UNIVERSITI TUNKU ABDUL RAHMANFACULTY OF ENGINEERING AND SCIENCEDEPARTMENT OF ARCHITECTURE AND SUSTAINABLE DESIGN
UEBA 2213CONSTRUCTION TECHNOLOGY IIISESSION: 2015/10
TUTORIAL ASSIGNMENT
WRITTEN BY
TAN YING KUAN 13UEB04620
GUIDED BY
MR LEONG HUNG SEK
SUBMITTED ON
06 NOVEMBER 2015
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 2/12
2
INSTRUCTION AND TABLE OF CONTENTS
Instruct ion
From your overall Site Visitation and inspection identify the Construction Technology
process at site. What were the challenges faces by the construction team in ensuring
the building was able to adhere to the construction program set forth? Discuss and
highlight the challenges face with the site from the early inception to the final
completion of the building.
Table of c ontents
Instruction and Table of Contents .............................................................................. 2
Introduction ................................................................................................................ 3
Challenges of Constructions ...................................................................................... 4
Stage 1: Inception and feasibility ............................................................................ 4
Stage 2: Planning and Design ................................................................................ 5
Stage 3: Execution and control ............................................................................... 7
Stage 4: Commissioning and Occupation ............................................................. 10
Conclusion ............................................................................................................... 11
References ............................................................................................................... 12
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 3/12
3
INTRODUCTION
onstruction of a building, from early inception stage until the final completion, isC
typically complex and involving a lot of decision making process. Usually, it takes
years to build a building as there are numerous challenges have to be overcome by
the design team, as well as the contractor. Architect as the person who is leading the
construction project, should be able to handle problems that might affect the
progress of construction, in order to ensure the building is able to adhere to the
schedule set forth. In this report, challenges that are usually being faced by architect
throughout the construction process are discussed, in chronological order, from the
very initial point until the building is certified as habitable.
The process of construction could be classified into 4 significant stages. Different
activities are carried out in each stage, and each activity will involve different
obstacles waiting the construction team to rectify it. The following chart shows the
general process of a construction:
Figure 1: Stages of Construction Project
Delays on a construction project occurs under two situations:
(a) The construction of a project or a part of the project is not completed within
the time period originally intended and as specified in the schedule; or
(b) The scope of the work as contemplated in the contract increases to the extent
that more work is required to be performed within the original contract time.
Usually, delays must be happened throughout the entire project timeline, and
delays under certain conditions are acceptable. However, the occurrences of delay
must be under-controlled and whenever applicable, the coming schedule should be
speeding up in order to complete the work on targeted time.
Inception andfeasibility
Planning anddesign
Execution andcontrol
Commissioningand occupation
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 4/12
4
CHALLENGES OF CONSTRUCTIONS
Stage 1: Inception and feasibi l i ty
In this stage, the objectives of the project are defined followed by production of
project brief. Requirements that related to the project are listed and examined, and
later, to investigate the feasibility of the project. During this stage, activities are
mainly preliminary investigation works that would affect the design of the building -
the site conditions, technical requirements, environmental factors, authority guidance,
rules and regulations are studied. At the end of this stage, a project brief stating all
the requirements and a detailed analysis that supporting the feasibility should be
gained and it must be persuasive enough to get approvals from the authorities.
Problems that probably encountered in this stage are relatively fewer but it would
bring huge impact to the construction progress if there is any problem arisen in this
stage. The followings are some common challenges faced by the team:
1. Land ownership
It is crucial to ensure that the client legally owns the land before any work is
carried out. If there is legal issue having by the owner of the land, typically when
the land ownership transferring is not been done, all the works have to be forced
to stop until the court release the judgement.
2. Conversation related matter
There are certain situation might lead to delay even discontinuation of project,
namely discovery of fossil, artefacts, historical building ruin, etc. The owner of theland is responsible to report to government for further investigation.
Archaeological investigation usually takes years even decades as a lot of
precautions have to be taken lead to slow speed. As a result, the project is not
likely possible to continue. Similarly, if there is existence of historical building at
the adjacent place, special precaution need to be taken and in some cases there
will be restriction applied to the site, this will lead to delay of the project too.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 5/12
5
3. Ground condition matter
Soil test will be carried out during inception stage by land surveyor. If the result of
the test is not satisfied or not meeting the requirements, it needs to be redone
until the feasibility of construction is proven by the soil survey result. The
challenges that normally faced by the team is high density network of
underground water, deep bedrock, huge size of land (require more surveying
works), etc. If the site is on or close to a hill slope, additional survey has to be
conducted to investigate the possible damages that would be happened.
Additionally, in design stage, special measures have to be applied to cope with
the slope. For sure, it lengthens the investigation process.
