commissioning check list ru40

Upload: bdtptit

Post on 01-Jun-2018

265 views

Category:

Documents


8 download

TRANSCRIPT

  • 8/9/2019 Commissioning Check List RU40

    1/40

     

    DN0939536Issue 04A

    © Nokia Siemens Networks 1 (40) 

    WCDMA RAN, Rel. RU40, OperatingDocumentation

    Commissioning Checklist for IPA-

    RNC

    DN0939536Issue 04A

    Approval date 2013-04-26

  • 8/9/2019 Commissioning Check List RU40

    2/40

    Commissioning Checklist for IPA-RNC

    2 (40) © Nokia Siemens Networks DN0939536Issue 04A

    The information in this document is subject to change without notice and describes only theproduct defined in the introduction of this documentation. This documentation is intended forthe use of Nokia Siemens Networks customers only for the purposes of the agreement underwhich the document is submitted, and no part of it may be used, reproduced, modified or

    transmitted in any form or means without the prior written permission of Nokia SiemensNetworks. The documentation has been prepared to be used by professional and properlytrained personnel, and the customer assumes full responsibility when using it. Nokia SiemensNetworks welcomes customer comments as part of the process of continuous developmentand improvement of the documentation.

    The information or statements given in this documentation concerning the suitability, capacity,or performance of the mentioned hardware or software products are given “as is” and allliability arising in connection with such hardware or software products shall be definedconclusively and finally in a separate agreement between Nokia Siemens Networks and thecustomer. However, Nokia Siemens Networks has made all reasonable efforts to ensure thatthe instructions contained in the document are adequate and free of material errors andomissions. Nokia Siemens Networks will, if deemed necessary by Nokia Siemens Networks,explain issues which may not be covered by the document.

    Nokia Siemens Networks will correct errors in this documentation as soon as possible. IN NOEVENT WILL NOKIA SIEMENS NETWORKS BE LIABLE FOR ERRORS IN THISDOCUMENTATION OR FOR ANY DAMAGES, INCLUDING BUT NOT LIMITED TOSPECIAL, DIRECT, INDIRECT, INCIDENTAL OR CONSEQUENTIAL OR ANY LOSSES,SUCH AS BUT NOT LIMITED TO LOSS OF PROFIT, REVENUE, BUSINESSINTERRUPTION, BUSINESS OPPORTUNITY OR DATA,THAT MAY ARISE FROM THEUSE OF THIS DOCUMENT OR THE INFORMATION IN IT.

    This documentation and the product it describes are considered protected by copyrights andother intellectual property rights according to the applicable laws.

    The wave logo is a trademark of Nokia Siemens Networks Oy. Nokia is a registered trademarkof Nokia Corporation. Siemens is a registered trademark of Siemens AG.

    Other product names mentioned in this document may be trademarks of their respectiveowners, and they are mentioned for identification purposes only.

    Copyright © Nokia Siemens Networks 2013. All rights reserved.

  • 8/9/2019 Commissioning Check List RU40

    3/40

  • 8/9/2019 Commissioning Check List RU40

    4/40

    Commissioning Checklist for IPA-RNC

    4 (40) © Nokia Siemens Networks DN0939536Issue 04A

    11.2 

    Performing SW update ......................................................................... 38 

    11.3  Safecopying SW build again ................................................................ 38 11.4  Recording item code and serial number ............................................... 38 

    12  Commissioning certificate of completion ........................................ 39 

  • 8/9/2019 Commissioning Check List RU40

    5/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 5 (40) 

    Summary of changes

    Changes between issues 04 (RU40, 2013-02-22) and 04A (2013-04-26, RU40)

    Interrogating SW build information (6.3)

    •  Table 16 Boot-SW versions checklist is updated to all supportedplug-in units in RN7.0.

    Verifying hardware data consistency with actual configuration (6.5)

    •  The section title is changed from “Interrogating hardware data”.

    Checking the memory size of the CCP1D-A plug-in unit (6.6)•  This is a new section.

    Changes between issues 03B (2012-10-24, RU30) and 04 (2013-02-22, RU40)

    Document structure and contents have been changed in accordancewith the document Commissioning  IPA-RNC, issue 17.

