commissioning and envelope leakage: using hvac operating ... · • vav double duct air handling...

44
PORTLAND ENERGY CONSERVATION, INC. Commissioning and Envelope Leakage: Using HVAC Operating Strategies to Meet Design and Construction Challenges Hannah Friedman, Tudi Haasl, Larry Luskay, Emily Moore, and David Sellers Portland Energy Conservation Inc.

Upload: others

Post on 18-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

PORTLAND ENERGY CONSERVATION, INC.

Commissioning and Envelope Leakage:Using HVAC Operating Strategies to Meet Design and Construction Challenges Hannah Friedman, Tudi Haasl, Larry Luskay, Emily Moore, and David Sellers Portland Energy Conservation Inc.

Page 2: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

26/14/2018© 2004 PECI; Do not reproduce with out permission

The Building Envelope …

… Making a Statement about the Building

and its Owner

• Aesthetics and visual appeal are key drivers

• Origins in the early phases of design

Page 3: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

36/14/2018© 2004 PECI; Do not reproduce with out permission

The Building Envelope …

• Resist energy transfer• Resist mass transfer

– Water– Air

• Allow occupant access

… An Essential Component of the Building Environmental Control System

These functions evolve later in the design process

Page 4: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

46/14/2018© 2004 PECI; Do not reproduce with out permission

Envelope Details …

• Thermal implications • Humidity implications• Pressure implications

…Impact HVAC Performance

Page 5: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

56/14/2018© 2004 PECI; Do not reproduce with out permission

It Takes A Lot of Detail ….

… to Assemble a Building Envelope

Shop drawing sets that define the curtain wall and window system for a 400 foot tall high-rise

Page 6: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

66/14/2018© 2004 PECI; Do not reproduce with out permission

The Contract Documents for the Same Project

Perhaps a clue about why there may be a few problems and where they are going to occur?

The Architectural Contract Documents

The Mechanical Contract Documents

Page 7: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

76/14/2018© 2004 PECI; Do not reproduce with out permission

Envelope Design Realities

• Multiple panels = Multiple joints• Different materials = Different physical characteristics• Different characteristics = Joint movement• Building movement = Joint movement• Entrances and exits = Envelope breaches• Building height = Stack effect

Page 8: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

86/14/2018© 2004 PECI; Do not reproduce with out permission

Envelope Fabrication Realities

• Construction timeline = Seasonal variations• Different materials = Multiple trade specialties• Architectural features = Hidden joints and construction• Plenums = Heightened performance requirements

from standard construction techniques• Special products = Special handling• Special products = Special installation processes in a

less than optimal environment

Page 9: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

96/14/2018© 2004 PECI; Do not reproduce with out permission

Detection By Inspection is Increasingly Difficult as Construction Progresses

Elevation makes assessment

from the exterior difficult

Page 10: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

106/14/2018© 2004 PECI; Do not reproduce with out permission

Detection By Inspection is Increasingly Difficult as Construction Progresses

Finishes make assessment from the interior virtually impossible

Page 11: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

116/14/2018© 2004 PECI; Do not reproduce with out permission

Sump Sump SumpSump

Sump

Complex Geometry Compounds the Problem

Atriums interconnect

floors

Page 12: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

126/14/2018© 2004 PECI; Do not reproduce with out permission

Sump Sump SumpSump

Sump

Multiple shafts create multiple

chimneys

Complex Geometry Compounds the Problem

Page 13: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

136/14/2018© 2004 PECI; Do not reproduce with out permission

Sump Sump SumpSump

Sump

Common mechanical room/relief

plenum interconnects

shafts and systems

Complex Geometry Compounds the Problem

Page 14: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

146/14/2018© 2004 PECI; Do not reproduce with out permission

Sump Sump SumpSump

Sump

Complex Geometry Compounds the Problem

Common return plenums and shafts mix air streams and interconnect

systems

Page 15: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

156/14/2018© 2004 PECI; Do not reproduce with out permission

Design and Fabrication Realities Lead to Operating Realities

• A weather tight building is not air tight• Uncontrolled, unanticipated air leakage leads to:

