comparative cost-benefit analysis of load reduction

9
EVE JOHNSTON April 24 th , 25 th & 26 th 2019 1 Eve Johnston COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION POLYMER COMPONENTS ON A EUROPEAN FOWT PROJECT.

Upload: others

Post on 28-Jan-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON April 24th, 25th & 26th 2019 1

Eve Johnston

COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION POLYMER COMPONENTS ON A EUROPEAN FOWT PROJECT.

Page 2: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

The Case:

• Pre-commercial small farm

• Semi-submersible 6MW platform – catenary chain spread mooring system.

• Enigmatic environment in shallower water conditions, the ULS:

• >30m/s wind speed

• >10m significant wave height

The Challenge:

• High peak tension in ULS cases (design driver)

• Cost increase for small frequency conditions.

CASE STUDY – EUROPEAN FOWT PROJECT

April 24th, 25th & 26th 2019 2

Page 3: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

Purpose of TFI Polymer Mooring component:

• Reduces compliance

• Reduce peak loads

• Minimise cyclic loading

How:

• Thermoplastic polymer compression shells • Material designed for cyclic loading

• Specifically designed non-linear stress-strain response

• Elongation of framework.

COST INNOVATION – POLYMER MOORING COMPONENTS

0

500

1000

1500

2000

0% 15% 30% 45% 60%

Load

(kN

)

Elongation (%)

Component Response

Response 1 Response 7

Page 4: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

DESIGN PROCESS

110 120 130 140 150 160 170 180 190 200 210

End

Ten

sio

n (

kN)

Time (s)

ULS End mooring line tension

Chain Component 2

April 24th, 25th & 26th 2019 4

Page 5: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

0

0,5

1

1,5

2

2,5

3

Mean (kN) Max (kN) Damage Life (years)

Comparitive Component Benefit

Original Chain Dia.

Chain case VS Component case

• Load reduction: • Greatest in extreme sea states.

• Benefits across most sea states.

• Minimisation of peak loads.

• Fatigue analysis: • Cyclic load reduction

• Frequency high load minimised.

• Damage reduction.

• Increase in fatigue life.

RESULTS- LOAD AND FATIGUE

Hs/Tp 5.2 7.8 9.1 11.7 13 15.6 18.2

2 5.6% 1.6% 4.1% 2.6% 2.0% 7.5% 8.7%

4 3.1% -1.8% 3.1% 2.2% -5.5% 8.0% 9.7%

6 -4.3% 2.0% 2.9% 20.0% 30.5% 40.0%

8 12.0% 37.5% 54.8% 61.7% 57.9%

10 71.5% 72.1% 67.5%

Percentage benefit on end loads

April 24th, 25th & 26th 2019 5

Page 6: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

Direct Impact:

• Cost of Mooring Line: • Chain and anchor,

• Connectors and tensioners

• Cost of Platform • Connections, reinforcements

• Sizing

Secondary Impact:

• Cost of Mooring Installation • Decrease in bollard pull

• Decrease in vessel handling requirements

• Cost of Platform Installation

• Reduced Installation Risk

CAPEX

-60

-50

-40

-30

-20

-10

0

Z fr

om

MSL

(m

)

Horizontal Span (m)

Mooring Line 3 Touchdown

Min S1 - Max

S2 - Max C - Max

0,0

0,2

0,4

0,6

0,8

1,0

Line Anchor Connectors Total

Selected Mooring CAPEX (Comparison)

April 24th, 25th & 26th 2019 6

Page 7: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

• Reduced Maintenance • Mooring: chain and anchor fatigue

• Platform: peak loads and fatigue

• Turbine: sudden impact damage

• Reduced Operations • Operational downtime

• Vessel size and time

• Port activities minimised

• Increased Capacity Factor • Due to decreased downtime

• Higher background load handling capability

OPEX AND AEP

0,0

0,2

0,4

0,6

0,8

1,0

Maintenace Port Activities Others Total

Selected OPEX (Comparison)

April 24th, 25th & 26th 2019 7

Page 8: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

LCOE SUMMARY

European Floating

Offshore Wind Farm

+

Polymer Mooring Component

(First FOWT Deployment)

Peak Load and Fatigue Reduction

=

>12% saving in LCOE 0 0,2 0,4 0,6 0,8 1 1,2

CAPEX (€Million/MW)

OPEX (€Million/MWh)

AEP (MWh)

LCOE (€/MWh)

Comparative Cost Benefit

April 24th, 25th & 26th 2019 8

Page 9: COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION

April 24th, 25th & 26th 2019 3

EVE JOHNSTON

PAUL MCEVOY

Questions ? Or want to get in contact:

COMPARATIVE COST-BENEFIT ANALYSIS OF LOAD REDUCTION POLYMER COMPONENTS ON A EUROPEAN FOWT PROJECT.

www.tfimarine.com

[email protected]

EVE JOHNSTON

[email protected]

April 24th, 25th & 26th 2019 9