Community CenterConceptual Design
City of Burlingame
03.19.20157:00 pm - 8:00 pm
Parks & Recreation Meeting
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 4
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 5
Community Outreach (subject to change) ROUND 1
MARCH 19th: Parks & Recreation Commission – Public Hearing/Meeting, 7pm – TODAY MARCH 21st: Community Open House @ Washington Park, 10am-2pm MARCH 22nd: Community Kiosk @ Farmers Market, 9am-1:30pm
ROUND 2MAY 30th: Community Open House @ Washington Park, 10am-2pm MAY 31st: Community Kiosk @ Farmers Market, 9am-1:30pmJUNE 18th: Parks & Recreation Commission – Public Hearing/Meeting, 7pm
PARTICIPATION OPPORTUNITIES OVERVIEW
Teen/Youth Specific OutreachWeek of May 4th – Lunchtime Kiosks at Burlingame High School and Burlingame Intermediate School
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 6
Community Outreach (subject to change) ROUND 3
TO BE SCHEDULED
Other - TO BE SCHEDULEDCommunity Open House – Downtown Merchants AssociationRotary Club MeetingsBurlingame Mother’s ClubTraffic and Safety Commission?
PARTICIPATION OPPORTUNITIES OVERVIEW
Presentations and Public Hearings (2) Planning Commission
Study Session – June 22nd
Fall 2015(2) City Council Meetings
City Council Check-in (Study Session) – June 15th
City Council Final Presentation – November 2nd
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
PROCESS GOALSCommunity engagement that is transparent and signified by the collaboration of a wide range of stakeholders and community members
Broad community input resulting in local pride and ownership in the plan recommendations
Plan recommendations that address the needs of a wide cross-section of residents, and bring the community together to focus on a common goal
Burlingame’s values are reflected in the process and development of the plan; participants’ feedback is listened to and affirmed by the plan recommendations
The recommended plan captures the goals, needs, and vision of all Burlingame residents, and successfully translates those into the end product: the new community center
7
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
PROJECT OUTCOME GOALSCreating a community center that becomes a pillar of community life and civic pride for Burlingame
A facility that is operationally, environmentally, and socially sustainable
The creation of a multigenerational community center that becomes a central meeting and gathering place for residents
Honoring the history and heritage of the Gunst Estate, Washington Park, Burlingame, and respecting the mature trees
Building a facility that meets the needs of today’s community, and has the flexibility to evolve to meet future needs
A community center that provides the opportunity for people to enrich themselves intellectually, emotionally, spiritually, and physically
8
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
SITE PLAN
1 0
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 1 1
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 1 2
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 1 3
SITE SECTIONS
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
BUILDING PROGRAM OPTION
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
LOBBY/COMMUNITY LOUNGE
COMMUNITY HALL
1 6
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
ENRICHMENT & PERSONAL DEVELOPMENT
CATERING KITCHEN
1 7
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
TINKER LAB/MAKER SPACE
LARGE MEETING ROOM
1 8
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5
PERFORMING ARTS, DANCE, & FITNESS
VISUAL & FINE ARTS
1 9
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 1
COMMUNITYHALL
MAKERROOM
CREATIVEARTS/
CERAMICS
LOUNGEFLEX
SPACE
KIT
CH
EN
TEENSCENE
RR
RAISEDPLATFORM
STOR.
PARKRR/
STOR. LOBBY
STOR.
STAFF
KILN
RECEPTION
PLAYGROUNDPARKPLAZA
ARTYARD
PARK PATIO
SURFACEPARKING
SURFACEPARKING
ENTRY PLAZA
BURLINGAME AVENUE
ABUILDING BUBBLE DIAGRAM – OPTION AFLOOR 1
S C A L E : 1 ” = 4 0 ’
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 2
COMM. HALLBELOW
FITNESS &WELLNESSSTUDIO
DANCE &STRETCHSTUDIO
LRG.MTG.
ROOM
FINEARTS
ADULTACTIVE
LOUNGE
ART DECK
ENRICHMENT CLASSROOM
DECK
KIDSTOWN
SERV
ICE
MUSICAL ARTS
SERVICE
RR
ABUILDING BUBBLE DIAGRAM – OPTION AFLOOR 2
S C A L E : 1 ” = 4 0 ’
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 3
COMMUNITYHALL
MAKERROOM
CREATIVEARTS/
CERAMICS
LOUNGEFLEX
SPACE
KITCHEN
TEENSCENE
RR
RAISEDPLATFORM
STOR.
PARKSTORAGE
LOBBY
STOR.
STAFF
KILN
RECEPTION
PLAYGROUNDPARKPLAZA
ARTYARD
PARK PATIO
SURFACEPARKING
SURFACEPARKING
ENTRY PLAZA
BURLINGAME AVENUE
BBUILDING BUBBLE DIAGRAM – OPTION BFLOOR 1
RR
PARKRR
RR
S C A L E : 1 ” = 4 0 ’
SERV
ICE
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 4
COMM. HALLBELOW
FITNESS &WELLNESSSTUDIO
DANCE &STRETCHSTUDIO
LRG.MTG.
ROOM
FINEARTS
ADULTACTIVE
LOUNGE
DECK
ENRICHMENT CLASSROOM
KIDSTOWN
MUSICAL ARTS
SERVICE
RR
BBUILDING BUBBLE DIAGRAM – OPTION BFLOOR 2
S C A L E : 1 ” = 4 0 ’
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 3 3
CONTEXTUAL INSPIRATION
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 3 4
TRADITIONALLY INFLUENCED
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 6
WARM + INVITING
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 3 2
CIVIC
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 9
RURAL + RUSTIC
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 8
EASY MODERN
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 2 7
COLORFUL
B U R L I N G A M E C O M M U N I T Y C E N T E R0 3 . 1 9 . 1 5 3 0
EXPRESSIVE
SITE INTEGRATION OPTIONS
AGENDA1. Welcome & Introductions
2. Project and Schedule Overview
Work Plan
Participation and Outreach Schedule
Process and Outcome Goals
3. Master Plan Review
4. Program Options
5. Building Bubble Diagram Options
6. Design Values Exercise
7. Next Steps
SITE INTEGRATION OPTIONS
NEXT STEPS
Community Outreach: ROUND 1
MARCH 21st, 10am-2pm – Community Open House with Neighbors and Park/Facility Users at Washington Park
MARCH 22nd, 9am-1:30pm – Community Kiosk at the Burlingame Farmers Market