clean development mechanism project design document form
TRANSCRIPT
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders‘ comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 2
SECTION A. General description of project activity
A.1. Title of the project activity:
Changshu Municipal Solid Waste Incineration Project
Document version 5
Date completed: 17 January 2011
A.2. Description of the project activity:
The Changshu Municipal Solid Waste Incineration Project (the Project) developed by Changshu Pufa
Thermal Power Energy Co., Ltd. (CPTPE) (the Project Developer) is a municipal solid waste
incineration project located in the city of Changshu, province of Jiangsu, China.
The Project‘s purpose is to reduce greenhouse gas (GHG) emissions by diverting organic waste from
disposal at the Nanhu landfill where anaerobic processes would have caused methane (CH4) emissions.
The Project will incinerate the waste and generate electricity using heat that is a by-product of the
incineration process. This electricity will feed into the Eastern China Power Grid. Thus, in addition to
directly eliminating the methane, the Project will also displace fossil fuel-based electricity generation
that would have emitted additional CO2.
Since 1992, the city of Changshu has been disposing off its waste in an open dumpsite. The waste mainly
comes from residents, but also includes floating debris on rivers, waste materials from business
establishments, trash from the streets and gardens, as well as fiber and cloth scraps from the textile
industry. There is no sorting or recycling of waste being done in the landfill and neither there is a landfill
gas capturing and flaring. In the absence of the project, the waste would continue being filled in the
landfill. The CDM revenues have provided an alternative to uncontrolled or improperly managed
landfills, which is common practice in China1.
The Project will be comprised of two different components: (i) the installation of a waste incinerator
system with a combined capacity of 660 tonnes of waste per day to achieve complete combustion and
restrict dioxin/furan generation. This component will also include the installation of a flue gas cleaning
technology to address pollutant emissions so as to meet international environmental standards; and, (ii)
the use of heat resulting from the incineration to run one electricity generator with an installed capacity
of 12 MW. Total GHG emission reductions (ERs) from the Project are estimated ex-ante around 570,562
tonnes of CO2e for the first 7-year crediting period.
In addition to GHG mitigation, the Project will make a number of additional positive environmental
contributions, as follows:
1 World Bank Working Paper 9, Waste Management in China: Issues and Recommendations, p. 30, May 2005
http://siteresources.worldbank.org/INTEAPREGTOPURBDEV/Resources/China-Waste-Management1.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 3
- The Project will dispose off around 219,780 tonnes of municipal solid waste (MSW) per year through
incineration technology that allows ―hygienization2‖ and reduction in the volume of waste to be disposed
off.
- The Project will provide a model for sustainable and environmentally friendly approaches for local and
provincial governments to better manage MSW and an efficient way to reduce the volume of waste and
demand for landfill space, while helping governments comply with local regulations and environmental
standards.
- Enhanced environmental compliance, which would not occur in the absence of the Project, will bring
about process benefits, such as the mitigation of volatile organic compounds (VOCs) and the prevention
of harmful leachate from entering underground aquifers or waterways. VOCs and leachate are negative
impacts of open dumpsites that typically are not controlled.
In addition to such environmental improvements, the Project will also contribute to sustainable
development by bringing about a range of local social and economic benefits. For example:
the Project will provide for both short- and long-term employment opportunities for local people;
i.e. long-term staff will be used to operate and maintain the system;
by bringing economic development to the area, the Project will make it a better and safer place in
which to live and do business;
the host community in the city of Changshu will have a healthier environment in general because
of improved local air quality, as well as the abatement of water and soil pollution;
the electricity generated using heat from the incineration process will provide an indigenous,
cheap and renewable source of energy, diversifying the country‘s energy sources while
displacing electricity that would otherwise be generated by fossil fuel-fired power plants;
financial returns will be provided to local entities and to local government; and,
proven and reliable renewable energy technology, which also serves as a waste management
process, will be transferred to local counterparts.
A.3. Project participants:
Name of Party involved
(*) ((host) indicates a
host Party):
Private and/or public entity(ies)
project participants(*) (as
applicable)
Kindly indicate if the Party
involved wishes to be considered as
project participant (Yes/No)
China (host)
Changshu Pufa Thermal Power
Energy Co., Ltd No
United Kingdom Endesa Generación S.A
No
2 Advanced treatment (thermal) which results in a higher reduction of E. Coli concentration in waste than conventional treatments
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 4
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
China
A.4.1.1. Host Party(ies):
China
A.4.1.2. Region/State/Province etc.:
Province of Jiangsu
A.4.1.3. City/Town/Community etc.:
City of Changshu
A.4.1.4. Details of physical location, including information allowing the
unique identification of this project activity (maximum one page):
The Changshu Municipal Solid Waste Incineration Project is located on the south-eastern part of Jiangsu
province in China, bordering on Wuxi on the West, Shanghai on the east and Suzhou on the south. The
geographic coordinates of the project are 31°35‘37‘‘N 120°39‘33‘‘E. The Yangtze River crosses through
the north of the city. Jiangsu province consists of 13 districts and counties and covers an area of 1,264
square kilometres (km2) with a population of 1,318 million residents. On the southwest area of urban
Changshu lies the factory site, and on the north, the Nanhu Landfill, close to the Nantang Lake for
fishing and irrigation purposes. The factory site is located 800 meters (m) from the Nanhu Farm and 15
kilometres (km) from Changshu urban area, and occupies a total estimated area of 49,333 m2.
Figure 1: Location of Changshu
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 5
A.4.2. Category(ies) of project activity:
This category would fall within 2 sectoral scopes:
Category 13: Waste handling and disposal; and,
Category 1: Energy industries (renewable / non-renewable sources)
A.4.3. Technology to be employed by the project activity:
The proposed project activity will install two grate incinerator units with MSW handling and incineration
capacity of 330 tonnes per day per unit. The boiler unit associated with the waste incineration and the
electrical generator nameplate is rated at 12 MW, with the total system average output rated at 8.5 MW
based on the 660 tonnes per day of the specified MSW fuel. The Project‘s annual power generation is
expected to be 68,000 MWh3. The Project will deliver approximately 80% of this electricity to China‘s
Eastern Power Grid. The specifications of the equipment are as follows:
Table 1. Equipment specifications
Equipment Supplier Specifications
Waste
incinerator
Keppel Seghers (Belgium) Processing capacity: 660 tonnes per day
Annual accumulated running time: 8,000 h;
Waste combustion temperature: ≥ 850°C ;
Flue gas detention time ≥ 2s;
Heat ignition loss rate of clinker ≤ 5%;
Furnace efficiency: 96.1%;
Maximum Continuous Rating:13.75 t/h,
5,500 kJ/kg;
Waste material liquid water content: 45 -
55%;
Waste density: 0.5 tonnes per m3
Boiler Shanghai Sifang Boiler (Group)
Co., Ltd.
SLC 300-4.0/400
Steam turbine Guangzhou SKODA-JINMA
Turbine Co., Ltd.
Extraction condensing steam turbine N12-
3.8/390
Generator Nanyang Explosion Protection
Group Co.Ltd.
QFW-12-2
Outlet voltage:10.5 kV
DSC equipment Beijing HollySys Co.Ltd. MACs SmartPro
The process of MSW incineration and power output is as follows: About 660 tonnes of waste is daily
delivered to the incinerator and weighted in the weighbridge. The collected waste is unloaded in the
3The electrical generator is nameplate rated at 12 MW, based on equipment manufacturer specifications and energy
content studies of MSW, the incinerator only provides enough raw energy for 8.5 MW of electrical power
generation. Generation could reach 12 MW only with the additional waste handling and incineration equipment
coupled with additional boiler capacity. Thus the plant‘s electrical output on an integrated design basis is 8.5 MW.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 6
waste handling area. Then it is fed into the charging conduit by grab bucket and pushed by feeder
machine into the two grate lines, the place where waste is rolled and stirred for desiccation and then
incinerated. Both of the waste flaring lines are imported from Keppel Seghers of Belgium, each with a
330 tonnes per day nominal capacity, and producing superheated steam with maximum furnace
temperature over 850 degrees Celsius. The waste is usually burned within 2 days. To start up the process
of ignition, diesel oil will be used as auxiliary ignition fuel in case of low temperature of incinerator.
After incineration, all the clinkers will be removed out by the slag remover. The flue gas from MSW
incineration will flow into boiler for steam production and then vented into the atmosphere after
purification. Waste gas is treated in three fields: semi-humid treatment lines, a reactor and a bag filter. A
charcoal injection system has also been installed to treat dioxins and furans. The stack gas from the
incineration may contain small amounts of methane and nitrous oxide. Emissions of N2O and CH4 are
estimated in section B 6.3 and B 6.4. The steam, which totals 88 tonnes per hour from the two furnaces,
supplies one turbo-alternator of 12 MW capacity. Two cooling towers help to condensate the water. The
annual electricity to be produced is 68 GWh of which 80% is expected to be supplied to the grid. All
operation management is automated through centralized computer controls.
Figure 2. Schematic representation of the waste treatment process.
The leachate from the project is diverted for treatment in aerobic conditions. The leachate is first drained
though the filter to screen for any bulky waste and then sent to the first aerobic denitrifying tank for
settlement. The tank is aerated to ensure that the process is aerobic and there is no methane generation. In
the second stage, more purified leachate flows into the second nitrating tank where it also undergoes the
aerobic process. After the leachate flows to the third nitrating tank to undergo the final stage of
purification and then it is discharged into the urban sewage pipeline network where the wastewater is
Waste storage pit
Leachate pit Grate incinerator
Waste heat boiler
Steam turbine
Electric generator
Electricity grid
Leachate treatment
station
WWT Plant
Pump
Drainage
pipeline
networks
Slag pit
Main
condenser
Cooling tower
Landfill
Lime slurry
drying tower
Flue gas
Draft
fan
Steam
Chimney
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 7
treated in Chengxi Sewage Wastewater Treatment Plant. Any leftover mud is sent back to the
incineration process. Schematic representation of leachate treatment process is provided below.
Figure 3. Schematic representation of leachate treatment process.
The Project will transfer environmentally sound technology to Jiangsu by:
training local labor on operation and maintenance;
providing an example of one of the most environmentally beneficial ways of solid waste
management (SWM);
expanding the knowledge on CDM potential for this type of activity.
A.4.4. Estimated amount of emission reductions over the chosen crediting period:
Table 2:Estimated Emission Reductions
Years Annual estimation of emission
reductions in tCO2e
(year 1) 1/08/2011- 31/07/2012 57,545
(year 2) 1/08/2012- 31/07/2013 67,874
(year 3) 1/08/2013- 31/07/2014 76,766
(year 4) 1/08/2014- 31/07/2015 84,445
(year 5) 1/08/2015- 31/07/2016 91,100
(year 6) 1/08/2016- 31/07/2017 96,887
(year 7) 1/08/2017- 31/07/2018 101,941
Total estimated reductions (tCO2e) 576,558
Total number of crediting years 7
Annual average over the crediting period of
estimated reductions (tCO2e) 82,365
Concentrated solution
Filthy mud back to waste
pit
Leachat
e
Automatic filter Bag filter Denitrifying pot Nitrating pot 1
Nitrating pot 2 Hyperfiltration Hyperfiltration pot
Sewage tank Waste pit
Residue
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 8
A.4.5. Public funding of the project activity:
There is no public funding involved in the project.
