  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    1/13

    Development of a Comprehensive Modernization Project at

    Polytechnic High School

    Community Meeting

    Thursday, March 10, 2016 

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    2/13

    Agenda

    Overview

    Program Goals

    Analysis

    Recommendations

    Timeline / Next Steps

    Questions and Answers

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    3/13

    Overview

    Polytechnic High School was identified for the development of a

    “Comprehensive Modernization Project”

    Board of Education approved in March 2015

    1 of 11 schools identified…so far

    What does this mean?

    A large-scale project is being developed to make major improvements

    to Polytechnic HS’s facilities

    The project will address the most critical physical conditions of school

     buildings and grounds Focus on safety

    Limit work on less critical items.

    The project is developed based on data, analysis, and community input

    Approximately 10 Times More Funding Than is Available Would be Needed to Address All the Capital

     Needs of All of Our Schools

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    4/13

    Board Approved Goals

    Schools Should be Physically Safe and Secure

    School Building Systems Should be Sound and Efficient

    School Facilities Should Align with Instructional Requirements andVision

    Projects will modernize, build and repair school facilities to improvestudent health, safety, and educational quality

    School Upgrade Program

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    5/13

    Comprehensive Modernization ProjectWork Completed 

    Conceptual Master Plans: 2010-2013

    Performed by Architects

    Included input from school users and stakeholders Produced a long-range roadmap to assist with future facilities

    improvements

    Facilities Condition Assessment: 2011-2015

    Performed by District Maintenance & Operations professionals

    Analyzed the condition of building systems

    Identified when building systems are anticipated to require

    maintenance and/or replacement

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    6/13

    Comprehensive Modernization ProjectWork Completed 

    Educational Programming: Spring - Fall 2015

    Developed by school site administrators and District leadership

    Identified school educational vision and academic programs

    Ensures facility improvements support educational programs

    Polytechnic HS serves ~ 3,000 students

    Community Input: Spring 2015 Accessible and safe path of travel for all students needs

    improvement

    Seismic safety is important

    Replacing portables with permanent buildings is important Science and music classrooms need upgrading

    Athletic facilities need upgrading

    Library needs upgrading

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    7/13

    Comprehensive Modernization ProjectWork Completed 

    Topographic, Geological and Utility surveys: Spring - Fall 2015

    Performed by professional surveyors and geotechnical experts

    Easements and utilities identified

    Soil conditions analyzed

    Utilized to gain understanding of various complex site conditions

    Infrastructure Analysis: Spring - Summer 2015 Performed by architects and engineers

    Capacity and condition of underground and above ground utilities

    were analyzed including:

    Sewer, storm water, plumbing, electrical, low voltagesystems, heating and cooling, etc.

    Utilized for budgeting and scoping major building system

    upgrades and/or replacements

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    8/13

    Comprehensive Modernization ProjectWork Completed 

    Seismic Evaluation: Spring - Fall 2015

    Performed by structural engineers

    Buildings with characteristics identified by the State of

    California Assembly Bill 300 were evaluated

    Utilized to determine whether seismic upgrades are needed and

    the extent of upgrades needed to further ensure safety

    Historic Evaluation: Spring - Summer 2015

    Performed by architectural historians

    Conducted research on history of school facilities and sites

    Existing buildings and sites were surveyed and analyzed toidentify character-defining architectural features

    Utilized to gain understanding of historic resources

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    9/13

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    10/13

    Major Findings

    Seismic Evaluation

    7 buildings requirestructural upgrades

    Campus infrastructure in poorcondition

    Security features require upgrade

    Polytechnic High SchoolWhat we learned  

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    11/13

    Proposed Scope of Work 

    New Building(s) to be Constructed

    Classrooms

    Gymnasium

    Cafeteria

    Auditorium

    Administration/Library

    Site Work 

    Site Infrastructure

    Student drop off 

    Parking

    Renovation of Existing Classroom

    Buildings

    Roofing

    Paint (Interior & Exterior)

    Flooring & Base

    Anticipated improvements valued at more than $100 Million!

    Polytechnic High SchoolWhat we recommend 

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    12/13

    Anticipated Project Timeline

    Project

    Development

    Environmental

    ~12-18 months ~2-4 Years

    DesignApprovals

    ~10-12 months

    Construction

    BOC

    BOE

    Project

    Definition

    BOC

    BOE

    ProjectApproval

    BOE

    Site

    Identification

    BOE

    CEQA

    Certification

    (if necessary)

    BOE

    Construction

    Contract

    Award

    *Timeline Assumes a Traditional

    Design, Bid, Build Procurement

  • 8/19/2019 Comp Mod Community Presentation Poly HS _3102016

    13/13

     For More Information Please Contact:

    José De Paz, FSD Community Relations Department

     [email protected]

    • Main Line (213) 241-1340 • Direct Line (213) 241-1334

    Questions and Comments