    Changes between issues 03A and 03B

    The cover page and references have been updated.

  • 8/9/2019 Commissioning Check List RU40

    6/40

    Commissioning Checklist for IPA-RNC

    6 (40) © Nokia Siemens Networks DN0939536Issue 04A

    1 Commissioning checklist Note

    The hardware product names in the checklists are written without thevariant designation unless it is specifically required.

    1.1 Using this checklist document

    Use this checklist document for recording the success and completion ofcommissioning procedures. Always carry out the procedures asinstructed in the document Commissioning IPA-RNC  and mark down thecompleted steps and procedures in this document.

    The checklist tables contain references to other product documentswhich may be necessary during each particular procedure. Also, keepthe Commissioning IPA-RNC  document available at all times.

    The last section of this document, Commissioning Certificate ofCompletion, can be used for acceptance.

    1.2 Preparation of commissioning

    Commissioning phase / related documents Completed

    Check the Installation Certificate of Completionand Site Deficiency Reports. Clear out correctionrequirements for commissioning.

    Check the availability of the tools andmeasurement devices that you need forcommissioning. Acquire the needed tools andmeasurement devices.

    Commissioning IPA-RNC

  • 8/9/2019 Commissioning Check List RU40

    7/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 7 (40) 

    Commissioning phase / related documents Completed

    Check the availability of the site documents

    delivered online. Acquire the missing sitedocuments.

    Hardware Configuration Management in IPA-RNC

    Cable Lists for RNC196

    Cable Lists for RNC450

    Cable Lists for RNC2600

    Equipment Lists for RNC196

    Equipment Lists for RNC450

    Equipment Lists for RNC2600

    MGW and IPA-RNC, Jumper Settings of the Plug-in Units and Hard Disk Drives

    Software Release Binder

    Installing the MGW and IPA-RNC

    Hardware Revision List  for WCDMA IPA-RNC

    Managing IPA-RNC Software Configuration

     ATM Links and LAN Connections in RNC196

     ATM Links and LAN Connections in RNC450

     ATM Links and LAN Connections in RNC2600

    Managing I/O System in IPA-RNC

    Diagnostics and Testing in IPA-RNC

     Administering Recovery and Unit Working States

    in IPA-RNC

    Synchronization and Timing in IPA-RNC

    Database Administration in IPA-RNC

    Change Note installation instruction (deliveredwith each Change Note Set)

    IPA-RNC Engineering Description 

    Table 1. Preparation of commissioning

  • 8/9/2019 Commissioning Check List RU40

    8/40

    Commissioning Checklist for IPA-RNC

    8 (40) © Nokia Siemens Networks DN0939536Issue 04A

    2 Safecopying FBEMPTY SW build Commissioning phase / related documents Completed

    Make a fallback copy of the SW build and verify it.Make FB build backup copies on OMU hard disksand/or USB stick

    Table 2. Safecopying SW build

  • 8/9/2019 Commissioning Check List RU40

    9/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 9 (40) 

    3 Inspecting hardware Commissioning phase / related documents Completed

    Inspect the door grounding.Check the inter-cabinet cables of the networkelement by comparing them with the cable lists insite documentation. Check all connectors forproper contact (for example, no plugs are loose).

    Hardware Configuration Management in IPA-RNC

    Cable Lists for RNC196

    Cable Lists for RNC450

    Cable Lists for RNC2600

    Check the locations of the plug-in units bycomparing them with equipment lists in sitedocumentation.

    Hardware Configuration Management in IPA-RNC

    Equipment Lists for RNC196

    Equipment Lists for RNC450

    Equipment Lists for RNC2600

    Check the interchangeability versions of the sub-

    racks by comparing them with the equipment listsin site documentation.

    Hardware Configuration Management in IPA-RNC

    Equipment Lists for RNC196

    Equipment Lists for RNC450

    Equipment Lists for RNC2600

    Hardware Revision List  for WCDMA IPA-RNC

  • 8/9/2019 Commissioning Check List RU40

    10/40

    Commissioning Checklist for IPA-RNC

    10 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Check the interchangeability versions of the plug-

    in units by comparing them with the equipmentlists in site documentation.

