commissioning of an office building - rehva · 2014-06-23 · –other feeders like ups, plug...
TRANSCRIPT
![Page 1: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/1.jpg)
Commissioning of an office building
Guruprakash Sastry
Regional Manager – Infrastructure
![Page 2: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/2.jpg)
A typical office building 2
Time
Design phase
Construction phase
Occupancy
![Page 3: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/3.jpg)
The problem
• Commissioning of a building is the most neglected
– No time?
– No interest? (O&M teams are happy if comfort is met)
– No understanding – commissioning for most people is ‘switching on’ equipments.
• Efficiency is a design issue only !
• Commissioning agent – one more vendor?
• HVAC contract split into many vendors for “commercial reasons” – single point
responsibility for the system missing.
3
![Page 4: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/4.jpg)
Examples
Case 1
• VAVs
– VAV supplied by one vendor
– VAV installation by another vendor
– BMS integration by a third vendor
– How to ensure efficiency of the
system?
4
![Page 5: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/5.jpg)
Examples
Case 2
• Chilled beams
– Technical details sometimes missed out
by consultants
– Chamber pressure Vs air flow Vs
nozzle type
– How to ensure efficiency of the
system?
5
![Page 6: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/6.jpg)
HVAC Optimization
Reduce Heat Gain
Energy simulation
Efficient heat
transfer mechanism
Efficient system
Equipment configuration
Efficient equipment
Control strategy
Continuous monitoring
HVAC energy
6
Optimization strategy
![Page 7: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/7.jpg)
Day lighting and Glare control – Glass and shading
Day light pane
View pane
External shading
Smart glazing
7
![Page 8: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/8.jpg)
8
I Innovation-x Impact of day lighting 8
![Page 9: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/9.jpg)
Lighting system design & operation 9
1,2
0,68
0,5 0,45
0
0,2
0,4
0,6
0,8
1
1,2
1,4
Average 2007levels
SDB-5 MYS SDB-1 TVM SDB-1 HYD
W/s
qft
Installed Lighting Power (W/sqft)
0,45
0,17
0
0,2
0,4
0,6
0,8
1
1,2
1,4
Average 2007 levels SDB-1 HYD
W/s
qft
Operating Lighting power (W/sqft)
![Page 10: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/10.jpg)
Design Vs Actual
Efficiencies
Benchmarking
Monitoring of key parameters – over time 10
![Page 11: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/11.jpg)
11
Monitoring of key parameters – over time
16 11 2013
11
![Page 12: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/12.jpg)
12
Monitoring of key parameters – over time
![Page 13: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/13.jpg)
Recommendations
• Get the commissioning team on board at design stage – earlier the better
• Commissioning should be followed by continuous monitoring
• Energy meters for every major equipment
– HVAC system – chillers, pumps, fans
– Lighting feeder
– Other feeders like UPS, plug loads, misc.
• Continuous monitoring of key parameters (hourly) Vs design.
– kW/TR of HVAC system
– Operating LPD of lighting
– EPI of the building (kWh/sqm per year) to be monitored against design/simulation
– Acceptable deviation to be defined
13
![Page 14: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/14.jpg)
Building energy performance 14
An
nu
al
kW
h/s
qm
2008
![Page 15: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR](https://reader033.vdocuments.us/reader033/viewer/2022043002/5f7fffd76bd9b212f805124f/html5/thumbnails/15.jpg)
© 2013 Infosys Limited, Bangalore, India. All Rights Reserved. Infosys believes the information in this document is accurate as of its publication date; such information is subject to change without notice. Infosys acknowledges the proprietary rights of other companies to the trademarks, product names and such other intellectual property rights mentioned in this document. Except as expressly permitted, neither this documentation nor any part of it may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, printing, photocopying, recording or otherwise, without the prior permission of Infosys Limited and/ or any named intellectual property rights holders under this document.
Thank You