitive Bidding NGO – Non-government organization OCR – Ordinary capital resources O&M – Operation and maintenance PRHD – Panchayats, Rural Housing and Rural Development Department PMC – Project Management Consultant RRP – Report and Recommendation of the President SGIA – Second Generation Imprest Account TA – Technical Assistance WACC – Weighted average cost of capital

WEIGHTS AND MEASURES

km – kilometer m – meter m2 – square meter m3 – cubic meter ppm – parts per million

NOTES

(i) The fiscal year (FY) of the Government of India, and the Gujarat government and its agencies ends on 31 March. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2000 ends on 31 March 2000.

(ii) In this report, "$" refers to US dollars.

Vice President Xiaoyu Zhao, Vice-President, Operations 1 Director General K. Senga, South Asia Regional Department Director T. Kondo, Country Director, India Resident Mission (INRM) Team leader S. Muramoto, Head, Project Administration Unit, INRM Team members A. Srivastava, Project Implementation officer, INRM V. Vishal, Assistant Project Analyst, INRM

CONTENTS Page

BASIC DATA i

MAP vi

I. PROJECT DESCRIPTION 1

II. EVALUATION OF DESIGN AND IMPLEMENTATION 1 A. Relevance of Design and Formulation 1 B. Project Outputs 3 C. Project Costs 6 D. Disbursements 7 E. Project Schedule 7 F. Implementation Arrangements 8 G. Conditions and Covenants 8 H. Related Technical Assistance 8 I. Consultant Recruitment and Procurement 9 J. Performance of Consultants, Contractors, and Suppliers 9 K. Performance of the Borrower and the Executing Agency 9 L. Performance of the Asian Development Bank 10

III. EVALUATION OF PERFORMANCE 11 A. Relevance 11 B. Effectiveness in Achieving Outcome 11 C. Efficiency in Achieving Outcome and Outputs 11 D. Preliminary Assessment of Sustainability 11 E. Impact 12

IV. OVERALL ASSESSMENT AND RECOMMENDATIONS 12 A. Overall Assessment 12 B. Lessons 13 C. Recommendations 14

APPENDIXES 1. Project Components and Outputs 16 2. Breakup of Foreign and Local Costs of ADB Financing 21 3. Allocation and/or Reallocation and Actual Disbursement 22

of ADB Financing By Category 4. Contract Awards and Disbursements 23 5. Summary of Contract Details 24 6. Project Implementation Arrangements 45 7. Status of Major Loan Covenants 47 8. Benefit Monitoring and Evaluation 49 9. Socio-cultural, Resettlement, and Environment Impacts 51 10. Technical Assistance Completion Report 52 11. Implementation Schedule: Appraisal–Actual 55 12. Selected Photographs 56

i

BASIC DATA A. Loan Identification 1. Country 2. Loan Number 3. Project Title 4. Borrower 5. Executing Agency 6. Amount of Loan 7. Project Completion Report Number

India 1826 Gujarat Earthquake Rehabilitation and Reconstruction Project India Gujarat State Disaster Management Authority US$500 million. PCR:IND 1061

B. Loan Data 1. Appraisal – Date Started – Date Completed 2. Loan Negotiations – Date Started – Date Completed 3. Date of Board Approval 4. Date of Loan Agreement 5. Date of Loan Effectiveness – In Loan Agreement – Actual – Number of Extensions 6. Closing Date – In Loan Agreement – Actual – Number of Extensions 7. Terms of Loan – Interest Rate – Maturity (number of years) – Grace Period (number of years)

12 February 2001 28 February 2001 15 March 2001 16 March 2001 26 March 2001 26 April 2001 24 July 2001 17 May 2001 Nil 30 June 2004 06 November 2007 three began as pool-based single currency with variable lending rate and changed to LIBOR-based lending from 02 April 2002 30 years 7 years

ii

8. Disbursements a. Dates Initial Disbursement

17 May 2001

Final Disbursement

06 November 2007

Time Interval

77 months

Effective Date

17 May 2001

Original Closing Date

30 June 2004

Time Interval

37.5 months

b. Amount ($ million}

Category or Sub loan

Original

Allocation

Last Revised

Allocation

Amount

Canceled

Net Amount

Available

Amount

Disbursed

Undisbursed

Balance Part A: Housing

200 12.50 187.50 12.50 12.35 0.15

Part B: Urban & Rural Infrastructure

173 248.74 (75.74) 248.74 238.38 10.36

Part C: Power

67 31.00 36.00 31.00 30.90 0.10

Part D: Livelihood Restoration

20 6.49 13.51 6.49 6.41 0.08

Part E: Consulting Services & Incremental Administrative Support

15 18.75 (3.75) 18.75 17.92 0.83

Part F: Multi-hazard Disaster Preparedness & Mitigation

20 5.50 14.50 5.50 4.18 1.32

Front -End Fee 5 5.00 0.00 5.00 5.00 0.00

Total 500 327.98 172.02 327.98 315.14 12.84

9. Local Costs (Financed) - Amount ($ million) 209.58 - Percent of Local Costs 78.92 - Percent of Total Cost 66.50 LIBOR = London Interbank Offer Rate C. Project Data

1. Project Cost ($ million)

Cost Appraisal Estimate Actual

Foreign Exchange Cost 112 56.73 Local Currency Cost 513 258.41 Total 625 315.14

iii

2. Financing Plan ($ million)

Cost Appraisal Estimate Actual

Implementation Costs Borrower Financed 125 75.48 ADB Financed 500 315.14 Other External Financing 0 0

Total 625 391.62 IDC Costs Borrower Financed ADB Financed Other External Financing Total

ADB = Asian Development Bank, IDC = interest during construction.

3. Cost Breakdown by Project Component ($ million)

Component Appraisal Estimate Actual

A. Housing 250 16.75 B. Urban and Rural Infrastructure 217 293.300 1. Urban 86 147.18 a. Equipment and Materials 16 3.12 b. Civil Works 70 144.06 2. Rural (Water Supply and Sanitation) 132 146.12 a. Equipment and Materials 28 103.50 b. Civil Works 104 42.62 C. Power 98 45.62 a. Equipment and Materials 86 41.82 b. Civil Works 12 3.80 D. Livelihood Rehabilitation 20 6.32 E. Consulting Services and Incremental Administrative Support

15 19.36

F. Multi-hazard Disaster Preparedness and Mitigation 20 4.26 Front -End Fee 5 5.00 Total 625

390.61

iv

4. Project Schedule

Item Appraisal Estimate Actual

Date of Contract with Consultants (18 consultancies) First consultancy contract on 17 May 2001 and the last one on 8 September 2003

Completion of Engineering Designs Civil Works Contract Date of Award Retroactive contracts

from 12 Feb 2001 First—18 Jan 2002

Completion of Work Last—Dec 2003 Last—14 June 2007 Equipment and Supplies Dates First Procurement Retroactive contracts

from 12 Feb 2001 27 June 2002

Last Procurement Last—Dec 2003 14 March 2005 Completion of Equipment Installation Dec 2003 Dec 2005 Start of Operations Completion of Tests and Commissioning Jan 2006 Beginning of Start-Up Jan 2006 5. Project Performance Report Ratings

Ratings Implementation Period

Development Objectives

Implementation Progress

01 March 2002 to 31 December 2002 S S 01 January 2003 to 30 June 2003 S HS 01 July 2003 to 28 February 2004 S S 01 March 2004 to 30 November 2006 S PS 01 December 2006 to 31 January 2008 S S S= satisfactory, HS= highly satisfactory, PS= partially satisfactory D. Data on Asian Development Bank Missions

Mission Type Staff Mission Start Date Mission End Date Actual Field Days Planned Days

Review PS 05-02-2001 05-02-2001 1 0 Inception SC 28-05-2001 30-05-2001 6 3

Inception PS 28-05-2001 30-05-2001 6 3

Inception 29-05-2001 0 2 Review PS 21-06-2001 22-06-2001 4 2

Review SC 27-06-2001 0 0

Review PS 07-09-2001 07-09-2001 2 1 Disbursement PS 07-09-2001 07-12-2001 4 4

Review PS 09-12-2001 13-09-2001 2 2

Review PS 09-12-2001 13-09-2001 4 0 Review PS 18-10-2001 19-10-2001 2 2

Review PS 28-11-2001 29-11-2001 4 2

Review PS 15-01-2002 17-01-2002 3 3

v

Mission Type Staff Mission Start Date Mission End Date Actual Field Days Planned Days

Review PS 04-02-2002 04-02-2002 1 1 Review PS 13-05-2002 13-05-2002 1 1

Disbursement PS 06-10-2002 15-06-2002 6 6

Review PS 09-02-2002 09-02-2002 1 1 Review PS 10-07-2002 10-07-2002 1 1

Review PS 26-11-2002 26-11-2002 1 1

Disbursement SC 17-02-2003 27-02-2003 22 0 Disbursement NO 17-02-2003 27-02-2003 11 0

Disbursement AS 17-02-2003 27-02-2003 11 0

Review PS 14-05-2003 16-05-2003 3 0 Review SC 14-05-2003 16-05-2003 6 0

Review SC 09-01-2003 09-01-2003 2 1

Review PS 22-10-2003 22-10-2003 1 1 Review PS 15-03-2004 27-03-2004 26 13

Review SC 15-03-2004 27-03-2004 26 13

Review PS 31-03-2004 04-01-2004 4 2 Review AS 31-03-2004 04-01-2004 2 2

Disbursement NO 07-12-2004 21-07-2004 10 10

Review AS 07-12-2004 21-07-2004 10 0 Review PS 09-07-2004 09-08-2004 2 1

Review PS 11-02-2004 11-03-2004 2 1

Review SC 11-02-2004 11-03-2004 4 0 Review PS 04-04-2005 04-08-2005 5 0

Review AS 04-04-2005 04-08-2005 5 0

Disbursement NO 13-06-2005 21-06-2005 9 0 Disbursement AS 13-06-2005 21-06-2005 9 0

Review AS 11-08-2005 11-12-2005 5 0

Review SC 11-08-2005 11-12-2005 5 0 Review AS 11-08-2005 11-12-2005 5 5

Review NO 26-07-2006 28-07-2006 6 0

Review PS 20-11-2006 21-11-2006 4 3 Review NO 09-04-2007 09-07-2007 8 4

Total days 252 91 AS= Administrative Assistant, NO= National Officer, SC= Staff Consultant, PS= Professional Staff

Gulf ofCambay

A r a b i a n S e a

Gulf of Kachchh

Gandhinagar

Ahmedabad

Adesar

Samakhiali

Malia

Sihori

Radhanpur

Santalpur

Surat

Navasari

Ahwa

Valsad

Bharuch

Rajpipla

Vadodara

GodhraNadhad

Anand

Himmatinagar

Patan

Mahesana

Deesa

Palanpur

Dahod

Bhuj

MandaviMundra

Kandla

Dwarka

Porbandar

Upleta

Veraval

Mahuva

Bhavnagar

PipavavJafrabad

Kuyiyana

Ranavay

DhovajiJetpur

Gondai

Junagadh

AmreliBhavnagar

Rajkot

Jamnagar

Bamanbore

Morbi

Wankaner

Surendranagar

NH8A

Ramvadi

Kothara

Deshapar

PatriRayan

Nakhatrana

Sarva

Ghaduli

Ravapar

Lodai

Khavda

Kera

ChobariRamvan

DudhaiPipar

Gedi

Jalawada

RaparBhojardo

Luna

Sunthari

Gandhidham

LakhaparBhachau

NH

8A

MAHESANA

P A T A N

BANASKANTHA

GANDHINAGAR

SABARKANTHA

K A C H C H H

KHEDAAHMEDABAD

SURENDRANAGAR

DAHOD

PANCHMAHAL

JAMNAGARVADODARA

ANAND

RAJKOT

PORBANDAR

AMRELI

JUNAGARH

BHAVNAGAR

DHANDHUKA

NAVSAR

VALSADDAMAN

THE DANGA

S U R A T

BHARUCHNARMADA

R A J A S T H A N

G U J A R A T

MAHARASHTRA

INDIA

GUJARAT EARTHQUAKE REHABILITATION ANDRECONSTRUCTION PROJECT

(as completed)

0 50 100

Kilometers

N

08-3999 EG

70 00’Eo

70 00’Eo

73 00’Eo

73 00’Eo

21 00'No21 00'No

24 00'No24 00'No

Project District

City Covered Under Urban Reconstruction Works

Earthquake Epicenter

State Capital

District Headquarters

Other Town

Port

Boundaries are not necessarily authoritative.

Malia Headworks

Water Supply Works

National Highway

Provincial Road

District Boundary

State Boundary

International Boundary

helpdesk
vi

I. PROJECT DESCRIPTION

1. The main objective of the Gujarat Earthquake Rehabilitation and Reconstruction Project was to reconstruct and restore damaged infrastructure in the earthquake-affected areas of Gujarat state, India. While a large area of the state was affected by the earthquake (intensity of 6.9 on the Richter scale) of 26 January 2001, the major loss of life, property and damage to infrastructure was centered in the five districts of Kutch, Jamnagar, Rajkot, Surendranagar and Patan. An important objective of the Project was to enable early restoration of economic and social activity, especially for the poor and lower income groups. The government of Gujarat, with support of the Asian Development Bank (ADB), World Bank and others, jointly assessed the rehabilitation and reconstruction costs at $2.3 billion.

2. The Project focused on restoring public and economic infrastructure. The joint assessment report1 (JAR) estimated the Project’s cost as at $625 million. The main components were:

(i) Part A: Housing. Reconstruction focusing on rural areas. (ii) Part B: Urban and rural infrastructure. Urban and rural water supply, sewerage,

drainage, sanitation, and civic buildings, plus development of sites and services. (iii) Part C: Power. Substations, switchgear and transformers, transmission and

distribution systems, staff quarters and buildings. (iv) Part D: Livelihood rehabilitation. Financial and infrastructure support with training

of skilled affected persons to restore their livelihoods. (v) Part E: Consulting services and incremental administrative support. (vi) Part F: Multi-hazard disaster preparedness and mitigation. Supporting disaster

management plans, information systems and management training.

3. Technical assistance (TA) for Capacity Building for Earthquake Rehabilitation and Reconstruction of Housing 2 was provided to support implementation of the government of Gujarat’s reconstruction program for earthquake damaged housing.

II. EVALUATION OF DESIGN AND IMPLEMENTATION

A. Relevance of Design and Formulation

4. The Project was an emergency project, and the rapid response enabled the loan to be approved within 2 months of the earthquake. The Project was quickly and jointly formulated with the government of Gujarat and other development institutions through an intensive 10-day field assessment conducted in the damaged areas, followed by 10 days of data assimilation and collation with the results summarized in the JAR. The government of Gujarat used the JAR to allocate various sectors to ADB, World Bank, bilateral donors, financial institutions and other donors. Housing, urban and rural infrastructure, and power were included in the ADB project. The World Bank financed agriculture, education, and transport, with bilateral donors focusing on health, capacity building, training and emergency preparedness. The Gujarat State Disaster Management Authority (GSDMA) was established by the state within a week of the disaster. Its mandate was to implement initial reconstruction and build the state’s capacity to manage future potential disasters effectively. 1 Joint Assessment Report by ADB, World Bank, USAID, and Government of Netherlands in 2001. 2 ADB. 2001. Capacity Building for Earthquake Rehabilitation and Reconstruction of Housing. Manila.(TA No.3644-

IND, for $1300,000, approved on 26 March 2001)..

2

5. The objectives and scope identified in the JAR and report and recommendation of the President (RRP)3 during project formulation were satisfactorily implemented. After substantially implementing the highest-priority earthquake-affected works in the first 3 years, the second-priority works were implemented during the project extension period. The second priority works became possible due to (i) cost savings realized through high competition among bidders, resulting in lower-than-estimated costs; and (ii) extensive use of international competitive bidding (ICB), which had the additional advantage of providing Indian suppliers with tax benefits.

6. Both the primary and secondary objectives were achieved within their respective adjusted cost estimates and within the time extensions. Implementing such a large-scale, complex project spread over a large area within the original specified period of 3 years was not possible, as several major towns had to be completely re-planned, with major relocation of residential areas involving complex legal and planning aspects, land swaps, land acquisition and totally new infrastructure.

7. There were two major changes in project scope. The first was a transfer by GSDMA of housing from the Project to the World Bank’s project, leaving only a modest budget for the rural housing component designated for the Project’s nongovernmental organization (NGO)–government of Gujarat partnership. The transfer was implemented because World Bank financing through International Development Association (IDA) was less costly (40-year term with 1% service charge) than the ADB ordinary capital resources (OCR)loan (32-year term, with interest rates varying from 1.1% to 5.6% during the project implementation period). The second change was addition of 14 additional state line agencies as implementing agencies (IAs), which was necessary to ensure ownership and decentralized implementation. The Roads and Buildings Department was added as an IA a year after the Project commenced to ensure that roads connecting state highways and villages were rehabilitated. Municipal corporations (Ahmedabad, Rajkot, Vadodara and Jamnagar) were also included because these were more efficient local entities for implementing small projects at distant locations in these cities. The Gujarat Energy Research Institute (GERI) was engaged for procurement of seismic equipment and establishment of seismic observatories. The four area development authorities (ADAs) of Kutch district (Bhuj, Anjar, Bhachau, and Rapar) and Ahmedabad Urban Development Authority (AUDA) had special projects and were also included as IAs. Gujarat Council of Science City was brought in to build the specialized planet earth pavilion. In addition the Irrigation Department did some emergency repairs that were retroactively financed.

