combustion profile of a grate- rotary kiln · pdf filecombustion profile of a grate-rotary...
TRANSCRIPT
COMBUSTION PROFILE OF A
GRATE-ROTARY KILN INCINERATOR
ABSTRACT
P. H. WOODRUFF
Roy F. Weston, Inc. Wilmette, Illinois
A study was made of a 300-ton-per-day grate-rotarykiln incinerator. Sampling data were obtained at the end of the rotary kiln, in the secondary combustion chamber, just ahead of the spray chambers, and in the stack. Samples were taken at several elevations at each point in the combustion train. Data were obtained on gas temperatures, particulate loading, hydrocarbon, oxygen, CO2 and co. Sampling data have been correlated with refuse loading and general operation of the incinerator to produce typical operating profiles. The promes illustrate gas flow and combustion characteristics of materials as they are burned in this type of incinerator. Data from the tests are presented and discussed.
As a result of these tests and observations several recommendations were made for modification to the combustion air supply system and gas mixing modifica-
• tlons.
INTRODUCTION
A grate-rotary-kiln incinerator, owned and operated by a city, had been a subject of public complaint on numerous occasions since the operation began. Visible emissions from the tall stack, of which there were few in the area, could be readily observed. The specific complaints alleged deposits of fly ash and odors. A distinguishable plume from a tall stack usually results in complaints both real and non-factual. The investigations of complaints
G. P. LARSON
Franklin Institute Philadelphia, Pennsylvania
327
had shown a number of cases when the incinerator was inoperative and individuals insisted that they were being affected. However, many persons were convinced that the operation of the incinerator resulted in nuisance conditions in areas adjoining the incinerator plant.
This criticism led to a careful study by the city of control devices which might be used to reduce the discharges from the stack. This preliminary study clearly defined the cost of electrical precipitators or baghouse controls. Aside from the cost, these systems were considered to be somewhat experimental and would materially complicate the operation of the incinerator.
Various proposals were also studied for improving the water-spray system as a means for reducing fly ash. The conclusion from these and other studies led to the recommendation that a study be made of the combustion process within the incinerator and of operating conditions, before arriving at final conclusions on the engineering modifications needed to reduce the nuisance complaints .
PURPOSE OF THE TEST
The tests were to determine the practicability of methods for increasing the combustion efficiency by setting criteria for modifying the design characteristics or to determine operational procedures which would result in compliance with air pollution regulations and to minimize any nuisances resulting from the incinerator.
The program called for conducting tests at several points throughout the combustion zones of the incinera-
;or and to determine the amount of solid particles and condensable materials being discharged into the atmosphere. Tests in the combustion zone were to include measurements of oxygen, carbon-monoxide, carbondioxide and the determination of velocities. The sampling program was designed to indicate the general combustion conditions inside the incinerator.
The results of the study and the recommendations are presented in this paper.
INCINERATOR OPERATION AND CONTROLS
The incinerator plant consists of drying and ignition grates where rubbish is ignited and moved continuously to a rotary kiln. Part of the burning mass is constantly turned over and moved progressively along the 24-foot length of the kiln as it slowly rotates. The outlet of the rotating burning chamber drops the unburnable ash to an ash pit for ultimate disposal. The combustion gases
)
(
SMFL11Ii AT Mia-SECTl� (F SECXMWIY c:oe ISTI(lI CHIIMBEII
til S02 FT /SEC
II
" ' "
• "
'"
9 S 16 1 77 16 1
2 2-14 2 161 6' 110
0 ,\6
NO"
. ... . '.L.!:::=jl . ' . .... . : � .
. ':' . -1'1: .. ' . , -, ... • • •
OASt£D LIlES IMlCATE [STIMATDI
I Jill AC TUAl MUSl..ll9lENT I
•
leaving the rotary kiln continue to burn in a secondary combustion zone, approximately 32 feet in length; subsequently they enter a water spray for removal of large ash particles. Gases are then discharged through a stack 200 feet in height.
The process is controlled by a single operator who can regulate the movement of the grates in the ignition chamber to introduce a continuous flow of burning rubbish to the rotary furnace. The speed of the rotary kiln can be regulated to control the time it takes for the burning mass to pass through the kiln. Air used for combustion is introduced under the grates in the ignition chamber. While dampers are provided for the introduction of air over the Gre, these dampers had not been used, as the operators felt this cooled the furnace below normal operating temperatures.
