Work Instruction CJ03 - JPN - Display WBS Structure
Purpose
Use this procedure to display a WBS structure.
Trigger
Perform this procedure when you need to display an WBS structure.
Menu Path
Use the following menu path(s) to begin this transaction:
Accounting > Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > CJ03 - Display
Transaction Code
CJ03
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
1/8
Work Instruction CJ03 - JPN - Display WBS Structure
Screen Flow
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
2/8
Work Instruction CJ03 - JPN - Display WBS Structure
Procedure
1. In SAP, start the transaction using the menu path or transaction code.
SAP Easy Access
2. Double-click the Accounting node .
3. Double-click the Project System node .
4. Double-click the Project node .
5. Double-click the Special Maintenance Functions node .
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
3/8
Work Instruction CJ03 - JPN - Display WBS Structure
6. Double-click the Work Breakdown Structure (WBS) node .
7. Click the Scroll-down button .
8. Double-click the CJ03 - Display node .
Display Project: Initial Screen
9. As required, complete/review the following fields:
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
4/8
Work Instruction CJ03 - JPN - Display WBS Structure
Field R/O/C Description
Project Def. R A framework for a business undertaking with a fixed goal to achieve with given resources.The project definition contains dates and organizational information that are binding for the entire project. Example: S.IT.CPC.BGO.TT1
10.
Click the Execute button .
Display Project: WBS Element Overview
11.
Click the Project Definition button .
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
5/8
Work Instruction CJ03 - JPN - Display WBS Structure
Display Project: Project Definition
12.
Click the Exit button .
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
6/8
Work Instruction CJ03 - JPN - Display WBS Structure
Result
You have displayed a WBS structure.
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
7/8
Work Instruction CJ03 - JPN - Display WBS Structure
Scenario
Instructions In this work instruction you are required to:
Display a WBS Structure in SAP ECC 6.0.
Required Data
This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.
Field Value
Project Def. S.IT.CPC.BGO.TT1
Tuesday, July 14, 2009 CO_CJ03_JPN_Display WBS Structure.udc
8/8