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
The following approved methodology and tools will be applied in the project:
- AM0025 ―Avoided emissions from organic waste through alternative waste treatment processes‖
Version 12;
- ―Tool to calculate the emission factor for an electricity system‖ Version 2;
- ―Tool to determine methane emissions avoided from disposal of waste at the solid waste disposal
site‖ Version 5;
- ―Tool for demonstration and assessment of additionality‖ Version 05.2.
B.2. Justification of the choice of the methodology and why it is applicable to the project
activity:
AM0025 is applicable under the following conditions:
The project activity involves one or a combination of the following waste treatment options for the fresh
waste that in a given year would have otherwise been disposed of in a landfill:
a. a composting process in aerobic conditions;
b. gasification to produce syngas and its use;
c. anaerobic digestion with biogas collection and flaring and/or its use. The anaerobic digester
processes only the waste for which emission reductions are claimed in this methodology. If the
biogas is processed and upgraded to the quality of natural gas and it is distributed as energy via
natural gas distribution grid, project activities may use approved methodology AM0053 in
conjunction with this methodology. In such cases the baseline scenario identification procedure
and additionality assessment shall be undertaken for the combination of the two components of
the project activity i.e. biomethane emission avoidance and displacement of natural gas;
d. mechanical/thermal treatment process to produce refuse-derived fuel (RDF)/stabilized biomass
(SB) and its use. The thermal treatment process (dehydration) occurs under controlled conditions
of up to 300 degrees Celsius. In case of thermal treatment process, the process shall generate SB
that would be used as fuel or raw material in other industrial process. The physical and chemical
properties of the produced RDF/SB shall be homogenous and constant over time;
e. incineration of fresh waste for energy generation, electricity and/or heat. The thermal energy
generated is either consumed on-site and/or exported to a nearby facility. Electricity generated is
either consumed on-site, exported to the grid or exported to a nearby facility. The incinerator is
rotating fluidized bed of hearth or grate type.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 9
The Changshu Municipal Solid Waste Incineration Project involves the treatment of fresh waste that in a
given year would have otherwise been disposed of in a landfill, and the project activity is based on the
incineration of fresh waste with energy generation for own consumption and for supply to the grid –
option e.
In case of anaerobic digestion, gasification or RDF processing of waste, the residual waste from
these processes is aerobically composted and/or delivered to a landfill.
- This applicability condition is not applicable to the Project activity.
In case of composting, the produced compost is either used as soil conditioner or disposed of in
landfills.
-This applicability condition is not applicable to the Project activity.
In case of RDF/stabilized biomass processing, the produced RDF/stabilized biomass should not
be stored in a manner that may result in anaerobic conditions before its uses.
- This applicability condition is not applicable to the Project activity.
If RDF/SB is disposed of in a landfill, project proponent shall provide degradability analysis on
an annual basis to demonstrate that the methane generation, in the life-cycle of the SB is below
1% of related emissions. It has to be demonstrated regularly that the characteristics of the
produced RDF/SB should not allow for re-absorption of moisture of more than 3%. Otherwise,
monitoring the fate of the produced RDF/SB is necessary to ensure that it is not subject to
anaerobic conditions in its lifecycle.
-This applicability condition is not applicable to the Project activity.
In the case of incineration of the waste, the waste should not be stored longer than 10 days. The
waste should not be store in conditions that would lead to anaerobic decomposition and, hence,
generation of CH4.
- The waste shall not be stored for more than 10 days as capacity of waste handling area is 8,874 m3 and
considering that the waste density is 0.5 m3, the waste would be stored for maximum 6 days.
The proportion and characteristics of different types of organic waste processed in the project
activity can be determined, in order to apply a multiphase landfill gas generation model to
estimate the quantity of landfill gas that would have been generated in the absence of the project
activity.
- The composition analysis of organic waste processed in the project has been done by Department of
Environmental Science and Engineering, Environmental and Chemical Science, Shanghai University.
Copy of the analysis done provided to the DOE.
The project activity may include electricity generation and/or thermal energy generation from
biogas, syngas captured, RDF/stabilized biomass produced, combustion heat generated in the
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 10
incineration process, respectively, from the anaerobic digester, the gasifier, RDF/stabilized
biomass combustor, and waste incinerator. The electricity can be exported to the grid and/or used
internally at the project site. In the case of RDF produced, the emission reductions can be
claimed only for the case where the RDF used electricity and/or thermal energy generation can
be monitored.
-The Project activity includes electricity generation from incineration process.
Waste handling in the baseline scenario shows a continuation of current practice of disposing the
waste in a landfill despite environmental regulation that mandates the treatment of the waste, if
any, using any of the project activity treatment options mentioned above.
- The fact that the MSW would be disposed of in landfill sites is demonstrated in section B.4.and B5. In
addition, there are no enforced regulations for treatment of MWS using any of the project activity
treatment options mentioned above in China.
The compliance rate of the environmental regulations during (part of) the crediting period is
below 50%; if monitored compliance with the MSW rules exceeds 50%, the project activity shall
receive no further credit, since the assumption that the policy is not enforced is no longer
tenable;
- At present, there are no enforced regulations with regards to the MSW and sewage sludge treatment.
Local regulations do not constrain the establishment of RDF production plants/thermal treatment
plants nor the use of RDF/stabilized biomass as fuel or raw material.
- This applicability condition is not related to the Project activity.
In case of RDF/stabilized biomass production, project proponent shall provide evidence that no
GHG emissions occur, other than biogenic CO2, due to chemical reactions during the thermal
treatment process (such as Chimney Gas Analysis report).
- This applicability condition is not related to the Project activity.
The project activity does not involve thermal treatment process of neither industrial nor hospital
waste ;
- The Project activity does not involve thermal treatment process nor hospital waste.
In case of waste incineration, if auxiliary fossil fuel is added into the incinerator, the fraction of
energy generated by auxiliary fossil fuel is no more than 50% of the total energy generated in the
incinerator.
- The fraction of energy generated by auxiliary fossil fuel is no more than 50% of the total energy
generated in the incinerator. The project uses diesel only for the start-up, the rest of the process is self
burning process where no additional fossil fuel is added.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 11
The Project therefore fulfils the conditions of option (e) above, (i.e., incineration of fresh waste for
energy generation electricity) and all above criteria, and thus AM0025 is considered to be applicable to
the project activity.
B.3. Description of the sources and gases included in the project boundary:
According to AM0025, the project boundary is the site of the project activity where the waste is treated.
This includes the facilities for processing the waste, on-site electricity generation and/or consumption,
onsite fuel use and the landfill site. The project boundary does not include facilities for waste collection,
sorting and transport to the project site.
Since the Project provides electricity to a grid, the spatial extent of the project boundary will also include
those plants connected to the energy system, to which the plant is connected.
Table 3: Project Activities and Emission Sources within the Project Boundaries:
Source Gas Justification/explanation
Base
lin
e
Emissions from
decomposition of
waste at the landfill
site
CH4 Included Major emission source in the baseline.
N2O Excluded
N2O emissions are small compared to CH4
emissions from landfills. Exclusion of this
gas is conservative.
CO2 Excluded CO2 emissions from the decomposition of
organic waste are not accounted.
Emissions from
electricity
consumption
CO2 Included Excluded as there is no electricity
generation or consumption in the baseline
CH4 Excluded Excluded as no electricity generation or
consumption in the baseline
N2O Excluded No electricity generation or consumption
in the baseline
Emissions from
thermal energy
generation
CO2 Included Excluded as no thermal energy generation
in the baseline.
CH4 Excluded No thermal energy generation in the
baseline
N2O Excluded No thermal energy generation in the
baseline
Emissions from
transportation CO2
Included Emissions from transportation could be
major source of emissions.
CH4 Excluded Excluded for simplification.
N2O Excluded Excluded for simplification.
Emissions from
residual waste
CO2 Excluded No residual waste in the baseline scenario
CH4 Excluded No residual waste in the baseline scenario
N2O
Excluded No residual waste in the baseline scenario
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 12
P
roje
ct A
ctiv
ity
On-site fossil fuel
consumption due to
the project activity
other than for
electricity
generation
CO2 Included Diesel fuel is used in the project for
ignition and thus it will be account for.
CH4 Excluded Excluded for simplification. This emission
source is assumed to be very small.
N2O Excluded Excluded for simplification. This emission
source is assumed to be very small.
Emissions from
onsite electricity
use
CO2 Included This parameter is excluded since electricity
is generated from waste incineration.
CH4 Excluded This parameter is excluded since electricity
is generated from waste incineration.
N2O Excluded
This parameter is excluded since
electricity is generated from waste
incineration.
Emissions from
thermal energy
generation
CO2 Included Excluded since there is no thermal energy
generation in the project activity
CH4 Excluded excluded since there is no thermal energy
generation in the project activity
N2O Excluded Excluded since there is no thermal energy
generation in the project activity
Direct emissions
from the waste
treatment
processes.
N2O
Included
Maybe an important source of emissions.
N2O can be emitted from incineration.
CO2
Included Can be a major source of emissions
CH4
Included
CH4 may be emitted from stacks from
incineration.
Emissions from
waste water
treatment
CO2
Excluded
CO2 emissions from the decomposition of
organic waste are not accounted.
CH4 Excluded The wastewater is treated aerobically.
N2O Excluded Excluded for simplification. This emission
source is assumed to be very small.
Lea
ka
ge
emis
sio
ns
Emissions from
residual waste
CO2 Excluded
CO2 emissions from the combustion of
biomass are not accounted as GHG
emissions.
CH4 Included Could be potential source of emissions
N2O Included Could be potential source of emissions
Emissions from
transportation
CO2 Excluded There are no incremental emissions due to
transportation in the project activity.
CH4 Excluded Excluded for simplification
N2O Excluded Exclude for simplification
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 13
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
Step 1: Identify alternative scenarios
For the baseline identification, AM0025 states that Step 1 of the latest version of the ―Tool for the
demonstration and assessment of additionality‖ shall be used to identify all realistic and credible baseline
alternatives. In doing so, relevant policies and regulations related to the management of landfill sites
shall be taken into account to determine realistic and credible alternatives for: (i) disposal of MSW in the
absence of the project activity; and (ii) power generation in the absence of the project activity.
In the case of disposal of MSW, in the absence of the project activity, the alternatives to provide the
same output or services that the project activity would provide are to include:
- M1: the proposed project activity (i.e. implemented without CDM revenues);
- M2: disposal of the waste at a landfill where the captured LFG is flared;
- M3: disposal of the waste at a landfill without the capture of landfill gas,
In case of power generation in the absence of the CDM project activity, to provide the same output or
services comparable with the proposed CDM project activity, there would be the following alternatives:
- P1: power generated from by-product of the waste treatment as listed in M1 (i.e. incineration of
waste) above, not undertaken as a CDM project activity;
- P2: existing or construction of a new on-site or off-site fossil fuel fired cogeneration plant;
- P3: existing or construction of a new on-site or off-site renewable based cogeneration plant;
- P4: existing or construction of a new on-site or off-site fossil fuel fired captive power plant;
- P5: existing or construction of a new on-site or off-site renewable based captive power plant ; and,
P6: existing and/or new grid-connected power plants
The credible and realistic scenarios for heat generation are not included as heat generation is not a part of
the baseline neither of the proposed project activity.
Step 2: Identify the fuel for the baseline choice of energy source taking into account national and/or
sectoral policies as applicable
The baseline for the energy source is the Eastern China Grid, whose fuel mix for the year 2005 is
summarized in the table below:
Table 4: Fuel Mix in the Eastern China Grid 2005
Fuel Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total
Thermal MW 13113.5 42506.4 27688.1 11423.2 9345.4 104076.6
Hydroelectric MW 0 142.6 6952.1 749.8 8224.9 16069.4
Nuclear MW 0 0 3066 0 0 3066
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 14
Wind and others MW 253.3 58.8 37.2 0 52 401.3
Total MW 13366.8 42707.8 37743.4 12173 17622.3 123613.