– Comfort problems– Energy waste– Catastrophic events

• Indoor air quality failures• Piping failures• Damage to finishes

Page 16: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

166/14/2018© 2004 PECI; Do not reproduce with out permission

• Energy crisis driven costs result in lobby air curtain shut down– Stack effect results in:

• Elevator shafts = Chimney

• Lobby = Hearth

A 1960’s Vintage Mid-West High Rise Experience circa 1978

Page 17: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

176/14/2018© 2004 PECI; Do not reproduce with out permission

• Energy crisis driven costs result in evening and weekend HVAC shutdown− Stack effect results in:

• Humid air infiltration

• Perimeter induction unit drain pan overflow

A 1960’s Vintage Mid-West High Rise Experience circa 1978

Page 18: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

186/14/2018© 2004 PECI; Do not reproduce with out permission

• Energy crisis driven costs result in lobby air curtain shut down– Stack effect results in:

• Elevator shafts = Chimney

• Lobby = Hearth

• Energy crisis driven costs result in evening and weekend HVAC shutdown− Stack effect results in:

• Humid air infiltration

• Perimeter induction unit drain pan overflow

A 1960’s Vintage Mid-West High Rise Experience circa 1978

Solutions:

− Live with the cold lobby and whistling

− In hot and humid weather:

• Run the chiller plant around the clock

• Keep one core air handling system running in full recirculation

Page 19: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

196/14/2018© 2004 PECI; Do not reproduce with out permission

• Complex building geometry makes envelope closure assessment difficult during construction– First cold snap results in:

• 55°F office space• Irate tenant• Questioning of

Engineer’s competence

A 1980’s Vintage Mid-West High Rise Experience circa 1988

(among other things)

Page 20: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

206/14/2018© 2004 PECI; Do not reproduce with out permission

A 1980’s Vintage Mid-West High Rise Experience circa 1988

• Field inspection by the Engineer:− Identifies a 4 foot by 40

foot hole to the exterior above the ceiling in the affected area

− Provides vindication

Page 21: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

216/14/2018© 2004 PECI; Do not reproduce with out permission

A 1980’s Vintage Mid-West High Rise Experience circa 1988

Solution:

− Fix the hole

− Buy the Engineer a beer

Page 22: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

226/14/2018© 2004 PECI; Do not reproduce with out permission

• Critical clean room pressurization requirement results in the following design:– Two parallel, 100% redundant fans:

• Only one fan runs normally• Provides 27,000 cfm at 3.5 inches w.c.

A 1990’s High Tech Experience circa 1998

Page 23: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

236/14/2018© 2004 PECI; Do not reproduce with out permission

A 1990’s High Tech Experience circa 1998

• Clean room leakage resulted in running both fans to achieve pressurization required− 14,000 extra cfm of outside air to move and

condition− Static requirement increased to 7 in.w.c.

Duct pressure class was 4 in.w.c.!!

Page 24: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

246/14/2018© 2004 PECI; Do not reproduce with out permission

A 1990’s High Tech Experience circa 1998

Solution:

− Run scared!

− Find and fix the leaks as time and money permit

• Repair work in an active clean room is difficult and expensive

• Looking for hundreds to thousands of small leaks not one large leak

Page 25: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

256/14/2018© 2004 PECI; Do not reproduce with out permission

Two 1990’s Health Care Experiences circa 1995

• Two Hospital renovations involving new entry lobbies– Reception staff and visitor

seating located near the entry

– Large, complex buildings constructed over a number of years

– Pressurization issues tended to make entry areas negative

Page 26: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

266/14/2018© 2004 PECI; Do not reproduce with out permission

Two 1990’s Health Care Experiences circa 1995

• Lobby HVAC designed to meet the challenges– Vestibules– Independent air handling system– Floor to desk top enclosure of reception work area– Occupant controlled radiant heat under the

