Commissioning Field Report Educational Service District 112 Form A-9 DAVENPORT K-8 SCHOOL Date: May 7, 2012 Site: Davenport K-8 School, Davenport School District Weather: Sunny, mid 60s Activities: HVAC Functional Testing A team of Russ Chambers and Rick Alexander visited Davenport Elementary School on May 7, 2012 to perform Functional Performance Testing and other Commissioning activities in preparation for project close out. Summary: This visit was scheduled to perform functional testing of HVAC equipment and do commissioning room surveys and review the resolution of controls issues previously identified during Phase I commissioning testing. The school was not ready for the scheduled activities. The control system programming was not complete, some HVAC equipment was not operational with startup activities taking place and room finishes were not complete in 50% of the

Upload: others

Post on 14-Jan-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

DAVENPORT K-8 SCHOOL

Date: May 7, 2012 Site: Davenport K-8 School, Davenport School District

Weather: Sunny, mid 60s Activities: HVAC Functional Testing A team of Russ Chambers and Rick Alexander visited Davenport Elementary School on May 7, 2012 to perform Functional Performance Testing and other Commissioning activities in preparation for project close out. Summary: This visit was scheduled to perform functional testing of HVAC equipment and do commissioning room surveys and review the resolution of controls issues previously identified during Phase I commissioning testing. The school was not ready for the scheduled activities. The control system programming was not complete, some HVAC equipment was not operational with startup activities taking place and room finishes were not complete in 50% of the

Page 2: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Phase II area. A partial survey was performed and deficiencies are noted in the following report(s). This is not a final or complete issues list. The deficiencies listed are examples of areas of concern and review by the Commissioning Agents. The next scheduled visit for functional testing and room surveys is for the week of July 9, 2012. The expectation of the Commissioning Team is that all work will be finished, the controls issues will have been resolved with all systems tested by installation contractors and previous Commissioning Issues Log will have been reviewed and all items corrected by contractors or accepted by district. Observed Deficiencies:

Construction cleanup not complete

Page 3: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

AC-1 has not been started up

Circuit breakers need to be labeled

Page 4: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Panel schedules need to be complete

Roof debris needs to be cleaned up. The amount of debris left on the membrane roof is a significant risk of punctures and leaks and not acceptable. The entire roof area needs to be surveyed and free of debris.

Page 5: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Construction adhesive both sides bottom cubby East of Room 118

Page 6: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Filter access for HP-33 blocked HP-33 Disconnect Switch not labeled

CU-2 condenser unit hat secured to curb

Sprinkler head in basement blocked by piping

Page 7: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Seal strips missing in Admin Entry storefront windows

Page 8: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Additional comments: Commissioning Issues Log will be used to track identified deficiencies through the end of the project and is attached at the end of this document. Each item must have a response before being closed. Please refer to the instruction sheet at the end of the issues log. Please feel free to contact me with questions or requests for clarification. Commissioning Agent will visit Davenport for further testing and room surveys on July 9, 2012. Back checks will be done on above issues presented as corrected.

________________________________

Russ Chambers, CEM, CEA, CBCP, LEED AP Retro-Commissioning & Energy Manager

ESD 112 2500 NE 65th Avenue - Vancouver WA 98661-6812 P 360.750.7500 x157 F 360.750.9706

Page 9: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

DAVENPORT K-8 SCHOOL

Date: June 28, 2012 Site: Davenport K-8 School, Davenport School District

Weather: Clear, mid 60s Activities: HVAC Functional Testing and Commissioning Back Checks Commissioning Team Russ Chambers and Rick Alexander visited Davenport Elementary School on June 27 & 28 to perform Functional Testing and Room Surveys in preparation of project close out. Summary: Phase II HVAC equipment was tested to assure functionality per project specification and sequence of operations. Issues identified in Phase I testing were back checked and room and exterior surveys were performed. The testing went well with few issues observed. At this time all mechanical equipment and controls are functional. There is an air flow with one heat recovery unit. The mechanical contractor is in the process of submitting an RFI to determine resolution. Issues found which were not resolved while the Commissioning Agents were on site are listed below and have been added to the Commissioning Issues Log.