4. Special requirements requested
For certain cases, the building is design for some special purpose, for instance, a
manufacturing factory of radioactive metal, a zoo which accommodates various
species of animals, a theme park involving large scale of landscaping, a building
targeted to be “green building”, etc. All this situations are requiring specialists
who have particular knowledge on respective sectors. Recruitment of suitable
specialist takes time as for certain field it is difficult to find them locally.
5. Slow or hesitate decision making
In principle, client is the person who makes decision, advised by consultants.
Therefore, when the client has no clear idea on what sort of outcome is aiming to
achieve, it will slow down the progress as the programme cannot be carried out
without a clear instruction. It comes to worse when the client is hesitate about his
decision and keep changing his mind; it will result into reworking on design and
planning.
Stage 2: Planning and Design
t this stage in the project the execution and full implementation of the project brief is A
started. Design consultancies start to come out with design of the building, along
with consistent communication with client, at the mean time produce planning
drawings and submit them to authorities to get approval. Technical design is started
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 6/12
6
to be prepared and once the project is approved, design consultancies will produce
tender documents for tendering. At the end of this stage, it will be the tender process
that selects the most fitting contractor to take the responsible of construct the
building. It could be done in three ways: selective tender, negotiated tender or open
tender.
There is a lot of decision making process involves in this stage. Therefore, it is
most likely to face a lot of problems if there is any interruption happened in the
decision making process. Problems arisen in this stage are usually not costing a lot
of money to resolve but undoubtedly it leads to waste of time. The followings are
some typical problems that might postpone the completion time of a project:
1. Communication between parties
Design team itself is involving architecture consultancy, engineering consultancy
(of different roles), quantity surveying consultancy, land surveyor consultancy, etc.
The design of a building requires high coordination among the members of
design team, therefore, if there is any miscommunication happened, it would
takes time to rectified and redo the work. For instance, structural engineer
misunderstands the architect’s drawing and produce a wrong drawing; quantity
surveyor is not getting the latest drawing and could not estimate the materials
and costs, etc. Similarly, communication between client and consultancies are
crucial at this stage too. Architect must ensure the client’s ideas are completely
understood and mutual agreement on the final design must be established.
2. Approval from authorities
In general, getting project approval from authorities takes longer time. Primarily,
all the planning needs to be approved by municipal or town hall, and there are
numerous requirements have to fulfil. Other than that, approval from some other
departments is required before the construction start, namely fire requirement,
sewerage requirement, drainage requirement, road requirement, etc. In some
cases, changes of requirement will cause the design team has to redesign the
building in order to comply with latest requirement, thereafter it is extremely
crucial to ensure that before the design start, the latest requirements are studied.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 7/12
7
3. Leadership matter
When it comes to the operation of a team, it always associates with management
strategy. Architect or project manager, the leader of the team is requiring
capability to command the team in order to reach the objectives effectively. The
common problem with leadership matter is when the leading person is lacking of
knowledge regarding his/her members’ sectors, the team is very likely to be
losing direction due to the reputation of the leader is not respectable. Meanwhile,
if the leader has limited knowledge on other fields, it is difficult to share common
sense among members, and they will hard to understand each other. As a result,
the bad leadership makes the decision making takes longer time.
4. Problems with tendering
Tendering is the process where most suitable contractor is selected and given
the responsibility to construct the building. If there is no mutual agreement
between client and architect on the criteria of selection, it might be lead to dispute
when client not agree with architect’s decision and for sure, it delays the overall
schedule. If negotiated tendering is applied, it would be time consuming to
negotiate with the contractor to achieved agreement that satisfy both parties.
Stage 3: Execut ion and co ntro l
his stage is where the actual construction being implemented. The contractor isT
given the job to arrange labour to work on the site, and seeking for subcontractors
for certain specialist’s works. During this stage, architect has to keep coordinate with
contractor to ensure that the drawings are interpreted correctly and run within the
schedule; meantime, contractor is required to finish the work stages by stages in line
with the contract and they will get payment stages by stages.
Challenges that might be encountered during this stage is relatively more as
many issue will only surface when the building start to be physically existed instead
of representing using lines and drawing. Also, more parties are now involving in the
construction progress thereafter more communications is needed. The following are
some of the common issues faced during the execution and control process:
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 8/12
8
1. Severe weather condition or natural disaster
When the weather condition is worrying for days, it would slow down the progress
of the construction as works are forced to be pause. It comes to worse when
there is natural disaster occurs at the site, namely flood, mudslide, earthquake,
etc. It not only interrupts the overall progress, but also causes extra works to be
done for repairing or reworking. It is costing time and money, and would be a
major problem to the client.
2. Financial issues
Client should perform obligation of make payment to contractor according to the
contract. If the client refuses to pay, it might lead to recess of construction as the
contractor could not continue the work. It becomes a major problem when the
client is bankrupt and the sudden loss of financial support will set aside the
project. Similarly, if the architect or the contractor is bankrupt, it takes time to
transferring the project to replacement architect or contractor, which causing
wastage of time.