    Hardware Configuration Management in IPA-RNC

    Equipment Lists for RNC196

    Equipment Lists for RNC450

    Equipment Lists for RNC2600

    Hardware Revision List  for WCDMA IPA-RNC

    Inspect the power supply:

    Measure the input voltages to the Cabinet PowerDistributors (CDP80). The voltages must bewithin the range of -40 V ... -57 V DC.

    Record all the values in the table Measuredvoltages below. Check that the voltages meet thetolerance requirements.

    Check the polarities of the supply lines asinstructed in Installing the MGW and RNC .

    Installing the MGW and IPA-RNC

    Inspect the hardware material visually. Payattention to mechanical damage and scratches,for example.

    Inspect accordance with approved site drawings.

    Table 3. Inspecting hardware

    Cabinet Voltage (V) Polarity checked

    RNAC (UB1)

    RNAC (UB2)RNBC (UB1)

    RNBC (UB2)

    Table 4. Measured voltages

  • 8/9/2019 Commissioning Check List RU40

    11/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 11 (40) 

    4 Verifying system startup 

    4.1 Powering onCommissioning phase / related documents Completed

    Power on the cabinet(s).

    Check that the LEDs on each unit are eitherblinking green, solid green, or yellow.

    Table 5. Powering on

    4.2 Logging into the MMI system for the first time

    Commissioning phase / related documents Completed

     Attach a computer by RJ-45 to the OMU serialport. Log into the MMI system by using the default

    administrator user ID and password SYSTEM. 

    Create a new MMI user profile (ZIAA).

    Create a new administrator user ID (ZIAH).

    Delete the default administrator user ID

    (SYSTEM)(ZIAD).

    Table 6. Logging into the MMI system for the first time

    The preset IP addresses are changed during integration.

  • 8/9/2019 Commissioning Check List RU40

    12/40

    Commissioning Checklist for IPA-RNC

    12 (40) © Nokia Siemens Networks DN0939536Issue 04A

    4.3 Verifying functional units’ start-up

    Commissioning phase / related documents Completed

    Check that all units have the correct workingstates and that there are no major alarms 

    Table 7. Verifying functional units’ start-up

  • 8/9/2019 Commissioning Check List RU40

    13/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 13 (40) 

    5 Managing network element specificdata 

    5.1 Changing system name

    Commissioning phase / related documents Completed

    Change the system name and then verify the newname from the NECONF file.

    Table 8. Changing system name

    5.2 Setting the calendar date and time

    Commissioning phase / related documents Completed

    Set the correct date and time (and optionally time

    zone) for the network element (ZDCS). 

    Set the correct NTP server IP address (ZDCM).

    NTP IP address:

    Table 9. Setting the calendar date and time

  • 8/9/2019 Commissioning Check List RU40

    14/40

    Commissioning Checklist for IPA-RNC

    14 (40) © Nokia Siemens Networks DN0939536Issue 04A

    5.3 Enabling CPLD upgrade

    Commissioning phase / related documents Completed

    Check the status of the CPLD remote upgrade. Ifit is disabled, enable it. 

    Table 10. Enabling CPLD upgrade

  • 8/9/2019 Commissioning Check List RU40

    15/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 15 (40) 

    6 Inspecting SW build and HW data 

    6.1 Creating Telnet or HTTP connection to OMUCommissioning phase / related documents Completed

    Establish a Telnet or HTTP connection to theOMU IP address, port 11111.

    Check that the logical files that are used inprinting out alarms are connected to the correct

    VPP devices (ZIID).

    If not, connect the corresponding logical files to

    the correct VPP devices (ZIIS).

    Record the devices in table Logical files and VPPdevice connections.

    Check that the state of the corresponding VPP

    devices is WO-EX (ZIHI).

    Check that you can see alarms on the Telnetterminal or the web browser.

    Table 11. Creating a Telnet or HTTP connection to OMU

    Logical file VPP device Logical file VPP device

     ALARMS ALACOMM2

     ALACOMM1 ALAQUAL2

     ALAQUAL1 ALAPROC2

     ALAPROC1 ALAEQUI2

     ALAEQUI1 ALAENVI2

  • 8/9/2019 Commissioning Check List RU40

    16/40

    Commissioning Checklist for IPA-RNC

    16 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Logical file VPP device Logical file VPP device

     ALAENVI1

    Table 12. Logical files and VPP device connections

    6.2 Inspecting Hardware Management System

    Commissioning phase / related documents Completed

     Activate the HMEXTE service terminal extension

    (ZLP:2,HME).