reception desktop

Page 27: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

276/14/2018© 2004 PECI; Do not reproduce with out permission

Two 1990’s Health Care Experiences circa 1995

Project 1 included the features in the base bid– Design goals met after commissioning– Well trained motivated staff ensures that the design intent

persists

Page 28: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

286/14/2018© 2004 PECI; Do not reproduce with out permission

Two 1990’s Health Care Experiences circa 1995

• Project 2 VE’d the features out due to budget issues– Site work problems ate a big chunk of contingency– Provisions made to add the features if operating

experience indicated they were desirable– Operating experience indicated they were desirable– Implementing the features made vast improvements

in lobby comfort

Page 29: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

296/14/2018© 2004 PECI; Do not reproduce with out permission

HVAC Modifications May Or May Not Be Able To Mitigate Air Leakage Problems …

Assess air leakage:– Magnitude– Location– Significance relative to other openings

• Entrances• Loading docks• Relief systems

… Understanding the problem is the key first step to developing a solution

Page 30: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

306/14/2018© 2004 PECI; Do not reproduce with out permission

• Procedures and Data Available– Standard Test Method For Determining Air

Leakage Rate By Fan Pressurization• ASTM Standard E 779 (ASTM 1992)• Rigorous

Assessing Air Leakage

Page 31: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

316/14/2018© 2004 PECI; Do not reproduce with out permission

Assessing Air Leakage

– Myths About Building Envelopes• March 1999 ASHRAE Journal • Documents DOE study results using ASTM E

779

• Procedures and Data Available

Page 32: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

326/14/2018© 2004 PECI; Do not reproduce with out permission

Assessing Air Leakage

– A Test Procedure for Assessing Envelope Leakage in Commercial Buildings: The Issues, the Process and the Results• NCBC 2004 (download at www.PECI.org)• Overview of other procedures and data• Abbreviated procedure based on ASTM E 799

discussed and included as an appendix

• Procedures and Data Available

Page 33: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

336/14/2018© 2004 PECI; Do not reproduce with out permission

• VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity

• Structural steel frame with curtain wall system

Measuring Leakage in a 1990’s Vintage High Rise circa 2003/2004

Nominal 450,000 square foot, 350 foot tall high rise federal court house

Projected leakage rate range from DOE study - 41,597 to 1,918,061 cfm @ 0.10 in.w.c.

Page 34: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

346/14/2018© 2004 PECI; Do not reproduce with out permission

Measuring Leakage in a 1990’s Vintage High Rise circa 2003/2004

Building Pressure Test Results

02468

1012141618

-0.1 -0.05 0 0.05 0.1 0.15

Building Pressure Relative to Outdoors; in.w.c.

Floo

r

Normal Operation, 58F sunny

Fans OFF

60% speed, pressurizing

70%, speed pressurizing

Nominal 450,000 square foot, 350 foot tall high rise federal court house

Projected leakage rate range from DOE study - 41,597 to 1,918,061 cfm @ 0.10 in.w.c.

Page 35: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

356/14/2018© 2004 PECI; Do not reproduce with out permission

Measuring Leakage in a 1990’s Vintage High Rise circa 2003/2004

Nominal 450,000 square foot, 350 foot tall high rise federal court house

Projected leakage rate range from DOE study - 41,597 to 1,918,061 cfm @ 0.10 in.w.c.

148,000 – 255,000 cfm of outdoor air− No relief− No return− No doors openNo positive pressure at the lobby level!

Page 36: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

366/14/2018© 2004 PECI; Do not reproduce with out permission

• Opportunity to save fan energy by not running return fans

• Opportunity to shift an exfiltration load to an infiltration load− Infiltration must be handled by perimeter system

as a heating load− Exfiltration handled by internal gains during

economizer operation• Potential to save $14,600 for a $5,000

implementation cost

Making Lemonade

Page 37: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

376/14/2018© 2004 PECI; Do not reproduce with out permission

Building Pressure Test, 2/2/04 43F outside air

0

2

4

6

8

10

12

14

16

18

-0.1 -0.05 0 0.05 0.1 0.15

Building Pressure Relative to Outdoors; in.w.c.

