comet facility beam line experiment area sc magnet pion production target

19
COMET Facility Beam line Experiment area SC magnet Pion production target

Upload: hannah-robertson

Post on 29-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COMET Facility Beam line Experiment area SC magnet Pion production target

COMET Facility

Beam lineExperiment area

SC magnetPion production target

Page 2: COMET Facility Beam line Experiment area SC magnet Pion production target

Construction of high-p/COMET beam lines

Steel-septum (Lambertson) magnet,Current-septum magnets x2

Beamline magnetsDx7, Qx8 Collimators

(H, V)

3 of existing beamline magnets(Dx1, Qx2) are replaced to avoid interference with new line

Most of beamline magnets(Dx7, Qx6) are reused ones

vertically steering magnets (x2) to make a bump orbit for beam extraction to high-p/COMET Installation in SY has started

Page 3: COMET Facility Beam line Experiment area SC magnet Pion production target

Construction of high-p/COMET beam lines

high-pbeam dump

COMETbeam dump

Capture Solenoid

FM

High-p beamline magnetsDx5, Qx3

COMET beamline magnetsDx5, Qx4

Beam plugs

Beam plugs

Most of beamline magnets(Dx8, Qx5) are reused ones

Installation in Hall will start next JFY

Page 4: COMET Facility Beam line Experiment area SC magnet Pion production target

Top View of the Branching Point from A-line

Steel-Septum(Lambertson)

Magnet

Current-SeptumMagnet

existing beam line

high-p/COMET beam line

5° in total

Page 5: COMET Facility Beam line Experiment area SC magnet Pion production target

Steel-Septum (Lambertson) Magnet

field free hole

coilvacuum chamber

bending field

yoke

proton beam

Page 6: COMET Facility Beam line Experiment area SC magnet Pion production target

Operation Modes at Branching Point

T1 T1 + High-p COMETall protons are

delivered to T1 target10-4 protons arebranched into

high-p/COMET line

all protons arebent into

high-p/COMET line

10-4 protons

vertical beam position at BP is adjustable using 2 steering magnets

Page 7: COMET Facility Beam line Experiment area SC magnet Pion production target

COMET Hall : B1F Plane View

Page 8: COMET Facility Beam line Experiment area SC magnet Pion production target

COMET Hall : B1F Plane View

Beam Room

Exp. Room

MachineRoom

BeamDump

Page 9: COMET Facility Beam line Experiment area SC magnet Pion production target

COMET Hall : Section View

Beam RoomExp. Room

MachineRoom

Installation Yard

Control Room

Page 10: COMET Facility Beam line Experiment area SC magnet Pion production target

Radiation Evaluation

0.05mSv/h(#100)

0.7mSv/h(#135)

2.6mSv/h(#167) 2.6

mSv/h

0.7mSv/h

0.05mSv/h

Radiation level around the COMET buildingwas evaluated using MARS simulation.

Each Box in the left figure correspondsto each point in right plot.

Radiation contamination of the soil is estimated to be smaller thanthe limitation of 11 mSv/h.

Page 11: COMET Facility Beam line Experiment area SC magnet Pion production target

Radioactivation of Air / Water

HalfLife

AirBeam room

(Bq/cc)

AirExp. Room

(Bq/cc)

Air Evacuation

Limit

Water(Bq/cc)

WaterDrainLimit

3H 12.26y 3.1E+00 7.07E-03 5.0E-03 542 60

7Be 53.4d 2.3E+00 7.32E-03 2.0E-03 1408 30

15O 2.04m 6.0E+01 1.00E-01 7.0E-04 180567 5

13N 9.97m 8.1E+01 2.01E-01 7.0E-04 2558 5

11C 20.4m 5.1E+00 2.00E-02 7.0E-04 5113 0.1

41Ar 1.85h 3.7E+01 4.81E-01 5.0E-04 NA NA

Radioactivation of air in the beam room / experimental room andcooling water after 90-days operation was evaluated based on MARS.

- Radioactive nuclide density in air exceeds evacuation limit. Both beam room and experimental room are air-sealed during beam operation.- Radioactive nuclide density in cooling water exceeds drain limit. 7Be is collected by filter. Short-life nuclides density is sufficiently reduced in 1 day. 3H must be drained after diluting.

