completed the installation of the back of house equipment into the budweiser events center worked...

9
BEC Video Display and Ribbon Board Options

Upload: coral-phillips

Post on 27-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

BEC Video Display and Ribbon Board Options

Page 2: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

Update of Project• Completed the installation of the Back of House equipment into the Budweiser

Events Center

• Worked with Larimer County Purchasing Department to write and distribute an RFP for the project

• Interviewed and ranked three contractors that submitted: Daktronics, YESCO, and Panasonic

• Awarded the project to Daktronics

• Negotiated terms and conditions of the contract

Page 3: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

Project Status• Completed contract negotiations with Daktronics

• Project Team has agreed on key design elements for the center hung video display consistent with the original selection criteria

• Established a final project timeline and budget

Page 4: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

BudgetUses

Back of House Equipment

2014 Expense

$400,000

Video Display 2015 Expense

$900,000

Ribbon Board 2015 Expense

$400,000

Total $1,700,000

Page 5: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

BudgetSources 2014 2015 Total

The Ranch Unallocated Reserves

$400,000 $850,000 - $1,150,000

$1,250,000 - $1,550,000

Global Spectrum

$150,000 $150,000

Eagles Partnership

$0 - $300,000

$0 - $300,000

Total $400,000 $1,300,000

$1,700,000

Page 6: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

ReservesSources

The Ranch Unallocated Reserves

January 2015

$2,135,466

Contribution to Project

2015 $850,000 - $1,150,000

Balance Remaining $985,500 - $1,285,500

Page 7: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

Elements

Page 8: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

Elements

Page 9: Completed the installation of the Back of House equipment into the Budweiser Events Center Worked with Larimer County Purchasing Department to write and

Calendar• Execute Agreement with Daktronics: May • Design Phase: May-June• Manufacture Cabinets and Boards: June• Prepare Arena: Power, structural, demolition of

old boards: June• Installation and Training: July• First Event: Larimer county Fair and PRCA

Rodeo: August 2, 2015