Floo

r As-found

AHU 1&2 return fans OFF, 100% OSA

AHU 1&2 relief dampers closed, 100% OSA

AHU 3&4 return fans OFF, 100% OSA

AHU 3&4 relief dampers closed, 100% OSA

Making Lemonade

Page 38: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

386/14/2018© 2004 PECI; Do not reproduce with out permission

• 27,000 square foot training facility and resource center

• Nominal 27,000 cfm VAV/reheat air handling system

• Poured concrete structure and wall system with windows and doors placed in cast-in-place openings

• Relief controlled to maintain the lobby at a positive pressure

Building Pressurization Test Results

-0.05

0

0.05

0.1

0.15

0.2

0.25

0.3

16:15 16:25 16:35 16:45 16:55 17:05 17:15 17:25 17:35 17:45

Time

Diffe

rent

ial P

ress

ure

to

Oudo

ors,

in.w

.c.

-10,000

-5,000

0

5,000

10,000

15,000

20,000

25,000

Flow

rate

, cfm

Roof pressure to outdoors 2nd floor pressure to outdoors Lobby pBasment pressure to outdoors Flow rate from face velocity

Measuring Leakage in a 1950’s Vintage Low Rise circa 2003/2004

Page 39: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

396/14/2018© 2004 PECI; Do not reproduce with out permission

The PEC Pressure GradientPressure to Outside in Different Modes

0

5

10

15

20

25

30

35

40

-0.050 0.000 0.050 0.100 0.150 0.200

Pressure difference, in.w.c.

Elev

atio

n, ft

.

Roof

2nd floor line

1st floor line

As found (estimated flow)

Air handling shut downcompleteFirst test point

Second test point

Final test point

Page 40: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

406/14/2018© 2004 PECI; Do not reproduce with out permission

The PEC Pressure GradientGood News!

− The building leakage rate is about 75% of what might be anticipated from data in the literature

− Anticipated range at .10 in.w.c. – 2,300 to 26,000 cfm− Measured leakage at .11 in.w.c. – 19,000− 12,000 – 18,000 cfm of air required to pressurize the lobby for

normal operation− The system spends a lot of time on economizer at 12,000 –

18,000 cfm− Relief damper control based on building static pressure looks

like a good approach

Page 41: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

416/14/2018© 2004 PECI; Do not reproduce with out permission

Conclusions

• Buildings are generally not air tight• Commissioning efforts can mitigate the effect with the

HVAC systems in some cases• In some cases, the leakage can overwhelm any

practical HVAC mitigation– Target and repair the leaks as a first step– Provide additional HVAC based mitigation if

necessary as a final step

Page 42: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

426/14/2018© 2004 PECI; Do not reproduce with out permission

Key Design Points to Consider

• Consider decoupling the temperature control and building pressure control functions associated with the economizer

• Provide vestibules on lobbies • Provide supplemental heat and draft protection at

workstations located in the lobby• Provide an independent HVAC system for the lobby

in high-rise and complex buildings

Page 43: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

436/14/2018© 2004 PECI; Do not reproduce with out permission

• Assume buildings will leak– Research and develop design and operating

strategies to allow HVAC systems to cope– Target leakage during commissioning

• Design phase• Construction observation phase• Start up and testing phase• Ongoing commissioning • Retro commissioning

Recommendations

Page 44: Commissioning and Envelope Leakage: Using HVAC Operating ... · • VAV Double Duct Air Handling systems, nominal 450,000 cfm total capacity • Structural steel frame with curtain

446/14/2018© 2004 PECI; Do not reproduce with out permission

Recommendations

Support the effort with ongoing research regarding:

− Existing building leakage performance

− Leakage mitigation techniques

− Improved construction techniques