    List the system configuration (Z2DP). Check that

    the information on the location of the plug-in unitsis correct.

    Make sure that each plug-in unit has a respectiveHMS slave node.

    Check that the version number of the HMSsoftware is the same for each plug-in unit thatbelongs to the same node type (master node, Avariant master node, bridge node, slave node, Avariant slave node).

    1. Block the following alarms: 1183, 1186,1291, 2689, 3287, and 3290.

    2. Ensure that all HMS slave nodes havethe same level of software version.

    3. Disable HMS independent switchover.

    4. Check the active HMS transmission line.

    5. Interrogate the software version of theHMS bridge nodes.

    6. Perform a switchover of the HMStransmission line and check that the

    transmission line switchover issuccessful.

    7. Interrogate the software version of theHMS bridge nodes.

    8. Enable HMS independent switchover andcheck that the status of HMSindependent switchover is ENABLED.

    9. Interrogate the software version of theHMS master nodes.

  • 8/9/2019 Commissioning Check List RU40

    17/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 17 (40) 

    Commissioning phase / related documents Completed

    10. Unblock the alarms you blocked in step 1.

    Record version numbers to the table HMSsoftware versions.

    Check that the version matches the requirementfor software level. 

    Software Release Binder

    Table 13. Inspecting Hardware Management System

    HMS node type All corresponding unitschecked

    Version number

    HMS master node

    HMS A variant masters

    HMS bridges

    HMS slaves

    HMS A variant slaves

    Table 14. HMS software versions

    6.3 Interrogating SW build information

    Commissioning phase / related documents Completed

    Verify that the correct software build is on thehard disk and loaded for every unit needed

    (ZWQO).

    Managing IPA-RNC Software ConfigurationSoftware Release Binder

    Default software package:

    Package-ID:

    Change Note ID:

  • 8/9/2019 Commissioning Check List RU40

    18/40

    Commissioning Checklist for IPA-RNC

    18 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Check the software build versions (ZWQB) to find

    any erroneous modules.Managing IPA-RNC Software Configuration

    Compare the versions with the site-specificdocuments.

    Software Configuration Management

    Software Release Binder

    Check the version of the flash memory bootpackage of the unit against the SW package. Seethe table Boot-SW versions checklist .

    Table 15. Interrogating SW build information

    Plug-in unit SW version Plug-in unit SW version

    CCP10 CCP18*

    CCP1D-A CDSP-DH

    MX1G6* MX622*

    NI16P1A NI4S1-B

    NP2GE-B NP8S1-B

    SF10 SF10E

    SF20H* refers to the plug-in unit itself or/and its variants

    Table 16. Boot-SW versions checklist

  • 8/9/2019 Commissioning Check List RU40

    19/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 19 (40) 

    6.4 Interrogating equipment database

    Commissioning phase / related documents Completed

    Check the state and integrity of the equipmentdatabase and copy database files to disk.

    Hardware Configuration Management in IPA-RNC

    Inquire cabinet information (ZWFI:J:..). Check

    that the cabinet information in the databasemeets the physical configuration. Correct any

    discrepancies (ZWFJ, ZWFK).

    Hardware Configuration Management in IPA-RNC

    Inquire sub-rack information (ZWFI:C:..). Check

    that the sub-rack information in the databasemeets the physical configuration. Correct any

    discrepancies (ZWFC, ZWFD).

    Hardware Configuration Management in IPA-RNC

    Inquire plug-in unit information (ZWFI:P:..).Check that the plug-in unit information in thedatabase meets the physical configuration.

    Correct any discrepancies (ZWFP, ZWFQ).

    Hardware Configuration Management in IPA-RNC

    Inquire connection information on plug-in unit

    ports (ZWFI:S:..). Check that the plug-in unit

    port connections in the database meet thephysical configuration. Correct any discrepancies

    (ZWFS, ZWFT).

