commercial construction project plan
TRANSCRIPT
-
8/19/2019 Commercial Construction Project Plan
1/60
ID Task
Mode
Task Name Duration Start Finish
0Commercial
Construction
344 days Thu
16 03 17
Tue
17 07 11
1General Conditions17 days Thu 16 03 17Fri 16 04 08
2 Receive notice
to proceed and
sign contract
3 days Thu
16-03-17
Mon
16-03-21
3 Submit bond
and insurance
documents
2 days Tue
16-03-22
Wed
16-03-23
4 Prepare and
submit project
schedule
2 days Thu
16-03-24
Fri 16-03-25
5 Prepare and
submit schedule
of values
2 days Mon
16-03-28
Tue
16-03-29
6 Obtain buildingpermits
4 days Tue16-03-22
Fri 16-03-25
7 Submit
preliminary shop
drawings
2 wks Mon
16-03-28
Fri 16-04-08
8 Submit monthly
requests for
payment
1 day Tue
16-03-22
Tue
16-03-22
9Long Lead
Procurement
70 days Wed
16 03 23
Tue
16 06 28
G.C. General Management
G.C. Project Management,G.C. General Management[
G.C. Project Management[25%],G.C. Scheduler
G.C. General Management[10%],G.C. Project Manag
G.C. Project Management[50%],G.C. Procurement[50
G.C. Project Management[50%],G.C. Procurement
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
2/60
ID Task
Mode
Task Name Duration Start Finish
10 Submit shop
drawings and
order long lead
items - steel
2 wks Wed
16-03-23
Tue
16-04-05
11 Submit shop
drawings and
order long lead
items - roofing
2 wks Mon
16-04-11
Fri 16-04-22
12 Submit shop
drawings and
order long lead
items - elevator
2 wks Mon
16-04-11
Fri 16-04-22
13 Submit shop
drawings and
order long lead
items - plumbing
2 wks Mon
16-04-11
Fri 16-04-22
14 Submit shop
drawings and
order long lead
items - electric
2 wks Mon
16-04-11
Fri 16-04-22
15 Submit shop
drawings and
order long lead
items - HVAC
2 wks Mon
16-04-11
Fri 16-04-22
Steel Erection Contractor Management
Roofing Contractor Management
Elevator Contractor Management
Plumbing Contractor Management
Electric Contractor Management
HVAC Contractor Management
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 A
ug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
3/60
ID Task
Mode
Task Name Duration Start Finish
16 Detail, fabricate
and deliver steel
12 wks Wed
16-04-06
Tue
16-06-28
17Mobilize on Site 10 days Tue 16 03 22Mon 16 04 04
18 Install
temporary
power
2 days Tue
16-03-22
Wed
16-03-23
19 Install
temporary
water service
2 days Tue
16-03-22
Wed
16-03-23
20 Set up site office 3 days Thu 16-03-24Mon 16-03-2
21 Set line and
grade
benchmarks
3 days Tue
16-03-29
Thu
16-03-31
22 Prepare site - lay
down yard and
temporaryfencing
2 days Fri 16-04-01 Mon
16-04-04
23Site Grading and
Utilities
35 days Tue
16 04 05
Mon
16 05 23
24 Clear and grub
site
3 days Tue
16-04-05
Thu
16-04-07
25 Stone site access
and temporary
parking area
2 days Fri 16-04-08 Mon
16-04-11
26 Rough grade site
(cut and fill)
1 wk Tue
16-04-12
Mon
16-04-18
Steel Erection Contractor Man
Electric Contractor
Plumbing Contractor
G.C. Superintendent,G.C. Labor Crew[10%]
G.C. Survey Crew
Site Grading Contractor,G.C. Labor Crew[10%]
Site Grading Contractor
Site Grading Contractor
Site Grading Contractor
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 A
ug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
4/60
ID Task
Mode
Task Name Duration Start Finish
27 Install storm
drainage
2 wks Tue
16-04-19
Mon
16-05-02
28 Install exterior
fire line and
building fire
riser
2 wks Tue
16-04-19