8. The Project was consistent with ADB’s country operational strategy (COS) for India4. The overall strategic objective of the COS is to promote economic efficiency and higher sustainable growth to improve employment and reduce poverty. Consistent with India’s development needs and ADB’s strategic emphasis, the Project’s focus was on poverty reduction. The strategic priorities for ADB’s contribution to reduce poverty included creating conditions for accelerated and sustainable growth, expanding social opportunities for the poor, and developing comprehensive partnerships for state-level operations. A key feature of the COS is a shift in ADB activities to support comprehensive economic and structural reforms in selected states . Gujarat was the first state chosen for ADB’s state-level operations. The Project

3 ADB: 2001. Report and Recommendation of the President to the Board of Directors on a Proposed Loan and

Technical Assistance Grant to India for the Gujarat Earthquake Rehabilitation and Reconstruction Project. Manila (Loan No.1826-IND, for $500 million, approved on 26 March 2001).

4 ADB. 1996. Country Operational Strategy. Manila. This was designed to support Government efforts to strengthen

the economic and social development of the country. The text is slightly modified and reproduced from the RRP, paras 25-27.

3

was formulated to rehabilitate damaged infrastructure and housing and provide support for livelihood rehabilitation to enable people to rebuild and resume normal life by restoring basic services such as drinking water and electricity, and to foster economic opportunities. This focus was fundamental for resuming the socioeconomic development process in Gujarat, one of ADB’s focal states. The Project was therefore in line with ADB’s COS for India and was in accordance with ADB’s overarching objective of poverty reduction.

B. Project Outputs

9. Most project outputs were achieved with some adjustments in scope, components and coverage. The major deviations in project scope are summarized below. Detailed achievements of outputs are elaborated in Appendix 1.

10. Part A: Housing. Despite the major change in scope resulting from the transfer of owner-constructed housing from the Project to the World Bank, the rural housing reconstruction by the NGO–government of Gujarat partnership financed by ADB was implemented successfully, with 41,902 houses constructed, exceeding the original target of 37,150 houses. Table 1 shows the details of houses built under various categories.

Table 1: Reconstruction under Public–Private Partnership

Package Description Villages Completed 1 Complete relocation at new site 24 5720

1+2 Partial relocation at new site 37 10014 2 In situ rehabilitation 77 14396

2B In situ rehabilitation with no Government share

148 11772

Total 286 41902

11. Most of the public–private partnership houses were built in situ with multi-hazard resistant technology after extensive consultation with beneficiaries. Over 29,600 masons and 6,500 engineers were trained in multi-hazard resistant housing construction and reconstruction. These houses are registered under the joint ownership of the husband and wife and have been insured. Compared to the pre-earthquake situation, the quality of construction has improved, houses are larger, and the proportion of houses with separate toilets has doubled (to 64%).

12. Part B: Urban and Rural Infrastructure. Gujarat Urban Development Company (GUDC) was entrusted with rebuilding urban infrastructure in 14 towns. The focus went beyond replacing lost capital stock and included the creation of holistically planned urban infrastructure in the towns. About 180 public consultations were held within 8 months to facilitate urban planning and relocation.

13. The four towns of Kutch that suffered major damage (Bhuj, Bhachau, Anjar and Rapar) were planned with a 20-year design horizon, so that the rebuilt towns would not be as vulnerable to future disaster risk. GUDC conducted 19 geotechnical and geological studies to determine the safety of in situ rebuilding. Development plans and town planning were completed at an accelerated pace in a consultative process with affected people. To ensure safety through building code compliance, the general development control regulations were amended to incorporate Indian Standard Codes for seismic and cyclone safety. The height of buildings in the four towns was restricted to two floors (ground floor plus one floor above). Congestion in the

4

towns was relieved through building of new housing areas and proper layouts with wider roads, while revised regulated development zoning addressed aesthetics and reduced future vulnerability by enabling more rapid emergency response. The four towns have been provided with a new upgraded water supply, internal roads, bypass roads, street lighting, public buildings and sewerage. The urban infrastructure in the 10 other towns that received less damage has been upgraded selectively, subject to need.

14. Significant economic growth has been realized in the reconstructed towns subsequent to the Project, and is a testimony to the Project’s successful implementation. In the 400-year-old town of Bhuj, which was badly damaged in the earthquake, in-situ town planning was carried out that led to large-scale modernization of civic infrastructure. It also resulted in the need to accommodate people affected by the earthquake in alternative rehabilitation sites, and GUDC consequently built three new relocation sites around Bhuj, where real estate values have appreciated significantly.5 Urban planning schemes and development plans were prepared to avoid haphazard development, and local ADAs were formed by the four major affected towns in the Kutch area to guide the planned development and redevelopment.

15. Rural infrastructure was composed primarily of water supply and roads. GWSSB was the IA for water supply distribution systems, GWIL for bulk water delivery systems and the Roads and Building Department for roads. After substantially implementing the highest-priority earthquake-affected water supply works in the first 3 years, the works with the next level of priority were implemented during the project extension period. Pipes damaged in the earthquake were replaced with corrosion-resistant metallic pipes with flexible joints. GWSSB & GWIL together implemented 60 contracts for 20 regional water supply schemes, which provided an improved water supply to 27 towns and 1867 villages. Within villages, distribution of water and operation and maintenance (O&M) of the system is being carried out in partnership with NGOs. These works helped provide a solution to the problem of drinking water in drought prone Kutch and adjoining districts. The final benefit monitoring and evaluation (BME) report6 states that close to 80% households now have access to piped water supply as against only 30% pre-earthquake. Restoration of water supply both in urban and rural areas was critical for ensuring health and hygiene in the earthquake affected areas. About 3,600 km of major district roads and village access roads in 12 districts were rehabilitated and upgraded by the Roads and Building Department.

16. Part C: Power. Restoration of the power supply was the most critical activity upon which all other relief and restoration measures depended. The earthquake disrupted the power supply to all nine towns and 925 villages in Kutch, with severe damage to transmission and distribution systems in Kutch and Rajkot. The Gujarat Electricity Board (GEB) acted quickly to restore partial power within 7 days of the earthquake to the affected areas. The short-term objective was to repair substations and provide temporary accommodation for operations staff. The medium- to longer-term objective was to replace redundant and damaged equipment, transmission lines and transformers to ensure reliable functioning of the power transmission and distribution systems and to improve system efficiency. Both the short- and long-term objectives have been met.

17. Part D: Livelihood Restoration. Cottage and village industries, a vital component of the economy, was affected through loss of assets, working capital and loss of demand due to the

5 The price of residential sites allotted to beneficiaries at the three relocation sites by the Bhuj Area Development

Authority was Rs20,000–Rs35,000 in 2002. Their market value in June 2008 was Rs400,000–Rs600,000. 6 The benefit monitoring and evaluation study was done by consulting firm KPMG.

5

earthquake. The Project focused on creation of an enabling environment by providing one-time assistance. Utilization of various types of assistance was between 92% and 100%. These measures helped restore and increase employment and income levels (refer footnote No.6).

18. The women’s livelihood restoration program was highly successful. The Project focused on facilitating social and economic activities for the benefit and empowerment of women. Under the component 16,030 women were targeted as beneficiaries and 14,147 actually benefited in the five earthquake-affected districts. The self-employment scheme targeted 2,500 women, with assistance in the form of working capital through a revolving fund for entrepreneurship. Employment has increased from 54% soon after the earthquake to 93%; the incomes of 72% of respondents have reportedly increased (refer footnote No.6).

19. Part E: Consulting Services and Incremental Administrative Support. Eighteen consultancies were awarded to provide assistance to the various IAs for tasks such as town planning, capacity building, training, design and supervision, technical audit material inspection and quality assurance. Summary details are provided in Table 2. These consultancies resulted in the Project being well designed, supervised, monitored and implemented.

Table 2: Summary Details of Consultancies

EA / IA Component Consultant firm(s) Purpose

GSDMA All KPMG BME

Housing NCCBM Technical audit and quality assurance of housing & buildings

Housing & disaster preparedness

Babtie Design of buildings and capacity building of IAs

Disaster preparedness LD College of engineering Training

Disaster preparedness Indian Institute of Technology, Kanpur

Training & capacity building

GUDC Urban infrastructure Gherzi Eastern Design & supervision

Urban infrastructure TCE Design & supervision

Urban infrastructure Dalal Town planning

Urban infrastructure CES Town planning

Urban infrastructure LEA Associates Town planning

Urban infrastructure EPC Town planning

ADAs Urban infrastructure Stup and CES, Technical advisory cells

Design Point Draft town planning scheme

GEB Power CES Buildings design & supervision

GWSSB Rural infrastructure (water supply)

Mecon Supervision and material inspection

R & B Rural infrastructure (roads)

Lea Technical audit and quality assurance

6

SPAN Technical audit and quality assurance

ADAs= Area Development Authority, BME= Benefit Monitoring and Evaluation , CES= Consulting Engineering Services, EPC= Environmental Planning Collaborative, GSDMA= Gujarat State Disaster Management Authority, GUDC= Gujarat Urban Development Company, GEB= Gujarat Electricity Board, GWSSB= Gujarat Water Supply and Sewerage Board, IA= implementing agencies, KPMG= KPMG Consultant, LD= LD College of Engineering, LEA= Lea Associates South Asia Pvt. Limited, NCCBM= National Council for Cement and Building Materials , TCE Consulting Engineers Ltd. Source: From GSDMA records and ADB Loan Financial Information System

20. Part F: Multi-Hazard Disaster Preparedness and Mitigation. Seismic equipment was procured through GERI and installed at 40 seismological observatories in Gujarat that are linked to the Institute of Seismic Research at Gandhinagar, enabling 24-hour online monitoring of earthquake activity. A “Planet Earth” pavilion has been constructed in Science City, Ahmedabad to improve disaster awareness among the general public. This work was 67% complete by the loan closing date; the remainder of the financing was provided by government of Gujarat and the building is substantially complete and exhibits are being procured and installed. Sophisticated medical emergency equipment (cardioscope pulse oxymeter, transport ventilator and defibrillator) has been procured by GSDMA and is in use. GUDC has procured 116 ambulances and provided them to local urban bodies for use in emergencies. Some components that were initially to be procured under the Project were instead procured by other bilateral and/or World Bank-financed components that included grant financing.

C. Project Costs

21. At appraisal, the project cost was estimated at $625 million, comprising foreign exchange of $513 million equivalent and local currency cost of $112 million equivalent; the ADB loan amount was $500 million. After five partial loan cancellations the loan amount was reduced to $315.14 million.

22. With the exception of three contracts, all the components comprising 333 contract packages have been fully implemented. Table 3 below provides a summary (by agency) of all contracts. The non-contracted amount of $13.54 million was spent on incremental administration and front-end fees.

Table 3: Summary of Contract Packages executed by each Implementing Agency

Agency No. of Contracts Contract Value ($ Million)

Undisbursed ($ Million)

GWSSB and GWIL 60 135.3 11.6 GUDCO 89 80.7 10.0 GEB 26 35.1 3.9 R&B 97 31.9 2.0 GSDMA 14 21.9 1.6 CCI 5 6.1 1.2 GERI 19 1.0 0.1 Others, towns 23 24 4.0 Total 333 336 34.4

CCI= Commissioner of Cottage Industries, GWSSB= Gujarat Water Supply and Sewerage Board, GWIL= Gujarat Water Infrastructure Limited , GUDCO= Gujarat Urban Development Company, GSDMA= Gujarat State Disaster Management Authority, GEB= Gujarat Electricity Board, GERI= Gujarat Energy Research Institute, R&B= Road and Building Source: GSDMA

7

D. Disbursements

23. Implementing such a large-scale, complex project spread over a large area within the originally specified 3-year period may have been overly ambitious. Implementation time doubled (from 3 to 6 years), and disbursements were consequently also spread out over 6 years. Provision of an imprest account was very helpful, but procedural delays at various levels resulted in ADB reimbursements to GSDMA being delayed, instead of being made “immediately” as specified in the Loan Agreement. For claims less than $100,000 the statement of expenditures (SOE) procedure was used and regular audit and verifications of SOE were carried out.

24. GSDMA suggests that the loan amount at completion should be flexible, because in every loan the IAs retain their allocations as long as possible before surrendering them. The IAs rated ADB’s procurement processes as good, but consider the disbursement process less efficient than the World Bank’s procedures. ADB’s requirement that reimbursement funds should reach the Second Generation Imprest Account (SGIA) immediately was not achievable. GSDMA also suggests that the EA should be allowed to maintain the SGIA as an interest-bearing savings account rather than a non-interest-bearing current account. This would avoid a loss of interest to borrower, and reduce the loan burden by providing interest income that could be utilized for incremental administration expenditures.

E. Project Schedule

25. After substantially implementing the highest-priority earthquake-affected works in the first 3 years, the remainder of the works were approved by GSDMA and implemented during the subsequent 3-year project extension period. This was possible due to (i) high competition among bidders, resulting in lower-than-estimated costs; and (ii) extensive use of ICB, which had the additional advantage of tax benefits to Indian suppliers. GSDMA had multiple sources of project finance and logically maximized the use of grants and kept tight budgetary control. Initially only the highest-priority works and activities were approved. When it became clear that significant savings had accrued, the lower priority works were approved. Both primary and secondary objectives were achieved within the estimated cost, but with a 3-year time extension.

26. Implementation delays resulted from (i) the lengthy (9–14 month) period to award ICB contracts, due to the need for multiple approvals by the IAs, GSDMA and ADB; (ii) cancellation of some contracts due to poor quality works or the slow pace of construction, necessitating re-tendering; (iii) provision of fraudulent bank guarantees by contractors led to contract cancellations and re-tendering, involving one GEB and three GWSSB contracts ; (iv) major steel price escalations following the award of a major ICB contract for mild steel pipe resulted in the contract not being completed, and the performance guarantee of the supplier being cashed, while three civil works contracts awarded in anticipation of the pipe supply had to be cancelled. All four contracts were re-tendered, causing a 14-month delay; (v) statutory clearances and permissions took a long time to obtain (e.g., from forest department and military authorities for the Bhuj ring road; from railways, the Gas Authority of India Limited and National Highways Authority of India for pipe crossings; and approval of the Design Supervision Consultant (DSC) engineers and their building designs by Gandhidham Development Authority); (vi) disruptions in processes and decision making as a result of frequent changes in the senior officials at the IAs, especially GUDC; (vii) late receipt of funds into the account of GSDMA sometimes caused delays in making payments to contractors; (viii) easement arrangements took much longer than expected; and (ix) encroachment removals had to be sensitively handled, which was time consuming.

8

F. Implementation Arrangements

27. Implementation arrangements envisaged at appraisal were substantially followed. A program-level project management consultant (PMC) (responsible to the Government, the Project, the World Bank, and bilateral and NGO-supported projects) was hired by GSDMA in place of an in-house PMC specially for the Project. Fourteen IAs were added to the original five, which made project management and processing more complex for both GSDMA and ADB. Most of the IAs (with the exception of GUDC) had management of fairly long tenure, thus ensuring continuity.

28. ADB’s extended mission in Gujarat (EMG) commenced in June 2001 and utilized two ADB staff consultants who coordinated effectively between IAs, GSDMA and the India Resident Mission (INRM). The GSDMA CEO stated that “The EMG, Gandhinagar has been very useful and many issues could be sorted out at Gandhinagar. The presence of EMG has expedited procurements and also has been extremely helpful in monitoring of the project. The EMG has been acting as a very useful link between ADB, New Delhi, GSDMA and other implementing agencies” 7.

29. Implementation arrangements for the Project, including empowering of GSDMA by the government of Gujarat and fielding of the EMG by ADB, were highly successful.

G. Conditions and Covenants

30. Processing and Board Approval for the loan were undertaken quickly as per the enabling procedures under the 1989 ADB emergency loan policy.8 The project performance rating by ADB for the overall Project was satisfactory.

31. Submission of audited financial accounts and financial statements generally were within the specified time. Instead of the 5 working days specified in the loan agreement, internal approvals within GSDMA and/or the IAs sometimes took 15 to 30 days. The condition specifying submission of a report within 3 months of physical completion of each subproject by GSDMA on the execution and initial operation of the Project could not be complied with. GSDMA submitted regularly monthly and quarterly progress reports, but could not submit a report on each of the approximately 300 subprojects; the IAs were busy with implementation and could not complete the necessary paperwork. All required environmental clearances for sewage treatment plants and landfill sites were obtained, and all social and financial covenants have been complied with.

32. The covenant requiring immediate credit of disbursement proceeds into SGIA was not complied with. The many levels of approvals and attendant delays resulted in ADB disbursements taking 2–3 months to be credited to SGIA. The status of compliance with loan covenants is shown in Appendix 7

H. Related Technical Assistance

33. TA for Capacity Building for Earthquake Rehabilitation and Reconstruction (refer footnote 2) had dual objectives: assisting GSDMA on a daily, hands-on basis throughout the rehabilitation process and building disaster management and training capacity within the state. The objectives of the TA were substantially achieved; further details are in Appendix 12.

7 Letter from CEO, GSDMA to ADB, 14 October 2003. 8 ADB. 1989. Rehabilitation Assistance After Disasters. Manila (R191-88).

9

I. Consultant Recruitment and Procurement

34. Goods, civil works, and services were procured in accordance with ADB’s Guidelines for Procurement and Guidelines on the Use of Consultants in force at the time of the Project. Because the Project was an emergency project, and to reduce procurement time, two GUDC DSCs and a GEB DSC were recruited by inviting proposals from firms already working on various ADB-financed projects in India. Preparation of the bid documents and bid evaluation reports plus long and multistage approvals needed within the IAs, GSDMA and ADB delayed the ICB contract awards.

