Planning Community Meeting Please sign in on your mobile device: http://communitymeeting.ocps.net/ August 26, 2019 Site 73-T-W-7: OTC @ Westside Campus

Upload: others

Post on 31-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Planning Community Meeting

Please sign in on your mobile device: http://communitymeeting.ocps.net/

August 26, 2019

Site 73-T-W-7: OTC @ Westside Campus

Page 2: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Site 73-T-W-7Meeting AgendaAugust 26, 2019 at 6:00pm

• Welcome – Melissa Bryd, School Board Member, District 7

• Introductions – Jessma Lambert, Facilities Director, Construction Planning

• Project Update – Faz Ali, Senior Facilities Director, Planning

Architect: DLR Group

Contractor: Wharton Smith

• Questions and Answers

• Adjournment2

Page 3: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Orange Technical College Vision

3Site 73-T-W-7

Page 4: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Orange Technical College Programs

4

Westside Campus:

• Construction Trades

• Welding Technology

• Apprenticeship

• Human Services

• Veterinary Assisting

Orlando Campus:

• Health Science Focus

Mid-Florida Campus:

• Industrial

• Transportation

• Manufacturing

• Culinary

• Hospitality

• Adult Education

Winter Park Campus:

• Information & Digital Technology

Site 73-T-W-7

Page 5: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Site 73-T-W-7 5

Existing OTC Westside Campus

New OTC Westside Campus

Ocoee High SchoolSite Location

Page 6: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Lake ApopkaOcoee Apopka Rd.

Fullers Cross Rd.

West Rd.

Ocoee High School

Hope Charter School

Glad Tidings Church

Retail Area

The Site

Future Connection

Main Access from 429

Traffic Light

Traffic Light

Main Access

Site 73-T-W-7

Site Aerial

Page 7: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Campus Programs

• Career Pathways:

7

• Building Construction Trades

• Human Services / Personal Care

• Veterinary Assisting / Technician

Site 73-T-W-7

Page 8: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Community Engagement: Cultural Continuum

8Site 73-T-W-7

Page 9: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Breakout to Engage in Cultural Continuum (10 minutes)

9Site 73-T-W-7

Page 10: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Community Engagement: Futurecasting

10Site 73-T-W-7

Page 11: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Breakout to Engage in Futurecasting (20 minutes)

11Site 73-T-W-7

Page 12: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Schedule

12

Design Phase Start: Summer 2019

Design Phase Completion: Summer 2020

Construction Phase Start: Fall 2020

Project Opening: Summer 2022

Site 73-T-W-7

Page 13: Community Meeting Title - Orange County Public Schools · 26/08/2019  · Breakout to Engage in Futurecasting (20 minutes) Site 73-T-W-7 11. Schedule 12 Design Phase Start: Summer

Questions & Answers

13