Mon
16-05-02
29 Perform final
site grading
2 wks Tue
16-05-03
Mon
16-05-16
30 Erect building
batter boards
and layout
building
1 wk Tue
16-05-17
Mon
16-05-23
31Foundations 33 days Tue 16 05 24Thu 16 07 07
32 Excavate
foundations
2 wks Tue
16-05-24
Mon
16-06-06
33 Excavateelevator pit
2 days Tue16-05-24
Wed16-05-25
34 Form column
piers and spread
foundations
4 days Tue
16-06-07
Fri 16-06-10
35 Rough-in electric
and plumbing in
elevator
4 days Thu
16-05-26
Tue
16-05-31
36 Form elevator
pit walls
4 days Wed
16-06-01
Mon
16-06-06
Site Grading Contractor
Plumbing Contractor
Site Grading Contractor
G.C. Survey Crew
Site Grading Contractor[50%]
Site Grading Contractor
G.C. Rough Carpenter Crew
Plumbing Contractor,Electric Contra
G.C. Rough Carpenter Crew
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
5/60
ID Task
Mode
Task Name Duration Start Finish
37 Set reinforcing
and anchor bolts
4 days Mon
16-06-13
Thu
16-06-16
38 Pour column
piers and
foundations
5 days Fri 16-06-17 Thu
16-06-23
39 Pour concrete
elevator walls
1 day Tue
16-06-07
Tue
16-06-07
40 Cure elevator
wall concrete
7 days Wed
16-06-08
Thu
16-06-16
41 Cure piers and
foundations
7 days Fri 16-06-24 Mon
16-07-04
42 Strip wall forms 1 day Fri 16-06-17 Fri 16-06-17
43 Strip column
piers and
foundation
forms
3 days Tue
16-07-05
Thu
16-07-07
44 Install
pneumatic tube
in elevator pit
3 days Mon
16-06-20
Wed
16-06-22
45 Prepare and
pour concrete
floor in elevator
pit
1 day Thu
16-06-23
Thu
16-06-23
46Steel Erection 45 days Fri 16 07 08 Thu 16 09 08
G.C. Rough Carpenter Crew
G.C. Concrete Crew
G.C. Concrete Crew
G.C. Labor Crew[10%]
G.C. Labor Crew[10%]
G.C. Labor Crew[10%]
G.C. Labor Crew
Elevator Contractor
G.C. Concrete Crew
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
6/60
ID Task
Mode
Task Name Duration Start Finish
47 Erect steel
columns, beams
and joist - 1st
and 2nd floors
2 wks Fri 16-07-08 Thu
16-07-21
48 Erect steel
columns, beams
and joist - 3rdfloor and roof
2 wks Fri 16-07-22 Thu
16-08-04
49 Install
miscellaneous
iron and bracing
- 1st and 2nd
floors
2 wks Fri 16-07-22 Thu
16-08-04
50 Install
miscellaneous
iron and bracing
- 3rd floor and
roof
2 wks Fri 16-08-05 Thu
16-08-18
51 Install stairs and
miscellaneous
iron railing
2 wks Fri 16-08-19 Thu
16-09-01
52 Touch-up paint
on steel
1 wk Fri 16-09-02 Thu
16-09-08
53Form and Pour
Concrete Floors
and Roof
85 days Fri 16 07 22 Thu
16 11 17
Steel Erection Contracto
Steel Erection Contra
Steel Erection Contra
Steel Erection Co
Steel Erection
Steel Erectio
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
7/60
ID Task
Mode
Task Name Duration Start Finish
54 Form 2nd floor
including all
floor openings
5 days Fri 16-09-09 Thu
16-09-15
55 Install rebar and
in-floor utilities
(including
mechanical,electrical,
plumbing)
5 days Fri 16-07-22 Thu
16-07-28
56 Pour 2nd floor
slab
4 days Fri 16-09-16 Wed
16-09-21
57 Cure 2nd floor
slab
7 days Thu
16-09-22
Fri 16-09-30
58 Strip forms from
2nd floor slab
2 days Mon
16-10-03
Tue
16-10-04
59 Form 3rd floor
including all
floor openings
5 days Mon
16-10-03
Fri 16-10-07
60 Install rebar and
in-floor utilities
(including
mechanical,
electrical,
plumbing)
5 days Mon
16-10-03
Fri 16-10-07
61 Pour 3rd floor
slab
4 days Mon
16-10-10
Thu
16-10-13
G.C. Roug
G.C. Labor Crew[33%],
G.C. Con
G.C. La
G.C. L
G.C.
G.C.
