October 2021

Common Terms and Worked Examples - English New Connection Rules

Effective from April 2022

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

1

About this document

This document is published by Ofwat under rules 11 and 12 of the Charging Rules for New Connections Services (English Undertakers).

It sets out:

• The common terms and definitions agreed between Water Companies and stakeholders for use by Water Companies including SmallCompanies (where appropriate) in their Charging Arrangements (in addition to those set out in the Charging Rules for New ConnectionsServices (English Undertakers)) issued by Ofwat; and

• the information requirements in a standard format that each Water Company (with the exception of Small Companies), as a minimum,must follow when presenting their Charging Arrangements.

The format for presenting the worked examples has been agreed collectively by companies, in consultation with stakeholders, during 2021. Any company wishing to present their Charging Arrangements using a different format or different worked examples may do so in addition to their obligations under these rules.

This document is approved and published by Ofwat on its website.

Ofwat may amend this document from time to time.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

2

Common terms

Water Companies are required, where appropriate, to use these terms as defined in their Charging Arrangements. Where a term is defined differently in this list of common terms from in the Charging Rules for New Connection Services (English Undertakers), this is because the definition here is phrased so as to be less legalistic and more intelligible to stakeholders rather than to alter its meaning. For the avoidance of doubt, in the event of a conflict between these common terms and the Charging Rules for New Connection Services (English Undertakers) or any statutory provision for the purposes of determination, dispute or other regulatory action by Ofwat, then the latter shall prevail.

Administration Fee

means the fee associated with general administration activities, after the cost advice stage, relating to the construction phase, which can include processing any payments, scheduling the works, supervision and project management, and processing information into relevant billing/management systems. This would not include site-based activities covered in construction costs, such as additional site visits.

Adoption means the process whereby assets are vested in the water company and subsequently maintained at its expense.

Alternative Point of Connection

means another location indicated by the Water Company which is neither i) a practical location indicated by the Developer Customer, nor ii) the nearest practical location where the existing Water Main or Sewer is the same size or larger than the new connecting Water Main or Sewer.

Annual Contestability Summary

means the standard format document published annually (or more frequently) by the Water Company on its website setting out which work and services are Contestable Work and Services and which are Non-contestable Work and Services as described in section 3 of the Water Sector Guidance (see www.water.org.uk/water-sector-guidance-approved-documents/).

Application Fee means the fee levied at point of application, which is associated with upfront application processing, which can include reviewing and acknowledging an application, checking that all relevant information has been received, preparing a cost advice, an agreement or the acceptance for the proposed works.

Barrier Pipe means a polyethylene (PE) pipe with an aluminium barrier layer conforming to water industry specification 4-32-19.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

3

Bond or Surety means a cash bond or financial guarantee underwritten by an appropriate warranty provider, bank or insurance company, which is accepted by the Water Company.

Branch Connection means the connection of new pipework to an existing Water Main such to provide a supply of water to a Development.

Communication Pipe

means any part of a Service Pipe which a Water Company could be, or have been, required to lay under section 46 of the Water Industry Act 1991. Typically, it consists of a pipe laid from an existing or newly laid Water Main to the boundary of a property and may include a meter housing and / or external stop valve. This can be seen in figure 1.

Figure 1:

Contaminated Land means land by which a water company will install or request the installation of barrier pipe, following review of the previous use of site, or where proven necessary, in accordance with section 78A of the Environmental Protection Act 1990.

Contestable Work means the work or services that can be completed by either a Water Company or an Accredited Third Party, with the work and services relating to the provision of water supplies defined in each Water Company’s Annual Contestability Summary. For work related to new sewerage services, the majority of work is considered contestable, excluding diversions and requisitions.

Design Checking Fee means the cost of checking a design submitted by an Accredited Third Party.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

4

Design Fee means the cost of designing against the application, providing a detailed site drawing and design, specification and cost-advice. This may also include activities identified in the Administration Fee (such as site visit) if that cost is not already charged by the particular Water Company.

