cognizant powerpoint template … · cognizant overview cognizant is a global leader in providing...
TRANSCRIPT
Cognizant Overview
Cognizant is a global leader in providing solution for IT , consulting, digital, technology and business process outsourcing services, dedicated to helping the world's leading companies build stronger businesses.
Headquartered in Teaneck, New Jersey, United States. Cognizant is included in the NASDAQ-100, S&P 500 indices, Forbes Global 2000 and became Fortune 200 company in year 2017. Cognizant is ranked among the top performing and fastest growing companies in the world.
The company has more than 260,000 employees globally, of which over 180,000 are in India across 10 locations with a plurality in Chennai.
US$ 14.81 billion in revenues for FY 2017.@2018 Cognizant2
Cognizant's Delivery Network
• 75+ delivery and operations centers globally and spread across 38 countries• Occupy 24 million+ built up area and 13.6 million Sq.ft. of Own Facility• Majority of these operations are in hot and humid climate and significant percentage
support 24X7 operations• More than 80% of the space is air-conditioned• Our data centers alone constitute more than 15% of the total energy consumption
@2018 Cognizant3
© 2018 Cognizant4
Type of building Leased, Multi-tenant
Occupied Sq.
foot2,37,938
Seating Capacity 2,807 nos.
No. of associates
as on date2,242 nos.
UPS Capacity4x 176 KVA
(Conventional UPS)
Building
Occupancy
Occupied 2 floors
during 2012
HYD-Raheja Mindspace Bld 20 Overview
© 2018 Cognizant5
Description 2014 2015 2016 2017
% Reduction
in 2015 Vs
2014
% Reduction
in 2016 Vs
2014-15
% Reduction
in 2017 Vs
2016
EPI: KWH/Sq. ft. /Month 0.96 0.92 0.89 0.82 4.17 3.26 7.87
Average Headcount 1828 1878 1904 1764 -2.7 -1.38 7.35
KWH/Person/Month 124.36 117.13 110.65 110.54 5.81 5.53 0.1
Energy Consumption in KWH 2728065 2639750 2528163 2340021 3.24 4.23 7.44
Energy Savings in KWH 88315 111587 188142
Energy Savings Cost in INR 626153 833555 1435523Unit Cost in INR 7.09 7.47 7.63
Reduction in EPI in last 3 years is 14%Reduction in KWH/Person/Month in last 3 years is 11%
Energy Efficient Summary, HYD-MDH Hyderabad
© 2018 Cognizant6
Energy Consumption Trend -2014 to 2017 (In KWH)
0
100000
200000
300000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Energy Consumption Trend
Year -2014 Year -2015 Year -2016 Year -2017
Consumpti
on DetailsJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Year -2014 192932 223070 220310 223569 222027 226751 271061 236005 236153 227781 243201 205205
Year -2015 204558 227649 220417 219889 227988 210835 219870 229964 237281 194221 209994 197357
Year -2016 182192 198560 206976 202498 210379 201365 230077 220865 249293 211527 215546 181987
Year -2017 158649 166050 167601 161875 184860 169150 210258 211810 180628 185381 199086 174130
© 2018 Cognizant7
Comparison with Benchmark Data- BEE
Benchmark Data- BEE for Buildings where Air-Conditioned area is more than
50% of Carpet area Bandwidth for Office Buildings for 3 climate zones
EPI in Kwhr./Sq. M. / Year
Star RatingWarm and
HumidComposite Hot and Dry
1 Star 200-175 190-165 180-155
2 Star 175-150 165-140 155-130
3 Star 150-125 140-115 130-105
4 Star 125-100 115-90 105-80
5 Star Below 100 Below 90 Below 80
Cognizant Raheja Building 20 EPI
Description 2014 2015 2016 2017
EPI: Kwh/SqM/Annum 123.4 119.4 114.4 105.86
© 2018 Cognizant8
Road Map for Raheja Facility as 4 Star Rated Building Reference to BEE Benchmark
Investment Initiatives
Hyderabad is defined under Hot Semi Arid Climate zone as per BEE- Energy
Conservation Building Code. CTS Facility is 6 years old and presently matches to BEE
standards of Three-Star rated building with more than 80% of the space is air-
conditioned.
Objective
• To achieve Specific Energy Consumption equivalent to 4 Star Rated Building
by year 2019
Road map to 4 Star Rated Building
To achieve set objective in coming years, we have planned various Energy
Conservation projects like retrofit of conventional UPS to modular UPS and LED
lightings.
