cm p time-cost

Upload: ahmed

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 CM P Time-Cost

    1/13

    Time-CostTrade-Off

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Duration and cost of activity depends on the amount an type

    of resources used

    Assuming more workers will normally reduce time and will

    change its cost

    This relationship between activity time and cost called

    time-cost Trade off

  • 7/28/2019 CM P Time-Cost

    2/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Why do we need to reduce project time?

    Finish the project in a predefined deadline date

    Recover early delays to avoid liquidated damages

    Free key resources early for other projects

    Avoid adverse weather conditions that might affect productivity

    Receive an early completion-bonus

    Improve project cash flow

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    What is the way to reduce activity duration?

    Working extended hours (Over time)

    Offering incentive payments to increase the productivity

    Using additional resources

    Using materials with faster installation methods

    Using alternate construction methods or sequence

  • 7/28/2019 CM P Time-Cost

    3/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Activity Time-Cost Relationship

    Decreasing activity duration will increase its cost

    Normal duration

    &

    Normal cost

    Crash duration

    &

    Crash cost

    Time

    Cost

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Activity Time-Cost Relationship

    Crash duration

    &

    Crash cost

    Time

    Cost

    Normal duration

    &

    Normal cost

  • 7/28/2019 CM P Time-Cost

    4/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Activity Time-Cost Relationship

    For simplicity, linear relationship is adopted

    Normal duration

    &

    Normal cost

    Crash duration

    &

    Crash cost

    Time

    Cost

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Activity Time-Cost Relationship (Example)

    Consider the following options

    1 scaffold set, 2 labors, 2 carpenter, 1 foreman

    2 scaffold set, 3 labors, 2 carpenter, 1 foreman

    2 scaffold set, 3 labors, 3 carpenter, 1 foreman

    5

    6

    7

    166

    204

    230

    Crew formationCrew size

    (men)

    Estimated daily

    production

    (square meter)

    Consider the following rates: Labor LE 96/day;carpenter LE 128/day;foreman LE144/day andscaffolding LE60/day

  • 7/28/2019 CM P Time-Cost

    5/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    51 x (1x60 + 2x96 + 2x128 + 1x144) = 33252

    42 x (2x60 + 3x96 + 2x128 + 1x144) = 33936

    37 x (2x60 + 3x96 + 3x128 + 1x144) = 34632

    50.6 (use 51)

    41.2 (use 42)

    36.5 (use 37)

    5

    6

    7

    Cost (LE)Duration (days)Crew

    size

    Activity Time-Cost Relationship (Example)

    8400 Sq meters of scaffolds

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Activity Time-Cost Relationship (Example)

    33000

    33200

    33400

    33600

    33800

    34000

    34200

    34400

    34600

    34800

    30 35 40 45 50 55

    Duration(days)

    Cost(LE)

    1

    2

    3

  • 7/28/2019 CM P Time-Cost

    6/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Project Time-Cost Relationship

    Project direct cost = summation of direct cost of individual

    activities

    Indirect cost comprises site and head office overheads

    Project indirect cost = daily indirect cost x project duration

    Direct cost increases as project duration decreases

    Indirect cost decreases as project duration decreases

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Project Time-Cost Relationship

    Project duration

    Project cost

  • 7/28/2019 CM P Time-Cost

    7/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Shortening Project Duration (Optimum Duration)

    It might be necessary to shorten project duration to meet

    specific deadline

    Or to determine the optimum project duration that is

    correspond to the least project total cost

    Many approaches can be used

    Heuristic Cost-Slope method will be applied

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Procedure for Shortening Project Duration

    Draw the project network.

    Perform CPM calculations and identify the critical path, use

    normal durations and costs for all activities.

    Compute the cost slope for each activity from the following

    equation:cost slope = crash cost normal cost /

    normal duration crash duration

  • 7/28/2019 CM P Time-Cost

    8/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Procedure for Shortening Project Duration

    Start by shortening the activity duration on the critical path

    which has the least cost slope and not been shortened to itscrash duration.

    Reduce the duration of the critical activities with least cost slope

    until its crash duration is reached or until the critical path

    changes.

    When multiple critical paths are involved, the activity(ies) to be

    shorten is determined by comparing the cost slope of the

    activity which lies on all critical paths (if any)

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Procedure for Shortening Project Duration

    Having shortened a critical path, you should adjust activities

    timings, and floats.

    The cost increase due to activity shortening is calculated as the

    cost slope multiplied by the time of time units shortened.

    Continue until no further shortening is possible, and then the

    crash point is reached.

    The results may be represented graphically by plotting project

    completion time against cumulative cost increase.