Developer Services

means, collectively, the activities associated with serving Developer Customers, which may include the provision of new Water Mains, new Sewers, Communication Pipes, Lateral Drains, diversions of water and sewerage assets and connections made to supply water for building purposes.

Domestic Use means water used primarily for domestic purposes, including for drinking, washing, cooking, central heating and sanitary purposes.

Excavation by Others means any work undertaken by someone other than the Water Company in excavation, backfilling or reinstatement.

Excavation by Water Company

means any work undertaken by the Water Company (or an agent acting on their behalf) in excavation, backfilling or reinstatement.

Existing Main means a Water Main or Sewer that was commissioned independently of development commencing.

Far Side Connection means a connection between premises and an existing water main on the opposite side of the street to those premises, to a maximum communication pipe length of distance of 18 metres, for which a straight linear meterage rate is not applied. Where the water main is located in the centre line of the street then the connection will be considered a Far Side Connection.

Fire Supplies means supplies provided solely for fire safety provision.

Fixed Charges

means charges which are fixed in amount or which are calculated by reference to a predetermined methodology set out in a Water Company’s Charging Arrangements, the application of which allows calculation at the outset of the total amount owing in a given Charging Year in respect of the charges in question. For the avoidance of doubt, a Water Company may impose Fixed Charges by reference to a unit measurement (for example, per megalitre). Furthermore, a Water Company may offer more than one Fixed Charge in charging for a service provided in accordance with the present rules (for example, by differentiating between different geographic areas).

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

5

Footpath means a hard-surfaced area intended for use by pedestrian or cyclists.

Household Premises means any premises used principally as a domestic dwelling or intended for such use, such as a house or flat.

Infrastructure Credit

means a credit which may be applied when there has previously been a billable account on the same site/address. The eligibility criteria and method of calculating Infrastructure Credits is defined by the Water Company in its Charging Arrangements. This term is autonomous from any incentives applied against the infrastructure charge, for water efficiency for example. These are defined in the term Water Efficiency Incentive.

Infrastructure Charge means the charges described in section 146(2) of the Water Industry Act 1991. That is, a charge paid by the Developer Customer to the Water Company when a property is connected to the company’s water supply or sewer network for the first time. The charges fund wider network reinforcement to meet the increased demand arising from the new connections.

Manifold Connection means where a Communication Pipe connects with a manifold to which separate Supply Pipes are connected and meters may be fitted.

NAV

means a company appointed by Ofwat through the new appointments and variations process to provide water and/or sewerage services to customers in an area previously served by the incumbent Water Company. A new appointment is made when Ofwat appoints a company for the first time to provide services for specific geographic area. A variation occurs where an existing appointment is varied to amend the area served.

Near Side Connection means a connection between premises and an existing Water Main on the same side of a street to those premises. Where the Water Main is in the centre line of the street then the connection will be considered a Far Side Connection.

Network Assembly means components such as sluice valves or washouts, including associated chambers, needed to operate and maintain a water network.

Network Reinforcement means work to provide or modify such other specified types of infrastructure (mains and tanks, service reservoirs, pumping stations, or sewers) as is necessary in consequence of the need to provide adequate water supply and/or sewerage capacity to a development at which mains, service pipes, public sewers and/or lateral drains have been installed or connected by the

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

6

company imposing the charge or by a company with whom the company has entered into an agreement for bulk supply or bulk discharge.

Non-contestable Work means work or services that can only be completed by the Water Company (or an agent acting on their behalf) and, in the case of work or services associated with the provision of water supplies, is defined in each Water Company's Annual Contestability Summary.

Non-domestic Use means water used primarily for non-domestic purposes, including anything not for Domestic Use, such as water for industrial or business use (including manufacturing processes, washing and cleaning and cooling), agricultural use and filling swimming pools.

Non-household Premises

means any premises not a household premises, being used principally for industrial, business, recreational or community purposes and not as a dwelling, or intended for such use.

Non-standard Connection

means a service sized above the standard size as defined by the Water Company.

Phase means a discrete part of a Development which the Developer Customer chooses to separately progress.

Pre-Planning Enquiry means an enquiry submitted by a Developer Customer to understand the infrastructure requirements or considerations for proposed developments.