Temperature-recording instruments are installed in order that the operator can control temperatures in the burning zones and avoid excessive temperatures which
SAMPliNG AT SEctJIlARy CDIISTION 0IAI1ER
SAfIIlINC AT STlCl
J«1'f 'N 1 ser. a ()I+81-0 16251:1 IS C F o '-I 6 PPM ALOOfYtls----... '4 14' CO2 16 Oi 02 o 2" CD
p() f C!lz 1 02 f co FT lsa:
•
•
'4 0 1'4 9 0) 85 11308 9 6 10 9 0 7
'OJ 31 J
311
SIWlI NC HAD � SPRAYS
NO fT /SEC CR IS C F
19 1 2 7 II 1505 0)5
III IJJ 0 22
•
•
•
lE&[NO
� ZONE (F It()t 'f'ELOCHY & 02 CIJCSlWTI(JI
�I /OJ( Of 11[000 VElocm • 0, ClJlSUFTIOI
I I /OJ( Of LOI VElOCITY • 0, ClJlSUFT""
j·: · ·: · ... '·. · ·1
FL. ASH .. . . .. . .
FIG. 1 INCINERATOR GAS FLOW DISTRIBUTION AND COMBUSTION PROFILE
328
would damage the grates in the ignition chamber. The speed of the kiln and the speed of the grates, which serve to regulate the flow of rubbish, can be changed instantaneously by the operator based on his judgment to avoid excessive temperatures or to maintain proper burning temperatures in the system.
The incinerator operates 24 hours per day during the regular 5-day work week. When the operation begins, approximately 24 hours is required to bring the furnace up to operating temperatures. No auxiliary fuel is provided for the warm-up. Rubbish is received during the entire week and the furnace operates through Friday evening. The design capacity of the unit is 12.5 tons per hour. The total input of rubbish is not weighed.
After the start-up period, temperature control is largely a function of the manner in which the operator controls the incinerator. Operating charts record temperature conditions in the incinerator on an hourly basis. Temperature records covering the operation during the period from January 6 to June 11, were reviewed. The periods of time when the temperature was below 1500 F for more than 3 hours were examined.
There were 12 days when the incinerator was below 1500 F for periods up to 30 percent of the total operating time. On 19 days, the temperature was below 1500 F, 31 to 69 percent of the time. On 6 days the temperature was below 1500 F more than 70 percent of the time. The majority of these low temperature conditions occurred during the night-time hours.
THIMBLE
GRAB SA�PLING FLASK (ORSAT ANALYSIS)
CONDENSATE TRAP
IN ICE BATH
CCI4 IMPINGERS
IN ICE BATH
The important consideration from this review is the fact that out of 64 days of operation picked at random, there were 37 days when the incinerator was below normal operating temperatures for substantial periods of time. These low temperature conditions prevailed from 3 to 16 hours. Under these temperature conditions, odors from the products of incomplete combustion could be expected.
Stagnant wind conditions generally prevail at night. Odors may travel many miles and are detected at lower threshold levels during the less active evening hours than during day-time activities.
TEST CONDITIONS
The testing program began after the inciner:>tor had been operating a sufficient length of time to reach operating temperatures. Observations of the operator's control demonstrated that temperature conditions could be maintained above 1500 F and all tests throughout the ensuing four days were taken when the temperature of the gas stream leaving the secondary combustion chamber was from 1500 F to 2000 F. Test locations are shown in Fig. 1 and were selected on the basis of accessability and in areas where representative measurements could be obtained.
The loading to the incinerator was determined by counting the bucket loads per hour deposited in the holding zone prior to charging. The weight of material
CONDENSATE TRAP
rir,ACUUM GAUGE
THERMOMETER -....
ROTOMETER DRY GAS METER
CONTROL VALVE
VACUUM PUMP
FIG. 2 PARTICULATE - COMBUSTIBLES SAMPLE TRAIN
329
was based upon estimates of 3 cubic yards of rubbish per bucket at an estimated weight of 450 pounds per cubic yard.