    Hardware Configuration Management in IPA-RNC

     ATM Links and LAN Connections in RNC196

     ATM Links and LAN Connections in RNC450

     ATM Links and LAN Connections in RNC2600  

    Inquire functional unit information (ZWFI:U:..).

    Check that the functional unit information in thedatabase meets the physical configuration.

  • 8/9/2019 Commissioning Check List RU40

    20/40

    Commissioning Checklist for IPA-RNC

    20 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Correct any discrepancies (ZWFU, ZWFV).

    Hardware Configuration Management in IPA-RNC

    Table 17. Interrogating equipment database

    6.5 Verifying hardware data consistency with actualconfiguration

    Commissioning phase / related documents Completed

    Interrogate all hardware data of plug-in units

    (ZWFL). Verify that the printed data are the same

    as on the labels of the plug-in units.

    Interrogate all hardware data of subracks (ZWFL).

    Verify that the printed data are the same as onthe subrack labels.

    Table 18. Verifying hardware data consistency with actual configuration

    6.6 Checking the memory size of the CCP1D-A plug-in unit

    Commissioning phase/Related documents Completed

    Check the memory pool size of the CCP1D-A

    plug-in unit (ZDOI). Ensure that the displayed

    memory pool size of the CCP1D-A unit is biggerthan 3000 MB.

    Table 19. Checking the memory size of the CCP1D-A plug-in unit

  • 8/9/2019 Commissioning Check List RU40

    21/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 21 (40) 

    6.7 Inspecting I/O system

    Commissioning phase / related documents Completed

    Display the I/O devices (ZWFI). Check their

    operating states and state transitions (ZIHI).

    Managing I/O System in IPA-RNC

    Diagnose hard disks (ZUDD).

    •  OMU (WDU-0)

    •  OMU (WDU-1)

    Managing I/O System in IPA-RNC

    Optional:

    1. Change the operating state of an opticaldisk or a USB memory stick to TE-EX

    and diagnose it (ZUDD).

    2. Display a list of running and queuing tests

    (ZUDQ).

    3. Display the history of the diagnostic

    reports (ZUDH).

    Managing I/O System in IPA-RNC

    Table 20. Inspecting I/O system

    6.8 Inspecting unit diagnostics and working states

    Commissioning phase / related documents Completed

    Print out the working states of the units (ZUSI).

    Check that the units are in the WO-EX or SP-EXstate. Check that all units of the network elementare on the list (compare with the equipment list).

    Equipment Lists for RNC196

    Equipment Lists for RNC450

    Equipment Lists for RNC2600

    Diagnostics and Testing in IPA-RNC

    Run unit diagnostics and perform change of unitstates.

  • 8/9/2019 Commissioning Check List RU40

    22/40

    Commissioning Checklist for IPA-RNC

    22 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Note

    There are differinginstructions for 2N redundantunits, N+1 redundant units,SN+ units and non-redundantunits in Commissioning IPA-RNC .

    First run diagnostics on SFUs, then continue withMXUs. Then perform diagnostics for all otherunits.

    Note

    The TBU units (connected to

    OMU 0/1) and all unitsconnected to SFU and MXUunits must be tested twice:First when the state of theOMU 0 / SFU 0 / MXU x isWO-EX, then when the stateof the OMU 1 / SFU 1 / MXU1 is WO-EX. MXU x is theMXU connected to the unit tobe tested.

    Diagnostics and Testing in IPA-RNC

    Note

    In some cases, one sub-rack slot may house different functional unitsdepending on the configuration of the network element. For detailed informationon the equipping of sub-racks in different configurations, see IPA-RNCEngineering Description, Equipment Lists for RNC196, Equipment Lists forRNC450, and Equipment Lists for RNC2600 . 