Pre-Planning Enquiry Response

means a report by the Water Company in response to a Pre-Planning Enquiry that will confirm i) if the development can be supplied with water, ii) capacity within the wastewater network, iii) if any reinforcement work will be required to supply the site together, iv) and, if applicable, identify any existing assets crossing the site which may require diverting or protecting, and v) if Network Reinforcement is required to supply the site, what indicative capital cost or range of costs is likely for these works.

Relevant Multiplier means a calculation to determine the Infrastructure Charges payable relating to Non-household Premises or Household Premises subject to a common billing agreement and is based on the number and type of water fittings proposed for those premises.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

7

Road means a hard-surfaced area intended for vehicles.

Self-certification means the activity whereby an Accredited Third Party inspects, checks and certifies installations, both internal and external to a premise, as being compliant with relevant standards and requirements.

Service Connection means the joining of a Service Pipe to a Water Main which is provided under section 45 and 46 of the Water Industry Act 1991.

Service Pipe means a pipe, which is, or is to be, connected with a Water Main for supplying water from that main to any premise. This can be seen in Figure 1.

Figure 1:

Sewerage Sector Guidance

means guidance documents published in accordance with Ofwat’s Code for adoption agreements, relating to the adoption of sewerage assets and available at www.water.org.uk/sewerage-sector-guidance-approveddocuments/.

Supply Pipe means the part of the Service Pipe that is not the Communication Pipe, and which remains the customer's responsibility. This can be seen in Figure 1.

Figure 1:

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

8

Sustainable Drainage Incentive

means, where offered, a reduction in infrastructure charges to a Developer Customer where they evidence that a Development will or does meet a stipulated threshold for use of a sustainable drainage solution, as defined in the Water Company’s Charging Arrangements and/or specific environmental policies.

Traffic Management Fees

means charges to cover the cost of working in the highway safely as a result of compliance with the Traffic Management Act 2004.

Trial hole means exploratory excavation to identify the location of apparatus, prior to works commencing.

Unmade Ground means ground which does not have a man-made surface, and may feature grass and topsoil.

Upsizing means where the Water Company instructs that new Water Mains and/or Sewers are increased in size beyond that required to satisfy the minimum design for a specific Development. This may be to facilitate future development and is deemed Network Reinforcement.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

9

Water Company means a company holding an appointment as a water or sewerage undertaker under the Water Industry Act 1991.

Water Efficiency Incentive

means, where offered, a reduction in infrastructure charges to a Developer Customer where they evidence that a Development will or does meet a stipulated threshold for reduced water consumption, as defined in the Water Company’s Charging Arrangements and/or specific environmental policies.

Water Industry Registration Scheme (WIRS)

means the scheme operated by Lloyd's Register EMEA on behalf of Water UK and its members, which certifies the competence of companies undertaking Self-Lay, or such other scheme as replaces it from time to time.

Water Regs UK means the company responsible for running the Water Industry Approved Plumber Scheme (WIAPS) on behalf of the water industry in England and Wales, formerly provided under the Water Regulations Advisory Scheme. The company promotes compliance with the Water Fitting Regulations 1999 and other relevant standards across the UK to protect customers.

Water Regulations Advisory Scheme (WRAS)

means a compliance mark that demonstrates that an item or product complies with standards set out by Water Supply (Water Fittings) Regulations 1999.

Water Sector Guidance means guidance documents published in accordance with Ofwat’s Code for adoption agreements, relating to the adoption of water assets and available at www.water.org.uk/water-sector-guidance-approved-documents/.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

10

Information requirements

With the exception of Small Companies, each Water Company must present its Charging Arrangements using worked examples for the following scenarios, and in the standard format set out below.

Scenarios summary

Each Water Company should represent the following six scenarios in worked examples in its Charging Arrangements.

1. Single connection to a house from an existing main. 2. Single connection to a block of flats from an existing main. 3. Medium housing development requiring new mains and communication pipes (excavation and reinstatement by others). 4. Medium housing development requiring new mains and communication pipes (excavation and reinstatement by Water Company). 5. Large housing development requiring new mains and communication pipes (excavation and reinstatement by others). 6. Large housing development requiring new mains and communication pipes (excavation and reinstatement by Water Company).