TEST METHODS
Standard procedures, such as those outlined in Western Precipitation Bulletin WP-50 and the Los Angeles County SouTce Testing Manual, were used for the collecting and processing of samples. Diagrams of the sampling trains are shown in Figs. 2 and 3.
For velocity determinations, a special pitot tube consisting of three four-foot lengths of stainless steel was used. Temperature measurements were determined using a chromel-alumel thermocouple in conjunction with a potentiometer.
Oxygen, carbon dioxide, and carbon monoxide samples were collected by liquid displacement and later analyzed using an Orsat gas apparatus. The Weston and Stack dissolved oxygen analyzer was used continuously to check the oxygen values obtained by Orsat. The solid particles in the gas stream were collected in alundum thimbles, which were later ashed in order to determine the amount of combustible material present in the thimbles. Material passing through the thimbles was collected by wet impingers following the thimbles and was weighed after evaporation of the water. Volatilized material was also condensed and collected by absorption in carbon tetrachloride.
compounds to decompose, freeing bisulfite ion equivalent to the aldehydes present. Standard iodine is then used to titrate the liberated bisulfite ion.
COMBUSTION PROFILE - SUMMARY OF GAS FLOW
AND OXYGEN DISTRIBUTION
The results at test locations 1, 2, and 3 are summarized and illustrated in Fig. 1. All of the air supplied by the fan enters under the grates. Combustion of the refuse begins in the primary chamber and is completed as the refuse passes through the rotary kiln. The oxygen supply must be sufficient for the fuel bed combustion process and the complete burning of volatilized gases in the secondary combustion zone. Infiltrated air for cooling and combustion is drawn into the incinerator though the charging chute, inspection doors, air ports, openings around the circumference of both ends of the rotary kiln, hopper at the charging end of the kiln, residue conveyor diversion gate assembly, expansion joint between the spray chamber and the stack, miscellaneous openings in the refractories.
Pitot tube measurements indicate that the forced draft fan, which has nominal capacity of 25,000 cfm at 100 F and 12 in. water static pressure, supplies only about one third to one fourth of the total gas leaving the stack.
The by-pass chamber which connects the ignition chamber with the secondary combustion chamber was partially blocked by brick work. No measurements were made to determine gas flow in the by-pass; however, flow was believed to be small.
Figs. 4, 5, and 6 show close ups of the sampling ports at test locations 1 and 2.
Although it would have been desirable to sample all
An impinger absorber train was used to collect aldehydes in the stack gas discharge. Sodium bisulfite solution was used as the absorber medium. Aldehydes react with the sodium bisulfite solution to form addition compounds. The excess bisulfite ion is destroyed with iodine solution. Adjustment of the pH of the solution causes the addition . points in the test program simultaneously to remove the
TH IIiBLE
STACK
IIiPINGER 100 ilL
IS NaHS03
I I ICE BATH CCI4
IIiPINGER IN ICE BATH
CONDENSATE TRAP ROTOIIETER
DRY GAS IIETER
FIG. 3 PARTICULATE - ALDEHYDE SAMPLE TRAIN
330
GAUGE
CONTROL VALVE
VACUUII PUIIP
possibility of conditions changing greatly at any one point during the test, the manpower and equipment requirements made this impractical. The incinerator was operated as uniformly as possible throughout the test period and little variation was found in velocity measurements at a couple of the sampling ports which were spot checked for similarity on several occasions. Thus, the test results are thought to be, in general, indicative of combustion conditions in the incinerator.
Tests for oxygen content of the combustion gases leaving the kiln at test location 1 are summarized in Table 1. These tests indicate the gases leaving the kiln in the zone immediately above the fIre bed were defIcient in oxygen. The horizontal velocity of the gas at the fIve measured points (all in vertical plane) at the end of the kiln was fairly uniform and suffIcient oxygen still remained in the upper portion of the gases leaving the kiln to complete the combustion of the volatilized matter.
FIG. 4 SAMPLING PORTS - TEST LOCA nON 1
331
In the event that oxygen, temperature and mixing conditions are correct as the gases reach the secondary combustion chamber, the combustible gases and particulate matter should continue to burn. Since oxygen was still available in the upper portion of the kiln, test location 2 in the secondary chamber should have shown continued improvement in burning conditions even though a defIciency of oxygen existed directly over the fIre bed at test location 1.