35. The program-wide PMC was financed by the World Bank, and as a result 192 person-months of PMC inputs provided for at appraisal were not utilized. A total of 320 person-months of BME consultant inputs were envisaged at appraisal, while actual deployment was 150 person-months. At appraisal, 3600 person-months of consulting services using individual domestic consultants were envisaged to assist GSDMA for housing design and construction supervision for which National Council for Cement and Building Materials provided 1100 person months. This reduction was primarily due to the shifting of the owner-driven housing component from the ADB loan to the World Bank loan. For urban and rural infrastructure 426 and 389 person-months of DSC input, respectively, were estimated at appraisal. The actual number of consulting firms and person-months of deployment, especially for urban infrastructure, was far higher (1490 person-months), because preparation of mandatory town planning schemes and development plans required far more intensive effort than estimated. The nascent ADAs needed technical advisory cells to provide guidance regarding approvals and in the design of multi-hazard-resistant structures. A total of nine consulting firms were used for the urban infrastructure component. For rural infrastructure Mecon provided 924 person-months of inputs. Consulting Engineering Services provided 72 person-months of inputs to GEB as DSC for the power component, compared to the 24 person-months originally envisaged. This increase was due to the scope of consultant services being expanded to include skeletal supervision in addition to the design services envisaged at appraisal. All the domestic consultants started their services between 2001 and 2003. The consultants undertook urban planning, topographical surveys, site investigation, detail design, construction supervision, and material inspection. Some of the consulting services had to be extended because of delays in project implementation. Overall, the project required 4342 person-months of domestic services, compared to the 4951 person-months provided for at appraisal.

J. Performance of Consultants, Contractors, and Suppliers

36. The performance of all the domestic consultants, except Gherzi Eastern, was rated satisfactory. Although not all consultants initially fully understood ADB procedures, the domestic consultants supervised the works efficiently and their reports were of acceptable quality. Gherzi Eastern’s services were terminated by GUDC because the collapse of an overhead reservoir in Bhuj was partly attributed to improper design and to some extent to poor supervision.

37. The IAs, contractors, suppliers, and consultants maintained close coordination and good relations, which allowed the Project to be completed without any major disputes. However, four contracts (all for works) were terminated due to fraudulent bank guarantees (one for GEB civil works and 3 for GWSSB design and build civil works), and nine contracts (six by GWSSB and three by GUDC) were terminated due to non-performance. One of the contractors whose two contracts were terminated by GUDC is still pursuing claims through the courts. Considering that 344 contracts were awarded under the Project, these problems may be considered minor and

10

acceptable. The terminated contracts were re-tendered and the envisaged scope of work was completed, albeit with delays.

K. Performance of the Borrower and the Executing Agency

38. The Borrower demonstrated strong ownership of the Project at the highest level, through (i) regular participation in bilateral and tripartite meetings with the Government and ADB, and (ii) timely provision of adequate counterpart funds.

39. GSDMA is credited with steering the Project well with the continuous support of the state ministerial-level governing body. GSDMA was provided executive authority and powers by the GSDMA Act passed by the state legislature. The success of GSDMA is attributed to its sustained focus on rehabilitation, selection of a good leadership team, and complete support from the government of Gujarat. Implementation of the Project has resulted in reconstruction of earthquake-affected infrastructure, homes, and buildings to multi-hazard resistant standards, as well as restoration of livelihoods. GSDMA was selected for two awards: the UN-Sasakawa award for disaster reduction in 2003 for its outstanding work in disaster management and disaster reduction, and the gold medal in the fourth biennial (2004) Commonwealth Association for Public Administration and Management–international innovations awards program for initiatives undertaken in governance. Performance of GSDMA is rated as highly satisfactory. The transfer of funds from the Government to the SGIA took about 3 months, because ADB disbursements must move through the Government, the Reserve Bank of India and the state finance department. ADB disbursements did not immediately reach the SGIA despite the best efforts of GSDMA, leading to suspension of disbursement by ADB on a number of occasions.

L. Performance of the Asian Development Bank

40. This was the first ADB-financed emergency project in India. ADB provided GSDMA and the IAs with training, quick approvals (in most cases), regular monitoring and advice. ADB provided the EMG in Gujarat with two full-time staff consultants who coordinated and facilitated bidding, contract awards and implementation, and GSDMA is on record as appreciating the EMG contribution. ADB has subsequently provided similar field-level support for two ongoing projects in India: the Tsunami Emergency Assistance (Sector) Project in the states of Tamil Nadu and Kerala9, and the Multi-Sector Project for Infrastructure Rehabilitation in Jammu and Kashmir10. ADB staff and EMG conducted many seminars for project staff on disbursement, procurement and project administration. ADB staff spent 252 field days (instead of the planned 91 days) in review and disbursement missions, and extended much assistance to GSDMA and the IAs. During implementation, ADB acted promptly to address problems as they occurred. Based on the above, ADB’s performance is rated satisfactory.

9 ADB. 2005. Report and Recommendation of the President (RRP) to the Board of Directors on a Proposed Loan to

India for the Tsunami Emergency Assistance (Sector) Project. Manila (Loan No.2166-IND, for $100 million, approved on 14 March 2005).

10 ADB. 2005. Report and Recommendation of the President (RRP) to the Board of Directors on a Proposed Loan to India for the Multisector Project for Infrastructure Rehabilitation in Jammu and Kashmir. Manila (Loan No.2151-IND, for $250 million, approved on 21 December 2004).

11

III. EVALUATION OF PERFORMANCE

A. Relevance

41. The Project was approved by ADB within 2 months of the major earthquake in Gujarat. The Project adopted a comprehensive approach to disaster management, formulating a reconstruction and rehabilitation program focusing on reducing risk and vulnerability. The Project was highly relevant, and helped rebuild housing, urban and rural infrastructure and livelihoods in earthquake-affected areas. The Project’s reconstruction was undertaken to a standard that ens-ures that future earthquakes will have minimal impact on the community. The Project was completed as initially planned except that owner-driven housing component was shifted from ADB to World Bank financing, resulting in a major ($150 million) reduction in the project loan. The Project achieved its goals and is rated “highly relevant”.

B. Effectiveness in Achieving Outcome

42. The Project fully achieved its objective of rehabilitation and reconstruction of damaged infrastructure and housing, and assisted in livelihood rehabilitation (refer Appendix 1)-----. It is now possible for people living in the earthquake-affected areas to resume their normal lives with better quality infrastructure and housing that have been built to resist multiple hazards. Basic infrastructure—such as drinking water, electricity, sewerage, sanitation and public buildings—is more widely available and far superior in quality than before the earthquake. The Project is rated “effective” in achieving its outcome.

C. Efficiency in Achieving Outcome and Outputs

43. The project funds were used efficiently. The money allocated was sufficient to complete the highest-priority works in about 3 years, and the balance of the loan funds were used to award and complete the remainder of the lower-priority works. Money was available from various sources and the use of grants and low-interest finance was maximized. Cost savings in the original scope were used to implement additional works, such as provision of water supply to Jamnagar district, improvements to rural roads and procurement of goods. The $150 million urban housing component was transferred to the World Bank to take advantage of grant funds (IDA credit of 40 years with 1% interest), with the equivalent ADB loan amount cancelled well before the project completion date. ADB support to the Project was both flexible and highly responsive. The Project is rated “efficient” in achieving the initially stated outcome and outputs.

D. Preliminary Assessment of Sustainability

44. The Project is “likely” to be sustainable. Drinking water supply and power are managed by experienced and efficient state organizations. O&M of facilities in some rural areas constructed under the Project, including water treatment plants and pumping stations, has been contracted out and these are being well maintained. However some municipally owned assets (such as water treatment plants and sewage pumping stations) are only being partially or sub-optimally used, especially in the town of Anjar.

45. The staff quarters of various utilities in urban areas are fully occupied, whereas those in rural areas are either empty or have been rented out. While the rented buildings are sustainable, the original objective of housing the O&M staff near their place of work has not been fully achieved. Municipal governance needs to be strengthened; public–private partnerships need to be explored to enable optimal utilization of municipal assets. A capacity-

12

building and revenue-enhancement program for the municipalities may be necessary to make urban municipal assets more sustainable. Privately owned assets such as rural houses built under public–private partnerships and livelihood tools and equipment programs are very well maintained.

E. Impact

46. Because the Project comprised an emergency loan that was very quickly prepared and approved, apart from the requirement to comply with the applicable environment and resettlement guidelines, no specific environmental and other safeguards were included in the RRP (refer footnote 3) or Loan Agreement. Implementation of the Project greatly enhanced the quality of both the built and natural environment, which had deteriorated due to the earthquake. All statutory environmental clearances for the facilities constructed under the Project have been obtained by the respective IAs. The Project was classified under environmental category B, because of potentially adverse environmental impacts related to centralized sewage and solid waste collection facilities.

47. The Project carried out resettlement of people who lost their homes as a result of the earthquake, but all resettlement was voluntary; the new serviced housing lots were offered at a token price, and GSDMA provided grants for house construction in accordance with state policy. The Project had no indigenous peoples issues. To lay water supply pipes in rural areas GWSSB and GWIL used easement arrangements with agricultural land owners. Positive social outcomes of the Project are (i) the choice of relocation or in situ reconstruction was determined by the village community. Newly built houses have been provided with access roads, electricity, water supply and community buildings, thereby restoring community life; (ii) livelihood support ensured that rural handicraft workers and tradesman now generate more substantial incomes, as they are better organized, have more skills, have been supplied with tools and been given a marketing platform; (iii) small industries, kiosks, shops, service and trade units were provided with cash assistance and/or temporary subsidies enabling them to regain their livelihoods; (iv) about 47,000 farmers were provided with input kits, assistance for construction of farm structures and irrigation assets such as tube wells and pumps; (v) livelihood creation and restoration for women benefited 14,147 women, from both conventional (e.g., handicrafts) and innovative sources (such as growing of aloe vera); and (vi) GSDMA has established itself as an effective institution for disaster preparedness, capacity building and disaster management.

48. Based on the above, the negative environmental and sociocultural impacts are rated negligible and the positive impacts significant. The overall strategy, policy and mechanisms of government of Gujarat and GSDMA for enabling rehabilitation and resettlement that is responsive to the community have been effective. There is a recognition by all stakeholders that the government of Gujarat was flexible and adopted a consultative process during both the relief and rehabilitation phases.

IV. OVERALL ASSESSMENT AND RECOMMENDATIONS

A. Overall Assessment

49. GSDMA and all the IAs consulted agreed that the Project was successful, and this feeling is shared by the beneficiaries. GSDMA is credited with steering the Project successfully with the continuous support of the government of Gujarat. The success of GSDMA is attributed to its sustained focus on rehabilitation, selection of a good leadership team and the total support of the state, with GSDMA provided authority through the GSDMA Act. The state’s capacity and

13

emergency response preparedness has been built up by the Project, and the assets that were constructed are being operated sustainably.

50. The Project was prepared, approved by ADB, signed and made effective rapidly, which suited the emergency situation and allowed a flexible response. All initial subprojects identified at appraisal were completed by the revised loan closing date of 30 June 2007, with one exception. The quality of works was acceptable. While there were implementation difficulties, including nine contracts that had to be terminated and re-tendered, the overall outcome of the Project was as anticipated. In conclusion, overall performance of the Project is rated “successful”.

B. Lessons

51. The construction of public buildings and staff quarters should be selective and minimized given the inability and/or lack of interest by municipalities to maintain and use them for the planned purpose. In particular, utility staff quarters should be built only where there is a need, such as in urban areas. In rural and/or remote locations these quarters are often not required or utilized effectively, because maintenance of the facilities is often contracted to the private sector.

52. Works, particularly within urban areas, should be sequenced so that water supply, sewerage, drainage, shifting of utilities (power and telephone lines, underground pipes and cables) is substantially complete before road contracts are awarded. Alternatively, road contract requirements and completion times should allow for re-construction or proper reinstatement following water supply and sewerage contracts.

53. ADB stipulates that reimbursement be “immediately” credited to the SGIA. The transfer of funds from the Government to the SGIA takes about 3 months. ADB disbursements must move through the Government, the Reserve Bank of India and the state finance department, meaning that “immediately” needs to be appropriately defined.

54. The loan was processed under the ADB 1989 emergency assistance policy and approved on 26 March 2001 with a loan closing date of 30 June 2004. Implementing a large-scale reconstruction program within the 3 years originally provided was not practical. Due to the scale and spatial spread of destruction cause by the earthquake, the consultation and planning process took nearly 2 years, leaving little time for actual reconstruction, which took an additional 3 years. In retrospect, the Project could have been better prepared as two separate loans, one for the recovery phase of immediate relief and rehabilitation and the second as a normal or sector loan project covering the reconstruction phase. Interestingly, the revised ADB Disaster and Emergency Assistance Policy11 does suggest separate financing facilities for recovery, transition and prevention. In the recovery phase, which is generally limited to 2 years for natural disasters, only immediate, short-term assistance is provided for the rehabilitation or reconstruction of critical infrastructure. This period can be exceptionally extended at most by an additional 2 years, taking into account the weakened absorptive capacity of the EA following the disaster. The transition and prevention phases can take longer and should use normal development projects and financing facilities.

55. Capacity building for O&M of assets requires careful attention and needs to be incorporated into loan processing, and included in the follow-up to the emergency loan. The

11 ADB. 2004. Disaster and Emergency Assistance Policy. Manila (R71-04).

14

capacity of municipalities to operate and maintain the urban municipal assets created under GERRP is limited. The government of Gujarat, GSDMA and GUDC will need to help municipalities with capacity building related to revenue collection and O&M.

56. Financing of O&M was not possible under the Project because an enabling policy did not exist in 2001. This resulted in less-than-optimal utilization of assets under the Project in a few instances. The ADB innovations and efficiency initiative on cost sharing and eligibility of expenditures now makes O&M costs eligible for financing.

C. Recommendations

1. Project Related

57. Statutory Clearances. Appropriate coordination mechanisms at the highest level are necessary to reduce the time needed for obtaining statutory clearances, if necessary, especially those required from union government departments such as railways and forests.

58. Sustainability. Better dialogue is often required between the EA and/or IAs and end-user agencies (e.g. municipalities) to prepare end-users to assume responsibility for and undertake O&M of the newly created assets within agreed timelines. Capacity building and training of urban local governments needs to start at an early stage of project implementation to enable them to better manage the newly constructed infrastructure. A program for strengthening the financial, management and O&M capabilities of urban municipalities should be implemented.

59. Future Monitoring. Continued monitoring of the project for 2 years is recommended, including provision of advisory services for improvement of O&M of assets. Fielding of follow-up missions every 6 months would be useful. ADB may consider providing advisory TA to explore the possibility of Public Private Partnership (PPP) for sustainability of urban assets and strengthening the competency of municipalities.

60. Covenants. Most of the project covenants were appropriate and adequately complied with, and the Loan Agreement covenants should consequently be maintained. The only covenant that should be reexamined is the requirement that disbursement proceeds be immediately credited into the SGIA.

61. Further Action or Follow-Up. The Project has been completed successfully and loan accounts properly closed following five partial loan cancellations and cancellation of the undisbursed loan amount. The project objectives as set forth at appraisal have been met.

62. Additional Assistance. GUDC may require TA to formulate PPP options to strengthen municipal capacity for optimal O&M of urban assets created under the Project. GSDMA would need to ensure that the $75 million worth of additional disaster management equipment proposed to be procured from World Bank finance or Government of Gujarat budget sources is procured and deployed early. GSDMA is considering assessing approximately 1 million houses to determine their earthquake resistance and strengthening needs. If the assessment shows that a significant number of houses need retrofitting, the provision of the needed financing could be considered as a new ADB loan.

15

63. Timing of the Project Performance Evaluation Report. The project performance evaluation report may be carried out in mid-2009 to allow time for the two GWSSB contracts in Jamnagar to be completed and O&M arrangements to be properly established.

2. General

64. Complex and widespread emergency assistance projects need more time for completion than the 2 to 4 years allowed for under the 1989 ADB emergency assistance policy, 12 which was in effect at the time the Project was implemented. The revised policy (2004) enables ADB to provide two separate financing facilities in the case of complex emergency assistance projects. Urban reconstruction, consultation and proper planning can themselves take 1–2 years. Future complex projects should first provide an emergency assistance loan and/or grant for immediate short-term recovery, rehabilitation and reconstruction to address shelter, food, public health, livelihood, water supply and sanitation needs. The second loan should be provided through a normal loan facility for medium- to long-term construction investment, risk-prevention and preparedness activities; to address planned urban reconstruction; and strengthening or expansion of water supply, power and transport. The revised emergency assistance policy has made this possible.

65. Construction of new buildings for public utilities should be selective and based on need, given the apparent inability or lack of interest of municipalities to use and maintain these for their original purpose. In particular, staff quarters should only be built within urban areas. Experience has shown that buildings in rural and/or remote locations are not utilized effectively.

66. Urban works should be sequenced so that water supply and sewerage are substantially complete before road contracts are awarded. Alternatively, road contract requirements and completion times should allow for reconstruction or proper reinstatement following water supply and sewerage contracts.

67. ADB disbursement processes could be aligned with World Bank processes, with the stringent conditions governing the use of and time limit for crediting the SGIA relaxed.