3
Source: China Electricity Yearbook 2006
Therefore, there will not be any supply constraint for the identified baseline scenario source of fuel.
Step 3: Investment analysis - step 2 of the latest approved version of the ―Tool for demonstration and
assessment of additionality‖ is applied in this step to show that the Project activity scenario (M1 and P1)
is not financially attractive scenario. The details of the investment analysis are described in the section
B.5 below.
Step 4: There is only one plausible alternative remains for each baseline scenario— M3 and P6 and thus
this step is not applicable.
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):
AM0025 Version 12 states that the Project‘s additionality should be demonstrated and assessed using the
¨Tool for the demonstration and assessment of additionality¨, Version 5.2 The following table shows the
timeline of the events of the proposed project showing that the CDM benefits were taken into account
when making decision to implement the project.
Table 5. Chronology of events and CDM consideration
Milestones Date Reference
Letter from project sponsor
requesting to consider CDM
revenues to make the project
viable.
3 September 2003 Please refer to Annex 29
FSR is approved 2 January 2004 Please refer to FSR
EIA is approved 8 October 2004 Please refer to Annex 16
Meeting between company Jumbo
Consulting and Shanghai Pudong
Group to discuss the opportunity
of pursuing the project as a CDM
project.
6 July 2004 Please refer to Annex 21
Contract is signed between
Changshu Pucheng Thermal
Power Ltd.‘ (the PP) and
Shanghai Pudong Engineering
Construction Company Ltd where
the PP entrusts the later company
with responsibility for all the
construction management from
5 August 2004 Please refer to Annex 39
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 15
the initial design to final
acceptance of construction.
The board of directors takes
decision to pursue the project as a
CDM project.
25 September 2004 Please refer to Annex 22
Meeting of the project sponsor
with AHL Carbono re sale of
CERs from the project.
20 January 2005 Please refer to Annex 23
Facility setting was signed
between Shanghai Pudong
Engineering Construction
Company and the Shandong
Industrial Facility Setting
Company.
31 March 2005 Please refer to Annex 24
Start of construction 17 October 2005 Please refer to Annex 40
Submission of a new
methodology for incineration of
MSW
22 June 2006 http://cdm.unfccc.int/methodologies/PA
methodologies/publicview.html?status=
pending&meth_ref=NM0174
The plant is commissioned 25 September 2006 Please refer to Annex 28
The project sponsor signs an LOI
with ENDESA
4 December 2006 Please refer to Annex 30
The methodology for incineration
is approved
4 May 2007 EB 31, Annex 5, 04 May 2007
The sponsor signs ERPA with
ENDESA
December 2007 Due to confidentiality of the
information, only made available to the
DOE
PDD of the project is published
for public comments on CDM
website
4 March 2008 http://cdm.unfccc.int/Projects/Validation
/DB/G6IGK3UBY9D81QBH2S72JCE2I
M7E22/view.html
LOA issued by host country DNA 18 March 2009 Please refer to Annex 31
LOA issued by UK DNA 18 November 2010 Please refer to Annex 43
As per Additionality Tool, the following steps are done:
Step 1: Identification of alternatives to the project activity consistent with current laws and
regulations
Step 2: Investment analysis
Step 3: Barriers analysis
Step 4: Common practice analysis
Step 1: Identification of alternatives to the project activity consistent with current laws and
regulations
Sub-step 1a: Define alternatives to the project activity
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 16
In the absence of the project activity, the alternatives to provide the same output or services that the
project activity would provide are to include:
- M1: the project activity (i.e. incineration of waste not implemented as a CDM project);
- M2: disposal of the waste at a landfill where the captured LFG is flared;
- M3: disposal of the waste at a landfill without the capture of landfill gas;
M1 is a plausible option however its financial viability is further discussed in step 2 investment analysis.
M2 is not a plausible scenario since LFG flaring alone, without the electricity generation component,
only adds to project costs without bringing in revenues.
M3 is a common practice and does not involve any additional cost but the cost which would occur in the
baseline scenario. It is the most likely scenario as it constitutes common practice in China due to the
absence of enforced regulations.
In case of power generation in the absence of the CDM project activity, to provide the same output or
services comparable with the proposed CDM project activity, there would be the following alternatives:
- P1: power generated from by-product of the waste treatment as listed in M1 (i.e. incineration of
waste) above, not undertaken as a CDM project activity;
- P2: existing or construction of a new on-site or off-site fossil fuel fired cogeneration plant;
- P3: existing or construction of a new on-site or off-site renewable based cogeneration plant;
- P4: existing or construction of a new on-site or off-site fossil fuel fired captive power plant;
- P5: existing or construction of a new on-site or off-site renewable based captive power plant ; and,
- P6: existing and/or new grid-connected power plants.
Alternative P1 is a plausible scenario however its financial attractiveness is discussed further in Step 2.
The alternatives P2 and P4 are not plausible scenarios and are excluded since there is no heat / electricity
demand in the baseline. Furthermore, no fossil fueled power plants below 135 MW are permitted in
China4.
The Alternative P3 and P5 are also excluded since there is no demand for heat or electricity in the
baseline scenario. No heat or electricity was consumed in the baseline scenario and there was no grid
connection. The only plausible scenario for power generation is alternative P6 - ―Existing and/or new
grid-connected power plants‖.
The credible and realistic scenarios H1 to H7 for heat generation are not included as heat generation is
not a part of the baseline neither of the proposed project activity.
4 General Office of the State Council, Decree no. 2002-6, Notice on Strictly Prohibiting the Installation of Fuel-fired
Generators with the Capacity of 135MW, http://www.gov.cn/gongbao/content/2002/content_61480.htm
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 17
Sub-step 1b: Ensure consistency with mandatory laws and regulations
All remaining alternatives comply with all applicable laws and regulations. The following is a list of
applicable laws on SWM in China:
- Policy 120 on Urban Waste Treatment and Pollution Prevention Technology5: This policy was put
into effect by the Ministry of Construction on 26 June 2000 in order to provide guidelines on
technology and equipment selection for waste collection, establishment of sanitary landfills and
incineration plants, and composting. It sets the criteria for the choice of technology and equipment
depending on local conditions, feasibility of the technology, reliability of the equipment reliability,
and system management. For example, in cities where land resource and natural conditions are
appropriate, landfills are adopted as the basic plan, whereas in cities where economic and waste heat
value conditions are met but where there is a shortage of land, incineration technology is developed.
Proper biological treatment technologies are being actively developed and comprehensive treatment
is encouraged. Random dumping and uncontrolled piling of garbage is forbidden. Waste heat
recovery from garbage incineration, LFG capture, high temperature composting and methane gas
production from organic garbage are encouraged.
- Standard for Pollution Control in MSW Incineration: It was adopted by the State Environmental
Protection Administration and came into effect on 1 January 2002. It sets standards and requirements
for site selection and design of waste incineration plants, waste entry, waste storage technology,
technological performance of incinerators, and pollutant discharge levels, as well as testing methods.
- Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008)6.
According to the Standard for Pollution Control on the Landfill Site of Municipal Solid Waste, the
LFG recovery facilities and flare should be installed when the landfill design capacity are more than
2.5 millions tonne and the landfill body depth are more than 20 meters, and for small scale landfill
the flare or measures to reduce methane emissions should be also used. However, due to financial
and technological difficulties, these regulations have not been widely enforced in China. This is
confirmed by World Bank Report ¨Waste management in China: Issues and Recommendations¨7
published in 2005. In addition, in 2007, the China Ministry of Construction inspected 372 landfill
sites in 31 provinces, cities and autonomous regions in China and it revealed that only 7.24%8 of the
total number of landfills has installed landfill gas recovery and utilization facilities. Therefore, it is
assumed that in the baseline there is no landfill gas capture and flaring and the Adjustment Factor is
assumed to be zero.
The following are China‘s laws on electricity generation using renewable energy sources:
5Policy 120 on Urban Waste Treatment and Pollution Prevention Technology www.mohurd.gov.cn
6 Standard for Pollution Control on the Landfill Site of Municipal Solid Waste (GB16889-2008)
http://www.gov.cn/zxft/ft108/content_957156.htm.
7 World Bank Report ¨Waste management in China: Issues and Recommendations¨ 2005
http://siteresources.worldbank.org/INTEAPREGTOPURBDEV/Resources/China-Waste-Management1.pdf
8 Ministry of Construction of China: Notification of Inspection Outcome on China National Sanitary Landfill Site, Page1, 6 Feb
2007
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 18
- Energy Regulation 13, Management of Electricity Generation from Renewable Energy9: Under the
auspices of the China National Development and Reform Commission, this law has been in effect
since 1 January 2006, governing hydroelectric, wind, biomass10
, solar, geothermal and ocean power
generation. It dictates that such power generation should follow principles of planned construction,
comply with all other laws and regulations, obtain the requisite permits, and take into full
consideration factors such as resource characteristics, market demand and environmental protection.
Annual reports are to be provided to the Energy Administration Department of the Provincial
Government on capacity and power generation.
- Order 33 of the President of the People‘s Republic of China, Law of Renewable Resources of
People‘s Republic of China11
: In effect since 1 January, 2006, this Order establishes the legal
requirements for exploration and development, application, price management/ cost sharing,
economic stimulation, technical support and monitoring measures for renewable energy resources.
It also stipulates state support for
grid connection of renewable resources, compliance with
permitting and licensing policies in accordance with State Council laws - including bidding
procedures, and state backing of clean biomass use - including energy crops - and economic
incentives for projects in rural areas.
Since alternatives to the Project that are consistent with current laws and regulations have been
identified, the Project is considered to be additional under Step 1.
Step 2: Investment analysis
Per the ―Tool for the demonstration and assessment of additionality‖, there are three options that can be
used for investment analysis: (I) simple cost analysis, where no benefits other than CDM income exist
for the Project; (II) investment comparison analysis, where comparable alternatives to the Project exist;
or (III) benchmark analysis.
Sub-step 2a: Determine the appropriate analysis method
Determine whether to apply simple cost analysis, investment comparison analysis or benchmark
analysis (Sub-step 2b).
According to the tool, if the CDM project activity and the alternatives identified in Step 1 generate no
financial or economic benefits other than CDM related income, then apply the simple cost analysis
(Option I). Otherwise, use the investment comparison analysis (Option II) or the benchmark analysis
(Option III). As the Project will generate revenues from electricity sales thus benchmark analysis is
applied. The project‘s internal rate of return (IRR) will be compared against an established benchmark.
Sub-step 2b: Option III. Apply benchmark analysis
The project IRR was calculated in order to provide a comparison with established norms and
expectations in China for comparable investment projects. The assumptions used in this analysis include:
9 Energy Regulation 13, Management of Electricity Generation from Renewable Energy http://www.martinot.info/china.htm
10 Including power generation through direct burning and gasification of agricultural and forest waste, waste incineration and
LFG.