  • 7/28/2019 CM P Time-Cost

    9/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Example Application

    Consider the following project

    Indirect cost LE 125/day

    Crash to 49 days

    7200

    5300

    4600

    5000

    1050

    3300

    6300

    2580

    3150

    10

    6

    12

    23

    4

    4

    15

    11

    10

    7000

    5000

    4000

    5000

    1000

    3000

    6000

    2500

    3000

    12

    8

    15

    23

    5

    5

    20

    13

    12

    -

    A

    A

    B

    B

    C

    E, C

    F

    D, G, H

    A

    B

    C

    D

    E

    F

    G

    H

    I

    Cost (LE)Duration (day)Cost (LE)Duration (day)

    CrashNormalPreceded byActivity

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    D (23)

    24 47

    20 43

    I (12)

    47 59

    47 59

    H (13)

    34 47

    32 45

    F (5)

    29 34

    27 32

    B (8)

    14 22

    12 20

    A (12)

    0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)

    22 27

    20 25

    G (20)

    27 47

    27 47

    2@40

    2@100 1@502@150

    3@200

    5@60

    1@300

    2@75

    Example Application

    Total direct cost LE 36500

  • 7/28/2019 CM P Time-Cost

    10/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-OffExample Application

    Activity G has the least cost slope 60 LE/day

    Crash G by 2 days, cost increase by 2 x 60

    D (23)

    22 45

    20 43

    I (12)

    45 57

    45 57

    H (13)

    32 45

    32 45

    F (5)

    27 32

    27 32

    B (8)

    14 22

    12 20

    A (12)

    0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)

    22 27

    20 25

    G (18)

    27 45

    27 45

    2@40

    2@100 1@502@150

    3@200

    3@60

    1@300

    2@75

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-OffExample Application

    Activity I has the least cost slope 75 LE/day

    Crash I by 2 days, cost increase by 2 x 75

    D (23)

    22 45

    20 43

    I (10)

    45 55

    45 55

    H (13)

    32 45

    32 45

    F (5)

    27 32

    27 32

    B (8)

    14 22

    12 20

    A (12)

    0 12

    0 12

    C (15)

    12 27

    12 27

    E (5)

    22 27

    20 25

    G (18)

    27 45

    27 45

    2@40

    2@100 1@502@150

    3@200

    3@60

    1@300

  • 7/28/2019 CM P Time-Cost

    11/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-OffExample Application

    Activity A has the least cost slope 100 LE/day

    Crash A by 2 days, cost increase by 2 x 100

    D (23)

    20 43

    18 41

    I (10)

    43 53

    43 53

    H (13)

    30 43

    30 43

    F (5)

    25 30

    25 30

    B (8)

    12 20

    10 18

    A (10)

    0 10

    0 10

    C (15)

    10 25

    10 25

    E (5)

    20 25

    18 23

    G (18)

    25 43

    25 43

    2@40

    1@502@150

    3@200

    3@60

    1@300

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-OffExample Application

    Activity H & G has the least cost slope 100 LE/day

    Crash H & G by 2 days, cost increase by 2 x 100

    D (23)

    18 41

    18 41

    I (10)

    41 51

    41 51

    H (11)

    30 41

    30 41

    F (5)

    25 30

    25 30

    B (8)

    10 18

    10 18

    A (10)

    0 10

    0 10

    C (15)

    10 25

    10 25

    E (5)

    20 25

    18 23

    G (16)

    25 41

    25 41

    1@502@150

    3@200

    1@60

    1@300

  • 7/28/2019 CM P Time-Cost

    12/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-OffExample Application

    Activity C & B has the least cost slope 350 LE/day

    Crash H & G by 2 days, cost increase by 2 x 350

    D (23)

    16 39

    16 39

    I (10)

    39 49

    39 49

    H (11)

    28 39

    28 39

    F (5)

    23 28

    23 28

    B (6)

    10 16

    10 16

    A (10)

    0 10

    0 10

    C (13)

    10 3

    10 23

    E (5)

    18 23

    16 21

    G (16)

    23 39

    23 39

    1@50

    1@200

    1@60

    1@300

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Example Application

    43.9956.12537.8749

    43.5456.37537.1751

    43.5956.62536.9753

    43.6456.87536.7755

    43.7457.12536.6257

    43.8757.37536.5059

    Total cost x 1000 LEIndirect cost x 1000 LEDirect cost X 1000 LEDuratio

    n

  • 7/28/2019 CM P Time-Cost

    13/13

    13/01/2002 Emad Elbeltagi

    Time-Cost Trade-Off

    Example Application

    0

    10

    20

    30

    40

    50

    48 50 52 54 56 58 60

    Time (days)

    LEx

    1000