closed conduit water supply
TRANSCRIPT
![Page 1: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/1.jpg)
CE 516
Design of Water Distribution Systems
In this section, we have learned how to size pipelines and pumps for pipe networks.We will now examine some of the practicalities which need to be considered whendesigning such closed conduit systems. This is a review of section 2.5 in yourtext (which you should read). The primary function of water distribution systemsare to
1. meet the water demands of users while maintaining acceptable pressures
in the system
2. supply water for fire protection at specific locations within the system,
while maintaining acceptable pressures for normal service.
3. provide sufficient level of redundancy to support minimum level of service
during emergency conditions (i.e. power loss or water main failure.)Components
The components of a water distribution system include:
• pipelines - carry water from the treatment facility to the users.
transmission mains - the largest pipes which carry flow from the water
treatment facility to the network. These pipes are often greater than
(D > 600 mm).
feeder mains - (pipelines which feed flow from the transmission main
to the individual pipe networks of every service area (D ∼ 400 - 500 mm)
distribution mains - the grid of pipelines which provides service to
all users (D ∼ 150 - 300 mm)
service lines - pipelines which go from the distribution mains to the
individual house/facility.
The individual lines are sized as per momentum equation (Darcy-Weisbach) andenergy equation (head loss equation.)
Closed Conduit Flow 1 of 12 Design of water distribution systems
![Page 2: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/2.jpg)
CE 516
Components (continued)
• pumps - maintain required pipeline service pressure. Because of variable de-mand requirements multiple pumps or pumps with variable motors are oftenrequired.
booster pumps - maintain required service pressure along long pipelines
fire-service pumps - provide additional capacity for emergency situations
Pumps operate at the intersection of pump performance and network
system curves and must adjust to highly variable demand. As such,
multiple pumps may be required for steady, cyclical, and emergency
demands
• storage facilities - accommodates demand fluctuation by storing excesswater until it’s necessary
ground storage - ground level storage which discharge water to the
system with a pump
elevated storage - storage tank at the elevation required to deliver
water at required pressure (or head).
• Valves - required for removing components and rerouting flows
• Meters - required for monitoring flows
Closed Conduit Flow 2 of 12 Design of water distribution systems
![Page 3: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/3.jpg)
CE 516
Component Design Life
The preferred design life for the various components of water supply systems isgiven with the following table (Chin, Table 3.11)
Component Design Period Design Capacity
(years)
Sources of supply
River indefinite Max daily
Wellfield 10-25 Max daily
Reservoir 25-50 Average annual
Pumps
Low-lift 10 Max daily
High Lift 10 Max hourly
Water Treatment 10-15 Max daily
Service Reservoir 20-25 Working storage +
fire + emergency
Distribution system
Pipe or Conduit 25-50 Max daily + fire OR
max hourly demand
Distribution Grid
Closed Conduit Flow 3 of 12 Design of water distribution systems
![Page 4: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/4.jpg)
CE 516
Operating Pressure of System
The required system pressure demands on several considerations listed below:
• excellent flow to a 3 story building requires 290 kPa
• adequate flow for residential areas requires 240 kPa
• adequate flow to a 20 story building requires 830 kPa**Please note this isn’t desirable because of waste and leak, instead most tallbuildings have their own on site pumps. Generally, pressures of greater than650 kPa should be avoided.
• adequate flow to most systems recommends 410-520 kPaordinary consumption for 10 story buildingsadequate service for sprinklers in buildings of 4-5 storiesadequate fire hydrant serviceadequate margin for fluctuations due to clogging and other losses
Closed Conduit Flow 4 of 12 Design of water distribution systems
![Page 5: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/5.jpg)
CE 516
Water Demand
Demands of the entire population must be considered before designing a waterdistribution system. Possible demand sources include:
• residential
• commercial
• industrial
• public
The average city requires 660 liters/day/person. The distribution of demandbetween all the possible sources is given in the table below.
Typical distribution of water use for an average city (Shin, 2000, Table 3.4)
Category Average use Percent of total
(liters/day)/person
Residential 260
Commercial 90
Industrial 190
Public 70
Loss 50
Total 660
Closed Conduit Flow 5 of 12 Design of water distribution systems
![Page 6: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/6.jpg)
CE 516
Water Demand (continued)
The distribution of average per capita rates among 292 water supply systems inthe U. S. that serve 95 million people is given in the table below.