11 Order 33 of the President of the People‘s Republic of China, Law of Renewable Resources of People’s Republic of China,
http://fdi.gov.cn/pub/FDI_EN/Laws/GeneralLawsandRegulations/BasicLaws/P020060620320783430128.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 19
Total static investment cost: 297,500,000 RMB (FSR)
Debt amount: 187,940,000 RMB (FSR)
Plant O&M costs: 622,810,000 RMB (FSR)
Power generation rate: 8,500 kW (FSR)
Total operating hours: 8,000 (FSR)
Total power output: 68,000 MWh (FSR)
Self consumption rate: 20% (FSR assumes 25%, however for conservativeness, the
project assumes 20% for self consumption rate)
Tariff: 0.50 RMB per kWh (FSR)
Tipping fee: 98 RMB per tonne of waste (Jiangsu Province Price Bureau.)
Income tax: 33 % (FSR)
The project includes 64% debt and the rest is equity financing. Under the assumptions above and in the
absence of CDM revenues, investment in the MSW incineration system and generation capacity results in
an IRR of 5.82 % after taxes. This return is not considered by the Project Developer to be adequate to
compensate for the risks and uncertainties of the Project. Furthermore, this IRR compares very poorly to
a comparative IRR hurdle rate for the country. In this case, the financial benchmark rate of return, after
tax, is adopted to be 8% of project IRR for Chinese Power Industries.12
In this comparison, the Project‘s
IRR compares quite unfavorably.
A sensitivity analysis was also applied to the IRR calculation to measure the impact of any potential
changes in the indicated parameters.
Table 6: Sensitivity Indicators (after taxes)
Sensitivity
indicator
Investment Self consumption
rate
O&M
costs
Tariff Production
+10% 4.94% 4.71% 5.15% 6.68% 6.68%
-10% 6.88% 6.89% 6.48% 4.94% 4.94%
-19% 8.15% - - - -
+26 - - 8.00 % 8.00%
-35% - - 8.06% - -
0% 7.92%
The sensitivity analysis shows that even significant beneficial changes across a range of project
performance parameters do not result in the Project‘s IRR surpassing the stated IRR benchmark rate. The
sensitivity on the pessimistic side of the same parameters results in very low returns. As a result of
project volatility, where these performance expectations cannot be definitive, but rather only estimated at
the investment decision point, these results would clearly lead to a no-invest decision by the Project
Developer.
The self-consumption rate is inherently self-limiting: while there is an incentive for the operator to
maximize sales to the grid to maximize revenue, the internal electrical requirements of the plant are
relatively fixed based on design engineering, and the known internal loads of the plant must be met either
12 Interim Rules on Economic Assessment of Electrical Engineering Retrofit Projects, 2003.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 20
by self-consumption or by purchases from the grid. As the sensitivity analysis showed, changing the self-
consumption rate from 20% to 10% (which is actually a reduction of 50% in the overall SC rate) only
increased the IRR to 6.89%. Even total removal of self-consumption only increases the IRR to 7.92%.
Thus, there is no likelihood that any foreseeable change in the self consumption rate would help the
project reach the benchmark.
The IRR reaches the benchmark when there is a decrease of investment costs by 19% and operations and
maintenance costs by 35%. The likeliness of decrease in investment and operation and maintenance costs
is very unlikely as incinerator equipment is imported from Keppel Seghers, Belgium, world known
producer of waste to energy technology. The incinerator requires proper maintenance to keep the
incinerator functioning properly and longer. Therefore, the O&M costs for these kinds of projects is quite
high and the costs cannot be reduced.
The project IRR reaches the benchmark when electricity tariff increases by 26%. The electricity tariff
(0.50 RMB/kWh) used at the time of investment decision is derived from the FSR. The electricity tariff
can be further confirmed through PPA. Based on historical electricity tariff trend13
, the variation in the
tariff by 26% is very unlikely. In China electricity tariff is strictly controlled by the central government.
The electricity tariff cannot be significantly changed without the permission of the central government. In
order to ensure the stability of the price for the whole country, the central government has very strict
control for the basic price such as the tariff and commodity price. The adjustment of electricity tariff
needs to be realized by negotiation of several government departments. Thus, the electricity tariff used
for financial analysis of projects cannot be forecasted and only fixed tariff can be adopted.
The project IRR also reaches the benchmark when the plant production goes up by 26% and it reaches
the 10.7 MW rating capacity. This is very unlikely because the plant has only two incineration lines with
capacity for treating max amount of 660 tonnes of waste per day which can produce steam only to fuel
maximum 8.5 MW of electricity. Increasing the production of electricity by 26% would imply adding
another line of incineration and increasing the amount of waste that can be treated per day. This is would
imply additional investment for the project and securing more volume of waste coming to the incinerator.
The prospect of CDM revenues provides the only significant mitigating factor against the above-
mentioned investment barriers in front of the Project. CDM revenues help the Project overcome these
investment barriers by:
a. offsetting the plant turnkey cost, including both the generation equipment and the MSW
incineration system that provides the fuel source, which in this case heavily front-load the project
economics;
b. improving the financial characteristic of the Project, including an improved debt coverage ratio,
and strengthening project cash flows with more liquid, international hard currency; and,
c. using the CDM future revenues to collateralize potential loans, thus providing the necessary
capitalization for investing in the Project. The combination of energy revenues and CER sales,
along with the use of ERPA revenues as collateral, is key to making overall project financing
viable.
13NDRC Economic Research Institute, A Study of Electricity Tariff Policy for Promoting Energy Conservation and
Renewable Energy Development. June 2005
http://www.efchina.org/csepupfiles/report/2006102695218562.184880057102.pdf/Pricing_IER_EN_final.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 21
Summarizing for the proposed Changshu Municipal Solid Waste Incineration Project, the most plausible
baseline scenario would be the business-as-usual scenario in China, i.e. the continued release into the
atmosphere of the landfill gas, which is a common practice in China. Landfills in China are often not
well operated, despite regulations calling for controlled management of LFG. The main shortcomings
are: (i) the presence of waste pickers, (ii) inadequate slopes, (iii) over-design and premature construction
of subsequent phases, arising in synthetic liners being exposed to the elements and huge additional
volumes of leachate being generated, (iv) inadequate collection and treatment of leachate, (v) insufficient
compacting and waste covering, and (vi) little, if any, landfill gas collection14
. In the absence of the
Project, the landfill would continue to release GHG emissions to the atmosphere from the fresh waste
disposed in the landfill. The proposed project will, at the least, avoid the generation and emission of new
LFG and thus reducing its greenhouse gas impact. Furthermore, in the absence of the project, the
business-as-usual scenario would include fossil fuel-fired electricity from the grid. With the electricity
generation component, electricity generated by the Project and sold to the grid will therefore displace
fossil fuel consumption from baseline levels.
Step 3: Barrier analysis
This step is skipped as step 2 is applied
Step 4: Common practice analysis
Sub-step 4a: Analyze other activities similar to the proposed project activity
As of May 2005, according to the World Bank Study15
, in China, 85% of MSW is treated through
landfilling, 12% through composting, and only 3% by incineration. Most landfills do not meet national
standards16
and projects that capture and/or utilize LFG are very few and limited in China. Currently, the
majority of all MSW is dumped into landfills, most of it in inappropriate dumps, which causes a severe
burden on the environment. The few secured landfill sites are overloaded long before the end of the
planned running time for the site, partly due to the use of unsuitable waste compactors and partly due to
the unexpectedly rapid increase in the volume of waste. Similar project occurring the in region are
discussed in Sub-step 4b. The common practice test is limited to Jiangsu region due to the following
reasons:
The tipping fee (subsidies) and the electricity tariffs are not the same across China and differ based on
economic development of each region, the electricity grid the plant is connected to, etc. As a result, local
government finance and local price levels are different. MSW incineration in China still very much relies
on financial support from the government. For example, the tipping fee in Changshu is 98 RMB/tonne, in
Shandong it is 100 RMB/tonne17
, and in Guangzhou it is 200 RMB/tonne18
.
14 World Bank Working Paper 9. Waste Management in China: Issues and Recommendations, p.40. May 2005. 15 World Bank Working Paper 9, Waste Management in China: Issues and Recommendations, p. 130. May 2005
16 World Bank Working Paper 9, Waste Management in China: Issues and Recommendations, p. 130. May 2005
17 Tonne Yi Bin, Hangzhou, Changzou Report, 21st Century herald, 4 April 2010
http://www.21cbh.com/HTML/2010-4-21/yNMDAwMDE3MzcyNQ.html
18 China Solid Waste Network, Too low waste subsidy in China. 5 May 2008
http://news.solidwaste.com.cn/k/2008-5/2008551314087288.shtml
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 22
In addition, the treatment approach for ash/clinker/wastewater is different and may have different cost
impacts on the company. In some provinces, the government is responsible for the treatment of ash,
clinker and the wastewater. In some provinces the local governments require on-site treatment of ash,
clinker and the wastewater. Jiangsu province has higher requirements for treatment of ash, clinker and
wastewater19
. Changshu project has to treat ash/clinker/wastewater on the site.
Sub-step 4b: Discuss any similar options that are occurring
According to the study done by Institute for Applied Environmental Technology, Germany20
, there were
only 19 municipal waste incinerators as of 2002 in China that treated only 2% of all the MSW produced
in China. Later, the World Bank study conducted in 2005 showed that only 3% of MSW was treated in
MSW incinerators. The list of identified incinerator plants which are operational is provided in Jiangsu
region in the below Table 7.
Table 7. List of incineration projects operational in Jiangsu region
Project name
Location
Invest.
costs
(RMB)
Type
of
contra
ct
Waste
(t/day)
Power
capaci
ty
(MW)
Start
of
opera
tions
Technolo
gy
CDM
projec
t
Project
owner
Costs
(RMB/t
of
waste)
1.Yiduo
Incineration
Project21
Wuxi,
Jiangsu
258,000,
000 BOT 1000
24
MW
Nov
2003
Circulatin
g
Fluidized
Bed
Combusto
r
No
Wuxi
Yiduo
Environ
mental
Protecti
on
Thermal
Power
Co, Ltd.
258,000
2. Suzhou
Waste-to-
energy project,
Phase I22
Suzhou,
Jiangsu
489,443,
000 BOT 1050
18
MW
July
2006
Moving
grate
Incinerati
on
No
China
Everbrig
ht
Internati
onal
Limited
466,136
3. Suzhou
Waste-to-
energy project,
Phase II23
Suzhou
Jiangsu
450,000,
000 BOT 1000
18
MW
June
2009
Moving
grate
Incinerati
on
No
China
Everbrig
ht
Internati
onal
Limited
450,000
19 China Environmental Health Forum, Jiangsu Province Recommendations for Waste Treatement
http://www.huanke.com.cn/bbs/dispbbs.asp?boardid=26&id=1592&page=0&move=next
20 Balz Solenthaler, Rainer Bunge; Waste Incineration in China, Institute for Applied Environmental Technology, Germany, http://umtec.hsr.ch/fileadmin/user_upload/umtec.hsr.ch/Dokumente/Doku-Download/Publikationen/Waste_Incineration_China.pdf 21 Integrated Solid Waste Management, Wuxi New District, PRC, International Environmental Technology Center
http://www.unep.or.jp/Ietc/SPC/news-oct09/WNDmanagement.pdf Page 13-14 22 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php
23 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 23
4. Yixing24
Waste-to-
energy project
Yixing
Jiangsu
238,300,
000 BOT 500 9 MW
June
2007
Moving
grate
Incinerati
on
No
China
Everbrig
ht
Internati
onal
476,600
5.
JiangyinWaste-
to-energy
project Phase
I25
Jiangyin
Jiangsu
388,740,
000 BOT 800
12
MW
May
2008
Moving
grate
Incinerati
on
No
China
Everbrig
ht
Internati
onal
Limited
485,925
6. Changzhou
Waste-to-
energy project26
Changzh
ou
Jiangsu
412,560,
000 BOT 800
12
MW
Nov
2008
Moving
grate
Incinerati
on
No
China
Everbrig
ht
Internati
onal
Limited
515,700
7.