    Table 21. Inspecting unit diagnostics and working states

    Functional unit OMU 0 (WO-EX) OMU 1 (WO-EX)

    TBU 0

    TBU 1

    Table 22. TBU 0 and TBU 1 units

  • 8/9/2019 Commissioning Check List RU40

    23/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 23 (40) 

    Functional unit MXU 0 (WO-EX) MXU 1 (WO-EX)

    SFU 0

    SFU 1

    Table 23. SFU 0 and SFU 1 units RNAC

    Functional unit SFU 0 (WO-EX) SFU 1 (WO-EX)

    MXU 0

    MXU 1

    MXU 2

    MXU 3

    MXU 4

    MXU 5

    MXU 6

    MXU 7

    MXU 8

    MXU 9

    MXU 10

    MXU 11

    MXU 12

    MXU 13

    MXU 14

    MXU 15

    Table 24. MXU units in RNAC and RNBC

    Functional unit MXU 0 (WO-EX) MXU 1 (WO-EX)

    DMCU 0

    DMCU 1

    DMCU 2

    DMCU 3

    ICSU 0

    OMU 0

  • 8/9/2019 Commissioning Check List RU40

    24/40

    Commissioning Checklist for IPA-RNC

    24 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Functional unit MXU 0 (WO-EX) MXU 1 (WO-EX)

    RSMU 0

    SFU 0

    TBU 0

    TBU 1

    SWU 0

    OMS

    Table 25. Functional units in sub-rack 1 (RNAC)

    Functional unit MXU 2 (WO-EX) MXU 3 (WO-EX)

    DMCU 4

    DMCU 5

    DMCU 6

    DMCU 7

    ICSU 1

    ICSU 2

    OMU 1

    RSMU 1

    SFU 1

    TBU 0

    TBU 1

    Table 26. Functional units in sub-rack 2 (RNAC)

    Functional unit MXU 4 (WO-EX) MXU 5 (WO-EX)

    DMCU 8

    DMCU 9

    DMCU 10

    DMCU 11

    DMCU 12

    EHU

    ICSU 3

  • 8/9/2019 Commissioning Check List RU40

    25/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 25 (40) 

    Functional unit MXU 4 (WO-EX) MXU 5 (WO-EX)

    ICSU 4

    ICSU 5

    ICSU 6

    ICSU 7

    TBU 0

    TBU 1

    Table 27. Functional units in sub-rack 3 (RNAC)

    Functional unit MXU 6 (WO-EX) MXU 7 (WO-EX)

    DMCU 13

    DMCU 14

    DMCU 15

    DMCU 16

    DMCU 17

    ICSU 8

    ICSU 9

    ICSU 10

    ICSU 11

    ICSU 12

    ICSU 13

    TBU 0

    TBU 1

    Table 28. Functional units in sub-rack 4 (RNAC)

    Functional unit MXU 8 (WO-EX) MXU 9 (WO-EX)

    DMCU 18

    DMCU 19

    DMCU 20

    DMCU 21

    DMCU 22

  • 8/9/2019 Commissioning Check List RU40

    26/40

    Commissioning Checklist for IPA-RNC

    26 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Functional unit MXU 8 (WO-EX) MXU 9 (WO-EX)

    ICSU 14

    ICSU 15

    ICSU 16

    ICSU 17

    ICSU 18

    ICSU 19

    TBU 0

    TBU 1

    Table 29. Functional units in sub-rack 1 (RNBC)

    Functional unit MXU 10 (WO-EX) MXU 11 (WO-EX)

    DMCU 23

    DMCU 24

    DMCU 25

    DMCU 26

    DMCU 27

    ICSU 20

    ICSU 21

    ICSU 22

    ICSU 23

    ICSU 24

    ICSU 25

    TBU 0

    TBU 1

    Table 30. Functional units in sub-rack 2 (RNBC)

    Functional unit MXU 12 (WO-EX) MXU 13 (WO-EX)

    DMCU 28

    DMCU 29

    DMCU 30

  • 8/9/2019 Commissioning Check List RU40

    27/40

  • 8/9/2019 Commissioning Check List RU40

    28/40

    Commissioning Checklist for IPA-RNC

    28 (40) © Nokia Siemens Networks DN0939536Issue 04A

    6.9 Inspecting messaging system

    Commissioning phase / related documents Completed

    Print out the working states of units (ZUSI).

    Check that all units are on the list (compare withthe equipment list).

    Run messaging system test. In detail, do thefollowing:

    •  Open a service terminal connectionRS232 to the active OMU or, if notpossible, open a new MMI terminal

    session (ZDDS).