Guidance for Water Companies

For the avoidance of doubt, worked examples should include every charge that the Water Company would impose in accordance with these rules, including where applicable in any of the scenarios:

• Requisition Charges; • Infrastructure Charges; • Connection Charges; • Income Offset;

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

11

• Relevant ancillary charges; • Clearly itemised unit costs for all relevant services.

Each Water Company should include in its worked examples:

• Adequate commentary to avoid inappropriate comparisons between Water Companies and in any place where the Water Company has chosen to take account of its own specific policies or area-specific terminology and practices.

• Any additional scenarios where the Water Company identifies issues with the scenarios or to highlight specific items that it considers could be of particular interest to its customers.

• Diagrams where the Water Company considers that this will make the worked examples more accessible to Developer Customers.

For all scenarios, when presenting worked examples:

• Assume typical soil type for your region, that there is no rock and the land is not contaminated. • Include all charges for activities and materials expected in an average job in the surface type being used • Include all relevant ancillary charges, such as (but not limited to) application and design fees, any other administrative fees charged

to developer customers for delivering the service, and meter costs and installation (where not included in the Connection Charges). • All items in the table which state ‘Y’ to ‘Applicable Charge?’ should be separated within your worked examples table and should remain

unchanged. These are identified as bold in the table to allow customers to easily identify consistent rows which are applicable to any water company.

• For any blank cell within the column ‘Applicable Charge?’, you should state whether or not it is applicable depending on the structure of your charges. If a charge item is not applicable, a ‘N’ should be placed in the column with ‘N/A’ across the charge item cells.

• Should you have additional charges which relate to an overall charge in Bold (i.e. Connection Charge or Mains Connection charge), you should include the rate in the table where it states ‘sub-charge 1,2,3…’ so that customers are able to relate the charges back to individual charging arrangements documents. The worked examples should reflect any ancillary charges which will be included in that part of work, i.e. thrust blocks.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

12

• Clearly identify that the worked examples assume that all contestable sewerage delivery activities are completed by a third party. Any fees associated with these activities, i.e. Section 106 sewer connection vetting fee, should be itemised under ‘Other Charges’.

• As individual water companies publish their own contestability summary documents, where an activity within a worked example table is not a contestable activity or is deemed irrelevant for a NAV company, you should grey these out.

• Present infrastructure charges in full, i.e. before any applicable reductions, for example an infrastructure credit or water efficiency incentive. However, should a Water Company offer such incentives, you should make this clear in the footnote of the worked example.

• Present all charges exclusive of VAT.

Scenarios in detail

The following pages in this document set out each scenario in detail, along with the standard format for presenting the applicable charges.

In each of the scenario tables, "Alternative Delivery Method" and the relevant charges presented under that heading assume that an SLP or NAV performs all contestable elements of the work, including design, and incurs the costs associated with these activities.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

13

Scenario 1: Single connection to a house from an existing main

This worked example provides charges for a single connection to an existing water main of 90mm diameter polyethylene (PE). If applicable, the worked example should include the associated charges for a single property connection to an existing sewer, which is completed by the Developer Customer. These charges are specified under ‘Other Charges’.

Within construction costs, this includes: Service pipe installation; Boundary box fitting; Meter installation; Excavation; Reinstatement

Pipework:

• 25 – 32mm diameter PE pipe • 4m pipework in road

Traffic management assumes the road (Type 3-4) is 40mph, has two lanes and does not require a road closure or lane closure. Two-way automated lights are required. There is also an assumption that the only payable council charges are for permitting.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

14

Scenario 1: Single connection to a house from an existing main Alternative Delivery Method