QidongTianyin
g Waste
Incineration for
Power
Generation
Project27
Qidong
Jiangsu
243,840,
000 BOT 600
15
MW
Dec
2008
A two-
phase
grate
furnace of
domestic
technolog
y
Yes
Qidong
Tianyin
g
Environ
ment
Protecti
on Co.,
Ltd
406,400
8. Project
activity
Changsh
u,
Jiangsu
297,500 BOT 660 12
MW
Sep
2006
Two
grate
incinerato
r units
Yes
Changs
hu Pufa
Therma
l Power
Energy
Co.Ltd
428,485
The project 1, Yiduo incineration plant was a first-of-a-kind plant built in the Jiangsu region as a pilot
effort (supported with special incentives28
provided by the government and exempted from paying taxes).
Further, the electricity generated is purchased by the government at 0.57 RMB/kWh29
to encourage
incineration based electricity generation. This project uses Circulating Fluidized Bed Combustor, which
has only half of investment required per tonne of waste treated as it can be seen from the table above
compared with proposed project activity. The Circulating Fluidized Bed Combustor (CFB)30
can burn
other fuels like coal, which other incinerator technologies cannot handle, and as a result it can enjoy a
higher profit from electricity sales. This is one of the big advantages of CFB combustor. The proposed
Changshu incineration plant uses moving grate technology that cannot burn coal and thus only relies on
the waste as a fuel.
24 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php
25 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php
26 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php
27 http://cdm.unfccc.int/Projects/Validation/DB/BMS7L6NKEMVG8EIL670J1CWTVN27E0/view.html 28Integrated Solid Waste Management, Wuxi New District, PRC, International Environmental Technology Center
http://www.unep.or.jp/Ietc/SPC/news-oct09/WNDmanagement.pdf Page 13-14 29 Integrated Solid Waste Management, Wuxi New District, PRC, International Environmental Technology Center
http://www.unep.or.jp/Ietc/SPC/news-oct09/WNDmanagement.pdf Page 13-14
30 http://en.wikipedia.org/wiki/Fluidized_bed_combustion
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 24
The next projects in the table (numbers 2,3,4,5,and 6) are all developed, capitalized, owned, and operated
by a single Hong Kong-registered company (Everbright Environment Co., Ltd31
), which enjoys a unique
tax status which significantly influences their viability. The 5 projects are fully invested by Everbright
Environment Co.,ltd itself, which means they do not need to borrow money from a bank and pay back the
interests. For that reason, they can have a much higher IRR. Everbright is China‘s largest environment
company and is a stock listed company in Hong Kong stock market; it has invested 5.05 trillion RMB on
environment projects in China. The company enjoys a preferential policy with investment in China
mainland (i.e. when the operation period is over 10 years, income tax years 1-5 is tax-free; and from year
6-10, income tax is reduced by 50%32
). And most importantly, considering its equity structure, the
company is considered to be a foreign company and thus cannot apply for an LoA in China for a CDM
project.
Project 7 is a CDM project, so does not need to be considered in the baseline.
To summarise, the primary competitive element in the market (Everbright) can avail itself of a
significantly different regulatory and pricing environment, a situation in which Changshu‘s only method
of achieving the same benefits is to apply for CDM. Other than Changshu, the only other project to
successfully enter the market has been Yiduo, which uses a less expensive domestic technology at lower
cost.
Thus, it can be concluded that the project is additional.
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
Methodology AM0025, Avoided emissions from organic waste through alternative waste treatment
processes- Version 12, addresses project activities where fresh waste originally intended for land filling
is treated either through:
a) Composting process in aerobic conditions;
b) Gasification to produce syngas and its use;
c) Anaerobic digestion with biogas collection and flaring and/or its use;
d) Mechanical/thermal treatment process to produce RDF/SB and its use. The thermal
treatment process (dehydration) occurs under controlled conditions of up to 300 degrees
Celsius. In case of thermal treatment process, the process shall generate SB that would
be used as fuel or raw material in other industrial process. The physical and chemical
properties of the produced RDF/SB shall be homogenous and constant over time;
e) Incineration of fresh waste for energy generation, electricity and/or heat. The thermal
energy generated is either consumed on-site and/or exported to a nearby facility.
Electricity generated is either consumed on-site, exported to the grid or exported to a
nearby facility. The incinerator is rotating fluidized bed of hearth or grate type.
31 China Everbright International China, http://www.ebchinaintl.com/e/business_energy.php 32 China Through a Lens, http://www.china.org.cn/english/features/55645.htm , Article 17
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 25
The Project consists of the diversion of MSW from disposal at the Nanhu landfill and its controlled
incineration. It therefore fulfils the conditions of option e), and thus AM0025Version 12 is considered as
an appropriate methodology for the Project.
―Tool to calculate the emission factor for an electricity system‖ (Version 2) and the ―Tool for determine
methane emissions avoided from disposal of waste at solid waste disposal site‖ Version 5 has been used
to calculate the emission reductions.
Project Emissions:
The project emissions in year y are:
PEy = PEelec,y + PEFuel, on-site,y + PEc,y+PEa,y+PEg,y +PEr,y +PEi,,y +PEw,y +PEco-firing,y (1)
where:
PEy = is the project emissions during the year y (tCO2e)
PEelec,y = Is the emissions from electricity consumption on-site due to the project activity in
year y (tCO2e). This parameter is not included since the electricity consumed onsite is produced by on-
site.
PEfuel, on-site,y = Is the emissions on-site due to fuel consumption on-site in year y (tCO2e). Included
PEc,y = Is the emissions during the composting process in year y (tCO2e). This parameter is excluded
since there is no composting in the project.
PEa,y = Is the emissions from the anaerobic digestion process in year y (tCO2e). This parameter is
excluded since there is no anaerobic digestion in the project.
PEg,y = Is the emissions from the gasification process in year y (tCO2e). This parameter is excluded since
there is no gasification process in the project.
PEr,y = Is the emissions from the combustion of RDF/stabilized biomass in year y (tCO2e)
This parameter is excluded since there is no RDF/stabilized biomass in the project.
PEi,y = Is the emissions from waste incineration in year y (tCO2e). Included
PEw,y = Is the emissions from wastewater treatment in year y (tCO2e). Excluded. The wastewater will be
treated aerobically.
PEco-firing,y= Is the emissions from thermal energy generation/electricity generation from on-site fossil fuel
consumption during co-firing in year y (tCO2e). Excluded. There is no co-firing in the project.
Emissions from fuel use on-site (PEFuel, on-site,y)
PEFuel, on-site,y = Fcons,y * NCVfuel * EFfuel (3)
where:
PEFuel, on-site,y is the CO2 emissions on-site due to fuel consumption on-site in year y (tCO2e);
Fcons,y is the fuel consumption on site in year y (kg);
NCV fuel is the net caloric value of the fuel (MJ/kg);
EFfuel is the CO2 emissions factor of the fuel (tCO2/MJ);
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 26
Emissions from waste incineration (PEi,y)
PEi,,y = PEf,y + PEi,y (11)
where:
PEi,,y is the emissions from waste incineration in year y (tCO2e);
PEf,y is the fossil-based waste CO2 emissions from waste incineration in year y (tCO2e); and,
PEi,y is the N2O and CH4 emissions from the final stacks from waste incineration in year y
(tCO2e).
Emissions from fossil fuel based waste (PEi,fy) is calculated using option 1.
PEf,y=
i Ai * CCWi * FCFi * EFi * 12
44
(12)
where:
PEf,y is the fossil-based waste CO2 emissions from waste incineration in year y (tCO2e);
Ai is the amount of waste type i fed into the waste incineration plant (t/yr);
CCWi is the fraction of carbon content in waste type i (fraction);
FCFi is the fraction of fossil carbon in waste type i (fraction);
EFi is the combustion efficiency for waste type i (fraction); and,
44/12 is the conversion factor (tCO2/tC).
Baseline emissions:
According to AM0025 to calculate the baseline emissions the following equation is used:
BEy = (MBy - MDreg,y) + BEEN,y (19)
where:
BEy is the baseline emissions during the year y (tCO2e);
MBy is the methane produced in the landfill in the absence of the project activity in year y
(tCH4);
MDreg,y is methane that would be destroyed in the absence of the project activity in year y (tCH4);
BEEN,y is the baseline emissions from generation of energy displaced by the project activity in
year y (tCO2e).
Adjustment factor (AF)
MDreg,y = MBy *AF (20)
Where AF = is adjustment factor for MBy (%)
The AF is assumed to be 0 since the landfill in the baseline had no landfill gas capture and flaring and
neither it was mandated by the contractual agreement. The regulations in the country require new landfill
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 27
to install the landfill gas capture system where possible but does not specify the amount of methane to be
captured and this regulation is systematically not enforced. The compliance rate in the country is below
7% according to the study performed in 2007 by the China Ministry of Construction, which inspected
372 landfill sites in 31 provinces, cities and autonomous regions in China and it revealed that only
7.24%33
of the total number of landfills has installed landfill gas recovery and utilization facilities.
The ‗Adjustment Factor‘ shall be revised at the start of each new crediting period taking into account the
amount of GHG flaring that occurs as part of common industry practice and/or regulation at that point in
the future.
Rate of compliance
In cases where there are regulations that mandate the use of one of the project activity treatment options
and which is not being enforced, the baseline scenario is identified as a gradual improvement of waste
management practices to the acceptable technical options expected over a period of time to comply with
the MSW Management Rules. The adjusted baseline emissions (BEy,a) are calculated as follows:
BEy,a = BEy * ( 1 RATECompliance
y) (21)
Where:
BEy= Is the CO2-equivalent emissions as determined from equation 14
RATECompliance
y=Is the state-level compliance rate of the MSW Management Rules in that year y. The
compliance rate shall be lower than 50%; if it exceeds 50% the project activity shall receive no further
credit.
In such cases BEy,a should replace BEy in Equation (25) to estimate emission reductions. The compliance
ratio RATECompliance
y shall be monitored ex post based on the official reports for instance annual reports
provided by municipal bodies.
Methane generation from the landfill in the absence of the project activity (MBy)
MBy = BECH4,SWDS,y (22)
The amount of methane that is generated each year (MBy) is calculated as per the latest version of the
approved ―Tool to determine methane emissions avoided from disposal of waste at a solid waste disposal
site‖ considering the following additional equation:
Methane generation from the landfill in the absence of the project activity (MBy) will be calculated
according to the ―Tool to determine methane emissions avoided from disposal of waste at a solid waste
disposal site Version 5. The calculation is based on a multi-phase first order decay (FOD) model, where
the amount of methane produced in the year y (BECH4,SWDS,y) is calculated as follows:
33 Ministry of Construction of China: Notification of Inspection Outcome on China National Sanitary Landfill Site, Page1, 6 Feb
2007
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 28
BECH4,SWDS,y = φ (1-f) ·GWPCH4 · (1-OX) · F · DOCf · MCF ·
y
x 1
j Wj,x · DOCj · e
-Kj (y-x) · (1- e
-Kj)
where:
BECH4,SWDS,y are methane emissions avoided during the year y from preventing waste disposal at
the solid waste disposal site (SWDS) during the period from the start of the project activity to the
end of the year y (tCO2e);
φ is the model correction factor to account for model uncertainties (0.9)
f is the fraction of methane captured at the SWDS and flared, combusted or used in another
manner;
GWPCH4 is the Global Warming Potential of methane, valid for the relevant commitment period;
OX is the oxidation factor, reflecting the amount of methane from SWDS that is oxidized in the
soil or other material covering the waste;
F is the fraction of methane in the SWDS gas (volume fraction) (0.5);
DOCf is the fraction of degradable organic carbon (DOC) that can decompose;
MCF is the methane conversion factor;
Wj,x is the amount of organic waste type j prevented from disposal in the SWDS in the year x
(tonnes);
DOCj is the fraction of degradable organic carbon (by weight) in the waste type j;
kj is the decay rate for the waste type j;
j is the waste type category (index);
x is the year during the crediting period: x runs from the first year of the first crediting period (x
= 1) to the year y for which avoided emissions are calculated (x = y); and,
y is the year for which methane emissions are calculated.