    Note

    The service terminalconnection or the secondMMI terminal connection isused for executing andmonitoring the test. The firstMMI terminal session is usedfor changing the states of theactive SFU and MXU unitsduring the test.

    •  Load a post office service terminalextension in the active OMU

    (ZLP:1,POH).

    •  List all computing units in the messaging

    system (Z1F:::1).

    •  Start messaging system test (Z1YY).

    Monitor the output for a minimum of 5minutes.

    •  Print the working state SFU unit (ZUSI).

    •  Print the working states of all MXU units

    (ZUSI). Record the index numbers of the

    active units in the table Checklist 1 for

    active MXU units. Mark the status of theactive MXUs for the active SFU in thetable Checklist 1 for active MXU units.

    •  Change the state of the working stateSFU unit to SP-EX, (WO-EX -> SP-EX),

    (ZUSC). Monitor the output for a minimum

    of 5 minutes.

    •  Print the working states of all MXU units

    (ZUSI). Record the index numbers of the

  • 8/9/2019 Commissioning Check List RU40

    29/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 29 (40) 

    Commissioning phase / related documents Completed

    active units in table Checklist 2 for activeMXU units. Compare with Checklist 1 for

    active MXU units that the index numberof each MXU is now different within eachMXU pair. Mark the status of the activeMXU units in the table Checklist 2 foractive MXU units for the active SFU.

    •  Change the states of working state SFUunits to SP-EX (WO-EX -> SP-EX),

    (ZUSC). Monitor the output for a minimum

    of 5 minutes. Record the status of theactive MXU units in the table Checklist 2for active MXU units for the new activeSFU unit.

    •  Stop the test (CTRL + C) and monitor theoutput. 

    Table 33. Inspecting messaging system

    MXU index SFU 0

    WO-EX

    SFU 1

    WO-EX

    MXU

    MXU

    MXU

    MXU

    MXU

    MXU

    MXU

    MXU

    Table 34. Checklist 1 for active MXU units

    MXU index SFU 0

    WO-EX

    SFU 1

    WO-EX

    MXU

    MXU

    MXU

  • 8/9/2019 Commissioning Check List RU40

    30/40

    Commissioning Checklist for IPA-RNC

    30 (40) © Nokia Siemens Networks DN0939536Issue 04A

    MXU index SFU 0

    WO-EX

    SFU 1

    WO-EX

    MXU

    MXU

    MXU

    MXU

    MXU

    Table 35. Checklist 2 for active MXU units

  • 8/9/2019 Commissioning Check List RU40

    31/40

  • 8/9/2019 Commissioning Check List RU40

    32/40

    Commissioning Checklist for IPA-RNC

    32 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Use ZDYR if you need to control general

    synchronization system settings.Synchronization and Timing in IPA-RNC

    Check outgoing references (ZDYP). If outgoing

    synchronization is not given, set it with the

    command ZDYE.

    Synchronization and Timing in IPA-RNC

    Check system clock operating modes, andchange them if needed.

    Synchronization and Timing in IPA-RNC

    Table 36. Inspecting synchronization system

  • 8/9/2019 Commissioning Check List RU40

    33/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 33 (40) 

    8 Configuring VDS device Commissioning phase / related documents Completed

    Define the size and number, and the overwrite,skipping, and compression mode of disk files

    (ZIFF).

    Managing I/O System in IPA-RNC

    Connect the desired logical file to the VDS device

    (ZIID, ZIIS).

    Managing I/O System in IPA-RNC

    Set alarm limits for the file group (ZIFA).

    Set time control for closing the data file of the

    VDS device (ZIFT).

    Managing I/O System in IPA-RNC

    Back up the VDS device.

    Managing I/O System in IPA-RNC

    Table 37. Configuring the VDS device

  • 8/9/2019 Commissioning Check List RU40

    34/40

    Commissioning Checklist for IPA-RNC

    34 (40) © Nokia Siemens Networks DN0939536Issue 04A

    9 Connecting RNC to standalone RNCOMS 

    Commissioning phase / related documents Completed

    Set up the RUOSTEQX service terminalextension.

    Set the OMS southbound IP address for the RNCO&M connection, and check that the connection

    works (ZQRS). 