Applicable Charge? Item Unit Qty

Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

Pre-Construction Charges

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges

Y Connection per connection

Connection sub-charge 1

Connection sub-charge 2

Connection sub-charge 3

Pipework - Road per metre

Traffic Management Per TM usage

Meters Per connection

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water Per property

Infrastructure Charge - Sewerage Per property

Income Offset

Y Income Offset – Water Per property

Income Offset – Sewerage Per property

TOTALS

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

15

Scenario 2: Single connection to block of flats from an existing main

This worked example provides charges for a block of 10 flats to be connected to an existing main of 90mm diameter PE. Each flat would be individually metered. If applicable, the worked example should include the associated charges for connection to an existing sewer, which is completed by the Developer Customer. Within construction costs, this includes: Service pipe installation; Boundary box fitting; Meter installation; Excavation; Reinstatement Pipework:

• 63mm diameter PE pipe • 4m pipework in road, 4m pipework in unmade ground

Traffic management assumes the road (Type 3-4) is 40mph, has two lanes and does not require a road closure or lane closure. Two-way automated lights are required. There is also an assumption that the only payable council charges are for permitting.

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

16

Scenario 2: Single connection to a block of flats from an existing main Alternative Delivery Method

Applicable Charge? Item Unit Qty Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

NAV Rate (£)

NAV Total Charge (£)

Pre-Construction Charges

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges

Y Connection per connection

Connection sub-charge 1

Connection sub-charge 2

Connection sub-charge 3

Pipework - Road per metre

Traffic Management Per TM usage

Meters Per connection

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water Per property

Infrastructure Charge - Sewerage Per property

Income Offset

Y Income Offset – Water Per property

Income Offset – Sewerage Per property

TOTALS

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

17

Scenario 3: Medium housing development requiring new mains and communication pipes (excavation and reinstatement by others)

This worked example provided charges associated with the provision of new water mains and individual connections from them for each of 50 new houses. If applicable, the worked example should include the associated charges for the 50 property connections to an existing sewer, which are completed by the Developer Customer. This worked examples assumes excavation and reinstatement activities are completed by others, except for the excavation leading to the connection to the existing water main.

Within construction costs, this includes: Mains laying; Service pipe installation; Boundary box fitting; Meter installation

Technical Specification (Connection)

Pipework (no excavation):

• Connection to Existing Main of 180mm diameter PE • 3m pipework laying (per communication pipe)

Technical Specification (Mains)

Pipework: Total length 300m, consisting of:

• 125mm diameter PE – 10m road type 3-4 road (leading to the point of connection to an existing water main)

• 125mm diameter PE – 190m • 90mm diameter PE – 100m

Design Considerations:

• 180mm diameter existing main, serving 150 existing customers • Three commissioning phases • Three sample chlorination and connections – footpath • Four washouts - unmade ground

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

18

• Five valves (1 x 150mm, 3 x 100mm, 1 x 80mm) - unmade ground • One trial hole - unmade ground

Traffic management assumes the road (Type 3-4) is 50mph, has two lanes and requires a road closure and eight parking pay suspensions. Any additional council charges for permitting should be included.

Scenario 3: Medium housing development requiring new mains and communication pipe (excavation and reinstatement by others) Alternative Delivery Methods

Applicable Charge? Item Unit Qty Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

NAV Rate (£)

NAV Total Charge (£)

Pre-Construction Charges - connection

Y Application Fee per application

Administration Fee per application

Design Fee per application

Pre-Construction Charges - mains

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges - connection

Y Service connection per connection

Pipework per metre

Y Meter Installation per meter

Construction Charges - mains

Y Mains connection per connection

Mains sub-charge 1

Mains sub-charge 2

Mains sub-charge 3

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

19

Pipework per metre

Traffic management per TM usage

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water per property

Infrastructure Charge - Sewerage per property

Income Offset

Y Income Offset – Water per property

Income Offset – Sewerage per property

TOTALS

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

20

Scenario 4: Medium housing development requiring new mains and communication pipes (excavation and reinstatement by Water Company)

This worked example provided charges associated with the provision of new water mains and individual connections from them for each of 50 new houses. If applicable, the worked example should include the associated charges for the 50 property connections to an existing sewer, which are completed by the Developer Customer. This worked example assumes that the excavation and reinstatement activities are completed by the Water Company. However, should the Developer appoint an SLP or NAV, this worked example assumes these (and other contestable items) would be carried out by the SLP or NAV.