The test results summarized in Table II, however, indicated high oxygen levels remained in the upper portion of the gas stream with only small amounts of CO2. The gas velocity in the upper level was almost the same, 18.3 ft per sec, as was found for the gases leaving the rotary kiln, 15 to 16.7 ft per sec. The upper sampling point, No. I, showed oxygen content as high as 20 percent on one occasion indicating essentially no burning in this sample area at that particular time.
FIG. 5 TEST LOCA T/oN 2
In the lower two-thirds of the gas stream passing over the bridge wall at test location 2, the velocities were 37 ft per sec, more than double the rate found at test location 1. The temperatures and oxygen were adequate in this zone for good combustion of the combustible solid and volatile materials in the gas stream. However, one sample of particulate matter taken from the center of the gas stream contained 30 percent combustible material. The sampling probe was not water cooled, so combustible particulates in the incinerator may have been even higher. These test results at location 2 indicate stratification of the flow and poor mixing conditions.
The testing probe at the lowest sampling point was completely covered with ash. The gases passed over the bridge wall carrying ash that, apparently, had no opportunity to drop into the ash pit. This material was large in size and appeared to be carried into the gas stream as a result of the turbulent action ahead of the bridge wall where the gas stream leaves the bottom half of the kiln.
Test location 3 was selected to give an indication of combustion conditions in the fmal burning area preceding the water sprays. The data for this test station are summarized in Table III. The average velocity measurements show that after the gases passed the bridge wall, high velocity (39 ft per sec) prevailed in the upper third of the chamber. This portion of gas was heavily loaded with particulate measuring 2.7 grains per standard cubic foot for just the material collected in the thimble or 3.5 grains per standard cubic foot including the material collected in the wet impingers. The velocity in the lower two-thirds of the chamber was extemely low (13 to 15 ft per sec) and contained very small amounts of particulates.
TABLE I
TEST LOCATION NO.1
• ; , , , • •
..., \ • II -.I
,-
• •
•
• •
•
• • •
\
, ,
• •
FIG. 6 CLOSE-UP OF TEST LOCA TION 2
MID·SECTION OF SECONDARY COMBUSTION CHAMBER
Sample Location
I
II
III
IV
VI
( ) Estimated
Vert. Dist. From Bottom Sampling Ports
Ft
7
6
4.5
2.5
0.0
Velocity Ft/Sec
332
16.7
16.7
16.7
15.0
15.6
Temperature Degree F
(1850)
(1850)
1930
1925
2130
Oxygen Percent
9.5
7.7
2.2 to 4.2
6. 1
Nil
Forced Fan Draft In. Water
4
6
4
•
Time Sample
Location
TABLE II
TEST LOCATION NO.2
SECONDARY COMBUSTION CHAMBER
Orsat Analysis
CO2 Percent Percent
CO Percent
Temp. of
---------------------------------------------------------------------------
17:20
17:45
18:00
10:05
12:10
13:20
15:25
16:15
16:50
I-A
I-B
I-C
II-A
II-B
II-C
III-C
III-B
III-A
0.4
3.2
8.4
12
5.6
8.0
18.0
10.0
0.8
20.4
17.2
11.2
7.8
13.2
12.8
2.8
9.6
20.4
0.2
0.4
0.2
0.8
0.8
0.8
0.8
0.8
0.4
1580
1660
1760
1600
1780
1700
2100
1880
1580
1. Location A, Band C correspond to points Y.., Y2 and 3,4 respectively across the combustion chamber at each sampling port.
TABLE III
TEST LOCA TI ON NO.3
SECONDARY COMBUSTION CHAMBER BEFORE SPRAYS
Estimated Flow, scfm Thimble Solids, grams Solids Collected in Wet Impinger, grams Total Solids Collected, grams Combustible Solids, percent Particulate Loading, grains/ scf Particulate Loading, lbs/hr Organics Collected in CCI4, grams Organics Collected in H20, grams Total Organics Collected in Impingers, grams Loading (Organics ColI. in Impingers), grams/scf Loading (Organics CoIl. in Impingers), lbs/hr Secondary Combustion Temp., of
Water Vapor (by Volume), percent Estimated Refuse Charged, lbs/hr
Top
82,000 1.9231 0.586 2.509 4.0 3.51 2,460 0.0571 0.0228 0.0799 0.112 78.7
1,650 17.4
25,650
Sample Location Center
34,000 0.3942 0.0927 0.4869 11.8 0.44 128 0.1170 0.0174 0.1344 0.129 37.6
1,500 11.3
22,950
NOTE: Flow rates were estimated by assuming the measured velocities were typical and multiplied by the appropriate cross sectional area.