G.C
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
8/60
ID Task
Mode
Task Name Duration Start Finish
62 Cure 3rd floor
slab
7 days Fri 16-10-14 Mon
16-10-24
63 Strip forms from
3rd floor slab
2 days Tue
16-10-25
Wed
16-10-26
64 Form roof slab
including all
floor openings
5 days Tue
16-10-25
Mon
16-10-31
65 Install rebar and
in-floor utilities
(including
mechanical,
electrical,
plumbing)
5 days Tue
16-10-25
Mon
16-10-31
66 Pour roof slab 4 days Tue 16-11-01Fri 16-11-04
67 Cure roof slab 7 days Mon 16-11-0 Tue 16-11-15
68 Strip forms fromroof slab
2 days Wed16-11-16
Thu16-11-17
69 Form 1st floor 4 days Wed 16-10-0 Mon 16-10-1
70 Install electrical
underground
1 wk Wed
16-10-05
Tue
16-10-11
71 Install plumbing
underground
1 wk Wed
16-10-05
Tue
16-10-11
72 Install rebar and
in-floor utilities
4 days Wed
16-10-05
Mon
16-10-10
73 Pour 1st floor
slab
4 days Wed
16-10-12
Mon
16-10-17
G.C.
Elec
Plu
G.C.
G.
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
9/60
ID Task
Mode
Task Name Duration Start Finish
74 Cure 1st floor
slab
7 days Tue
16-10-18
Wed
16-10-26
75 Strip forms from
1st floor slab
2 days Thu
16-10-27
Fri 16-10-28
76Carpentry Work 15 days Fri 16 11 18 Thu 16 12 08
77 Install exterior
sheathing and
metal studs
3 wks Fri 16-11-18 Thu
16-12-08
78Masonry Work 110 days Fri 16 08 19 Thu 17 01 19
79 Rough-in
plumbing at
toilets and
masonry walls
4 wks Mon
16-10-31
Fri 16-11-25
80 Lay masonry at
core,
mechanical, andtoilets
4 wks Fri 16-08-19 Thu
16-09-15
81 Install exterior
masonry work
5 wks Fri 16-12-09 Thu
17-01-12
82 Install roof
drains
2 days Fri 17-01-13 Mon
17-01-16
83 Install tile in
toilet rooms
2 wks Mon
16-11-28
Fri 16-12-09
84 Clean masonry 1 wk Fri 17-01-13 Thu 17-01-19
85 Clean toilet
room tile
1 wk Mon
16-12-12
Fri 16-12-16
Masonry C
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
10/60
-
8/19/2019 Commercial Construction Project Plan
11/60
ID Task
Mode
Task Name Duration Start Finish
97Building Finishes 80 days Fri 17 02 17 Thu 17 06 08
98 Install millwork
and wood trim
3 wks Fri 17-03-24 Thu
17-04-13
99 Paint walls and
woodwork
4 wks Fri 17-04-14 Thu
17-05-11
100 Install conduit at
ceiling plenum
space
3 wks Fri 17-02-17 Thu
17-03-09
101 Install duct in
ceiling plenum
space
3 wks Fri 17-03-24 Thu
17-04-13
102 Install ceiling
grid
2 wks Fri 17-04-14 Thu
17-04-27
103 Install ceiling tile 2 wks Fri 17-04-28 Thu
17-05-11
104Hang wallpaper 2 wks Fri 17-04-28 Thu 17-05-11
105 Install building
carpet
4 wks Fri 17-05-12 Thu
17-06-08
106 Install hardware
and accessories
3 wks Fri 17-05-12 Thu
17-06-01
107 Complete
interior and
exterior sod and
plantings
2 wks Fri 17-05-12 Thu
17-05-25
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
12/60
ID Task
Mode
Task Name Duration Start Finish
108 Pave, curb, and
stripe parking
lot
2 wks Fri 17-05-26 Thu
17-06-08
109Elevators 40 days Fri 16 09 16 Thu 16 11 10
110 Set elevator
equipment in
shafts
4 wks Fri 16-09-16 Thu
16-10-13
111 Set equipment
in mechanical
room
2 wks Fri 16-10-14 Thu
16-10-27
112 Test and align
doors and
equipment
2 wks Fri 16-10-28 Thu
16-11-10
113Plumbing 90 days Fri 17 01 20 Thu 17 05 25
114 Rough-in
plumbing in
drywall walls
4 wks Fri 17-02-17 Thu
17-03-16
115 Tie-in fire line
riser and set
valves
2 wks Fri 17-01-20 Thu
17-02-02
116 Set plumbing
fixtures and trim
3 wks Fri 17-03-17 Thu
17-04-06
117 Flush, test, and
clean piping and
fixtures
2 wks Fri 17-05-12 Thu
17-05-25
118Electrical 139 days Mon 16 10 31Thu 17 05 11
Ele
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
13/60
ID Task
Mode
Task Name Duration Start Finish
119 Rough-in
electrical in
masonry walls
4 wks Mon
16-10-31
Fri 16-11-25
120 Rough-in
electrical in
drywall walls
4 wks Fri 17-02-17 Thu
17-03-16
121 Pull wire inconduit and set
area
transformers
3 wks Fri 17-03-10 Thu17-03-30
122 Install and
terminate
electrical
devices
3 wks Fri 17-03-31 Thu
17-04-20
123 Make electrical
terminations for
HVAC
equipment
2 days Fri 17-03-31 Mon
17-04-03
124 Install light
fixtures - test
and clean
2 wks Fri 17-04-28 Thu
17-05-11
125Heating and
Ventilating AC
180 days Fri 16 09 16 Thu
17 05 25
126 Set equipment
in mechanical
room
2 wks Fri 16-09-16 Thu
16-09-29
HVAC
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
14/60
ID Task
Mode
Task Name Duration Start Finish
127 Rough-in
mechanical in
masonry walls
4 wks Mon
16-10-31
Fri 16-11-25
128 Rough-in
mechanical in
drywall walls
2 wks Fri 17-02-17 Thu
17-03-02
129 Install duct inbuilding chase
3 wks Fri 17-02-17 Thu17-03-09
130 Set HVAC trim
and test and
balance system
4 wks Fri 17-04-28 Thu
17-05-25
131Final Clean up and
Occupancy
60 days Fri 17 03 24 Thu
17 06 15
132 Install hard tile
flooring in
common areas
1 wk Fri 17-03-24 Thu
17-03-30
133 Clean hard tile
floors
4 days Fri 17-03-31 Wed
17-04-05
134 Remove debris
from building
and do final
clean-up
4 days Fri 17-06-09 Wed