    If BTS O&M connection is not established, restartBOI (506) and BOR (A0F) processes

    Table 38. Connecting RNC to standalone RNC OMS

  • 8/9/2019 Commissioning Check List RU40

    35/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 35 (40) 

    10 Verifying OMS system startup 

    10.1 Verifying OMS BIOS system timeCommissioning phase/ Related documents Completed

    Check the time (#date) and change it if needed. 

    Table 39. Verifying OMS BIOS system time

    10.2 Testing TCP/IP connections for OMSCommissioning phase/ Related documents Completed

    Ping all IP addresses as specified in Commissioning IPA-RNC.

    Table 40. Testing TCP/IP connections for OMS

    10.3 Testing OMS software startup

    Commissioning phase / related documents Completed

    Log into OMS and check that all the services tostart.

  • 8/9/2019 Commissioning Check List RU40

    36/40

    Commissioning Checklist for IPA-RNC

    36 (40) © Nokia Siemens Networks DN0939536Issue 04A

    Commissioning phase / related documents Completed

    Check that the status returns no disabled

    processes.

    Table 41. Testing OMS software startup

    10.4 Testing Element Manager applications

    Commissioning phase / related documents Completed

    Install the Application Launcher (EM client).

    Start the Application Launcher and log into theElement Manager.

    Start and close each Element Managerapplication.

    Check OMS Syslog (master-syslog) for errormessages.

    Table 42. Testing Element Manager applications

    10.5 Testing secure Element Manager MMI window

    Commissioning phase / related documents Completed

    Start the Application Launcher and log into theElement Manager. 

    Open the MMI window by double-clicking theicon. Give MML commands to test the MMIwindow application.

    Make a switchover to the OMU.

    Give MML commands to test the MMI windowapplication.

    Log out from the Application Launcher.

    Check OMS Syslog for error messages.

    Table 43. Testing Element Manager's MMI window

  • 8/9/2019 Commissioning Check List RU40

    37/40

  • 8/9/2019 Commissioning Check List RU40

    38/40

    Commissioning Checklist for IPA-RNC

    38 (40) © Nokia Siemens Networks DN0939536Issue 04A

    11.2 Performing SW update

    Commissioning phase / related documents Completed

    If the pre-installed package is not compatible withthe network CD level, update the SW. 

    Table 45. Performing SW update

    11.3 Safecopying SW build again

    Commissioning phase / related documents Completed

    Make a fallback copy of the SW build and verify it.

    Make FB build backup copies on OMU hard disksand/or USB stick

    Table 46. Safecopying SW build

    11.4 Recording item code and serial number

    Table 47. Recording item code and serial number

    Commissioning phase / related documents Completed

    Record the item codes and serial numbers of thenetwork element.

  • 8/9/2019 Commissioning Check List RU40

    39/40

    Commissioning Checklist for IPA-RNC

    DN0939536Issue 04A

    © Nokia Siemens Networks 39 (40) 

    12 Commissioning certificate ofcompletion CUSTOMER NAME

    CONTRACT NO.

    NETWORK ELEMENT TYPE

    DELIVERY NO.

    SITE NAME

    SITE NO.

    SITE ADDRESS

    SOFTWARE RELEASE

    SOFTWARE VERSION / BUILD

    CHANGE NOTES / CN SETS

    COMMISSIONING STAGE COMPLETE / OK (initials)

    Preparation of commissioning

    Safecopying FBEMPTY SW build

    Inspecting hardware

    Verifying system startup

    Managing network element specific data

    Inspecting SW build and HW data

    Inspecting synchronization system

    Configuring VDS device

    Connecting RNC to standalone RNC OMS

    Verifying OMS system startup

    Finalizing commissioning

    COMMENTS / DEFICIENCIES

    Nokia Siemens Networks hereby states that the whole of the supplies detailed above have been inspected, tested and, unlessotherwise stated, conform to the specified requirements in the contract or order identified above.

    Date: _______________________________________________________________________________________________

    Signature of site responsible: ____________________________________________________________________________

  • 8/9/2019 Commissioning Check List RU40

    40/40

    Commissioning Checklist for IPA-RNC