12 The 1989 policy Rehabilitation Assistance after Disasters (footnote 6), issued in February 1989, has been revised

as the Disaster and Emergency Assistance Policy (footnote 7).

Appendix 1 16

PROJECT COMPONENTS AND OUTPUTS

1. Part A: Housing. The nongovernment organization (NGO)-government of Gujarat partnership rural housing reconstruction financed by the Asian Development Bank (ADB) was implemented by building 41,902 houses instead of the originally targeted 37,150 houses. Owner-driven housing (involving construction of approximately 200,000 new and repairs and retrofitting of 800,000 existing houses) was to be financed by ADB, but this component was transferred to a World Bank loan by the Gujarat State Disaster Management Authority (GSDMA) due to the lower financing cost. The houses built under the NGO-government of Gujarat partnership are larger and of better quality than those that existed before the earthquake, and the number of houses with separate toilets has doubled (to 64%).

2. GSDMA’s housing construction program covered a vast geographical area comprising 21 out of 27 districts of Gujarat and included 7633 villages and many urban areas. The ADB-financed government of Gujarat-NGO partnership housing covered 286 villages in 12 districts. The housing recovery program was converted into the largest disaster-preparedness program with people’s participation. The government of Gujarat has been able to convert housing reconstruction in the affected areas into a participatory, long-term disaster (earthquake and cyclone) preparedness program by adopting an owner-driven reconstruction strategy, assisting owners financially and technically, and providing materials.

3. Part B: Urban and Rural Infrastructure. The Gujarat Urban Development Company (GUDC) was the implementing agency (IA) for urban infrastructure in 14 towns, including four in the Kutch district (Bhuj, Anjar, Bhachau and Rapar) that suffered the maximum impact from the earthquake. About 180 public consultations were held to facilitate urban planning and relocation activities. Table 1 lists the works implemented in the 14 towns by GUDC.

Table A1.1: Works Implemented in the 14 Towns by GUDC

Item Scope

(Number of contracts and size) Completed Cost of Work Rs. millions.

Roads 26 350.45 Km 350.45 Km 1845.0 Water Supply 702.92 Km 702.92 Km Sewerage 27 352.24 Km 352.24 Km WSS Structures 52 Nos. 52 Nos.

1661.5

NH I Railway Crossings

9 16 Nos. 16 Nos. 55.4

Buildings 18 174 Nos. 174 Nos. 392.4

5

Goods – Municipal Solid Waste Management

642 - Container 30 - Tractor

15- Dozer 15- Loader

15 - Power Tiller 17 - Dumper

Placer 15 – Vacuum Emptier

642 - Container, 30 - Tractor,

15- Dozer, 15- Loader,

15 - Power Tiller, 17 - Dumper

Placer, 15 – Vacuum Emptier

73.8

1

Disaster Management Component

116 Ambulances

116 Ambulances 64.1

Total 4031.7

Appendix 1 .

17

Km= kilometer, GUDC= Gujarat Urban Development Company, NH = National Highway, WSS= Water Supply and Sewerage Source: From Gujarat Urban Development Company records

4. Urban works were implemented by the municipal corporations. Ahmedabad and Rajkot cities had significant outlays. The Ahmedabad Urban Development Authority (AUDA) implemented water supply, sewerage and drainage works outside the Ahmedabad municipal limits.

5. Rural infrastructure comprised water supply and roads. GWSSB was the IA for water supply distribution systems, Gujarat Water Infrastructure Limited (GWIL) the IA for bulk water delivery systems, and the Roads and Buildings Department the IA for roads. The activities planned and implemented under the water supply component were reconstruction of village-level facilities (e.g., storage systems), reconstruction of water distribution networks, strengthening of water pipeline transmission systems, and upgrading of the pumping and captive power generation system. GWSSB and GWIL together implemented 60 contracts for 20 regional water supply schemes in which 2,576 kilometers (km) of pipeline was laid, based on village clusters, which ensured regular water supply to 27 towns and 1857 villages. Construction under the 60 contracts included 619 water supply structures (reservoirs, pump rooms, and staff quarters), 270 pump sets, and 17 water treatment plants. Tube wells (222) were drilled in the 152 villages that had no other reliable water supply source.

Table A1.2: Works Implemented by GWSSB

Component Units Target Completed Work in progress

% completed

Tube wells No. 222 222 0 100% Pipelines Km 2,689.46 2,576.10 45.20 96% Civil Works No. 619* 602 0 100% Pumping machinery and related electrical works

No. 270 270 0 100%

Water treatment plant No. 17 17 0 100% Railway crossing (Box culvert)

No. 5 5 0 100%

Pipe lining Works Km 40 40 0 100% Km= kilometer, GWSSB= Gujarat Water Supply and Sewerage Board Source: From Gujarat Water Supply and Sewerage Board records

6. About 3,600 km of major district roads and village access roads in 12 districts were rehabilitated and upgraded by the Roads and Building Department.

Table A1.3: Works Implemented by Roads and Buildings Department

Component Units Target Completed % completed Panchayat KM 1531.35 1531.35 100 State KM 1748.39 1748.39 100

Total KM 3279.74 3279.74 100 KM= kilometer Source: From Roads and Buildings Department Records

7. Part C: Power. The Gujarat Electricity Board (GEB) made every effort to bring the power supply almost back to normal within 7 days of the earthquake. Severe damage to transmission and distribution systems in Kutch and Rajkot occurred, and repair and

Appendix 1 18

strengthening of 2,547 km of the transmission network and 2,676 km of the distribution network was undertaken. All damaged transmission equipment (in five significantly affected districts) was repaired. Permanent buildings (67 in total, comprising control rooms, administrative buildings, and staff quarters) and temporary shelters (448) for GEB staff were built. Only 52% of the villages had electricity in the immediate aftermath of the earthquake, but all the villages now have access to electricity.

Table A1.4: Works implemented by GEB

Component Unit Target Completed % Completion (a) Reconstruction of GEB Buildings

Office Buildings No. 10 10 100 Quarters No. 44 44 100 Control Rooms Buildings No. 13 13 100

(b) Power Transmission Networks

Equipments No 465 465 100 220 KV lines Km 576.00 576.00 100 132 KV lines Km 2107.00 2107.00 100 66 KV lines Km 576.00 576.00 100

TOTAL Km 3259.00 3259.00 100

(c) Power Distribution Networks

Immediate Restoration Km 33.75 33.75 100

11 KV Dist. Lines Km 5355.37 5355.37 100 DIST. LT LINE: 3 Phase (4 & 5 wire) Km 150.51 150.51 100 DIST. LT LINE: 1 Phase (2& 3 wire) Km 236.11 236.11 100

Km 5775.74 5775.74 100 Repairs of distribution equipment Consumer service; damage to meters Single Phase Meter No 189000 189000 100

Three Phase Meter No 1527 1527 100 DIST. TRANSFORMERS No 4042 4042 100 10-60 amp TVM whole current meter No 30000 30000 100

100/5 CT operated meter No 1350 1350 100 CT= KV= kilo volt, GEB= Gujarat Electricity Board, Km= Kilometer, CT = current transformer, TVM= Tri vector meter Source: From Gujarat Electricity Board records

8. Part D: Livelihood Restoration. The earthquake caused cottage and village industries, a vital component of economy, to lose assets, working capital and demand. The Project focused on creation of an enabling environment by providing one-time assistance. Over 3,400 handloom weavers were provided with looms and as many as 2,500 were assisted with working capital assistance. More than 31,000 tool kits were distributed to artisans and handicraft workers. Small industries (1,629) were provided with subsidy assistance and 13,299 kiosks and shops were provided with cash assistance. A handloom park was set up with project assistance by an NGO, Swa Sanstha of Ahmedabad. Except for a very small minority who left their line of employment, most residents were actively employed, with demand returning to normal.

Appendix 1 .

19

9. The various schemes and beneficiaries under each component implemented by the Cottage and Rural Industries Department are presented Table 5.

Table A1.5: Beneficiaries Cottage and Rural Industries Department Program

Component Beneficiaries/Applications disbursed Loan subsidy 14,245 Tool kits to artisans 18,309 Tool kits to handicraft artisans 12,652 Toolkits to masons 27,000 Looms to handloom artisans 3,419 Working capital assistance for handloom weavers 2,500 Revolving fund scheme 7 TOTAL 78,132

10. The women’s livelihood restoration program was highly successful. Under the component 16,030 women were targeted as beneficiaries and 14,147 actually benefited in the five earthquake-affected districts. The self-employment scheme covered 2,500 women, and provided working capital through a revolving entrepreneurship fund. The Project focused on facilitating social and economic activities to uplift and empower women. Employment has increased from 54% soon after earthquake to 93%, and the incomes of 72% of respondents has reportedly increased 1.

Table A1.6: Details of Various Women’s Livelihood Restoration Projects

Beneficiaries Organization District Target

(In Nos.) Actual

(In Nos.)

Disbursement (Rs. million)

Cohesion Foundation Kutch/Rajkot 2898 3054 3.60 Gramin Seva Trust Surendranagar 325 275 2.60 Deepak Charitable Trust Surendranagar 900 900 5.42 HUM (Handspun Urban Market)

Kutch 350 350 2.25

Jivan Jamnagar 785 1224 6.77 Premal Jyot Society Rajkot 1500 739 1.55 Rudmi Surendranagar 450 450 1.91 Marag Surendranagar 700 658 3.33 Lok Vikas Patan 300 238 0.37 Yousuf Meherally Centre Kutch 510 510 2.20 Udyog Bharti Foundation Patan 300 181 0.36 Shri Vardhman Gruh Udhog Mahila Mandal

Surendranagar 250 250 1.49

Self Employment Projects All 5 districts 6762 5318 24.41 Give Foundation All 5 districts 0 0 0.23 Totals 16030 14147 56.49

Source: From Gujarat State Disaster Management Authority Records

1 The benefit monitoring and evaluation study was done by consulting firm KPMG.

Appendix 1 20

11. Part E: Consulting Services and Incremental Administrative support. Eighteen consultancies were awarded to provide assistance to various IAs for tasks such as town planning, capacity building, training, design and supervision, technical audit material inspection and quality assurance. Summary details are provided in Table 7. These consultancies benefited the design, supervision, monitoring and implementation of the Project.

Table A1.7: Summary Details of Consultancies

EA / IA Component Consultant firm(s) Purpose GSDMA All KPMG BME Housing NCCBM Technical audit and quality assurance

of housing & buildings Housing & disaster

preparedness Babtie Design of buildings and capacity

building of IA's Disaster preparedness LD College of engineering Training Disaster preparedness Indian Institute of

Technology, Kanpur Training & capacity building

GUDC Urban infrastructure Gherzi Eastern Design & supervision Urban infrastructure TCE Design & supervision Urban infrastructure Dalal Town planning Urban infrastructure CES Town planning Urban infrastructure LEA Town planning Urban infrastructure EPC Town planning ADA's Urban infrastructure Stup and CES, Technical advisory cells Design Point Draft town planning scheme GEB Power CES Buildings design & supervision GWSSB Rural infrastructure

(water supply) Mecon Supervision and material inspection

R & B Rural infrastructure

(roads) Lea Technical audit and quality assurance

SPAN Technical audit and quality assurance ADA= Area Development Authority, GWSSB= Gujarat Water Supply and Sewerage Board, GWIL= Gujarat Water Infrastructure Limited , GUDCO= Gujarat Urban Development Com pany, GSDMA= Gujarat State Disaster Management Authority, GEB= Gujarat Electricity Board, GERI= Gujarat Energy Research Institute, R&B= Road and Building Source: From GSDMA records and ADB Loan Financial Information System

12. Part F: Multi-hazard Disaster Preparedness and Mitigation. Seismic detection equipment was procured through the Gujarat Energy Research Institute and installed at 40 seismological observatories in Gujarat, which are linked to the Institute of Seismic Research at Gandhinagar, enabling online 24-hour monitoring of earthquakes. A “Planet Earth” pavilion has been constructed in Science City, Ahmedabad to improve disaster awareness. This work was two thirds complete by the loan closing date, with the rest of the funds provided by government of Gujarat. The building is now substantially complete and exhibits are being procured. Sophisticated medical emergency equipment (cardioscope pulse oxymeter, transport ventilator and defibrillator) has been procured by GSDMA and is in use. GUDC has procured 116 ambulances, 48 VHF base stations, 186 VHF mobile stations and 96 walkie-talkies and provided them to the urban local bodies for use in case of disasters and emergencies. Some components that were initially to be procured under the Project were shifted to other bilaterally and/or World Bank-financed components, as these included grants.

Appendix 2 .

21

BREAKUP OF FOREIGN AND LOCAL COSTS AF ADB FINANCING ($ million)

Appraisal Actual Item Cost Foreign

Currency Local Currency

Cost Foreign Currency

Local Currency

Part A Housing 250 30 220 16.75 2.01 14.74

Part B Urban & rural Infrastructure

217 45 173 293.3 60.82 232.48

Part C Power 98 24 74 45.62 11.17 34.45

Part D Livelihood Rehabilitation

20 2 18 6.32 0.63 5.69

Part E Consulting Services & Incremental Administrative Support

15 1 14 19.36 1.94 17.42

Part F Multi-hazard disaster preparedness & Mitigation

20 5 15 4.26 2.26 2.00

Front -End Fee 5 5 0 5 5 0

Total 625 112 513 390.61 83.83 306.78 Source: Asian Development Bank estimates.

Appendix 3 22

ALLOCATION AND /OR REALLOCATION AND ACTUAL DISBURSEMENT OF ADB FINANCING BY CATEGORY

($ million)

Category or Sub loan

Original Allocation

Last Revised

Allocation

Amount Cancelled

Net Amount Available

Amount Disbursed

Undisbursed Balance

Part A; Housing

200 12.50 187.50 12.50 12.35 0.15

Part B: Urban & Rural Infrastructure

173 248.74 (75.74) 248.74 238.38 10.36

Part C; Power 67 31.00 36.00 31.00 30.90 0.10 Part D; Livelihood Restoration

20 6.49 13.51 6.49 6.41 0.08

Part E; Consulting Services & Incremental Administrative Support

15 18.75 (3.75) 18.75 17.92 0.83

Part F; Multi-hazard Disaster Preparedness & Mitigation

20 5.50 14.50 5.50 4.18 1.32

Front End Fee 5 5.00 0.00 5.00 5.00 0.00

Total 500 327.98 172.02 327.98 315.14 12.84

Source: Asian Development Bank and Gujarat State Disaster Management Authority records

Appendix 4

23

CONTRACT AWARDS AND DISBURSEMENTS

Total Packages Contracts Awarded Component Allocation

Number Value Number Value ($million)

GUDC 73.26 74 73.77* 72 69.39

Rural Roads 31.00 90 30.96** 89 31.74

Ahmedabad Municipal Corporation 5.75 9 6.31 9 6.31

Rajkot Municipal Corporation 1.75 5 1.74 5 1.74

Baroda Municipal Corporation 0.09 1 0.08 1 0.08

Jamnagar Municipal Corporation 0.40 1 0.45 1 0.45

Ahmedabad Urban Development Authority

10.50 5 11.49 5 11.49

GWSSB 130.50 49 153.29*** 44 132.91

Power 35.00 48 31.47 48 31.47

Livelihood Rehabilitation 7.00 6 7.46 6 7.46

Consulting & Incremental Costs

18.75 21 17.18 21 17.18

Multi-hazard Disaster Preparedness 6.50 19 7.43**** 19 7.43

Total? 320.5 328 341.63 316 316.77 GUDC= Gujarat Urban Development Corporation, GWSSB= Gujarat Water Supply and Sewerage Board Source: Last quarterly progress report (January – March 2007) of GSDMA

Note: The above allocation does not include Housing component (USD 14 million) and Front end fee (USD 5 million) * Balance 6 works to the tune of USD 4.38 Million are proposed to be taken from GoG funding. ** 1 Contract to the tune of USD 0.22 Million is proposed to be taken from GoG funding. 2 packages have been terminated. *** 5 Contracts (Jamnagar water distribution) to the tune of USD 20.38 Million is proposed to be taken from GoG funding **** 4 Contract to the tune of USD 0.88 Million are proposed to be taken from GoG funding

Appendix 5 24

SUMMARY OF CONTRACT DETAILS

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

01 0082 13,102,559 12,346,933 755,626 Housing-PPP Various

05 0029 1,416,540 1,340,405 76,135

Non-government organizations (contracts with Women's Livelihood Restoration Project) Various

05 0103 1,684,851 1,615,924 68,927

Assistance/toolkits to masons, handicraft, handloom artisans & the self-employed Various

05 0104 2,343,223 1,840,741 502,482 Bankable scheme for self-employment Various

05 0105 1,390,602 1,208,153 182,448

Revolving fund to rehabilitate earthquake-affected self-employed artisans Various

05 0255 368,852 3,955 364,897

Establishment of handloom/handicraft park for rehabilitation of craftsman cottage and rural industries

Shree Swashrayi Mahila Sewa Sangh

05 0256 349,641 239,028 110,612

Construction of handloom/handicraft park for rehabilitation of craftsman cottage and rural industries

Shree Nehru Foundation for Development

06 0001 454,155 373,253 80,903 Consultancy services for town planning (Bhuj)

Environmental Planning Collaborative

06 0002 172,886 144,927 27,959 Consultancy services for town planning (Anjar)

Lea Associates South Asia Pvt.

06 0003 236,973 152,205 84,768 Consultancy services for town planning (Bhachau)

Dalal Consultants And Engineer

06 0004 89,987 64,583 25,404 Consultancy services for town planning (Rapar)

Consulting Engineering Services (I) Ltd.