Within construction costs, this includes: Mains laying; Service pipe installation; Boundary box fitting; Meter installation; Excavation; Reinstatement

Technical Specification (Connection)

Pipework (unmade ground):

• Connection to existing main of 180mm diameter PE • 3m pipe laying (per communication pipe)

Technical Specification (Mains)

Pipework: Total length 300m, consisting of:

• 125mm diameter PE – 10m pipework in road (including connection to existing 180mm PE Main)

• 125mm diameter PE – 50m pipework in footpath • 125mm diameter PE – 140m pipework in Unmade ground • 90mm diameter PE – 100m pipework Unmade ground

Design Considerations:

• 180mm diameter existing main, serving 150 existing customers • Three commissioning phases

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

21

• Three sample chlorination and connections - footpath • Four washouts - unmade ground • Five valves (1 x 150mm, 3 x 100mm, 1 x 80mm) - unmade ground • One trial hole - unmade ground

Traffic management assumes the road (Type 3-4) is 50mph, has two lanes and requires a road closure and eight parking pay suspensions. Any additional council charges for permitting should be included.

Scenario 4: Medium housing development requiring new mains and communication pipe (excavation and reinstatement by Water Company) Alternative Delivery Methods

Applicable Charge? Item Unit Qty Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

NAV Rate (£)

NAV Total Charge (£)

Pre-Construction Charges - connection

Y Application Fee per application

Administration Fee per application

Design Fee per application

Pre-Construction Charges - mains

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges - connection

Y Service connection per connection

Pipework - footpath per metre

Y Meter Installation per meter

Construction Charges - mains

Y Mains connection per connection

Mains sub-charge 1

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

22

Mains sub-charge 2

Mains sub-charge 3

Pipework – unmade per metre

Pipework - footpath per metre

Pipework - road per metre

Traffic management per TM usage

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water per property

Infrastructure Charge - Sewerage per property

Income Offset

Y Income Offset – Water per property

Income Offset – Sewerage per property

TOTALS

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

23

Scenario 5: Large housing development requiring new mains and communication pipes (excavation and reinstatement completed by others)

This worked example provided charges associated with the provision of new water mains and individual connections from them for each of 200 new houses. If applicable, the worked example should include the associated charges for the 200 property connections to an existing sewer, which are completed by the Developer Customer. This worked examples assumes excavation and reinstatement activities are completed by others, except for the excavation leading to the point of connection to the existing water main.

Within construction costs, this includes: Mains laying; Service pipe installation; Boundary box fitting; Meter installation

Technical Specification (Connection)

Pipework (no excavation):

• Connection to existing main of 180mm diameter PE • 3m pipe laying (per communication pipe)

Technical Specification (Mains)

Pipework: Total length 1000m, consisting of:

• 180mm diameter PE – 20m pipework in type 3-4 road (leading to point of connection

• 180mm diameter PE – 100m pipework • 125mm diameter PE – 480m pipework • 90mm diameter PE – 400m pipework

Design Considerations:

• 250mm diameter existing main, serving 150 existing customers • Six commissioning phases • Six sample chlorination and connections - footpath • Ten washouts – unmade ground

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

24

• Eight valves (1 x 150mm, 5 x 100mm, 2 x 80mm) - unmade ground • Two trial holes - unmade ground

Traffic management assumes the road (Type 3-4) is 50mph, has two lanes and requires a road closure and eight parking pay suspensions. Any additional council charges for permitting should be included.