Page 10: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Specific Observations and Comments: • Stage lighting – light #2 does not work (2nd light from East end) • Two damaged ceiling tile in entry commons

• Room 206 – Bad fluorescent light outside row South end • Library 205 – Bad fluorescent light in row above Southeast door • Room 113 – Fluorescent light above window has very dirty diffuser lens • Room 111- Fluorescent light North row 3rd from West has 1 lamp out • Room 109 – Bad fluorescent light South row 2nd from West end • Heat Pump Loop Pump #2 is very noisy. Sounds like a bad motor bearing on

the inboard end • Heat Pump Loop discharge side pressure gauges need to be changed out for

100psi gauges. Project documents call for 60psi gauges and that is what was installed, however they are running “pegged” beyond the 60psi mark. For accurate measurement the gauges should be changed.

Page 11: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Area 1 roof flashing at the “pop up” needs to be checked out for proper installation. The ridge cap is installed over the flashing and the flashing corners are not fully caulked. It is the Commissioning Agents opinion that the flashing is to be installed over the roofing.

Page 12: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Additional cleanup needs to be done around HP-32

• Electrical box on HP-32 needs a cover

Page 13: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Conduit under cooling tower needs to have straps installed

• Joint in trim above main entry outside does not appear to be caulked

Page 14: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Need to check for caulk exterior top Commons storefront windows.

The Commissioning Agent will schedule a trip for back check when he has been notified that all the issues on the accompanying Commissioning Issues Log have been resolved. Additional comments: Commissioning Issues Log will be used to track identified deficiencies through the end of the project and is attached at the end of this document. Each item must have a response before being closed. Please refer to the instruction sheet at the end of the issues log. Please feel free to contact me with questions or requests for clarification.

________________________________

Russ Chambers, CEM, CEA, CBCP, LEED AP Retro-Commissioning & Energy Manager

ESD 112 2500 NE 65th Avenue - Vancouver WA 98661-6812 P 360.750.7500 x157 F 360.750.9706

Page 15: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

DAVENPORT K-8 SCHOOL

Date: July 7, 2012 Site: Davenport K-8 School, Davenport School District

Weather: Clear, mid 90s Activities: Commissioning Back Checks Commissioning Agent Russ Chambers visited Davenport Elementary School on July 7 to perform Commissioning Issues Log backchecks preparation of project close out. Summary: Most outstanding Commissioning issues have been corrected. Two new issues were identified and described in the body of this report. Issues found which were not resolved while the Commissioning Agent was on site are listed below and have been added to the Commissioning Issues Log.

Page 16: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

Specific Observations and Comments: Issues Log:

• Item 21 – Science Room floor Drain - This issue has been on the log since August 2011. I would expect there will be no change to floor contour. Need disposition per issues log instruction page.

• Items 26-29 – Basketball hoop height - Minor issues, installation contractor has been notified and is working the time for adjustment into schedule.

• Item 57 – Stage Lights – The #2 light is not working. At re-test the remote panel would not work and main controller had an error. Should be checked by knowledgeable person. May have been operator error.

• Item 64 - #2 Heat Pump Loop Pump – the pump motor has been worked on since the June 27 issues log, however it is still has excessive vibration and the pimp bearing is running hot. If this issue is not correctly resolved it will cause premature pump failure. It needs to be properly investigated and resolved.

Page 17: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Item 73 – Roofing nail protruding from roof – new item see pictures below

General Location

Closer

Nail

Page 18: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

• Item 74 – Asphalt Repairs – Repaired areas are poor quality and do not match surrounding area. Area around drain will cause water pooling, area by door will allow water penetration and eventual cracking and breakouts.

Patched area higher than surrounding

open saw cuts at corners

Area rough, patched area not properly prepared

Page 19: Commissioning Field Report DAVENPORT K-8 SCHOOL

Commissioning

Field Report

Educational Service District 112 Form A-9

The Commissioning Agent will schedule a trip for back check when he has been notified that all the issues on the accompanying Commissioning Issues Log have been resolved. Additional comments: Commissioning Issues Log will be used to track identified deficiencies through the end of the project and is attached at the end of this document. Each item must have a response before being closed. Please refer to the instruction sheet at the end of the issues log. Please feel free to contact me with questions or requests for clarification.

________________________________

Russ Chambers, CEM, CEA, CBCP, LEED AP Retro-Commissioning & Energy Manager

ESD 112 2500 NE 65th Avenue - Vancouver WA 98661-6812 P 360.750.7500 x157 F 360.750.9706