06 0005 2,515,152 2,441,757 73,395

Technical audit & quality assurance of earthquake reconstruction program in Gujarat (consultancy)

National Council For Cement & Buildings Materials

06 0006 336,799 170,412 166,387

Consulting services for technical advisory cell for Bhuj and Rapar

Stup Consultants Ltd. & Assoc.

06 0007 238,783 119,364 119,418

Consulting services for technical advisory cell for Anjar and Bhachau

Consulting Engineers Services

06 0008 1,749,997 1,367,241 382,756

Consulting services for infrastructure design and supervision for package I (Bhuj & Rapar)

Gherzi Eastern Limited

Appendix 5

25

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

06 0009 4,641,222 4,212,140 429,082

Consultancy services for infrastructure design and supervision for package Ii (Anjar & Bhachau)

TCE Consulting Engineers Ltd

06 0010 5,495,439 4,844,262 651,178

Incremental administrative expenses for all implementing agencies Various

06 0011 336,841 331,771 5,070

Consultancy services for construction & completion of control room bldg., staff quarters & admin. bldg. of GEB

Consulting Engineering Service

06 0028 63,076 58,796 4,280

Consultancy contract for preparation of the draft town planning scheme (Anjar)

M/S Design Point

06 0039 146,334 146,269 66

Consultancy services for technical audit (Roads and Buildings Department)

Lea Associates South Asia Pvt

06 0117 328,231 309,410 18,821

Consultancy services for construction supervision and inspection of materials for WSS Mecon Limited

06 0118 2,284,209 1,842,322 441,887

Consultancy services for construction supervision & inspection of materials for WSS (GWSSB) Mecon Limited

06 0183 5,736 2,695 3,041

Institutional training & capacity building on disaster mitigation/management measures

Indian Institute of Tech

06 0184 23,066 10,903 12,163 Teacher training program Indian Institute of Tech

06 0187 433,380 352,601 80,779

Consultancy services for benefit monitoring and evaluation

KPMG Advisory Services Pvt. Ltd.

06 0194 4,525 0 4,525 Teacher Training Program (St-1)

LD College Of Engg

06 0215 220,189 217,925 2,263

Consultancy services for technical audit & quality assurance for package 1

Span Cons ultants Pvt. Ltd.

06 0216 176,346 163,776 12,570 Consultancy services for technical audit package 1

Lea Associates South Asia Pvt

07 0199 19,525 19,475 50

Training and capacity building program for capacity building for multi -hazard disaster preparedness GSDMA

07 0238 13,679 13,679 0

Constructing seismological observatory at Geri, Gotri, Vadodara

Gauri Constructions

07 0239 3,850 2,340 1,510

Const. of vault room near Ghabhana seismological observatory of Ghabhana Tal. Nandod Dist Narmada M/S R.M. Patel

Appendix 5 26

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

07 0250 5,844 5,844 0

Addition & alteration of observatory bldg at Chattarpura village & construction of new vault room

Shri G.B. Vanjara

07 0261 8,462 8,446 17

Construction of seismological observatory recording room, vault room and compound wall at Ghunta

Sardar Construction Co.

07 0262 15,007 11,673 3,334

Construction of seismological observatory station at Rampar (Naliya)

Shri Shakti Enterprise Ltd.

07 0263 8,983 7,907 1,076

Construction of seismological observatory station & platform at Madhuban colony

Nikam Construction

07 0264 3,956 3,800 156

Construction of compound wall, record room, link road for seismological station at Madhuban colony

Nikam Construction

07 0265 16,564 14,993 1,570

Construction of seismological observatory Station at Khavda

Vaghela Meghrajji Samubha

07 0266 16,080 9,211 6,869

Construction of seismological observatory at dam site

Shivshakti Construction

07 0308 12,799 12,620 179

Construction of seismological observatory near Aji dam site

Reliable Construction Co, Rajkot

07 0309 11,459 6,201 5,258

Construction of seismological observatory near Wadhwan Bhogavo, Surendranagar

Jai Sukhanath Construction

07 0311 1,330 1,330 0

Providing EI to seismological observatory field hydraulic lab. at Geri, Gotri, Vadodara

Sr. A.V.Joshi, Vadodara

07 0319 4,166,458 2,755,680 1,410,778 Construction of pavilion "Planet Earth"

M.S. Khurana Engineering Ltd.

07 0324 4,269 4,000 269

M&R to seismological observatory building & Chowkidar Quarter at Sipu dam site Umiya Builders

07 0327 12,163 0 12,163

Supply, installation & commissioning of seismological instruments and accessories

Gannon Dunkerley & Principal Supplier Geosis

07 0327 815,280 733,752 81,528

Supply, installation & commissioning of seismological instruments and accessories

Gannon Dunkerley & Principal Supplier Geosis

07 0329 10,583 9,561 1,022

Construction of seismological observatory near WALMI campus, Sector

Rajratna Construction

Appendix 5

27

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

8, Gandhinagar

07 0345 5,978 5,561 417

Construction of compound wall approach road water supply, sanitary installation at seismological observatory

Amin Construction

07 0346 7,740 7,233 507

Construction of approach road and water supply for seismological observatory at Ghuntu

Govindbhai Dayabhai Dangar

07 0347 38,737 0 38,737 Swaraj mazda chassis cowl and WB 3335

Swaraj Mazda Limited

07 0348 77,954 74,274 3,680 Fabrication with medical equipment essentials

Usha Dragor Pvt Ltd

07 0349 7,949 7,527 422 Defibrillator Criticare Systems India

07 0350 35,121 32,768 2,353 Transport ventilator Pulmocare Consultants

07 0351 10,682 9,414 1,268 Cardioscope pulse oxymeter Larsen & Toubro

07 0353 15,700 0 15,700

Constructing seismological observatory at Jhagadia Dist. Bharuch Shri H.J. Kavat

07 0355 135,232 132,316 2,916

Procurement of equipment for strengthening capabilities of municipalities in Gujarat state for disaster mitigation

Kohlbros Communications Pvt. Ltd.

02A 0298 512,483 429,779 82,704

Purchase of implements and equipment for handling solid waste in towns of Kutch,Surendranagar Lot 1

M/S. Shriram Products

02A 0299 433,274 413,558 19,716

Purchase of implements and equipments for handling solid waste in towns of Kutch Surendranagar Lot 2

M/S. Same Deutz-Fahr India Pvt

02A 0300 37,743 35,480 2,262

Purchase of implements and equipment for handling s olid waste in towns of Kutch, Surendranagar & Rajkot Lot 3

Ms/Dhru Tractors

02A 0325 271,671 268,480 3,191

Purchase of implements and equipment for handling solid waste in towns of Kutch, Surendranagar & Rajkot Lot 4

Industrial Plants & Waste Treatment Corporation

02A 0325 42,330 42,241 89

Purchase of implements and equipment for handling solid waste in towns of Kutch, Surendranagar & Rajkot Lot 5

Industrial Plants & Waste Treatment Corporation

02A 0328 337,828 331,599 6,229

Purchase of implements and equipment for handling solid waste in towns of Kutch, Surendranagar & Rajkot

Industrial Plants & Waste Treatment Corporation

Appendix 5 28

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02A 0328 100,125 99,915 210

Purchase of implements and equipment for handling solid waste in towns of Kutch, Surendranagar & Rajkot

Industrial Plants & Waste Treatment Corporation

02A 0339 5,197,500 4,960,964 236,536 Procurement of m.s. Pipe-Lot 4

Man Industries (I) Ltd,

02A 0354 1,140,767 1,140,767 0

Procurement of equipment for strengthening capabilities of municipalities in Gujarat state for disaster management

Force Motors Limited

02B 0012 73,591 73,478 112

Improvement of rural road in Kadi Taluka (Mehsana District) (M-1)

Perfect Construction Co.

02B 0013 422,062 412,238 9,824

Improvement of rural roads in Patan, Chanasma, Sidhpur, Harij Taluka (Patan District) (P-1)

Rao Construction Private Ltd.

02B 0014 444,980 437,642 7,338

Improvement of rural roads in Sami, Radhanpur, Santalpur Taluka (Patan District) (P-2)

Rao Construction Co. (P) Ltd.

02B 0015 378,635 378,175 460

Improvement of rural roads in Rapar Taluka Kutch District (K-2)

Classic Construction Co.

02B 0016 459,322 451,298 8,024

Improvement of rural roads in Taluka Anjar- Gandhidham (Katch District) (K-3)

Jivanlal J. Patel

02B 0017 587,459 567,685 19,774

Improvement of rural roads in Bhachau Taluka, Kachchh District (K-1)

Katira Construction Co.

02B 0018 269,575 255,381 14,194

Improvement of rural roads in Mundra Taluka Kachchh District (K-4)

Katira Construction Co.

02B 0019 560,749 559,952 797

Improvement of rural roads in Mandavi Taluka Kachchh District (K-5)

Daud Ladha Rayama

02B 0020 440,046 433,759 6,287

Improvement of rural roads in Abdasa-Lakhpat Taluka In Kachchh District (K-6)

Rabadia Construction

02B 0021 608,561 601,851 6,710

Improvement of rural roads in Nakhtrana, Lakhpat Taluka, Kuchchh District (K-7)

Shamji Maya & Co.

02B 0022 509,748 506,199 3,549

Improvem ent of rural roads in Taluka Bhuj Kachchh District (K-8)

Jivanlal J. Patel

02B 0023 368,429 344,573 23,856

Improvement of rural road in Jamnagar-Lalpur Taluka (J-1)

Parishram Builders Veraval

02B 0024 276,102 261,207 14,896

Improvement of rural roads in Dhrol, Kalawad Taluka, Jamnagar District (J-2)

Union Construction Co.

Appendix 5

29

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0025 299,860 287,098 12,762

Improvem ent of rural roads in Jodia Taluka, Jamnagar (J-3)

Jitendra G. Patel

02B 0026 409,338 390,802 18,536

Improvement of rural roads in Bhanwad Taluka, District Jamnagar (J-4)

Ambar Builders

02B 0027 192,434 162,788 29,647

Improvem ent of rural roads in Khambhalia, Kalyanpur Taluka, District Jamnagar (J-5)

Tacon Infrastructure Pvt. Ltd.

02B 0032 517,528 511,931 5,597

Improvem ent of rural roads in Wadhawan/Chotila Sayla Taluka (Surendranagar District) S-1

M/S Backbone Enterprise

02B 0033 439,468 425,100 14,367

Improvement of rural roads in Limbdi/Chuda/Lakhtar Taluka (Surendranagar District) S-2

M/S Shriji Construction Co.

02B 0034 642,877 632,195 10,682

Improvement of rural roads in Halvad/Muli/ Dharangdhra Taluka (Surendranagar District) S-3

Natraj Construction Co.

02B 0035 248,884 244,975 3,909

Improvem ent of rural roads in Dasada Taluka (Surendranagar District) S-4

Varun Construction Co., Mehsana

02B 0037 424,313 416,225 8,088

Improvement of rural roads in Banaskantha District (Bk1) (R&B) D.R. Agarwal

02B 0040 177,211 172,012 5,199

Resurfacing of four city roads of Bhuj City (western part) (Kachchh District) (Kch-Bu-R2)

Daud Ladha Rayma

02B 0041 34,353 31,752 2,601

Resurfacing of one city road of Bhachau City (Kachchh District) (Kch-Ba-R6) M.V. Armani

02B 0042 148,272 141,523 6,749

Resurfacing of four city roads of Anjar City (Kachchh District) (Kch-An-R4)

Sachem Vijay Company

02B 0043 148,850 140,325 8,525

Resurfacing of two city roads of Anjar City (Kachchh District) (Kch-An-R3)

Shamji Maya & Co.

02B 0045 337,273 327,719 9,554

Improvement of rural roads in Rajkot District (R&B) Gandalf, Kotada-Sangani, Jasdan, Jetpur, Dhoraji

Amber Builders

02B 0046 156,250 145,468 10,782

Rural roads in Rajkot district (Taluka-Morbi, Maliya) (R&B) (R-4)

Tirupati Construction Co.

02B 0047 380,866 319,484 61,381

Rural roads in Rajkot District (Taluka-Rajkot, Wankaner, Padadhari, Lodhika) (R&B) (R-1)

Classic Construction Co.

02B 0048 385,296 338,895 46,400

Rural roads in Rajkot District (Taluka-Morbi, Tankara) (R&B) (R-2)

Gayatri Construction Co.

Appendix 5 30

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0049 601,304 595,550 5,754

Improvement of rural roads of Porbander, Ranavav, Kutiyana Taluka, Porbander Distt.

Tacon Inf. Pvt. Ltd.

02B 0050 164,482 164,482 0 Land rehabilitation at Bhuj Dineshchandra R. Agarwal

02B 0055 84,890 84,890 0

Civil works for the first phase of restoration of Pratapura Sarovar

Shashin Const. Co.

02B 0057 240,199 240,199 0

Civil works for municipal office bldg. Kankarvav shopping complex, Ghatwadi works office & garage

M.S. Khurana Engineering Pvt L

02B 0058 253,072 253,072 0

Const. of municipal bldg Snanagarh, public toilets, crematorium, library, fire brigade station extension

Hetu Const. Pvt. Ltd.

02B 0059 216,940 209,810 7,130

Resurfacing of five city roads of Bhuj City (Easter Part).

Rabadia Construction

02B 0060 106,818 102,669 4,149 Resurfacing three city roads of Rapar City.

Dadabhai Hathibhai

02B 0065 2,019,227 2,019,227 0

Construction of outer ring road (part 1) including Node No.209 To 238. Incl. culverts, drains, curbs

Nicco Corporation

02B 0066 970,019 970,019 0

Land development and construction of roads, storm water drains, fencing & street light at Site 2, Bhuj

M.S. Khurana Engineering Ltd.

02B 0067 2,065,867 2,065,867 0

Construction of outer ring road (part 3) from node283-209(6.439 km) including culverts, drains, curbs , footpath

Nicco Corporation Ltd.

02B 0068 2,312,491 2,312,491 0

Construction of outer ring road (part 2) from Node238-283 (5.771 km) incl. culverts, drains, curbs ,

Backbone Projects Ltd.

02B 0069 1,359,805 1,307,357 52,448

Rehabilitation and reconstruction of internal municipal roads in Bhachau (GUDCO)

Backbone Enterprise

02B 0070 1,861,490 1,558,042 303,448

Rehabilitation and reconstruction of internal municipal roads and bypass road in Anjar (GUDCO)

N.Gulabsinghji & G.H.Vijapura

02B 0071 1,066,508 1,066,508 0

Land development and construction of roads, drains, fencing etc. for the rehabilitation site no.1 (Ravalwadi)

Backbone Projects

02B 0075 2,046,245 1,981,842 64,403

Providing water distribution network in Anjar, Kutch (GUDCO)

IVRCL Infrastructure & Project

Appendix 5

31

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0084 552,463 552,463 0

Rehabilitation and construction of roads in Bhachau

Narayansingh & Gulabsingh JV

02B 0089 379,309 379,309 0

Land development and construction of roads, SWD, fence, street lighting etc. for site 3 (near RTO), Bhuj

V.K.Patel & Co.

02B 0092 402,790 378,054 24,736

Construction of 4-lane bridge across Navnalla at Jamnagar

Mahendrakumar & Co.

02B 0093 1,331,468 1,331,468 0

Construction of middle ring road, radial and grid roads (part 1) at Bhuj

M/S Backbone Projects Ltd

02B 0094 967,586 967,586 0

Construction of middle ring road, radial and grid roads (part 2) at Bhuj

M/S Backbone Projects Ltd.

02B 0095 1,464,982 1,464,982 0

Construction of middle ring road, radial and grid roads (part 3) at Bhuj

Backbone Projects Ltd

02B 0096 1,548,789 1,548,789 0

Construction of middle ring road, radial and grid roads (part 5) at Bhuj

Backbone Projects Ltd.

02B 0097 1,129,546 1,129,546 0

Construction of middle ring road, radial and grid roads (part 6) at Bhuj

Backbone Projects Ltd.

02B 0098 851,595 851,595 0

Construction of middle ring road, radial and grid roads (part 4) at Bhuj, Kachchh

M/S N.Gulabsingh JV

02B 0099 1,540,548 1,540,548 0

Road works including repairs, widening, resurfacing, storm water drains, street lighting etc. at Sure

M/S N.Gulabsingh JV

02B 0100 1,889,956 1,307,066 582,891 Water supply and sewerage system at Rapar, Kutch

M/S Unitech Machines

02B 0101 363,262 363,024 238

Water transmission mains, construction of staff quarters and other civil works, pumping system , etc.

M/S Backbone Projects Ltd

02B 0102 1,132,765 968,572 164,193 Road works at Dhrangadhra, Surendranagar District.

M/S Kalthia Engg & Const. Ltd

02B 0107 2,022,046 1,949,597 72,449

Water distribution system (part 1) in zones 2, 3 and 7 and construction of ESR at Shivkrupanagar and Rawalwadi

Electrosteel Castings Ltd

02B 0108 1,151,443 1,151,443 0

Water supply and sewerage system (collection/distribution) at Bhuj

Bridge & Roof Co.(I) Ltd

02B 0109 901,980 901,980 0 Construction of roads at Mandvi

Kantilal K. Bhalala

02B 0110 580,041 580,041 0

Civil works for town hall, Nagarpalika building and other buildings in Bhachau

Patel Infrastructure Pvt. Ltd

Appendix 5 32

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0111 3,487,723 3,039,022 448,701

Sewage collection system including pumping stations in western & eastern parts of Simtal

Unitech Machines Ltd. J/V

02B 0112 210,278 158,259 52,018 Sewage collection system at Anjar N.V.Kharote

02B 0114 1,902,732 1,392,019 510,714

Water distribution system (part 1) & const of ESR Shivkrupanagar and Rawalvadi HW, Bhuj

Electrosteel Castings Ltd.