333
Bottom
30,000 0.2291 0.0805 0.3096 11.9 0.30 77 0.0268 0.0392 0.0660 0.066 17.0
1,450 8.9
20,250
The particulate matter collected in the thimble at each of the three sampling locations indicated that the fly ash contained less than 12 percent organic material. However, the thimbles were not water cooled and some combustion of organic matter may have occcurred during the sample collection period. Volatilized organics which may condense in the atmosphere after leaving the stack still remained at this point. This combustible material was collected in the iced, wet impingers and iced impingers containing carbon tetrachloride used in conjunction with this test. The impinger collected organic material indicating the organic discharge rate at location 3 varied from 17 to 79 pounds per hour.
EVALUATION OF SPRAY CHAMB ER
EFFECTIV ENESS
An exact analysis of spray-chamber performance was impractical with the available manpower and equipment due to the need to obtain simultaneous sampling of inlet and outlet of the spray chamber. With the inlet section of the spray chamber exhibiting extremely unequal dust loading and flow distribution, the inlet sampling would have had to be accomplished at several points in the cross section of the chamber simultaneously for an exact measurement. It is not possible to make a meaningful estimate of the mean
particulate loading going into the sprays with the limited data available. Therefore, unfortunately, no estimate
. can be made on the efficiency of the sprays in removing fly ash from the combustion gas.
STACK EMISSIONS
Two samples were taken in the stack to measure the amount of particulate matter being emitted to the atmosphere. The two samples were collected about two hours apart on the same day. The results varied considerably and showed the usual wide fluctuations in the amount of material discharged during the operation of large incinerators, even during times of exceptionally "steady" operation. Based upon the results shown in the accompanying tables, the particulate matter discharged in one test was 103 pounds per hour and in the other case 36 pounds per hour.
The grain loading in Test A was 0.502 and in Test B was 0.175 grains per scf of dry gas calculated on the basis of 50 percent excess air.
During the course of the stack tests, the operating temperature of the incinerator was kept above 1600 F and the refuse charging rate was estimated to be about 70 percent of the design loading rate. During most of the preceding sampling work the refuse charging rate was estimated to be about 90 percent of the design
TABLE IV
STACK SAMPLING STATION EMISSION SUMMARY
Test
Refuse Charged, lbs/hr Particula te Discharge \ lbs/hr Particulate Discharge, 2 grains/scf Combustible Particulates Collected in Thimble, percent Aldehydes, ppm Organics Not Collected in Thimble2 , grains/scf Organics Not Collected in Thimble, lbs/hr Orsat Analysis3 :
02' percent CO2, percent CO, percent
Water Vapor (by Volume), percent
A
17,500 103 0.502 18.5 0.99 0.412 84
16.0
4.4 0.2 120
B
17,500 36 0.175 12.5 1.62 0.282 57
9.9
Average
17,500 69. 5 0.338 15.5 1.30 0.347 70.5
NOTE: 1. Stack gas flow calculated to be 73,300 sefm, velocity 13.8 fps and temperature measured at 380 F (Average Values).
2. At 68 F and 50 percent excess air (dry basis).
3. Excess air calculated to be 305 percent.
334
rating. Fig. 7 illustrates typical appearance of the stack during the test period.
In addition to the above data, a sample for aldehyde determination was taken during the course of the test, as an index of odoriferous materials which might be discharged as a result of incomplete combustion. The amount of aldehyde found was extemely low. The test team reported no odors were observed in the discharge gases during the course of the test.
