Common Grid Model and Operational Planning Data environment (OPDE)
concepts and development
Jean-Philippe Paul
System Operation European Stakeholder Committee14 March 2017
From SOGL/CACM requirements to implementation by all TSOs and RSCs
Page 2
SOGL (/CACM)
Operational planning activities to
be coordinated
RSCs to provide 5 services based
on CGM
All data shared in a common OP
Data Environment (OPDE)
Common format definition
CGM
Methodology
Data quality controls
CGMA (Alignment of Net
Positions) service
…
Applications
& general
services Merging
function
CGMES 2.4
Reliable &
secure network
Data Exchange & Services Conceptual Picture
Page 3
OPDEstorage: OPDM
Protocols: ECP/EDX
Data Publishing
Data Subscription
TSO
Data Publishing Data Subscription
Data Publishing
Data Subscription
RSC
Individual Grid Model
IGM
1.Subscription to all IGMs
2.Merging process
3. Publishing of CGMATOM
CGMA – QAS
PEVF - Boundary
common
applications
common midware
services
OPDE and ATOM Service Providers
Page 4
ATOM
BACKBONENODE
ATOM BACKBONE
NODE
TSO
TSO
TSO
RSC
ATOM BACKBONE
NODE
ATOM BACKBONE
NODE
NETWORK
APPLI-
CATION
(OPDE)
Shared component
hosting and operation
Shared component
hosting and operation
ECP DirectoryEDX
Catalogue
OPDM Service Provider
CGMA Boundary
ManagementQA
Portal
OPDM Service Provider
RSCRSC
Network operation center
Network security center
Page 4
SUPPLIER Agreements
• Operating OPDE
• Hosting of OPDE shared components
• IT operation of OPDE shared components
• OPDE ASC (Application Network Centre)
• OPDE Service desk
• Operating ATOM
• ATOM NOC (Network Operation Centre)
• ATOM NSC (Network Security Centre)
Contract framework :ENTSO-E – Legal Party in the middle
Users:
TSOs
RSCs
…
Suppliers:
RSCs
TSOs
IT providers
…
ENTSO-ECorporate
Entity
USER Agreements
• Access to OPDE
• Access to ATOM
Page 5
CGM-OPDE Program Phases: current planned milestones
Page 6
11 December 201713 January 2017 11 June 2018
Development
Phase
Develop software,
Services and
the ATOM network
All TSO’s/RSC’s
Implement
CGMES
Set up of the
ATOM/OPDE
design and
contract
Transition
Phase
TSO’s/RSC’s
connect to OPDE/
ATOM
Test processes,
optimize
(individual)
connections/
process
Hybrid merging
(RG CE only)
Stability
Phase
Parallel run of
UCTE + CGMES of
6 months (RGCE only)
CGMES provided for
operational purposes,
fallback to UCTE
format possible
Users of CGMES data
get used to new data
format in operational
processes
Operational
Phase
CGMES used for
pan-European
operational
services
THANK YOU FOR YOUR ATTENTION
Jean-Philippe PaulPG Coordinated Security Analysis Convenor
RTE
System Operation Framework*Implementation Activities
Tahir Kapetanovic
System Operation European Stakeholder Committee14 March 2017
* System Operation Guideline and Network Code Emergency & Restoration
KEY IMPLEMENTATION ACTIVTIES
Page 9
IMPLEMENTATION** SO Guideline only, because ER is Network
Code hence no „implementation“ after its
entering into force
Data exchange, § 40(6)
Y-1 outage planning scenarios, § 65
Operational security analysis method., § 75
Synchronous area agreements, § 118
Min. FCR activation in CE & Nordic, § 156(10-11)
Min. inertia study per SA, § 39(3)(a)
Outage coordination methodology, § 84
Short/medium term adequacy, § 81
Determination of LFC blocks, § 141(2)
YA/DA/ID CGM from IGM, §§ 67(1), 70(1) * A large part of SO GL
implementation –
subject to NRAs
approval – is prepared
through rollout of 5
standard services by
the Regional Security
Coordinators
RSCs*
… RSCs
REPORTING
ICS Report, § 15SO GL NC ER
RSC Report § 17
LFC Report § 16
RSC on TSOs defence & restoration plans, § 6(3)
ENTSO-E on market suspension consistency, § 36
& REPORTING
RSC „WHATABOUTS“
Page 10
#1: „trigger“ in the past
* „Options for the future of power systems regional coordination“, FTI-CR Study, www.entsoe.eu
All TSOs‘
MLA
12/2015
#2: contract
#5: Possible future enhancements of:
operational planning, balancing,
long-term adequacy, network
planning*
CACM SO GL & NC ER
#3: legal framework
#4: five stand. services by RSCs
CORESOTSC
NORDIC RSC
BALTIC RSC
SCC
SEE-T RSC
PRELIMINARY TIMELINE
Page 11
1
20182 3 6 74 5 8 9 10 11 12 1
20192 3 6 74 5 8 9 10 11 12
1st published, for 2019
1st
rp
td
ue ICS Report, § 15SO GL NC ER
RSC Report § 17
LFC Report § 16
RSC on TSOs defence & restoration plans, § 6(3)
ENTSO-E on market suspension consistency, § 3609/2019
09/2019
09/2020
201710 11 128 96 7
LEGEND
SO GL EIF
Public consultation / WS
Stakeholder workshop
Delivery by TSOs/ENTSO-E
Approval by NRAs
no methodology approval, but rollout as 1 of 5 RSC
services
5
Data exchange, § 40(6)
Min. FCR activation in
CE & Nordic, §156(10-11)
Tim
elin
e in
clu
din
g N
RA
ap
pro
va
l
Determ. of LFC blocks, §141(2)
Oper. security analysis method., § 75
Synchronous area agreements, § 118
Min. inertia study per SA, § 39(3)(a)
Outage coordination methodology, § 84
Short/medium term adequacy, § 81
YA/DA/ID CGM, §§ 67(1),70(1)
Y-1 outage planning scenarios, § 65
CBA methodology
Proposal of min. activation period
THANK YOU FOR YOUR ATTENTION
Tahir KapetanovicSO Framework Convenor
ENTSO-E RSC Project Manager
Austrian Power Grid AG