3. Soil condition is not as expected
If the soil survey that conducted is not carefully examined, it will become a major
problem during the construction of foundation. The dissatisfied actual soil
conditions require the design team to move backwards and start over again from
soil surveying, and the design stage has to be redone too.
4. Late information from design team
Contractor is instructed by design team through drawings. By referring to the
drawings, with specifications stated, they will know how to construct the building.
It is crucial for detailing as without detail drawing, the contractor might interpret
the design wrongly. Thus, late production of details from design team might
slower down the construction, as the contractor has to wait the instruction from
design team.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 9/12
9
5. Changes of design
In some circumstance, either the client or architect change their mind and want to
change the design of the building. It will be a big issue if that particular part has
been constructed – it means that it has to be demolished and start over again. It
is not only charge twice to the client, but it also double ups the works that need to
be done, plus the additional work on demolishing what that has built.
6. Accidents on site
Construction site is a dangerous place that full with matter that could cause injury
and death. If they is accident happened on site, particularly involving death of
workers, the site is seems likely to be closed for police ’s investigation. Related
parties need to carry legal liability as well, especially when the accident is
involving unrelated person, a more complex process has to be gone through to
resolve the problem.
7. Poor workmanship or non expertized labour
Contractor is responsible to carry out the construction work carefully and must
reach the expected quality. Poor workmanship will result into failure of structure
especially when the concrete is not pouring correctly, or when the formwork is not
been done correctly. Reworking on fail structure extends the construction process
as well as increase the cost. Similarly, if the labour has no enough experience in
carrying out certain job, the outcome of the work might not achieving targeted
quality; therefore it is crucial to ensure that the workers are qualified for the job.
8. Unavailability of labour, material or equipmentEspecially when there is special requirement apply on the project, there will be a
need for specific labour, material or equipment. Most of the time, it is difficult to
get them as their availability on market are relatively low. For instance, if the
client request for a bare brick wall finishing, skilled labour that experienced on
handling facing brick and flushing is necessary. The idea is applied on material
and equipment too. Difficulties of obtaining resources lengthen the overall
schedule.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 10/12
10
Stage 4: Comm ission ing and Occupat ion
he final stage of the construction indicates the completion of building. Once theT
physical building is completely constructed, there are plenty of certification works
and follow ups need to be done, namely, BOMBA, IWK, JKR, municipal or town hall
need to be invited to investigate the quality of the building, to check whether the
building meets with all listed requirements. After gone through all the investigation,
and until getting the certificate of completion and compliance (CCC), then only the
users accommodate the building.
The challenges that faced by the team at this phase are usually related to
cumbersome paperwork and documentation. Non-effective management would
cause delays to the project.
1. Authorities investigation
It is necessary to get approval from authorities before the occupation. Whenever
there is any unsatisfied part, authorities have the power to order the team to
reconstruct that particular part of the building. Going through this process will
consume longer time if the requirements are not well studied before the
construction.
2. Client extra demands
Client has the right to instruct contractor to make changes on unsatisfied area,
and the contractor will only able to get payment if architect signs the certificate of
completion and certificate of payment to them. Extra demands from client will
cause extra works and ultimately the project could not be finished on schedule.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 11/12
11
CONCLUSION
n conclusion, it is unavoidable to face with various kinds of challenges throughoutI
the entire construction process. The key that all project managers and architects
needs to keep it in mind is, they must be flexible enough to handle all these possible
challenges, to ensure that commitment of time can be achieve as per stated in the
contract. At this level, the ability they need to have, is no longer related to their
knowledge, neither design nor construction technology; but it is all about their
management techniques and strategy, in leading a large scale team, that consists of
members from different sectors.
7/24/2019 Common Challenges Faced Throughout the Construction Timeline
http://slidepdf.com/reader/full/common-challenges-faced-throughout-the-construction-timeline 12/12
12
REFERENCES
CCPM. (2010). Complete Construction Project Management . Retrieved from
http://www.complete-construction-project-management.com/index.php
Chapman, N., Davis, L. C., & Parkman, W. H. (2014, April 30). Resolving problems
and disputes on construction projects: Tackling contract performance delays.
Retrieved from http://www.lorman.com/resources/resolving-problems-and-
disputes-on-construction-projects-tackling-contract-performance-delays-15142
Ip, S. (2012, October 31). An overview of construction claims: How they arise and
how to avoid them. Retrieved from
https://www.cwilson.com/publications/construction/construction-claims.pdf
Muir, B. (2005). Challenges Facing Today’s Construction Manager . Retrieved from
http://www.ce.udel.edu/courses/CIEG%20486/Challenges%20Facing%20Tod
ay's%20CM.pdf
Proverbs, D. G., Holt, G. D., & Cheok, H. Y. (2002). Construction industry problems:
The views of UK construction directors. Retrieved from
http://www.arcom.ac.uk/-docs/proceedings/ar2000-073-
081_Proverbs_Holt_and_Cheok.pdf