Baseline emissions from generation of energy displaced in Scenario 1 is determined by:
BEEN,y = BEelec, y + BEthermal,y (23)
where:
BEelec, y is the baseline emissions from electricity generated utilizing the biogas collected in the
project activity and exported to the grid (tCO2e); The EF is fixed for the crediting period. and,
BEthermal,y is the baseline emissions from thermal energy produced utilizing the biogas collected in
the project activity displacing thermal energy from on-site/off-site fossil fuel fueled boiler
(tCO2e)
BEelec, y = EGd,y * CEFd (24)
where:
EGd,y is the amount of electricity generated utilizing combustion heat from incineration and
exported to the grid in the project activity during the year y (MWh); and,
CEFd is the carbon emissions factor for the displaced electricity source in the project scenario
(tCO2e/MWh).
As the proposed project activity does not include a thermal component BEthermal,y equals zero.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 29
As per AM0025, CEFd is calculated according to the ¨Tool to calculate the emission factor for an
electricity system¨ since the generated electricity from incineration will displace the electricity that
would have been generated by other power plants connected to the baseline grid. The procedure for
calculating CEFd is as follows:
Step1. Identify the relevant electric power system
Using the boundary definitions of the Chinese NDRC34
, The spatial extent of the project boundary
includes the proposed project and all power plants connected physically to the East China Power Grid
that the CDM project power plant is connected to. The East China Power Grid is defined as the project
electricity system, which consists of independent province-level electricity systems including Shanghai,
Jiangsu, Zhejiang, Anhui and Fujian province that can be dispatched without significant transmission
constraints. The connected electricity system is Centre China Power Grid and Yangcheng Power Plant,
which is connected by transmission lines to the project electricity system. Power plants within the
connected electricity system can be dispatched without significant transmission constraints but
transmission to the project electricity system has significant transmission constraint.
Step 2.Choose whether to include off-grid power plants in the project electricity systems (optional)
The project chose not to choose this option.
Step 3. Select an operating margin (OM) method
The calculation of the operating margin emission factor (EFgrid,OM,y) is based on one of the following
methods:
(a) Simple OM; or
(b) Simple adjusted OM; or
(c) Dispatch data analysis OM; or
(d) Average OM.
Dispatch data is unavailable for the East China Power Grid; therefore, this PDD selects option (a), the
Simple OM method, to calculate this parameter. The low-cost/must-run resources constitute less than
50% of total East China Power Grid generation in each of the five most recent years for which data is
available. Therefore, the option a) Simple OM is applicable.
In calculating the simple OM, the ex-ante option of a 3-year generation-weighted average is chosen,
and is based on the most recent data available at the time of submission of the CDM-PDD to the DOE
for validation, thus removing the requirement to monitor and recalculate the emissions factor during
the crediting period. For the calculation, 2003, 2004 and 2005 are chosen as the data for these is the
most recent.
Step 4. Calculate the operating margin emission factor according to the selected method
34 http://cdm.ccchina.gov.cn/web/index.asp.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 30
The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per unit
net electricity generation (tCO2/MWh) of all generation power plants serving the system, not including
low-cost/must-run power plants/units. It is calculated based on data on the total net electricity generation
of all power plants serving the system and the fuel types and total fuel consumption of the project
electricity system (option B) because (a) the necessary data for option A is not available, (b) nuclear and
renewable power generation are considered as low-cost/ must-run power sources and the quantity of
electricity supplied to the grid by these sources is known and (c) off-grid power plants are not included in
the calculation. Electricity imports are treated as one power plant m.
y
i
yiCOyiyi
yOMsimplegridEG
EFNCVFC
EF )( ,,2,,
,, (7)
Where:
EFgrid, OMsimple, y = Simple operating margin CO2 emission factor in year y (tCO2/MWh)
FCi,y = Amount of fossil fuel type i consumed in the project electricity system in year y (mass or volume
unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ / mass or volume unit)
(country-specific values are used)
EFCO2, i, y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGy = Net electricity generated and delivered to the grid by all power sources serving the
system, not including low-cost / must-run power plants / units, in year y (MWh)
i = All fossil fuel types combusted in power sources in the project electricity system in year y
y = The relevant year as per the data vintage chosen in Step 3
Step 5. Identify the group of power units to be included in the build margin
The sample group of power units m used to calculate the build margin consists of either:
a. The set of five power units that have been built most recently; or
b. The set of power capacity additions in the electricity system that comprise 20% of the system
generation in (MWh) and that have been built most recently.
However, due to the fact that data on electricity generation of each power plant / unit in the grid is
currently not available in P. R. China option (b) the set of power capacity additions in the electricity
system that comprises 20% of the system generation capacity (in MW) and that have been built most
recently is selected.
Since data on the electricity generation of each individual power plant / unit in the grid is not available in
P.R. China, power plants registered as CDM project activities cannot be isolated and are taken into
account in the build margin. The ―Tool to calculate the emission factor for an electricity system‖ offers
the choice between two data vintages to calculate the BM:
Option 1. For the first crediting period, the build margin emission factor is calculated ex-ante based on
the most recent information available on units already built for sample group m at the time of CDM-PDD
submission to the DOE for validation. For the second crediting period, the build margin emission factor
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 31
should be updated based on the most recent information available on units already built at the time of
submission of the request for renewal of the crediting period to the DOE. For the third crediting period,
the build margin emission factor calculated for the second crediting period should be used. This option
does not require monitoring the emission factor during the crediting period.
Option 2. For the first crediting period, the build margin emission factor shall be updated annually, ex
post, including those units built up to the year of registration of the project activity or, if information up
to the year of registration is not yet available, including those units built up to the latest year for which
information is available. For the second crediting period, the build margin emissions factor shall be
calculated ex ante, as described in Option 1 above. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used. The BM emission factor
(EFgrid, BM, y) is calculated ex-ante using the data from 2003, 2004 and 2005 available in the China
Energy Statistics Yearbook of 2004, 2005 and 2006. These data from the yearbook remains fixed during
the first crediting period and will be updated for the second crediting period.
Option 1 is selected.
Step 6. Calculate the build margin emission factor
According to the ―Tool to calculate the emission factor for an electricity system‖, EFgrid,BM,y is the
generation-weighted average emission factor of all power units m during the most recent year y for which
power generation data is available. However, due to the fact that data on both electricity generation and
emission factor of each power plant / unit in the grid is currently not available in P.R. China (see Step 3),
EB guidance on the estimation of the build margin in P.R. China can also be applied for the purpose of
estimating the BM emission factor and EFgrid, BM, y is calculated as follows:
m
ym
mi
ymELym
EG
EFEG
,
,
,,,
yBM, gridEF (13)
Where:
EFgrid,BMs, y = Simple operating margin CO2 emission factor in year y (tCO2/MWh);
EGm, y = Net electricity generated and delivered to the grid by m in year y;
EFEL, m, y = Emission factor in year y (tCO2/MWh);
m = Power units included in the build margin;
y = Most recent historical year for which power generation data is available.
The CO2 emission factor of each power unit m (EFEL,m,y) should be determined as per the guidance in
Step 4 (a) for the simple OM, using options A1, A2 or A3, using for y the most recent historical year for
which power generation data is available, and using for m the power units included in the build margin.
For off-grid power plants, EGm,y should be determined as per the guidance in Step 4.
Because capacities of technologies using coal, oil and gas cannot be separated from the total thermal
power generation from publicly available statistics, the following method is used for the calculation:
first, use the energy balance data of the most recent year available and calculate the percentages of CO2
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 32
emissions of power generation using solid, liquid and gas fuel in the total CO2 emission. Second,
calculate grid thermal power emission factors, using the percentages (as weights) and emission factors of
technologies corresponding to best available efficiencies. Lastly, the thermal power emission factor is
multiplied by the percentage of thermal power in the newest 20% capacity in the grid, and the result is
the Build Margin emission factor of the grid. Note that the data used can not distinguish the capacity
installed in coal, fossil fuel, and gas from total fire power generation. Therefore, the calculation used as
following:
Detailed steps and formulas are shown below:
Step 1: Calculate the proportions of CO2 emissions corresponding to solid, fluid and gas fuels used for
power generation to the total emissions.
ji
jiyji
jCOALi
jiyji
COEFF
COEFF
,
,,,
,
,,,
Coal
ji
jiyji
ji
jiyji
COEFF
COEFF
,
,,,
,Oil
,,,
Oil
ji
jiyji
ji
jiyji
COEFF
COEFF
,
,,,
,GAS
,,,
Gas
where:
Fi, j, y represents the consumption of fuel i (tce) of the jth
province in the yth year.
COEFi, j, y represents the emission factors of fuel i (tCO2/tce). Here the carbon content and oxidation rate
of fuel i consumed in the y year are considered.
COAL, OIL and GAS are the subscript sets for solid, fluid and gas fuels respectively.
Step 2: Calculate the corresponding thermal power emission factor.
Adv,GasGasAdv,OilOilAdv,CoalCoalThernal EFEFEFEF
EFCoal,Adv, EFOil,Adv and EFGas,Adv correspond respectively to the emission factors of coal, fuel oil and gas
power generation technologies with commercialized optimal efficiencies. For specific parameters and
calculation, please see Appendix 2.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 33
Step 3: Calculate the grid BM.
Thernal
Total
Thernaly,BM EF
CAP
CAPEF
Here, CAPTotal is the total new capacity, and CAPThermal is the new thermal power capacity.
Step 7. Calculate the combined margin emission factor
The combined margin emission factor is calculated as follows:
EFgrid, CM,y = EFgrid, OM,y × wOM,y + EFgrid,,BM,y × wBM,y (14)
Where:
EFgrid,BM,y Build margin CO2 emission factor in year y (tCO2/MWh)
The following default values should be used for wOM and wBM:
• Wind and solar power generation project activities: wOM = 0.75 and wBM = 0.25 (owing to their
intermittent and non-dispatchable nature) for the first crediting period and for subsequent crediting
periods;
• All other projects: wOM = 0.5 and wBM = 0.5 for the first crediting period , and wOM = 0.25 and wBM =
0.75 for the second and third crediting period, unless otherwise specified in the approved methodology
which refers to this tool.
The following default values will be applied for wOM and wBM for the project:
wOM = 0.5 and wBM = 0.5 for the crediting period.
Leakage:
The sources of leakage considered in the methodology are CO2 emissions from off-site transportation of
waste materials In case of waste incineration, leakage emissions from residual waste of MSW incinerator
should be accounted for. Positive leakage that may occur through the replacement of fossil-fuel based
fertilizers with organic composts are not accounted for. Leakage emissions should be estimated from the
following equation:
Ly = Lt,y + Lr,y + Li,y + Ls,y (28)
Where:
Lt,y = Is the leakage emissions from increased transport in year y (tCO2e). Not included.