17-06-14
135 Substantial
completion date
1 day Thu
17-06-15
Thu
17-06-15
136Complete Final
Inspections
6 days Thu
17 06 15
Thu
17 06 22
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 14
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
15/60
ID Task
Mode
Task Name Duration Start Finish
137 Complete
elevator
inspection and
certification
3 days Thu
17-06-15
Mon
17-06-19
138 Perform
architect's
inspection
1 day Tue
17-06-20
Tue
17-06-20
139 Perform local
building agency
inspection
1 day Wed
17-06-21
Wed
17-06-21
140 Perform Fire
Marshal's
inspection
1 day Thu
17-06-22
Thu
17-06-22
141 Complete punch
list items from all
inspections
2 wks Fri 17-06-23 Thu
17-07-06
142 Obtain certificate
of occupancy
2 days Fri 17-07-07 Mon
17-07-10
143 Issue final
completion
documents
including
warranties
1 day Fri 17-07-07 Fri 17-07-07
144 Issue final request
for payment
1 day Tue
17-07-11
Tue
17-07-11
W S T M F T S W S T M F
'16 Jan 17 '16 Mar 13 '16 May 08 '16 Jul 03 '16 Aug 28 '1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 15
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
16/60
ent[25%]
anagement
nt[50%]
ment[50%]
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 16
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
17/60
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 17
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
18/60
r Management[50%],Steel Erection Contractor[50%]
]
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 18
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
19/60
ontractor
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 19
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
20/60
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 20
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
21/60
tractor
ontractor
ontractor[75%]
n Contractor[75%]
ction Contractor[50%]
rection Contractor[20%]
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 21
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
22/60
Rough Carpenter Crew,G.C. Labor Crew[20%]
33%],Plumbing Contractor[33%],Electric Contractor[33%]
. Concrete Crew
.C. Labor Crew[10%]
G.C. Labor Crew
G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
G.C. Concrete Crew
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 22
Project: Commercial Constructio
Date: Thu 16-03-17
b l
-
8/19/2019 Commercial Construction Project Plan
23/60
G.C. Labor Crew[10%]
G.C. Labor Crew
G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
G.C. Concrete Crew
G.C. Labor Crew[10%]
G.C. Labor Crew
G.C. Rough Carpenter Crew
Electric Contractor
Plumbing Contractor
G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]
G.C. Concrete Crew
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 23
Project: Commercial Constructio
Date: Thu 16-03-17
'16 O t 23 '16 D 18 '17 F b 12 '17 A 09 '17 J 04 '17 J l 30 '17 S 24 '17 N 19 '18 J 14 '18 M 11 '18 M 06
-
8/19/2019 Commercial Construction Project Plan
24/60
G.C. Labor Crew[10%]
G.C. Labor Crew
Drywall Contractor
Plumbing Contractor
nry Contractor
Masonry Contractor
Roofing Contractor
Tile Contractor
Masonry Contractor[50%]
Tile Contractor[50%]
F T S W S T M F T S W S T M F T S W S T M F T S W
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 24
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
25/60
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
-
8/19/2019 Commercial Construction Project Plan
26/60
G.C. Finish Carpenter Crew
Painting Contractor
Electric Contractor
HVAC Contractor
Drywall Contractor
Drywall Contractor
Painting Contractor
Carpet Contractor
G.C. Finish Carpenter Crew
Landscape Contractor
F T S W S T M F T S W S T M F T S W S T M F T S W
16 Oct 23 16 Dec 18 17 Feb 12 17 Apr 09 17 Jun 04 17 Jul 30 17 Sep 24 17 Nov 19 18 Jan 14 18 Mar 11 18 May 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 26
Project: Commercial Constructio
Date: Thu 16-03-17
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
-
8/19/2019 Commercial Construction Project Plan
27/60
Paving Contractor
Elevator Contractor
Elevator Contractor
Elevator Contractor
Plumbing Contractor
Plumbing Contractor
Plumbing Contractor
Plumbing Contractor
F T S W S T M F T S W S T M F T S W S T M F T S W
6 Oct 3 6 ec 8 eb p 09 Ju 0 Ju 30 Sep o 9 8 Ja 8 a 8 ay 06
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 27
Project: Commercial Constructio
Date: Thu 16-03-17
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
-
8/19/2019 Commercial Construction Project Plan
28/60
Electric Contractor
Electric Contractor
Electric Contractor
Electric Contractor
Electric Contractor
Electric Contractor
VAC Contractor
F T S W S T M F T S W S T M F T S W S T M F T S W
p p y
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 28
Project: Commercial Constructio
Date: Thu 16-03-17
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
-
8/19/2019 Commercial Construction Project Plan