© 2018 Cognizant9
Installation of pull cord switches for 750 fixtures of 4x14w T5 light fitting
with approx. annual energy saving of 33,750 KWH.
Pull cord cost was INR 50 each with total amount of INR 80,000 (1600
nos)
Weekend load reduction by switching of water dispensers, coffee
machines, toilet exhaust, kitchen equipment's and
Strictly maintaining workspace temperature in the range of 24-26 Deg
together annual saving of energy 54,500 KWH.
Energy conservation projects implemented in 2015-2016
© 2018 Cognizant10
Installation of pull cord switches during 2015 - 16
Installation of pull cord switches
• Installation of pull cord switches for 1577 nos of 4x14w T5 light fittings.
BEFORE AFTER
© 2018 Cognizant11
Installation of pull cord switches for total of 1577 fixtures of 4x14w T5
light fitting with approx. annual energy saving of 70,963 KWH.
Energy conservation projects implemented in 2016-2017
© 2018 Cognizant12
Modify 4x14 watt Lamps with 3x14 watt for 1260nos. Annual
saving of energy was approx. 58,021 KWH.
Energy conservation projects implemented in 2017-2018
© 2018 Cognizant13
Energy conservation projects implemented in 2017-2018
BEFORE AFTER
• Remove 1x14 watt Light in 4x14 watt at Workstation area
© 2018 Cognizant14
Strategic Path
EMP Energy Team
• As per EMP – Energy
Team is formed under
Corporate Workplace
Service Head which
includes different
department members.
EHS lead and BEE
certified Energy Auditor
Account
Management
• Yearly Energy
Conservation Plan
• Identifying
opportunities
• Process
improvements
• Implementation
• Periodic Review
•Site specific tailor
made Energy
Management Plan
rolled out for the
period of year
2011-2019
Strategic Path
© 2018 Cognizant15
In-House Energy MonitoringDaily
•Energy consumption updating in FMS Portal
•Top energy profile review (UPS ,Lighting, Cafeteria, Utilities)
Weekly
• Weekly energy call
• Energy Coordinators meeting
Monthly
• MMR
• EPI Review
• Energy profile analyze
0%
47%44%
6%
3%
Computing (UPS)
split ac, Lighting &Raw Power
Ventillation (AHU &HRW)
Cafeteria
Effective Monitoring and Control Methodology
© 2018 Cognizant16
Activity Frequency Responsible Accountable Consulted Informed
Daily Energy
DashboardDaily Facilities Team
CWS Location
ManagerCWS Energy POC CWS Ops lead
Facility Management
System (FMS System)Daily Facilities Team
CWS Location
ManagerCWS Energy POC CWS Ops lead
Energy Review Monthly Facilities Team Energy LocationCWS Energy city
lead
CWS Location
Manager
City review QuarterlyCWS Energy City
lead
CWS India Energy
Manager
CWS Energy India
lead
Sustainability
Team
Update to CWS
Operation LeadQuarterly
CWS Location
Head
Energy India lead
/Sustainability
Team
CWS Ops lead
Update to Energy
CommitteeQuarterly
Sustainability
TeamHead-Sustainability
Energy India lead /
Energy Manager
Dashboard on
Equipment’s & AMCYearly
CWS Energy
City lead
CWS India Energy
ManagerEnergy India lead CWS Ops lead
© 2018 Cognizant17
“Awareness is the greatest agent for Change”
Employees Awareness through
• Various Signage and Posters Competition/
Campaigns.
• Innovations Awareness Campaigns
• Energy and Environment
Awareness Mailers
Employee Awareness
© 2018 Cognizant18
Induction Training
Training
conducted on
basic OHSAS &
EMS Knowledge
for new joiner.
Earth Hour Celebration
• One hour for our Earth as
One Humanity…
Could make a huge
difference…
Vendor & OEM Training
Vendor & OEM
training are based on
job requirement
Best Practices - Training
© 2018 Cognizant20
Way forward (2018-2019)
Installation of LED
lights
Modular UPS Installation Installation of LED lights
UPS Retrofit in 2019 :Removing Existing Conventional UPS 176 KVA X 4 No’s and Install the
150KVA x 2 No’s Modular UPS
• Estimated Annual Electrical Savings (Kwh/Year) is 53000
Lighting retrofit in 2019: LED lights are considered in place of existing lights.
• Estimated Annual Electrical Savings (Kwh/Year) is 41442
To initiate battery operated cars in 2019.