Lr,y = Is the leakage emissions from the residual waste from the anaerobic digester, the gasifier, the
processing/combustion of RDF/stabilized biomass, or compost in case it is disposed of in landfills in year
y (tCO2e). Not applicable.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 34
Li,y = Is the leakage emissions from the residual waste from MSW incinerator in year y
(tCO2e). Included
Ls,y = Is the leakage emissions from end use of stabilized biomass. Not included, not applicable.
The incineration plant is located on the site of the landfill where the waste would otherwise be disposed
off, thus there are no incremental emissions due to transportation of waste as the waste would have been
transported to the site in the baseline scenario. Thus only the leakage from residual waste of MSW
incinerator is accounted for.
Leakage emissions from the residual waste from MSW incineration (Li,y)
In case of waste incineration, leakage emissions from the residual waste of MSW incinerator should be
accounted for using the following equations:
If the residual waste from the incinerator contains up to 5% residual carbon, then:
Li,y = A residual *FC residual*44/12 (31)
If the residual waste from the incinerator contains more than 5% residual carbon, then;
Li,y= A residual,y *0.05*44/12+Aresidual,y *(FC residual – 0.05) *16/12*21 (32)
Where:
L1,y = is the leakage emissions from the residual waste of MSW incinerator in year y (tCO2e)
Aresidual = is the amount of the residual waste from the incinerator (t/yr)
FCresidual=is the fraction of residual carbon contained in the residual waste (%)
44/12= is a factor to convert from carbon to carbon dioxide
16/12 = is factor to convert from carbon to methane
21= is the global warming potential of methane (tCO2/tCH4)
Emission Reductions:
To calculate the emission reduction from the anaerobic digestion and electricity generation project
activity, the following equation is applied:
ERy = BEy – PEy – Ly (36)
where:
ERy is the emissions reductions in year y (tCO2e);
BEy is the emissions in the baseline scenario in year y (tCO2e);
PEy is the emissions in the project scenario in year y (tCO2e); and
Ly is the leakage in year y (tCO2e).
B.6.2. Data and parameters that are available at validation:
Data / Parameter: Φ
Data unit: -
Description: Model correction factor to account for model uncertainties
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 35
Source of data used: Default value from ―Tool to determine methane emissions avoided from
disposal of waste at a solid waste disposal site‖
Value applied: 0.9
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
Default value from ―Tool to determine methane emissions avoided from
disposal of waste at a solid waste disposal site‖
Any comment: N/A
Data / Parameter: OX
Data unit: -
Description: Oxidation factor (reflecting the amount of methane from SWDS that is oxidized
in the soil or other material covering the waste)
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories, Chapter 3
Table 3.2
Value applied: 0.1
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
The baseline landfill is managed and covered with CH4 oxidising material.
Using IPCC default value which is conservative
Any comment: N/A
Data / Parameter: F
Data unit: -
Description: Fraction of methane in the SWDS gas (volume fraction)
Source of data used: 2006 IPCC Guidelines for National Greenhouse Gas Inventories, volume 5,
page 3.15
Value applied: 0.5
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
A default value of 0.5 is recommended by IPCC.
Any comment: This factor reflects the fact that some degradable organic carbon does not
degrade, or degrades very slowly, under anaerobic conditions in the SWDS.
Data / Parameter: DOCf
Data unit: -
Description: Fraction of degradable organic carbon (DOC) that can decompose
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 36
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories Value applied: 0.5
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Using 2006 IPCC Guidelines for default value
Any comment: N/A
Data / Parameter: MCF
Data unit: -
Description: Methane conversion factor
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories
Value applied: 1.0
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
The following IPCC definition is used:
1.0 for anaerobic managed solid waste disposal sites. These must have
controlled placement of waste (i.e., waste directed to specific deposition
areas, a degree of control of scavenging and a degree of control of fires)
and will include at least one of the following:
(i) cover material;
(ii) (ii) mechanical compacting; or
(iii) (iii) leveling of the waste;
The placement of waste at the landfill is controlled and cover material and
levelling of the waste. Therefore, 1.0 for anaerobic managed solid waste
disposal sites is justified.
Any comment: N/A
Data / Parameter: DOCj
Data unit: -
Description: Fraction of degradable organic carbon (by weight) in the waste type j
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories (adapted from
Volume 5, Tables 2.4 and 2.5) Value applied: Waste type DOCj wet waste
Pulp, paper and cardboard 40
Wood & Straw (excl. lignin) 43
Garden/Park Waste (organic putrescibles) 20
Food, food waste, beverages and tobacco 15
Textiles 24
Glass, plastic, metal and other inert waste 0
Justification of the
choice of data or
Using 2006 IPCC Guidelines for default value
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 37
description of
measurement methods
and procedures
actually applied:
Any comment: N/A
Data / Parameter: K
Data unit: -
Description: Decay rate for the waste type j
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories (adapted from
Volume 5, Table 3.3)
Value applied: Determined as per ―Tool to determine methane emissions avoided from
disposal of waste at a solid waste disposal site‖.
MAT-20 C35
MAP-1,000 mm36
PET-923 mm37
Based on this data the climate is classified as Boreal and Temperate Wet.
Waste type Kj
Pulp, paper and cardboard 0.060
Wood & Straw (excluding lignin) 0.030
Garden/Park Waste (organic putrescibles) 0.100
Food, food waste, sewage sludge,
beverages and tobacco 0.185
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Recommended by IPCC 2006 Guidelines for National Greenhouse Gas
Inventories (adapted from Volume 5, Table 3.3)
Any comment: N/A
Data / Parameter: CEFelec
Data unit: tCO2/MWh
Description: Emission factor of displaced electricity by the project activity
Source of data used: As per ‖Tool to calculate the emission factor for an electricity system‖
Value applied 0.9047
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
Calculated as per above tool. The EF recalculated at the renewal of each
crediting period.
35 http://www.jiangsu.net/city/city.php?name=changshu#Geography_Resources_Climate
36 http://www.jiangsu.net/city/city.php?name=changshu#Geography_Resources_Climate
37 http://gupea.ub.gu.se/bitstream/2077/21737/3/gupea_2077_21737_3.pdf, Page 34. Figure 3
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 38
Any comment: Calculated as per appropriate methodology at start of crediting period
Data / Parameter: NCVfuel
Data unit: MJ/ kg of fuel
Description: Net calorific value of fuel
Source of data used: China Energy Statistical Yearbook 2006
Value applied: 42.6
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Fixed ex-ante
Any comment: N/A
Data / Parameter: EFfuel
Data unit: tCO2/MJ
Description: Emission factor of the fuel
Source of data used: IPCC 2006 Guidelines for National Greenhouse Gas Inventories
Value applied: 74,800 kg/TJ
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
2006 IPCC Guidelines. Volume 2: Energy, Chapter 2: Stationary Combustion.
Table 2.2. Fixed ex-ante
Any comment: N/A
Data / Parameter: AF
Data unit: %
Description: Methane destroyed due to regulatory or other requirements
Source of data used: Local and/or national authorities
Value applied 0%
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
The AF was set at 0%. This value is justified based on the fact that the
regulatory requirements do not indicate any specific amount of gas collection
and destruction or utilization and that in practice, no amounts of LFG are
actually flared. It represents the common practice in China. Changes in
regulatory requirements, relating to the baseline landfill(s) will be monitored in
order to update the adjustment factor (AF). This is done at the beginning of each
crediting period.
Any comment: N/A
Data / Parameter: CCWi
Data unit: Fraction
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 39
Description: Fraction of carbon content in waste type i
Source of data used: 2006 IPCC guidelines
Value applied: MSW Component
Total carbon content in % of dry
weight
Paper/Cardboard 46
Textiles 50
Food waste 38
Wood 50
Garden & Park waste 49
Plastic 75
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Default values from 2006 IPCC Guidelines for National Greenhouse Gas
Inventories. Volume 5: Waste, Chapter 2: Waste Generation, Composition and
Management Data, Table 2.4
Any comment: N/A
Data / Parameter: EFN2O
Data unit: kg N2O/tonne waste
Description: Aggregate N2O emission factor for waste incineration.
Source of data used: Default values from 2006 IPCC Guidelines for National Greenhouse Gas
Inventories. Volume 5, Chapter 5, Table 5.6 Continuous incineration
Value applied: 0.05 kg N2O/tonne waste (on wet weight basis)
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Default data for continuous incineration for stoker technology
Any comment: N/A
Data / Parameter: EFCH4
Data unit: Kg CH4/ tonne waste
Description: Aggregate CH4 emission factor for waste incineration.
Source of data used: Default values from 2006 IPCC Guidelines for National Greenhouse Gas
Inventories. Volume 5, Chapter 5: Continuous incineration . Table 5.3
Value applied: 0.0002 kg CH4/tonne waste (on wet weight basis)
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied:
Default data for continuous incineration for stoker technology
Any comment: N/A
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 40
B.6.3. Ex-ante calculation of emission reductions:
Baseline emissions:
There are two gases and two sources associated with the baseline:
a. CH4 emissions from waste diverted to the incineration facility, which would have otherwise been
disposed at Nanhu landfill;
b. CO2 emission from the displacement of fossil fuel-based grid electricity generation.
The baseline emissions from the anaerobic digestion project activity are determined by the following
formula:
BEy = (MBy - MDreg,y) + BEEN,y
The methane produced in the landfill in the absence of this specific project activity in year y (MBy) is
calculated according to the Tool to determine methane emissions avoided from disposal of waste at a
solid waste disposal site based on a multi-phase first order decay (FOD) model where the amount of
methane produced in the year y (BECH4,SWDS,y) is calculated as follows:
BECH4,SWDS,y = φ · (1-f) · GWPCH4 · (1-OX) · 12
16
· F · DOCf · MCF ·
y
x 1
j Wj,x · DOCj · e
-Kj (y-x) · (1- e
-Kj)
Input values to the multiphase model are specified in table below:
Table 8: Inputs to the Multi-phase Model
Parame
ter
Note Value Used
Φ Model correction factor 0.9
F
Fraction of methane captured at the SWDS and
flared, combusted or used in another manner
0
GWP Global Warming Potential of methane 21
OX Oxidation factor IPCC 2006, Volume 5 Chapter
3 Table 3.2
0.1
F Fraction of methane in the SWDS gas 0.5
DOCf Fraction of degradable organic carbon 0.5
MCF Methane conversion factor 1
Aj,x Amount of organic waste type j prevented from
disposal in the SWDS in the year x
173,626 tonnes (79% of total waste)
DOCj
Fraction of degradable organic carbon
Waste type DOCj for wet
waste
Pulp, paper and cardboard 40
Wood & Straw (excl. lignin) 43
Garden/Park Waste (organic
putrescibles) 20
Food, food waste, beverages
and tobacco 15
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 41
Textiles 24
kj
Decay rate for the waste type
adapted from IPCC 2006 Guidelines for
National Greenhouse Gas Inventories (adapted
from Volume 5, Table 3.3)
Waste type Kj
Pulp, paper and cardboard 0.06
Wood & Straw (excl. lignin) 0.03
Garden/Park Waste (organic
putrescibles) 0.10
Food, food waste, beverages
and tobacco 0.185
J Waste type category -
MAT38
Mean annual temperature 20 degrees Celsius
MAP39
Mean annual precipitation 1,000 mm
PET40
Potential evapo-transpiration 923.3 mm
Table 9: Composition of the Changshu MSW % (on wet basis)
Test time Kitchen
leftover Paper Fabric Plastic Rubber
Incombustible
Material
2007-10-25 52.41% 7.93% 12.93% 12.37% 2.24% 12.12%
2007-10-26 68.14% 6.48% 9.10% 8.92% 0.42% 6.94%
2007-10-27 63.26% 8.73% 8.95% 11.53% 0.72% 6.81%
2007-10-28 68.02% 8.74% 6.96% 8.80% 1.19% 6.29%
2007-10-29 60.24% 7.04% 6.09% 9.98% 3.81% 12.84%
Max. 68.14% 8.74% 12.93% 12.37% 3.81% 12.84%
Min. 52.41% 6.48% 6.09% 8.80% 0.42% 6.29%
AVG 62.41% 7.78% 8.81% 10.32% 1.67% 9.00%
Source: Sample taken at Changshu Incineration Plant Waste Receiving Area
Table 10: Waste Content by Type (wet basis)
Waste Type Percentage (%)
Pulp, paper and Cardboard 7.78
Wood & Straw (excl. lignin) 0
Garden/Park Waste (organic putrescibles) 0
Food, food waste, beverages and tobacco 62.41
Textile 8.81
Total 79
Inorganic 21
According to the 2006 IPCC Guidelines, Volume 5, Chapter 5: Incineration and Open Burning of Waste,
Table 5.2, the combustion efficiency of incineration plants for municipal solid waste is 100%.