Page 12: COMET Facility Beam line Experiment area SC magnet Pion production target

Air ventilation diagramof the COMET Hall

Page 13: COMET Facility Beam line Experiment area SC magnet Pion production target

Superconducting Magnet

Iron Yoke

Tungsten Shield

Proton Target

8GeV proton

m

6.4m

Field distribution in OPERA3D

Pion Capture Solenoid Transport

Solenoid

Status of SC Mag. Production:Engineering design of SC coilshas been initiated

Procurement of superconducting cable was started.

5T

3T

Page 14: COMET Facility Beam line Experiment area SC magnet Pion production target

14

~15 MPa

~30 MPa

SEQV

Model-2

FEM analysis of Mises stress in coils with thick outer shell

pure Al thermal link

GFRP(BT) spacer

GFRP(BT)Al strip guide

GFRP(BT) lead cable guide

Welding to shell

Support Shell

2-phase He

CS0 coil structure

Conceptual Design of Tungsten Shield Supports

Supports 40ton shieldwith <5mm distortion

Layout in exp. hall

Layout in experimental hall is almost fixed.

Concept of yoke, shield is developed.

Detailed design of coil structure, cooling system, current leads etc. are underway.

Page 15: COMET Facility Beam line Experiment area SC magnet Pion production target

Production Target

• Phase I (Radiation cooling)– Graphite (IG-43)

• Refractory material and so is tolerant to high temperature operation

• Experience in T2K

– Tungsten (optional)• Larger muon yield• Radiation cooling may be OK but need careful assessment

• Phase II (Active cooling)– Tungsten

• Bad chemistry between tungsten and water• Helium cooling instead of water cooling

Page 16: COMET Facility Beam line Experiment area SC magnet Pion production target

Energy Deposit by 3.2kW proton beam on a graphite rod (4cm diam. & 60cm L)

Page 17: COMET Facility Beam line Experiment area SC magnet Pion production target

Temperature distributionmaterial emissivity of 0.75

Page 18: COMET Facility Beam line Experiment area SC magnet Pion production target

Accident Scenarios (Phase I)• Accidental fast extracted beam pulse

– T2K target temperature rise in a cycle is 100K– sx = 4mm in T2k while sx=2mm in COMET– 750 kW in T2K while 3.2kW in COMET

– Well below graphite evaporation temperature– Detection system of extraction failure and temperature monitoring are mandatory

• Loss of vacuum during operation– Any sublimation or oxidation ?

• The COMET target is expected to run at a temperature well below the level

– May be possible to contain the target within a thin metal capsule• Protects the target from oxidation and radiates the heat load

– An alternative is• Coat the graphite with a refractory metal e.g. tantalum or iridium

– Connecting the pump exhausts to a vessel through a filter system is an issue• Failure of any of dipole magnets bending the beam from the high-p line

– Status will be included in MPS; If any of them is off, stop the accelerator– Even if any magnet fails during extraction, magnetic field goes down slowly due to the

coil inductance and thus the beam won’t localize a small area on the beam duct/magnet.

Page 19: COMET Facility Beam line Experiment area SC magnet Pion production target

COMET Phase I Facility Schedule

• 2013– Design of the building & beam line

• Bid tendering and start construction

– Design of superconducting solenoid magnets and start of construction

• Production of SC wires as well

– Design of the pion production target• 2014

– Completion of the building– Construction of superconducting solenoid magnets– Start magnet and radiation shielding (and beam

dump) installation• Transport solenoid

– Start preparation of cryogenic system– Tests of the target production target

• 2015– Construction of superconducting solenoid magnets– Preparation of cryogenic system– Construction of the pion production target

• 2016– Installation of the capture solenoid– Completion of the cryogenic system

• Tests of the magnet system

– Installation of the target– Ready to accept the 8GeV beam

JFY 2013 2014 2015 2016COMET building

design

construction

Solenoid magnet

SC wire

Capture magnet

Transport magnet

Cryogenic system

Magnet system test

Radiation shield

Beam dump

Pion target

Design & test

construction