The amount of volatilized organics remaining in the incinerator gases was determined by absorption in carbon tetrachloride in traps immersed in an ice bath. Test A showed 84.2 pounds per hour of condensible organic material being discharged. Test B showed 57 pounds per hour of the same type of material being emitted to the atmosphere. The resultant average of 70.5 pounds per hour of unburned organic vapors which were condensed and absorbed in carbon tetrachloride is equal to
I
FIG. 7 T,YPICAL STACK APPEARANCE
335
the average of the particulate matter i.e., 69.5 pounds per hour discharged during the same testing period.
The volatilized organic material found in the carbon tetrachloride was collected for the purpose of comparison with similar samples taken at test location 3 ahead of the water sprays. Samples of the collected particulate matter were burned in ,the laboratory to determine the combustible content. An average of 15 percent of unburned material was found in these samples.
CONCLUSIONS
As a result of this study the following conclusions were drawn:
1) Operation control to maintain secondary combustion chamber temperatures above 1500 F was lacking during a high percentage of the operating days.
2) The start-up period was excessive since no provisions were made to use auxiliary fuel to preheat the • • mcmerator.
3) Further improvement in fly ash removal by the water sprays could probably be expected if the extremely unequal dust loadings in the secondary combustion chamber could be equalized by improving the gas flow pattern.
4) The organic constituents found in the secondary combustion chamber both in the ash particulate matter and as condensable gas-phase material indicate combustion is not complete before the gas stream reaches the water sprays.
5) Lack of positive means for introducing and/or mixing air with the products of combustion in the secondary combustion zone leads to deficiencies in the burning process.
6) The use of air under the grates promoted the suspension of excessive amounts of particulate matter in the gas stream.
7) Turbulent action of the combustion gases leaving the lower portion of the rotary kiln entrained large quantities of particulate matter which should have been deposited in the ash pit.
8) Outside air drawn into the ash pit may have been a factor in producing a turbulent condition which prevents the lighter ash particles from depositing in the pit.
RECOMMENDATIONS
Based upon the conclusions reached in this study, the following recommendations for operating changes, design modifications, and further engineering investigations were suggested for action in the following order.
Start-Up Procedure
The incinerator should be operated on a seven-day basis, if possible, to eliminate any nuisance which results during the start-up period. Investigate the availability of additional supplies of rubbish which would pay for the additional operating time.
If continuous operation cannot be achieved, supplementary fuel, preferably natural gas, should be used to bring the incinerator up to temperature and to assist in burning the initial loads during start-up periods. The installation of burners in the primary combustion chamber and in the secondary burning zones would be required.
Temperature Control
The operation of the incinerator during the test demonstrated that temperatures in the proper operating range can be maintained. The use of the operator's daily report should be continued and inspected each day to insure that the responsible individuals maintain a continuous supply of rubbish during the operating period and that the floor operator makes the necessary adjustments to keep the temperature above 1500 F.
Air Control
Reduce the amount of underfire air presently being introduced and divert a portion of this air over the fire bed in the primary chamber for the purpose of reducing suspension of fly ash in the gas stream. Duct work and dampers to permit this diversion of air and its introduction into the primary combustion chamber could be accomplished with minor alterations to the system. The exact amount of air to be placed under the grate should be determined experimentally after the modification so
336
as to supply the necessary air to control grate temperatures at safe levels.
I nfiltrated Air
Investigate the feasibility of reducing infiltrated air into the ash pit through the diversion gate assembly. The diversion gate could be protected either through the use of water or by the use of refractories. Every effort should be made to reduce this air flow, which appears to be a factor in carrying light ash upward into the turbulent gas stream as it leaves the rotary kiln.
Tests and Complaints
Maintain a careful record of complaints and investigate each complaint carefully for at least six months after the operating changes suggested in 1 and 2 have been accomplished.
Upon completion of items 1 through 4, a relatively simple testing program should be undertaken to determine the benefits achieved in the stack characteristics.
I mproved Mixing Conditions
Make an engineering study on the feasibility of installing appropriate baffles or checker work across the secondary combustion chamber at the point after the gases have passed over the existing bridge wall. This alteration would serve to mix the gases to achieve better combustion and distribute the flow of gas reaching the water sprays. Some improvement in the effectiveness of the water spray system would result. This effect, together with the improved burning conditions created through better mixing after the bridge wall, will reduce the discharge to the atmosphere and would be expected to improve the appearance of the plume.