Scenario 5: Large housing development requiring new mains and communication pipe (excavation and reinstatement by others) Alternative Delivery Methods

Applicable Charge? Item Unit Qty Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

NAV Rate (£)

NAV Total Charge (£)

Pre-Construction Charges - connection

Y Application Fee per application

Administration Fee per application

Design Fee per application

Pre-Construction Charges - mains

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges - connection

Y Service connection per connection

Pipework per metre

Y Meter Installation per meter

Construction Charges - mains

Y Mains connection per connection

Mains sub-charge 1

Mains sub-charge 2

Mains sub-charge 3

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

25

Pipework per metre

Traffic management per TM usage

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water per property

Infrastructure Charge - Sewerage per property

Income Offset

Y Income Offset – Water per property

Income Offset – Sewerage per property

TOTALS

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

26

Scenario 6: Large housing development requiring new mains and communication pipes (excavation and reinstatement completed by Water Company)

This worked example provided charges associated with the provision of new water mains and individual connections from them for each of 200 new houses. If applicable, the worked example should include the associated charges for the 200 property connections to an existing sewer, which are completed by the Developer Customer. This worked example assumes that the excavation and reinstatement activities are carried out by the Water Company, however, should the Developer appoint an SLP or NAV, this worked example assumes these (and other contestable items) would be carried out by the SLP or NAV.

Within construction costs, this includes: Service pipe installation; Boundary box fitting; Meter installation; Excavation; Reinstatement

Technical Specification (Connection)

Pipework (unmade ground):

• Connection to existing main of 180mm diameter PE • 3m pipe laying (per communication pipe)

Technical Specification (Mains)

Pipework: Total length 1000m, consisting of:

• 180mm diameter PE – 20m pipework in type 3-4 road (leading to point of connection

• 180mm diameter PE – 100m pipework in footpath • 125mm diameter PE – 480m pipework in unmade ground • 90mm diameter PE – 400m pipework in unmade ground

Design Considerations:

• 250mm diameter existing main, serving 150 existing customers • Six commissioning phases • Six sample chlorination and connections - Footpath

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

27

• Ten washouts - Unmade Ground • Eight valves (1 x 150mm, 5 x 100mm, 2 x 80mm) - Unmade Ground • Two trial holes - Unmade Ground

Traffic management assumes the road (Type 3-4) is 50mph, has two lanes and requires a road closure and eight parking pay suspensions. Any additional council charges for permitting should be included.

Scenario 6: Large housing development requiring new mains and communication pipe (excavation and reinstatement by Water Company) Alternative Delivery Methods

Applicable Charge? Item Unit Qty Rate (£)

Total Charge (£)

Barrier Pipe Uplift/Rate

Barrier Pipe Total Charge (£)

Contestable? (Y/N)

Self-Lay Rate (£)

Self-Lay Total Charge (£)

NAV Rate (£)

NAV Total Charge (£)

Pre-Construction Charges - connection

Y Application Fee per application

Administration Fee per application

Design Fee per application

Pre-Construction Charges - mains

Y Application Fee per application

Administration Fee per application

Design Fee per application

Construction Charges - connection

Y Service connection per connection

Pipework - footpath per metre

Y Meter Installation per meter

Construction Charges - mains

Y Mains connection per connection

Mains sub-charge 1

Mains sub-charge 2

Water Services Regulation Authority This document issued under the Charging Rules for New Connection Services (English Undertakers)

Water Industry Act 1991, sections 51CD, 105ZF, 143B and 144ZA

Common Terms and Worked Examples - English New Connection Rules from April 2022

28

Mains sub-charge 3

Pipework – unmade per metre

Pipework - footpath per metre

Pipework - road per metre

Traffic management per TM usage

Other Charges

As applicable (ie S106 vetting fee)

Infrastructure Charges

Y Infrastructure Charge - Water per property

Infrastructure Charge - Sewerage per property

Income Offset

Y Income Offset – Water per property

Income Offset – Sewerage per property

TOTALS

Ofwat (The Water Services Regulation Authority) is a non-ministerial government department. We regulate the water sector in England and Wales.

OfwatCentre City Tower7 Hill StreetBirmingham B5 4UAPhone: 0121 644 7500

© Crown copyright 2021

This publication is licensed under the terms of the Open Government Licence v3.0 except where otherwise stated. To view this licence, visit nationalarchives.gov.uk/doc/ open-government-licence/version/3.

Where we have identified any third party copyright information, you will need to obtain permission from the copyright holders concerned.

This document is also available from our website at www.ofwat.gov.uk.

Any enquiries regarding this publication should be sent to [email protected].