02B 0119 415,198 415,197 0

Repair/replacement of water supply pipe lines in east & south zone of AMC (AMC-ADB-02) (Lot-1)

N.V. Kharote Construction Pvt. Ltd.

02B 0120 399,295 394,962 4,333

Repairs/replacement of water supply pipeline in west & central zone of AMC (AMC-ADB-02) (Lot-2)

N.V. Kharote Construction Pvt Ltd

02B 0121 416,297 412,045 4,252

Repairs/replacement of water supply pipeline in north zone of AMC (AMC-ADB-02) (Lot-3)

N.V. Kharote Construction Pvt Ltd

02B 0122 1,377,654 1,360,301 17,353

Repairs/replacement of sewage pipelines (Amc-Adb-04)

The Modern Construction Co. Pvt. Ltd.

02B 0123 617,552 617,552 0

Repairs/replacement of storm water drainage pipe lines in east & central zone of AMC

JMC Projects (I) Ltd,

02B 0124 980,060 980,060 0

Repairs/replacement of storm water drainage pipe lines in west zone of AMC

JMC Projects (I) Ltd.

02B 0128 630,100 630,100 0 Sewage collection system for Bhachau

M.S.Khurana Engineering Pvt. Ltd.

02B 0129 568,948 496,221 72,727

Civil works for community hall & municipal office bldg in Gandhidham

Engineering Projects (I) Ltd.

02B 0130 1,273,055 1,236,909 36,146 Water supply & sewerage system at Mandvi, Kachchh

M/S Backbone Projects Ltd.

02B 0131 246,201 246,201 0

Const. Of Snangrah, public toilets, crematorium, fire brigade station and library at Mandvi, Kachchh

National Builders

02B 0132 1,007,537 943,431 64,106

Const. of municipal bldgs (part 1) including Ws&S, WW disposal and elect. At Bhuj, Kachchh

Quality Construction Co.,

02B 0133 129,660 129,660 0

Const. of roads including repairs, widening, storm water drains, street lighting etc., at Lambda

Backbone Enterprise Ltd.

02B 0134 1,406,664 1,406,664 0 Construction of roads (part 1) At Rapar, Kachchh

Backbone Enterprise Ltd.

Appendix 5

33

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0135 433,134 433,134 0

Civil works for library & clock tower, ten ward offices and other buildings in Anjar

Katira Construction Co.

02B 0136 242,071 242,071 0

Construction of vegetable market, municipal office and library at Limbdi

Quality Construction Co.

02B 0137 553,551 553,551 0

Const. of municipal bldg, town hall & library including WS, San, drainage and elect. etc. at Rapar

Quality Construction Co.

02B 0138 77,037 77,037 0

Const. of municipal stores, city tower at Surendranagar, library bldg at Wadhwan and Thangadh

Malani Constructions Co.

02B 0141 191,788 191,788 0

Construction of toilets , Bal Mandir, staff quarters, Pathikashram and Seetaghat at Drangadhra R.N.Dobaria

02B 0142 1,573,488 1,573,488 0 Water supply & sewerage system at Bhuj, Kachchh

Electrosteel Castings Ltd.

02B 0143 1,191,289 976,599 214,690

Construction of Gamtal ring road including repairs, widening, resurfacing, storm water drains at Bhuj

Backbone Enterprises Ltd.

02B 0144 1,559,749 1,108,828 450,921

Gamtal inner roads, sectoral roads, storm water drains & street lighting at Anjar

Backbone Enterprises

02B 0145 1,722,620 1,345,203 377,418

Water distribution network and sewage collection system for Anjar Gamtal & Bhachau Gamtal and Cwt A

N.V.Kharote Construction Pvt Ltd

02B 0146 634,363 617,099 17,264

Gamtal inner roads, internal municipal roads, SWD, slab culvert at Bhachau

Backbone Enterprises

02B 0154 1,870,517 1,135,339 735,178

Water supply & sewerage system at Dhrangadhra, Surendranagar District

Electrosteel Castings Ltd.

02B 0155 655,640 519,253 136,387 Civil works for town hall in Anjar

Engineering Projects (I) Ltd.

02B 0161 1,878,304 0 1,878,304

Water supply & sewerage system, pumping station at Limbdi, Surendranagar District

Electrosteel Castings Ltd.

02B 0163 343,119 343,119 0

Civil works for library-shopping centre-community hall, fire tender & ambulance garage etc in Bhachau

Patel Infrastructure Pvt. Ltd.

02B 0166 835,446 738,408 97,039 Water supply & sewerage structures in Anjar

Gammon India Ltd.

02B 0167 2,293,924 2,293,924 0

Const. of roads incl. repairs, widening, resurfacing, storm water drains, street lighting, etc.

Kalthia Engg. & Const Pvt

02B 0169 389,110 389,110 0

Civil works for municipal buildings and public toilets in Morbi, Wankaner & Halvad

Balaji Associates

Appendix 5 34

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0173 409,986 206,318 203,669

Repairs to 16 hospital buildings in Ahmedabad Municipality

P.C.Snehal Construction Co.

02B 0179 619,466 618,462 1,004 Strengthening of roads in old Rajkot area

Backbone Ent., Rajkot

02B 0180 621,710 611,178 10,533 Strengthening of roads in new Rajakot area

Backbone Ent. Rajkot

02B 0181 64,910 57,786 7,124 Repair/modification of swimming pool.

Bhuptani Associates, Rajkot

02B 0182 205,855 205,853 1 Construction of GSR at Aji filter plant.

Jaihind Projects, Ahd

02B 0188 446,317 446,317 0

Repairs to hospital buildings damaged due to earthquake in Ahmedabad

Manibhai & Brothers

02B 0190 64,475 59,685 4,790 Restoration of Hamirsar tank at Bhuj

Saraswati Const. Co

02B 0191 40,719 38,346 2,373 Restoration of Hamirsar tank at Bhuj

Kaushik M. Patel

02B 0192 25,920 24,089 1,831 Restoration of Hamirsar tank at Bhuj

Lalji Karsan Hirani

02B 0193 41,977 0 41,977 Restoration of Hamirsar tank at Bhuj

Dhara Const Co

02B 0202 477,298 436,311 40,987

Reconstruction/improvement of rural roads in Rapar- Bhachau Taluka (Kutchh District)

Mohandas V. Rajani

02B 0203 469,832 427,845 41,987 Reconstruction/improvement of roads in Bhuj Taluka

Mohandas V. Rajani

02B 0204 476,040 475,978 62

Reconstruction/ immprovement of rural roads in Anjar-Bhachau Taluka (Kutchh District)

Daud Ladha Rayma JV

02B 0205 539,924 489,187 50,737

Reconstruction/improvement of rural roads in Rapar-Bhachau Taluka (Kutchh District)

Mohandas V Rajani

02B 0206 528,418 526,967 1,451

Reconstruction /improvement of rural roads in Abdasa-Lakhpat-Nakhatrana Taluka (Kutchh District)

Katira Const. Co.

02B 0207 492,373 395,448 96,925

Reconst/improvement of rural roads in Mandvi Taluka (Kutchh District)

Katira Const Co.

02B 0208 442,941 336,827 106,115

Reconstruction/improvement of roads in Anjar-Mundra Bhuj Taluka

Daud Ladha Rayma In Jv

02B 0210 140,071 140,071 0

Construction of municipal buildings, incl. water supply, sanitation, drainage and electrification

Quality Const. Co.

02B 0217 3,255,540 3,008,947 246,593

Providing sewerage system in the west AUDA area under AUDA

Modern Construction Co P Ltd

02B 0223 99,700 82,517 17,183 Resurfacing Hamiramora-Luni-Vadala road and

Rajhans Construction

Appendix 5

35

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

Modsar-Surgaria road Co.

02B 0224 167,079 164,990 2,089

Resurfacing Of Bhachau Ramvav Rapar road and Rapar Rateneshwar Village road

Anish Construction Co.

02B 0225 89,010 63,854 25,156

Resurfacing of Bhuj-Nagor-Kunariya-Dhori-Sumarasar Loriya road

Tacon Infrastructure Pvt Ltd

02B 0226 1,250,880 1,158,897 91,983

Rising main from sumps to ESRs And Distribution Network In 5 Urban Agglomerations In Western AUDA Area

Nicco Corporation

02B 0227 1,235,716 938,254 297,462

Construction of civil works for water supply in 5 urban agglomerations in western AUDA area

Nicco Corporation Ltd.

02B 0228 1,748,234 1,692,585 55,649

Construction of roads in 5 urban agglomerations in TP 37, 38, 39 & 41

Vijay Mistry Const. & Rajkamal

02B 0229 3,033,580 1,967,116 1,066,464

Construction of roads in 5 urban agglomerations in TP 42, 43, 51, 52

M.S.Khurana Engineering Ltd.

02B 0240 374,300 374,300 0

Improving/resurfacing rural roads in earthquake affected district Ahmedabad

Natraj Construction Co.

02B 0241 291,817 277,474 14,343

Improving/resurfacing rural roads in earthquake affected district Ahmedabad.

Rao Constructions

02B 0242 546,533 518,047 28,486

Improving/resurfacing rural roads in earthquake affected district Ahmedabad District

Rao Construction Pvt. Ltd.

02B 0243 168,700 134,578 34,122

Improvement/resurfacing of rural road in earthquake affected district Ahd.

Digvijay Const Pvt Ltd.

02B 0244 676,277 657,740 18,537

Improving/resurfacing rural roads in earthquake affected district Patan

G.H. Vijapura & Co.

02B 0245 501,287 493,061 8,226

Improving/resurfacing rural roads in earthquake affected district Patan

Saraswati Construction Co.

02B 0246 681,386 669,672 11,713

Improving/resurfacing rural roads in earthquake affected district Patan.

G.H. Vijapura & Co.

02B 0247 644,070 644,065 5

Improving/resurfacing rural roads in earthquake affected district Banaskantha

Jugalkishore R Agrawal & Co.

02B 0248 416,967 415,613 1,354

Improving/resurfacing rural roads in earthquake affected dist Banaskantha

Jugalkishore R. Agrawal & Co.

02B 0249 670,684 604,199 66,485

Improving/resurfacing rural roads in earthquake affected district Banaskantha

G.H. Vijapura and Co.

Appendix 5 36

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0251 385,411 366,622 18,789

Improvement of rural roads of Dasada/Dhg/Halwad Taluka In Surendranagar district

Varun Construction Co.

02B 0252 352,510 341,858 10,652

Improving/resurfacing rural roads in earthquake affected district Kachchh.

Anish Const Co.

02B 0253 544,300 527,928 16,372

Improving/resurfacing rural roads in earthquake affected district Kachchh

Katira Const Co.

02B 0254 344,686 332,287 12,399

Improving/resurfacing rural roads in earthquake affected district Kachchh

Anish Const Co.

02B 0257 2,109,899 1,562,976 546,923 Providing water distribution network in Morbi (Part A)

Larsen & Toubro Ltd.

02B 0258 1,979,126 1,411,115 568,011 Providing water distribution network for Morbi (Part B)

M/S Larsen & Toubro Limited

02B 0259 229,047 229,047 0

Addition/alteration work of GSR, pumping station and construction of PS at Nyari filter point in war

M/S Sutreja & Co.

02B 0260 640,437 128,465 511,972

Repair/replacement of sewage pipelines damaged due to earthquake in Ahmedabad

Modern Construction Co. Pvt. L

02B 0267 258,465 159,291 99,174

Improving resurfacing rural roads in earthquake affected district, Porbandar and Jamnagar, L-4a

M/S Parishram Builders

02B 0268 229,275 217,209 12,066

Improving resurfacing rural roads in earthquake affected district, Jamnagar and Porbandar L-4b

M/S Ambar Builders

02B 0269 173,004 168,471 4,533

Improving resurfacing rural roads in earthquake affected district, Jamnagar & Porbandar, L-1b

M/S Classic Networks Ltd.

02B 0270 232,099 217,662 14,437

Improving resurfacing rural roads in earthquake affected dis trict, Jamnagar & Porbandar, L-2

M/S Classic Networks Ltd.

02B 0271 239,531 199,678 39,853

Improving resurfacing rural roads in earthquake affected district, Jamnagar & Porbandar, L-1a

M/S Amber Builders

02B 0272 153,717 136,333 17,384

Improving resurfacing rural roads in earthquake affected district, Jamnagar & Porbandar, L-3

M/S Tacon Infrastructure Pvt L

02B 0278 231,430 219,293 12,137

Improving/resurfacing rural roads in earthquake affected districts.

Classic Network Ltd.

02B 0279 309,637 300,492 9,145

Improving/resurfacing rural roads in earthquake affected districts, District Junagadh

Amber Builders, Dhoraji

Appendix 5

37

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0280 211,511 200,464 11,047

Improving/resurfacing rural roads in earthquake affected districts, District Junagadh

M/S. Sutreja & Co.

02B 0281 289,546 277,516 12,030

Improving/resurfacing rural roads in earthquake affected districts, Junagadh,8/Jun/L-1(C)

M/S. Sutreja & Co.

02B 0282 190,417 179,972 10,445

Improving/resurfacing rural roads in earthquake affected districts, District-Junagadh(8/Jun/L-2(B)

M/S. Classic Network Ltd.

02B 0283 343,984 212,534 131,450

Improving/resurfacing rural roads in earthquake affected districts, district-Amreli/Amr-L1(B)

M/S. Back Bone Enterprises Ltd

02B 0284 239,780 166,611 73,169

Improving/resurfacing rural roads in earthquake affected districts, District-Amreli,9/Amr/L-1a

Ms/. Ambar Builders

02B 0285 142,626 114,028 28,598

Improving/resurfacing rural roads in earthquake affected districts, District-Amrel,9/Amr/L-2a

M/S. Amber Builders

02B 0286 300,214 261,561 38,653

Improving/resurfacing rural roads in earthquake districts, District-Amreli, 9/Amr/L-2b

Ms. Classic Network Limited

02B 0287 212,285 208,780 3,505

Improving/resurfacing rural roads in earthquake districts, District-Surendranagar, 5/Snr/L-1a

M/S.Gujarat Construction Co.

02B 0288 336,307 304,401 31,906

Improving/resurfacing rural roads in earthquake districts, District-Surendranagar, 5/Snr/L-2b

M/S. Back Bone Enterpriprises

02B 0289 322,841 316,837 6,004

Improving/resurfacing rural roads in earthquake districts , District-Surendranagar, 5/Snr/L-1c

M/S. Shreeji Construction Co.

02B 0290 276,648 276,523 125

Improving/resurfacing rural roads in earthquake districts, District-Surendranagar, 5/Snr/L-3a

M/S. Back Bone Enterprises

02B 0291 240,960 168,981 71,979

Improving/resurfacing rural roads in earthquake districts, District-Surendranagar, 5/Snr/L-3b

M/S.Digvijay Construction(P)

02B 0292 264,205 254,160 10,045

Improving/resurfacing rural roads in earthquake districts , District-Surendranagar, 5/Snr/L-2a

M/S. Natraj Construction Co.

02B 0293 305,384 272,440 32,943

Improving/resurfacing rural roads in earthquake districts, District-Surendranagar, 5/Snr/L-1b

M/S. S.N.Shah & Co

02B 0294 616,363 616,330 33

Construction of new mpl. building, veg mkt. and other strs. including W.S.

M/S. I.B. Patel & Com.

Appendix 5 38

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

sanitation etc

02B 0295 245,070 237,622 7,448 Sewerage pumping station at Bhachau

M/S. Ramkay Infrastructure

02B 0297 73,026 73,026 0

Improving/resurfacing rural roads in earthquake affected districts, Junagadh

N/S. Jitendra G. Patel

02B 0301 232,142 206,884 25,258

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

M/S.Digvijay Construction(P) Ltd.

02B 0302 227,844 212,614 15,231

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

Amber Builders

02B 0303 330,657 330,657 0

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

Classic Network Pvt Ltd

02B 0304 343,821 341,195 2,626

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

M/S. Back Bone Enterprises

02B 0305 294,183 289,518 4,666

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

M/S. Back Bone Enterprises

02B 0306 203,335 170,270 33,064

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

Classic Network Pvt Ltd

02B 0307 189,177 189,177 0

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

M/S. Back Bone Enterprises

02B 0310 311,657 301,450 10,207

Improving/resurfacing rural roads in earthquake-affected districts, Rajkot

M/S. Back Bone Enterprises

02B 0312 208,645 145,132 63,513

Improving/resurfacing rural roads in earthquake-affected Districts. Bhavnagar

M/S.Digvijay Construction(P) Ltd

02B 0313 291,902 258,040 33,862

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar

M/S. Back Bone Enterprises Limited

02B 0314 265,208 224,973 40,235

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar

M/S. Back Bone Enterprises Limited

02B 0315 356,721 353,484 3,237

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar7/Bvn-L2a Shiv Builders

02B 0316 354,405 309,056 45,350

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar7/Bvn-L2b

M/S. Back Bone Enterprises Limited

02B 0317 248,222 245,165 3,057

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar7/Bvn-L3a

Classic Network Pvt Ltd

Appendix 5

39

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

02B 0318 227,755 183,312 44,443

Improving/resurfacing rural roads in earthquake-affected districts. Bhavnagar7/Bvn-L3b

M/S. Jitendra G. Patel

02B 0320 913,840 913,840 0 Upgrading of roads in Halwad

S.N.Shah & Co.

