SOUTHEAST METRO NATURAL GAS PROJECT Project Overview Xcel Energy proposes to install, operate, and maintain approximately five miles of 20-inch-diameter-steel natural gas pipe and associated gas system facilities. The Southeast Metro Natural Gas Project will allow Xcel Energy to continue providing the safe, reliable natural gas service our customers expect in the southeastern Denver metropolitan area. Additionally, the project will provide flexibility in the operation of our natural gas system. The project begins near the intersection of South Yosemite Avenue and East Hampden Avenue in Denver and ends near the intersection of East Caley Avenue and South Troy Circle in Centennial. Project work will occur in parts of unincorporated Arapahoe County, Aurora, Centennial, Cherry Creek State Park, Denver, and Greenwood Village. Project Schedule Construction could start as soon as summer 2020. We anticipate that construction – including restoring work areas and bringing the pipe into service – could be completed by the end of 2021. We are currently requesting permits for the project. Project schedule is subject to change. Project Communications One of the goals of this project is to ensure that we maintain consistent communication with our stakeholders – elected officials, government agencies, businesses, property owners, residents and schools. Prior to construction starting, businesses, residents and other impacted parties near the project area will be notified about construction start dates and property access needs. Amongst others, notification tactics will include direct mail, electronic and static notification roadside signage and targeted social media. " Þ CHERRY CREEK RESERVOIR E HAMPDEN AVE § ¨ ¦ 25 E BELLEVIEW AVE CHERRY CREEK STATE PARK § ¨ ¦ 225 S DAYTON ST S PEORIA ST E UNION AVE S BOSTON ST E ORCHARD RD S YOSEMITE ST APPLICANT PROPOSED ROUTE ¯ Contact us During and after construction, Xcel Energy will maintain contact through our dedicated project website, information line and email list. For additional information, to sign up for project updates or to submit questions, visit XcelEnergySEMetro GasProject.com, call our project information line at 866.267.7419, or email us at Info@XcelEnergySEMetro GasProject.com. INFORMATION SHEET COLORADO xcelenergy.com | © 2019 Xcel Energy Inc. | Xcel Energy is a registered trademark of Xcel Energy Inc. | 19-10-611

Upload: others

Post on 12-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: coloraDo GaS Project · 2019-12-31 · T:\X cel Energy\P roje cts \XCEL_ 034_S E_Metr o_NG_Proje ct\ G_GIS\MXD\Pro ducti on\S MNGP_ PostC ard_Grap hic. mxd ¯ APPLICANT PROPOSED ROUTE

SoutheaSt Metro Natural GaS Project

Project OverviewXcel Energy proposes to install, operate, and maintain approximately five miles of 20-inch-diameter-steel natural gas pipe and associated gas system facilities. The Southeast Metro Natural Gas Project will allow Xcel Energy to continue providing the safe, reliable natural gas service our customers expect in the southeastern Denver metropolitan area. Additionally, the project will provide flexibility in the operation of our natural gas system. The project begins near the intersection of South Yosemite Avenue and East Hampden Avenue in Denver and ends near the intersection of East Caley Avenue and South Troy Circle in Centennial. Project work will occur in parts of unincorporated Arapahoe County, Aurora, Centennial, Cherry Creek State Park, Denver, and Greenwood Village.

Project ScheduleConstruction could start as soon as summer 2020. We anticipate that construction – including restoring work areas and bringing the pipe into service – could be completed by the end of 2021.

We are currently requesting permits for the project. Project schedule is subject to change.

Project CommunicationsOne of the goals of this project is to ensure that we maintain consistent communication with our stakeholders – elected officials, government agencies, businesses, property owners, residents and schools.

Prior to construction starting, businesses, residents and other impacted parties near the project area will be notified about construction start dates and property access needs. Amongst others, notification tactics will include direct mail, electronic and static notification roadside signage and targeted social media.

CHERRY CREEKRESERVOIR

E HAMPDEN AVE

§̈¦25

E BELLEVIEW AVE

CHERRY CREEKSTATE PARK

§̈¦225

S D

AYTO

N S

T

S PE

OR

IA S

T

E UNION AVE

S B

OST

ON

ST

E ORCHARD RD

S YO

SEM

ITE

ST

T:\Xcel Energy\Projects\XCEL_0034_SE_Metro_NG_Project\G_GIS\MXD\Production\SMNGP_ PostCard_Graphic.mxd

APPLICANT PROPOSED ROUTE¯

Contact us

During and after construction, Xcel

Energy will maintain contact through

our dedicated project website,

information line and email list. For

additional information, to sign up

for project updates or to submit

questions, visit XcelEnergySEMetro

GasProject.com, call our project

information line at 866.267.7419, or

email us at Info@XcelEnergySEMetro

GasProject.com.