Average distribution of per capita water demand (Shin, 2000, Table 3.5)
Range Number of Percent of total
(liters/day)/person systems
190-370 30 8
380-560 132 34
570-750 133 34
760-940 51 13
950-1130 19 5
>1140 27 7
Please note: these figures are based on 392 US water supply systems serving 95million people (1984 Water Utility Operating Data, 1986 AWWA)
Closed Conduit Flow 6 of 12 Design of water distribution systems
![Page 7: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/7.jpg)
CE 516
Water Demand Projections
When planning for a water supply system, the water demand at the end of thenetwork design life is generally used as the basis for the project design. Becausethe demand of the system 20 years in the future is not known, it is necessary tomake some kind of prediction or forecasting about the municipality growth. Avariety of Forecasting models exist, including:
• aggregate models - treat the population as a whole
• disaggregate models - break up the population into groups and predict thegrowths of each group. An example of this is cohort analysis (Sykes 1995)which segregates age and gender. These models require large quantities ofdata.
• empirical models - are based solely on data.
Please note that after 10 years, empirical models are as reliable as disaggregatemodels.
Population growth is not generally steady and tends to grow at varying rates.
Closed Conduit Flow 7 of 12 Design of water distribution systems
![Page 8: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/8.jpg)
CE 516
Geometric growth phase - occurs when there are wide open spaces and ismodelled with
Arithmetic growth phase - occurs after the initial growth has leveled off andis modelled with
Declining growth phase - occurs when growth becomes limited by availableresources
Each of the above phases is generally limited to 10 years in duration. For situa-tions when a longer projection is required a long term projection can be approx-imated with an S-curve (most common used is a logistic curve)
Please note, use existing data to determine a & b.Please note, that for projections of less than 10 years a 10% error can be ex-pected, but for projections greater than 20 years a 50% error can be expected.
Closed Conduit Flow 8 of 12 Design of water distribution systems
![Page 9: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/9.jpg)
CE 516
Demand Variations
The demand in a water distribution system varies, daily, weekly, seasonally, andin the case of emergencies such as fires. Typical daily variations are given in thebelow figure (Chin, Figure 3.23)
Closed Conduit Flow 9 of 12 Design of water distribution systems
![Page 10: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/10.jpg)
CE 516
The range of demand conditions are specified with peaking or demand factors.An example of the demand factors is found in the below table (Chin, Table 3.6).
Condition Range of Typical
demand factors value
Daily average in maximum month 1.1-1.5
Daily average in maximum week 1.2-1.6
Maximum daily demand 1.5-3.0
Maximum hourly demand 2.0-4.0
Minimum hourly demand 0.2-0.6
In emergency situations as a result of fires the demand may increase significantly.The most common method for estimating peak demands due to fires is a methodproposed by the Insurance Services Office (ISO, 1980). Their method estimatesthe Needed Fire Flow, NFF, with
NFFi = CiOi(X + P )i
whereC is the construction factor
O is the occupancy factor
X is the exposure factorP is the proximity factori is the location where the flow is needed
The maximum needed fire flow is less than 45,000 L/min
Please see Chin for a more complete discussion of needed fire flows and the re-quired coefficients
Closed Conduit Flow 10 of 12 Design of water distribution systems
![Page 11: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/11.jpg)
CE 516
Required fire flow durations to satisfy insurance requirements (Chin, Table 3.10)
Required fire flow Durations
(L/min) (hours)
<9,000 2
11,000-13,000 3
15,000-17,000 4
19,000-21,000 5
23,000-26,000 6
26,000-30,000 7
30,000-34,000 8
34,000-38,000 9
38,000-45,000 10
Closed Conduit Flow 11 of 12 Design of water distribution systems
![Page 12: closed conduit water supply](https://reader031.vdocuments.us/reader031/viewer/2022020122/54651db0af795969458b49c7/html5/thumbnails/12.jpg)
CE 516
Example
A water-supply system is being designed to serve a population of 200,000 people,with an average per capita demand of 600 L/day/person and a needed fire flowof 28,000 L/min. If the water supply is to be drawn from a river, then whatshould be the design capacity of the supply pumps and water treatment plant?For what must be kept in the service reservoir to accommodate a fire? Whatshould the design capacity of the distribution pipes be?
Solution
assume:a) find design capacity given:
b) determine required flow duration and volume
c) determine design capacity for pipes
Closed Conduit Flow 12 of 12 Design of water distribution systems