![Page 1: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/1.jpg)
Electrical grids - latest evolutions
Clément Robert/ François Gibelli (DGEC-3C)OFATE
Paris 24.11.2016
![Page 2: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/2.jpg)
Connection to electrical grids : why adaptating the rules for the RES ?
According to the previous French regulation, each project promoter had to finance fast the entire costs of connecting its power plant to the grid.
It could happen that the promoter had to fund an entire substation when needing only part of the capacity.
Thus
a deterrent effect for small-volume producers, due to the cost of reinforcement
a risk of freeriders: the following producers may connect to the grid without paying
![Page 3: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/3.jpg)
Due to transformers technical standards, there is a significant risk of oversizing the facilities => risk of barriers to entry, especially for small power plants
A risky environment (without S3RENR) : high barriers to entry
Initial situation : a wind farm (power = 30 MW) available grid capacity = 40 MW => remaining grid capacity for a new project = 10 MW
30 MW
Project: a wind farm (power = 30 MW) => the wind farm can be built only if increasing the substation’s capacity
30 MW
![Page 4: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/4.jpg)
New project: a solar farm (power = 10 MW)No need for a new reinforcement: the project promoter will benefit from wind farm producer-funded capacities=> risk of freeriding
Initial grid capacity = 40 MW Additional grid capacity (funded by wind power producer) = + 40 MW Available grid capacity: 40 + 40 – 30 – 30 = 20 MW
30 MW
30 MW
10 MW
A risky environment (without S3RENR): freeriding
![Page 5: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/5.jpg)
Rethinking the connection solutions:The benefits of the Regional development
Plans for RES Connection (S3RENR)
Planning a long-term development of RES at the regional level
Debating with all the stakeholders
Main responsability: TSO (approved by the Préfet de région)
Fixing a RES target
Forecasting the evolutions of electrical grids
Giving visibility to the whole process for the investors
Flexibility facilities
Partly sharing the costs between all the RES producers through a financial contribution (« quote-part »)
![Page 6: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/6.jpg)
Shared costs in the regional Development Plans or RES Connection
Power plantConnection line Distribution
substation Transmission network
Connectionpoint
Non-shared costs Shared costs
![Page 7: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/7.jpg)
Key elements for setting up a realistic Regional development Plan for RES Connection (S3RENR)
A prospective analysis
Generation opportunities
Grid capacity
Environmental constraints
Issues : avoiding as much as possible the reviewing of the scheme (and thus the financial contribution)
Consulting all major stakeholders
taking into account the issues at stake (political, environmental, economical...)
Feedback
![Page 8: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/8.jpg)
For new generators and those having been modified (Art.4)
Existing generators (Art. 4.2) precised by each member State
Derogations (Art 60-) according to conditions fixed by member State
UE Network code RfG :Requirements for Generators
D
C
B
A
Commongeneral
frequency requirements
Control, monitoring, voltage dip,
automatic response
Active frequency and voltage control
50MW18MW
75MW
1MW
Pmax
![Page 9: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/9.jpg)
Constructive capacities (Art 13)
Frequency variation stability
High frequency behaviour (droop)
Admissible power loss in low frequency
Logical input
Conformity
Compliance certificate (Art. 30)
UE Network code RfG :Requirements for type A Generators
![Page 10: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/10.jpg)
Compliance with type A requirements
Reactive power capacity (Art. 17)
Additionnal contructive capacities
Voltage dip profile (Art 14 and 20 for non synchronous generators)
Logical input for reactive power
Conformity
Active frequency control (LFSM-O), Art 44 and 47 for non synchronous generators
Conformity tests can be replaced by simulations (Art 51 and 54)
Operational notification by Art. 31 and 32
UE Network code RfG :Requirements for type B Generators
![Page 11: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/11.jpg)
Compliance with requirements for type A and B (Art 15)
Reactive power conditions (Art. 18 and 21 for non synchronous)
Low frequency behaviour
Primary and secondary frequency adjustment
Voltage adjustment
Power control
Monitoring instruments
Power variation slopes
Conformity according to Art 45 and 48
Simulations for conformity compliance (Art 52 and 55)
Operational notification Art 31 and 32
UE Network code RfG :Requirements for type C Generators
![Page 12: Clément Robert/ François Gibelli (DGEC-3C) OFATE · Gibelli (DGEC-3C) OFATE Paris 24.11.2016. Connection to electrical grids : why adaptating the rules for the RES ? According to](https://reader034.vdocuments.us/reader034/viewer/2022051807/600530de9e8cae435c65d74b/html5/thumbnails/12.jpg)