02B 0326 356,200 345,524 10,676

Repairs and rehabilitation of water supply system of Wankaner and Halwad

M/S. Mahendrakumar & Co.

02B 0330 75,683 40,604 35,078

Supply and fixing of interiors in town halls at Anjar , Bhachau & Gandhidham

Vijayjoti Seats Pvt. Ltd.

02B 0331 157,159 9,953 147,206 Interior works in town halls at Bhuj And Rapar

Decor Home Pvt Ltd

02B 0332 925,089 580,577 344,512 Water supply structure for Morbi

M/S. Back Bone Projects Limited

02B 0333 184,868 125,230 59,638

Ventilation and fire protection systems for the town halls at Bhuj And Rapar

Extinct Fire Engineers (Jv) Associated Engg

02B 0342 675,610 568,911 106,699 Water stabilisation ponds at Anjar And Bhachau

M/S. Mahendrakumar & Co.

02B 0343 1,246,613 1,021,948 224,664

Water stabilisation ponds for sewage collection system in towns of Bhuj, Rapar, Mandvi, Limdi & Dhrangadhra

M/S. Ramkay Infrastructure Ltd.

02B 0344 557,575 376,855 180,721

Landfill site development for SWM In Gandhidham, Anjar, Bhachau, Morbi, Wankaner And Halwad

Back Bone Enterprises Limited

03A 0044 10,018,232 10,017,912 320 Purchase of m.s. pipe (Gwssb/Adb/02)

PSL Holdings Ltd.

03A 0061 9,456,803 9,456,803 0 Purchase of ductile iron pipes (GWSSB)

Electrosteel Castings Ltd.

03A 0062 2,435,247 2,435,247 0 Purchase of UPVC pipes (GWSSB)

Jain Irrigation Systems Ltd.

03A 0078 176,276 176,276 0

Procurement of stainless steel submersible pump sets (GWSSB) (Lot-1)

Universal Engineers

03A 0079 45,697 45,697 0

Procurement of cubical control panel board (Lot-3) GWSSB Sun Industries

03A 0080 53,830 53,830 0 Procurement of H.D.P.E. pipe (Lot-4) GWSSB

Royal Plastic Ltd.

03A 0081 32,670 32,589 82 Procurement of flat PVC cable (GWSSB)

Chandresh Cables Ltd.

03A 0106 12,823,890 12,823,890 0 Supply of m.s. pipes

Welspun Gujarat Stahl Rohren L

03A 0170 582,906 510,677 72,229

Procurement & installation of pumping machinery & related electrical work for water supply projects Voltas Ltd.

Appendix 5 40

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

03A 0171 547,498 537,544 9,954

Proc. & installation of pumping machinery & related electrical work for water supply project.

Flow More Pvt.Ltd.

03A 0175 2,174,015 2,174,015 0 Procurement Of DI, PVC, & m.s. Pipe

Electrosteel Castings Ltd.

03A 0176 2,254,599 2,254,599 0 Procurement of DI pipe Electrosteel Castings Ltd.

03A 0177 846,816 813,606 33,210 Procurement of m.s. pipe (Lot 4) PSL Ltd.

03A 0178 938,307 328,822 609,485 Procurement of UPVC pipes (Lot Iii)

Swastik Tubes Pvt. Ltd.

03A 0212 482,207 320,082 162,125

Procurement & installation of pumping machinery & related electrical work for water supply Projects

Efficient Engrs (I) P Ltd.

03A 0219 1,386,932 1,386,932 0 Procurement of mild steel pipes.

PSL Limited, Mumbai

03A 0334 8,000,064 7,926,963 73,101 Procurement of m.s. pipe-Lot8

Ratnamani Metals & Tubes Ltd,

03A 0335 5,005,417 4,921,967 83,450 Procurement of m.s. pipe-Lot5

Ratnamani Metals & Tubes Ltd,

03A 0336 0 0 0 Procurement of m.s. pipe-Lot1

Man Industries (I) Ltd,

03A 0337 2,585,405 2,453,622 131,783 Procurement of m.s. pipe-Lot2

Man Industries (I) Ltd,

03A 0338 8,127,000 7,459,672 667,328 Procurement of m.s. pipe-Lot3

Man Industries (I) Ltd,

03A 0340 16,574,860 14,829,112 1,745,749 Procurement of m.s. pipe-Lot6

Welspun Gujarat Stahi Rohren Ltd

03A 0341 4,396,482 4,395,614 868 Procurement of m.s. pipe-Lot7 PSL Ltd.,

03A 0352 3,548,619 2,838,894 709,725 Procurement of mild steel Pipe Lot 1 (revised) PSL Limited

03B 0030 422,680 417,632 5,048 Porbandar bulk water supply scheme

IVRCL Infrastructure Projects

03B 0031 324,277 272,049 52,228 Bhuj bulk water supply scheme (GWSSB)

BRC Constructions

03B 0036 386,628 340,971 45,657

Kandla Gandhidham complex water supply scheme (GWSSB)

BRC Constructions

03B 0038 1,967,346 1,950,955 16,391 Morbi-Maliya-Jodiya water supply scheme (GWSSB)

IVRCL Infrastructure & Projects

03B 0051 946,794 946,794 0 Santalpur regional water supply scheme

Modern Const. Co. Pvt. Ltd.

03B 0052 737,168 737,168 0 Banni regional water supply scheme

Modern Construction Co. Pvt.Ltd

03B 0053 1,494,509 1,398,438 96,071

Drilling Of 250/200 mm dial tube wells by direct rotary drilling rig/dth rig

Gujarat Apollo Equipment Ltd.

Appendix 5

41

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

Kutch/Surendranagar-GWSSB

03B 0056 57,667 57,667 0 Drilling of tube wells 250/200mm dia

Backbone Ent & M/S J.H. Jadeja

03B 0072 258,980 258,980 0 Bhuj Taluka water supply scheme (GWSSB)

Offshore Industrial Const. Pvt

03B 0073 91,540 91,540 0 Mandvi bulk water supply scheme (GWSSB)

H.H. Rupani Engineers, Pune

03B 0074 239,831 239,051 779

Shivalakha rural regional water supply scheme (GWSSB)

IVRCL Infrastructure & Project

03B 0076 205,192 203,491 1,701 Morbi bulk water supply scheme (GWSSB)

Indian Construction Co.Jamnaga

03B 0077 126,807 86,289 40,518 Bhachau bulk water supply (GWSSB) H.H. Rupani

03B 0083 439,791 314,875 124,916 Pipeline project from Samkyali to Rapar

H.H.Rupani Engineers, Pune

03B 0113 2,800,700 2,726,097 74,603 Bulk water transmission main from Bhachau to Anjar

Engineering Projects India Ltd

03B 0115 3,920,016 3,619,219 300,797

Bulk water transmission main from Anjar-Kukma-Mundra-Mandvi

IVRCL Infrastructure And Proj

03B 0116 85,321 85,321 0 Bhachau Taluka water supply scheme

BRC Constructions

03B 0147 126,705 126,705 0

Design, build, construction of RCC box culvert for crossing the railway track

Mahesh & Co. In Jv With Urmi Engineers

03B 0149 940,539 940,539 0

Drilling of tube wells including supply and installation of submersible pumps and other mechanical equipment

Gujarat Apollo Equipments (Jv)

03B 0165 666,045 502,537 163,508 Mundra regional water supply scheme

BMS Projects Pvt Ltd.

03B 0168 659,535 375,270 284,265 Anjar Taluka regional water supply scheme

BMS Projects P. Ltd

03B 0172 1,065,939 1,064,166 1,774 Khijadia regional water supply scheme

Backbone Projects Ltd.

03B 0209 240,182 240,182 0

Inside onsite cement mortar lining work in mild steel pipe-Santalpur water supply scheme

IVRCL Inf. & Projects

03B 0230 2,773,720 2,627,858 145,862

Bulk water transmission main from Jamnagar (Khijadia) to Moti Khavdi

IVRCL Infrastructure & Project

03B 0232 79,060 78,844 217 RCC box culvert for crossing the railway track

Nemi Engineering Services

Appendix 5 42

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

03B 0235 4,683,263 2,200,514 2,482,749

Design-build contract for Panchdevda-Kalyanpur and Samana-Khambhaliya water supply scheme.

IVRCL Inf & Proj Ltd.

03B 0236 5,643,805 3,083,783 2,560,022 Ratanpur To Panchdevda water supply scheme

IVRCL Infrastructures & Projects

03B 0237 2,103,805 2,037,251 66,554 Construction of water treatment plants

Acquafil Polymers Co. Pvt. Ltd

03B 0273 214,661 214,059 601

Const. of water treatment plants with commissioning and training.

Krishna Corporation

03B 0274 232,602 232,082 520

Const. of water treatment plants with commissioning & training Rajkot, Porbandar & Jamnagar District

Phoenix Projects Pvt.Ltd.

03B 0275 222,884 221,273 1,611

Const of water treatment plants with commissioning & training Krishna Corp.

03B 0276 383,214 380,801 2,413

Construction of water treatment plants with commissioning & training.

Phoenix Projects P Ltd.

03B 0296 417,504 288,760 128,744

Kandla-Gandhidham complex water supply scheme IVRCL

04A 0063 276,223 194,988 81,235

Procurement of four packages of prefabricated housing (GEB-Retroactive)

Sintex Industries Ltd.

04A 0064 4,130,594 3,396,464 734,130

Purchase of 42 packages of various equipment, materials, works (GEB-Retroactive Financing) Various

04A 0085 4,164,079 3,550,021 614,058 Supply of ACSR zebra conductor

Gupta Cables Pvt. Ltd (Jv)

04A 0085 80,828 11,126 69,702 Supply of ACSR zebra conductor

Gupta Cables Pvt. Ltd (Jv)

04A 0086 8,567,635 7,209,742 1,357,893 Supply of ACSR panther conductor

Gupta Cables Pvt. Ltd.(Jv)

04A 0086 151,418 116,793 34,625 Supply of ACSR panther conductor

Gupta Cables Pvt. Ltd.(Jv)

04A 0087 917,495 801,325 116,170 Supply of ACSR dog conductor

Gupta Cables Pvt Ltd.(Jv)

04A 0087 7,197 281 6,916 Supply of ACSR dog conductor

Gupta Cables Pvt Ltd.(Jv)

04A 0088 656,938 427,726 229,213 Supply of GSS earth wire Uic Wires Ltd.

04A 0090 1,249,709 1,143,363 106,346 Supply of 120 Kn anti fog disc insulators

W.S.Industries (India) Ltd.

04A 0091 1,827,282 1,818,646 8,637 Supply of 90 Kn antifog disc insulator

Bharat Heavy Electricals Ltd

04A 0125 46,462 46,462 0 Supply of Ehv grade neptha-based transformer oil Various

04A 0126 53,258 52,551 708 Supply of 11 kV pin insulator

Premier Sanitary Wares

04A 0127 92,552 90,332 2,220 Supply of 4 mm dia GI plain Bedmuth Wire

Appendix 5

43

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

wire Company Ltd.

04A 0139 62,673 62,451 223 Supply of 11 kV disc insulator

Birla Ngk Insulators Ltd.

04A 0140 23,684 20,439 3,245 Supply of 7/2.5 mm GI stay wire

Vandana Udyog Ltd.

04A 0148 178,762 178,646 117 Supply of 66 kV Sf6 circuit breakers

Asia Brown Boveri Ltd.

04A 0150 40,887 39,765 1,122 Supply of 11 kV (pin insulators) spindle w/ nut

Asbesco (India) Pvt Ltd.

04A 0151 1,685,877 1,678,945 6,932 Supply of 55 sq mm AAA conductors

Sterlite Industries Ltd.

04A 0151 80,104 0 80,104 Supply of 55 sq mm AAA conductors

Sterlite Industries Ltd.

04A 0152 59,163 59,163 0 Supply of 11 kV lightning arrestors

Alstom Transmission & Distribution

04A 0153 111,072 108,310 2,762 Supply of 245 kV And 145 kV Sf6 circuit breakers

Asia Brown Boveri Ltd.

04A 0156 194,850 194,100 750

Supply of hardware and accessories for zebra conductors

Asbesco India Pvt Ltd.

04A 0157 425,793 416,793 9,000

Supply of hardware and accessories for panther conductors

Asbesco India Pvt Ltd.

04A 0158 87,056 86,932 124

Supply of hardware and accessories for dog conductors

Asbesco India Pvt Ltd.

04A 0159 34,519 33,274 1,245 Supply of 11 kV disc hardware

Classic Industries

04A 0160 235,516 234,527 989 Supply of 11 kV and 66 kV capacitor banks

Asia Brown Boveri Ltd.

04A 0162 75,842 75,842 0 Supply of ms bolts & nuts Techman (India)

04A 0164 85,641 85,003 638 Supply of hardware for earth wire 3.15mm

Rumika Engineering Co In Jv

04A 0174 62,364 62,077 287 Procurement of 11 kV AB switch

Bharat Elect.of India (Jv)

04A 0185 256,121 217,082 39,039 Supply of single phase and tree phase metal meter box

Shri Ram Switchgears Pvt. Ltd.

04A 0186 84,518 84,339 179 Supply of Kit Kat fuses

Electro Insulators of India Jv

04A 0189 410,577 410,577 0

Supply of 25,63,100 kVA Lt distribution boxes with MCCB

Stelmec Switchgears (Jv)

04A 0196 99,179 99,179 0 Supply of 100 mm X 116 mm and above ms beams

Bhuwalka Steel Ind. Ltd.

04A 0197 135,973 135,973 0 Supply of 65 mm X 6 mm ms angle

Bhuwalka Steel Ind Ltd.

04A 0198 138,170 138,170 0 Supply of 100 mm X 50mm X 5/6 mm ms channels

Bhuwalka Steel Ind. Ltd.

04A 0200 53,544 53,292 252

Supply of 100/5 amp, 3 phase whole current LT static meters

Secure Meters Ltd. Udaipur

Appendix 5 44

PCSS In $ equivalent

Category No. Contract

Value Disbursed Un-

disbursed Description Contractor

04A 0201 356,246 327,154 29,092 11 kV HG/DO fuse & ADB Switch -400 Amp (Lot I)

Danke Products

04A 0211 65,877 65,877 0 Supply of 4 sq mm & 6 sq mm 4 Core Lt PVC cable

Ravi Cable Industries

04A 0213 51,972 43,986 7,986

Procurement of 3.5 Core X25, 50, 70 & 150 sq mm LT PVC cables.

Krishna Electrical Industries

04A 0214 158,203 17,567 140,636 Procurement of 2 Core 2.5 mm 2 Lt PVC cables

Vardhman Cables (I) P Ltd.

04A 0218 700,929 700,929 0

Procurement of 3 Phase Lt Static Meter 10-60 amp (3 Phase 4 wire AC lt static whole current tri vector

Secure Meters Ltd.

04A 0220 140,613 139,539 1,074 Supply of 10sqmm And 16 sq mm LT PVC cable

Suyog Electricals Limited

04A 0221 423,722 418,723 4,999 Supply of 63 kVA distribution transformers

Nucon Switchgears Pvt Ltd.

04A 0222 767,261 755,102 12,158 Supply of 100 kVA distribution transformers

Nucon Switchgears

04A 0231 4,337 4,236 101 Procurement of GI bolt with nut and spring washer

S.P.Iron Industries

04A 0233 34,083 34,083 0 Supply of 16 mm m.s.round bars

M/S Shah Alloys Ltd.

04A 0234 6,492 6,492 0

Supply of HT guy insulators, LT guy insulators and LT shackle insulators

M/S Anupam Pottery Works

04A 0277 34,933 33,330 1,603

Ms flat 50 mm X 6 mm for the supply of ms flat 50 mm X 6 mm

Bhuwalka Steel Ind. Ltd.

04A 0321 718,332 715,947 2,385 Procurement of 66 kV & 11 kV capacitor banks Lot 1

ABB Ltd. Bangalore

04A 0322 938,760 937,608 1,152 Procurement of 66 kV & 11 kV capacitor banks lot 2

ABB Ltd. Bangalore

04A 0323 951,322 929,631 21,692 Procurement of 66 kV & 11 kV capacitor banks Lot 3

Shreem Capacitors Pvt. Ltd.

04B 0195 2,485,277 2,324,608 160,669

Const. of control room, staff quarters and other ancillary bldgs of GEB in Kutch District

Unity Infra Projects Ltd.