29/60
HVAC Contractor
HVAC Contractor
HVAC Contractor
HVAC Contractor
Tile Contractor
Tile Contractor[50%]
G.C. Labor Crew
G.C. Superintendent
F T S W S T M F T S W S T M F T S W S T M F T S W
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 29
Project: Commercial Constructio
Date: Thu 16-03-17
'16 Oct 23 '16 Dec 18 '17 Feb 12 '17 Apr 09 '17 Jun 04 '17 Jul 30 '17 Sep 24 '17 Nov 19 '18 Jan 14 '18 Mar 11 '18 May 06
-
8/19/2019 Commercial Construction Project Plan
30/60
Elevator Contractor
G.C. Superintendent[50%],G.C. Project Management[50%]
G.C. Project Management[50%],G.C. Superintendent[50%]
G.C. Superintendent[50%],G.C. Project Management[50%]
G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Co
G.C. Project Management
G.C. Project Management
G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]
F T S W S T M F T S W S T M F T S W S T M F T S W
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 30
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
31/60
S T M F T S W S T M F T S W S T M F T S W S T M F
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 31
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
32/60
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
33/60
S T M F T S W S T M F T S W S T M F T S W S T M F
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 33
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
34/60
S T M F T S W S T M F T S W S T M F T S W S T M F
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 34
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
35/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 35
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
36/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 36
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
37/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 37
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
38/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 38
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
39/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 39
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
40/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 40
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
41/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 41
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
42/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 42
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
43/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 43
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
44/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 44
Project: Commercial Constructio
Date: Thu 16-03-17
S T M F T S W S T M F T S W S T M F T S W S T M F
'18 Jul 01 '18 Aug 26 '18 Oct 21 '18 Dec 16 '19 Feb 10 '19 Apr 07 '19 Jun 02 '19 Jul 28 '19 Sep 22 '19 Nov 17 '20 Jan 12 '20
-
8/19/2019 Commercial Construction Project Plan
45/60
ontractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]
]
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 45
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
46/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 46
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
47/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 47
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
48/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 48
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
49/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 49
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
50/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 50
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
51/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 51
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
52/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 52
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
53/60
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
54/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 54
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
55/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 55
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
56/60
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
57/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 57
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
58/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 58
Project: Commercial Constructio
Date: Thu 16-03-17
T S W S T M F T S W S T M F T S W S T M F T S W S
Mar 08 '20 May 03 '20 Jun 28 '20 Aug 23 '20 Oct 18 '20 Dec 13 '21 Feb 07 '21 Apr 04 '21 May 30 '21 Jul 25 '21 Sep 19 '21 N
-
8/19/2019 Commercial Construction Project Plan
59/60
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 59
Project: Commercial Constructio
Date: Thu 16-03-17
-
8/19/2019 Commercial Construction Project Plan
60/60