04B 0356 19,282 18,909 373

Providing bella masonry plinth and shed for temporarily relocation of control room at various S/S in Kutch H.N. Pancholi

04B 0357 27,923 22,007 5,916

Providing bella masonry & shed for temporary relocatation of control room at various S/S at Anjar V.K. Baldaniya

Totals 335,944,706 301,353,923 34,590,789

Source: ADB’s Loan Financial Information System and Gujarat state Disaster Management Authority records

45 Appendix 6

PROJECT IMPLEMENTATION ARRANGEMENTS GERRP ORANIZATION CHART

ACTUAL

Urban and Rural Infrastructure Power QC Housing Livelihood Rehabilitation DSC Urban Rural DSC DSC Disaster Management DSC BMC - benefit monitoring consultant QC - quality control consultant NGOs - nongovernmental organizations DI&M - Department of Industries and Mines GERI - Gujarat Energy Research Institute

GUDCO (IA) AMC (IA) AUDA (IA) RMC (IA) JMC (IA) VMC (IA) Bhuj ADA (IA) Bhachau ADA (IA) Anjar ADA (IA) Rapar ADA (IA)

GSDMA-PMCU (EA)

BMC PMC

GWSSB (IA) GWIL (IA) R&B (IA) Irrigation (IA) Department

GERI (IA) Council of Science city (IA)

PRHD (IA)

DI & M/DSJ & E (IA)

GEB (IA)

46 Appendix 6

PMC - project management consultant DSC - design and construction supervision consultants GWIL - Gujarat Water Infrastructure Limited PMCU - Project Management and Coordination Unit DSJ&E - Department of Social Justice and Empowerment JMC - Jamnagar Municipal Corporation PRHD - Panchayats, Rural Housing and Rural Development Department EA - Executing Agency RMC - Rajkot Municipal Corporation GEB - Gujarat Electricity Board VMC - Vadodara Municipal Corporation GWSSB - Gujarat Water supply and Sewerage Board GSDMA - Gujarat State Disaster Management authority R&B - Roads and Buildings Department IA - Implementing Agency AMC - Ahmedabad Municipal Corporation ADA - Area Development Authority AUDA - Ahmedabad Urban Development Authority GUDCO - Gujarat Urban Development Company

Appendix 6 46

Appendix 7 47

STATUS OF COMPLIANCE WITH LOAN COVENANTS

Covenant

Reference to Loan

Agreement

Status of Compliance (i) GOG will ensure that all facilities rehabilitated and reconstructed under the Project are operated and maintained by GSDMA, and thereafter by the relevant agencies taking over from GSDMA after completion of the works. GOG will make available, on a timely basis, the necessary funds for operation and maintenance of all the rehabilitated and reconstructed public facilities during and after implementation. (ii) GOG will allocate, on a timely basis, adequate counterpart funds from its budget for each fiscal year during project implementation. (iii) GOG will ensure that the GSDMA is adequately staffed by competent and qualified personnel for the effective implementation of the Project. (iv) The PMCU and IAs will actively seek NGO and community involvement and participation in the implementation and monitoring of rehabilitation and reconstruction of infrastructure under the Project. (v) The Government will upon receipt of the loan proceeds immediately and fully transfer such proceeds to the second-generation imprest account established by GSDMA. Such transfers will be treated as additional central plan assistance to GOG. (vi) GOG will ensure that the reconstruction of affected houses and other urban and municipal infrastructure under the Project will proceed; incorporating strengthened seismic, high wind (cyclone), earthquake, and flood resistant specifications and provisions. To this extent, GOG will monitor and ensure quality control of the construction, materials to be used in the reconstruction of infrastructure and houses, and clearing and approval of contractors and builders for the reconstruction, where applicable. (vii) GOG will initiate administrative approvals to ensure compulsory comprehensive insurance of reconstructed public infrastructure and housing property, and encourage similar insurance for private property; this will include insurance against natural calamities such as earthquake, cyclones, and flood.

Schedule 5, Para 17 Schedule 5, Para 4 Schedule 5, Para 2 Schedule 5, Para 9(c) Schedule 5, Para 11 Schedule 5, Para 12(a) Schedule 5, Para 14

Generally complied. Some municipal assets are being sub optimally maintained. GOG / GSDMA need to intervene to build municipal capacity or explore PPP options to ensure better O&M. Complied. There was no shortfall in the timely availability of counterpart funds. Complied. Complied. NGOs were intensely involved in housing, livelihood, disaster mitigation and urban infrastructure sectors Not complied. Delays of up to 2 months encountered in crediting reimbursement from ADB into SGIA Complied. Some delays occurred in approval of contracts due to approvals needed at various levels Complied. All houses built under PPP are insured against 14 types of hazards.

48 Appendix 7

Covenant

Reference to Loan

Agreement

Status of Compliance (viii) GOG will ensure and monitor that proper audit and accounting procedures are in place to ensure efficient and economical use of the loan proceeds for the beneficiaries. Accounts and financial statements in relation to the Project and subprojects will be maintained and certified by independent private auditors acceptable to ADB. GSDMA, through GOG, will provide to ADB (i) reports on such accounts and financial statements on a quarterly basis within 45 days of the close of each quarter, and (ii) accounts and financial statements as audited and certified, on a semi-annual basis within 60 days of the close of each semi-annual period. The Government and GOG will allow ADB representatives to carry out spot or random checks on flow of funds through the imprest account, to be maintained by the Government, and the second-generation imprest account, to be maintained by GSDMA.

Schedule 5, Para 14

Complied. Separate accounts of the project were kept and audited. Financial statements were submitted with some delays

Appendix 8 49

BENEFIT MONITORING AND EVALUATION

1. The Gujarat State Disaster Management Authority (GSDMA) engaged KPMG as the benefit monitoring consultant to monitor benefits derived by the society from the various programs under the World Bank- and ADB-assisted Gujarat Earthquake Rehabilitation and Reconstruction Project . Because a baseline survey was not conducted at the beginning of the Project (immediately after the earthquake), baseline information was collected using the perceptions and the recollections of the beneficiaries surveyed. The first sample survey, covering 8000 beneficiaries, was conducted during June 2003 (over 2 years after the earthquake), with results submitted to GSDMA in October 2003. The second sample survey covering 4000 beneficiaries was conducted during March–April 2004, and the results were submitted to GSDMA in July 2004. The third sample survey covering 8000 beneficiaries was submitted to GSDMA in August 2007. 2. In addition to the three sample surveys, specific studies addressing community participation, capacity building and disaster preparedness, trade and commerce, and urban infrastructure were carried out from November 2003 to June 2007, and covered 2500 households. 3. The surveys and studies covered six earthquake-affected districts over a 3-year span. Summary of findings of the benefit monitoring and evaluation (BME) report1 are:

• The housing sector was badly affected by the earthquake, but now boasts of owner-driven reconstruction with high awareness and usage of multi-hazard resistant technology.

• Cottage and village industries were affected with loss of assets, working capital and demand due to the earthquake. The Project focused on creation of an enabling environment by providing one-time assistance, which helped restore and increase employment and income levels.

• The Women’s livelihood and restoration program focused on facilitating social and economic activities that benefit and empower women. Both employment and income levels have increased.

• Trade and commerce in the affected regions has been restored to at least pre-earthquake levels.

• Road reconstruction provided an opportunity to strengthen and repair rural connectivity, which is usually ignored.

• Restoration of rural water supply was critical for ensuring health and hygiene in the affected areas. Reconstruction gave an opportunity to provide a solution to the problem of drinking water in the drought-prone Kutch district.

• Only 52% of villages had electricity immediately after the earthquake, but all villages now have access. The quality and duration of the power supply in both rural and urban areas has improved.

• Communities have gained from most of the aspects of the reconstructed urban infrastructure. Road connectivity has increased; congestion of narrow streets and over-hanging balconies has been drastically reduced. Public satisfaction with street lights, drainage and sewerage system is high. There is higher coverage of piped water supply connections among communities. People have started to appreciate the important role played by community bins, garbage dumps, and garbage collection

1 The benefit monitoring and evaluation study was done by consulting firm KPMG.

50 Appendix 8

vehicles in improving the overall town environment. People are satisfied with the various aspects of the Project, such as the time frame, public participation, and implementation of town planning schemes.

• A pro-people attitude was displayed by the administration after the earthquake, which is recognized and appreciated by residents.

• Municipalities must assess the operational and financial viability of all the completed projects in detail. Public–private partnership options should be explored wherever possible.

Appendix 9 51

SOCIO-CULTURAL, RESETTLEMENT, AND ENVIRONMENT IMPACTS

1. The overall strategy, policy and mechanisms of the government of Gujarat for enabling community responsive rehabilitation and reconstruction have been effective. There is recognition by the multiple stakeholders that government of Gujarat was flexible and adopted a consultative process during the relief and rehabilitation phase. 2. Implementation of the Gujarat Earthquake Rehabilitation and Reconstruction Project greatly enhanced the quality of both the built and natural environment, which had deteriorated due to the earthquake. All statutory environmental clearances for the facilities constructed under the Project have been obtained by the respective implementing agencies. The Project was classified under environmental category B, as it had some adverse environmental impacts. 3. The negative environmental and sociocultural impacts are rated negligible and the positive impacts significant. The overall strategy, policy and mechanisms of the government of Gujarat and the Gujarat State Disaster Management Authority for enabling community responsive rehabilitation and resettlement have been effective. There is recognition among stakeholders that the government of Gujarat was flexible and adopted a consultative process during the relief and rehabilitation phase.

52 Appendix 10

TECHNICAL ASSISTANCE COMPLETION REPORT Division: SARD

Amount Approved: $1.3 million TA No. and Name

TA3644-IND: Capacity Building for Earthquake Rehabilitation and Reconstruction of Housing

Revised Amount: $1.3 million

Executing Agency: Gujarat State Disaster Management Authority

Source of Funding: ADB TASF

TA Amount Undisbursed $105,592.95

TA Amount Utilized $1,194,407.05

Date Closing Date Approval 26 March 2001

Signing 15 May 2001

Fielding of Consultants 26 November 2001

Original 30 April 2002

Actual 28 April 2004

Description: The TA was piggy backed to Loan 1826-IND: Gujarat Earthquake Rehabilitation and reconstruction Project for $500 million, approved on 26 March 2001. The project was formulated in response to a request from the Borrower for support to reconstruction of the heavily damaged housing, infrastructure and livelihoods of hundreds of thous ands of affected persons. The emergency loan was approved by ADB’s Board just 2 months after the disastrous earthquake struck. The TA was provided to support the various state agencies with incorporation of earthquake strengthening measures in the reconstruction of housing and other structures. The original Executing Agency (EA) was the State Department of Urban Development, but once the Gujarat State Disaster Management Authority (GSDMA) was established, the TA was shifted to GSDMA for its implementation. When the TA was transferred to GSDMA, its scope was broadened to include day to day support to GSDMA with state wide disaster management planning, related facilities as well as capacity building to improve implementation of the associated loan project. This is why the original 12 month implementation of the TA was extended to 3 years, and the work plan of the consultants was adjusted to enable the longer term support. Objectives and Scope: The original objective of the TA was to support the Urban Development and Housing Department, the Rural Development Department and the local districts with implementation of the State’s reconstruction program. This would include (i) capacity building and development of regulatory systems and codes, land use planning, zoning development planning and upgrade the earthquake building standards, (ii) support to the urban and rural development and housing departments to oversee the rehabilitation and reconstruction of housing, through NGOs and local governments, (iii) establish cash flow systems for release of housing grants, and (iv) development of quality control and monitoring procedures to ensure that new housing met the updated building codes and standards with special emphasis on strengthening the structures against earthquake and other disasters. However, the State received considerable support for house reconstruction from various Central Government, bilateral and NGO programs, reducing the need for loan funds. Within one year of the loan approval, the State decided to utilize World Bank IDA funds for the remaining housing in urban sector and cancelled ADB’s involvement. The ADB loan was subsequently reduced by $150 million, to $350 million. While ADB did stay involved with the State’s 50% share of NGOs supported rural/village housing, the need for the substantial capacity building support under the TA was reduced. At the request of the Borrower, the scope of the TA was adjusted to provide more broad based disaster management support to GSDMA, along with making GSDMA the Executing Agency. In addition to strengthening housing standards, the TA was adjusted to support GSDMA with day to day management of implementation of the loan project, which ended up with more than 340 separate contracts, with emphasis on monitoring and quality control. The TA also was used to update the earthquake related design standards for housing, buildings, bridges, roads and other infrastructure. It also helped train hundreds of engineers and inspectors in the State. Finally the TA developed a State wide disaster management system, specifications for disaster rescue and emergency equipment and facilities and designed a typical regional disaster management center, for the long term operation of GSDMA. In short the TA helped operationalize GSDMA as the permanent disaster management authority in the State. Evaluation of Inputs: The TA included 115 months of consulting services, 15 months of international and 100 months of domestic specialists. The original terms of reference had to be substantially amended to reflect the ground realities and the quickly changing needs of the State’s rehabilitation. This is not surprising for an emergency loan where the loan and TA were formulated during a 3 week combined fact finding and appraisal mission, conducted under local emergency conditions. This was complicated by the fact that there were dozens of major donors on the ground the first few months, and initially there was considerable confusion as to who was doing what. The State and the Borrower were appreciative of ADB’s flexibility in adjusting the scope of the TA to enable it to provide real help to GSDMA. The Babtie Group, UK (later became Jacobs Babtie, UK) were the successful consultants. They provided the

Appendix 10 53

international disaster management specialist from several renowned institutes in the UK and USA, and domestic specialists from their Ahmedabad office. While the international specialist provided the overall disaster planning and guidance, it was the domestic team that GSDMA came to rely on heavily, therefore the eventual 2 year extension. Generally the consultants, with the exception of one individual who was found unsuitable, were excellent and met or exceeded their term of reference. The implementation of the loan project and the TA was supported by ADB’s Extended Mission in Gujarat (EMG). The EMG staffed by 2 experienced specialists, one engineering the other livelihood, was located in Gandhinagar, the State capital. The EMG provided hands on support to GSDMA, the 19 implementing agencies and the dozens of towns and district supported by the project. EMG provided assistance to GSDMA and the IAs with preparation of tender documents, tendering and management of more than 340 contracts. This was a major benefit for GSDMA as approvals of draft documents and evaluation reports were provided in only 1 to 2 days. The presence of the EMG also encouraged more beneficiary involvement as the staff consultants traveled frequently to the affected areas and beneficiary towns, villages and communities. The EMG staff attended numerous public meetings and consultations, especially during formulation of the disaster management plans, which was incorporated into the new town area development plans prepared for the towns of Bhuj, Anjar, Rapar and Bhachau which were almost completely destroyed in the quake and rebuilt under the loan project. The project and TA were also supported by monthly review missions from ADB’s India resident mission in Delhi (INRM). More than 20 such missions were carried out during the TA implementation period. The input for the TA was excellent and exceeded expectations. ADB has received many expressions of appreciation form the State, the local governments, NGOs and beneficiaries for the support provided under the TA. Evaluation of Outputs: The nature of the TA was project implementation support and capacity building, rather than a specific stand alone action or report. But the consultants did prepare a final report. In addition, they conducted dozens of training sessions on incorporating earthquake strengthening measures which included hundreds of engineers, architects and builders, public consultations, community activities including street plays, provided revisions to the curricula of engineering colleges to incorporate earthquake designs, established quality control measures of new housing and buildings, updated the State’s building codes, developed state, regional and community disaster management plans, conducted drills in evacuation and rescue with local communities, prepared policy framework for the State disaster management plan, planned, designed and specified the regional disaster management centers, and provided capacity building/training and advice to GSDMA on project related issues for 2 years. As indicated, these activities and outputs greatly exceeded that in the original TORs. The revisions in the TA scope and TORs led to substantial improvements in the outputs of the TA. The various reports and outputs are available in INRM’s files. Overall Assessment and Rating: Based on feedback from the State agencies, and GSDMA, and the above evaluation, the TA is considered highly successful. Major Lessons Learned: 1. The objectives and scope of emergency loans and associated TAs should be developed with a view to flexibility. The TORs should be left quite open, to enable easy adjustment as ground realities and needs become clear. 2. Capacity building TAs are particularly useful for emergency loans, where the local governments and EAs are usually completely unprepared and not experienced with rehabilitation and reconstruction. (In India, even normal loans to the urban sector are supported by capacity building TAs.) 3. While a modest amount of international expertise is useful in the early days of the TA, to plan the program, bring international expertise and best practices, and on an intermittent basis during implementation, it is the day to day support by local specialists under the TA that was highly beneficial to GSDMA/EA. 4. The TA should have been set up as a long term TA from the beginning.

54 Appendix 10

Recommendations and Follow-Up Actions: 1. The loan project was still ongoing 1 year after the TA was completed. The EA, GSDMA had requested that the TA be extended further to help them. But there comes a time when such an organization should be able to develop its own in house capacity. GSDMA became overly dependent on the TA consultants, and EMG, and had lost some focus since both were ended at the end of 2004. 2. The EA needs to develop more ownership and the State should have deputed more experienced staff to GSDMA. 3. While all contracts have been tendered, most works will be completed by end of 2006, though some will likely take until mid 2007 to be completed. INRM will continue to support and monitor the project. Prepared by

Alex Jorgensen

Designation

Principal Urban Specialist

55 Appendix 11

IMPLEMENTATION SCHEDULE(Appraisal Vs. Actual)

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

A. Housing (Identification & Implementation)

B Urban & Rural Infrastructurea. Immediate Phase(Minimum basic Services)

b Medium term(i) Design/Procurement

(ii) Implementation

C Powera Immediate Phase

b Design/Procurement

c Implementation

D Livelihood Rehabilitationa Immediate Phase

b Beneficiary Identification

c Reconstruction/Implementation

E Consulting Services

F Multihazard Disaster Preparedness & Mitigationa Establishing PMCU

b Establishing Disaster Mitigation Unit

Appraisal ActualSource: ADB estimates

Item2001 2002 2003 2004 2005 2006

56 Appendix 12

Selected Photographs Illustrating the Change in Situation from Just After Earthquake to After Project Implementation

Appendix 12 57

58 Appendix 12

Appendix 12 59

60 Appendix 12

Appendix 12 61

62 Appendix 12