38 http://www.jiangsu.net/city/city.php?name=changshu#Geography_Resources_Climate
39 http://www.jiangsu.net/city/city.php?name=changshu#Geography_Resources_Climate
40 http://gupea.ub.gu.se/bitstream/2077/21737/3/gupea_2077_21737_3.pdf Page 34, Figure 3
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 42
Table 11. Emission reductions from waste decomposition in the baseline
Year Methane avoidance using FOD
model (tCO2e)
Year 1 89,385
Year 2 99,714
Year 3 108,605
Year 4 116,285
Year 5 122,940
Year 6 128,728
Year 7 133,779
Total 799,437
Project Emissions:
The project emissions in year y are:
PEy = PEFuel, on-site,y + PEi,,y +PEw,y
Emissions from fuel use on-site (PEfuel, on-site,y)
PEFuel, on-site,y = Fcons,y * NCV fuel * EFfuel
where:
PEfuel, on-site,y = Is the CO2 emissions due to on-site fuel combustion in year y (tCO2)
Fcons,y = Is the fuel consumption on site in year y (l or kg)
NCVfuel = Is the net caloric value of the fuel (MJ/l or MJ/kg)
EFfuel = Is the CO2 emissions factor of the fuel (tCO2/MJ)
For the ex-ante calculations it is estimated an amount of light diesel consumption on-site for the
incinerators‘ auxiliary burners of:
Fcons,y = 100,000 kg
NCV fuel = 42.6 MJ/kg 41
EFfuel = 74,800 kg/TJ 42
Emissions from waste incineration (PEi,y)
PEi,,y = PEf,y + PEs,y
Emissions from fossil fuel based waste (PEf,y), Option 1
PEf,y=
i Ai * CCWi * FCFi * EFi * 44/12
41 China Energy Statistical Yearbook 2006
42 2006 IPCC Guidelines, Volume 2: Energy, Chapter 2: Stationary Combustion. Table 2.2
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 43
Table 12. Component of dry weight used for CCWi calculations
Table 13. Default dry matter content, total carbon content and fossil carbon fraction of different
MSW components.
Content
Dry matter
content in % of
wet weight
Total carbon content
in % of dry weight
Fossil carbon fraction
in % of total carbon
Paper/cardboard 90 46 1
Textiles 80 50 20
Food waste 40 38 -
Wood 85 50 -
Garden and park
waste 40 49 0
Diapers 40 70 10
Rubber and leather 84 67 20
Plastic 100 75 100
Metal 100 NA NA
Glass 100 NA NA
Other, inert waste 90 3 100
Source: 2006 IPCC Guidelines. Volume 5, chapter 2: Waste Generation, Composition and Management
Data. Table 2.4
According to the 2006 IPCC Guidelines, Volume 5, Chapter 5: Incineration and Open Burning of Waste,
Table 5.2, the combustion efficiency of incineration plants for municipal solid waste is 100%.
And using Option 2 from AM0025 for the Emissions from waste incineration (PEi,y)
Test time Kitchen
leftover paper Fabric Plastic Rubber
Incombustible
Material
2007-10-25 43.94% 3.80% 11.50% 11.01% 4.54% 25.22%
2007-10-26 45.66% 8.26% 14.79% 10.93% 1.14% 19.21%
2007-10-27 46.30% 11.69% 12.37% 12.46% 1.62% 15.53%
2007-10-28 48.71% 11.54% 11.23% 10.51% 2.80% 15.21%
2007-10-29 38.49% 7.85% 7.41% 10.74% 8.00% 27.52%
Max. 48.71% 11.69% 14.79% 12.46% 8.00% 27.52%
Min. 38.49% 3.80% 7.41% 10.51% 1.14% 15.21%
AVG 44.62% 8.63% 11.46% 11.13% 3.62% 20.54%
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 44
PEi,y = Qbiomass,i * (EFN2O * GWPN2O + EFCH4 * GWPCH4) * 10-3
For the ex-ante calculations, 2006 IPCC Guidelines default values are used:
Q biomass,i = 660 tonnes
EFN2O = 0.05 kg N2O/tonne waste43
(on wet weight basis)
EFCH4 = 0.2 Kg CH4/Gg waste44
(on wet weight basis)
With the above assumptions, the ex-ante Project emissions per year during the first crediting period are
summarized in the table below:
Table 14. Ex-ante project emissions for the first crediting period
Year
Project emissions
due to fuel
consumption on-
site (tCO2e)
Project emissions
from waste
incineration
(tCO2e)
Project emissions
from waste
incineration
stacks (tCO2e)
Emissions
from
wastewater
treatment
Total
project
emissions
(tCO2e)
Year 1 319 71,786 2,547 0 74,652
Year 2 319 71,786 2,547 0 74,652
Year 3 319 71,786 2,547 0 74,652
Year 4 319 71,786 2,547 0 74,652
Year 5 319 71,786 2,547 0 74,652
Year 6 319 71,786 2,547 0 74,652
Year 7 319 71,786 2,547 0 74,652
Total 2,233 502,502 17,829 0 522,564
For the amount of methane destroyed in the baseline scenario, we use the following equation:
MDreg,y = MBy * AF
where:
MDreg,y is methane that would be destroyed in the absence of the project activity in year y (tCH4);
MBy is the methane produced in the landfill in the absence of the project activity in year y
(tCH4); and,
AF is the adjustment factor in percentage (%).
The AF was considered to be zero. This value is justified based on the fact that the regulatory
requirements do not indicate any specific amount of gas collection and destruction or utilization and that
is common practice in China that no LFG is actually collected and flared. Therefore, MDreg,y will be equal
to zero for the ex-ante ER calculation. Nevertheless, laws and regulations will be reviewed at the renewal
of the crediting period and the AF will be modified accordingly in case any law or regulation requires a
minimal amount of methane to be captured and/or destroyed.
43 2006 IPCC Guidelines, Volume 5, Chapter 5: Table 5.6 Continuous Incineration
44 2006 IPCC Guidelines, Volume 5, Chapter 5: Table 5.3 Continuous Incineration.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 45
Rate of compliance
The adjusted baseline emissions (BEy,a) are calculated as follows:
BEy,a = BEy * ( 1 RATECompliance
y)
The rate of compliance is considered to be zero. This value is justified based on the fact that the
regulation is not enforced. However, the rate of compliance shall be monitored ex-post and adjusted.
Emissions from electricity displacement
The baseline emissions from the displacement of fossil fuel-based grid electricity generation are
determined using the grid emission factor calculated in detail in Annex 3 (Baseline Information) and an
estimation of the net quantity of electricity displaced by the project. The amount of power to be exported
to the grid for the purposes of ex-ante calculations is 8.5 MW. Emission reductions will only be claimed
for the net electricity supplied to the grid. However, the actual electricity exported to the grid will be
monitored and taken into account for the ex-post project emissions calculation.
According to the ¨Tool to calculate the emission factor for an electricity system¨, the electricity baseline
emission factor is calculated as the weighted average of the Operating Margin emission factor (EFOM,y)
and the Build Margin emission factor (EFBM,y) where the weights wOM and wBM, by default, are 50% (i.e.,
wOM = wBM = 0.5). This is presented below.
Eastern China Grid OM Ex-Ante (tCO2/MWh) 0,9421
Eastern China Grid BM Ex-Ante (tCO2/MWh) 0,8672
Eastern China Grid CM Ex-Ante (tCO2/MWh)) 0,9047
The baseline emissions are the sum of emissions due to the landfilling of MSW in the absence of the
proposed project activity and those due to the displacement of grid-connected electricity during year y.
The GHG emissions from waste diverted to incineration facility and from the displacement of fossil fuel-
based grid electricity generation in tCO2e per year, for the first crediting period are summarized in the
table below. The emission factor is calculated ex-ante and fixed for the crediting period.
Table 15: ERs from Electricity Displacement
Year Baseline emissions – Electricity
displacement (tCO2e)
Year 1 49,216
Year 2 49,216
Year 3 49,216
Year 4 49,216
Year 5 49,216
Year 6 49,216
Year 7 49,216
Total 344,512
Leakage:
The sources of leakage considered in the methodology are CO2 emissions from off-site transportation of
waste materials. Since the project is located next to the landfill where the waste would otherwise be
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 46
disposed off, there are no incremental emissions due to transportation of the waste. In case of waste
incineration, leakage emissions from residual waste of MSW incinerator should be accounted for.
If the residual waste from the incinerator contains up to 5% residual carbon, then:
Li,y = A residual *FC residual*44/12
If the residual waste from the incinerator contains more than 5% residual carbon, then;
Li,y= A residual,y *0.05*44/12+Aresidual,y *(FC residual – 0.05) *16/12*21
Where:
Li,y = is the leakage emissions from the residual waste of MSW incinerator in year y (tCO2e)
Aresidual = is the amount of the residual waste from the incinerator (t/yr)
FCresidual=is the fraction of residual carbon contained in the residual waste (%)
44/12= is a factor to convert from carbon to carbon dioxide
16/12 = is factor to convert from carbon to methane
21= is the global warming potential of methane (tCO2/tCH4)
For ex-ant estimations, the value adopted for residual carbon from residual waste is 2,93%, which is
based on actual lab test done by Environmental and Chemical Engineering Department of Shanghai
University. The average volume of residual waste produced is 59,605 tonnes per year. Using the formula
above for residual waste containing up to 5% residual carbon, the emission reductions are calculated as
follows:
Li,y = A residual *FC residual*44/12
Li,y =59,605 * 2,93%*44/12 = 6,404 tonnes of CO2 per year
Table 16. Leakage emissions
Year Leakage emissions from residual carbon
Year 1 6,404
Year 2 6,404
Year 3 6,404
Year 4 6,404
Year 5 6,404
Year 6 6,404
Year 7 6,404
Total 44,828
The actual emissions due to residual waste will be monitored ex-post and any adjustments to leakage
emission will be done ex-post.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 47
Emissions from wastewater treatment are not considered since it is treated under aerobic conditions and
thus CH4 emissions are assumed to be zero. However, the possible methane emissions are monitored ex-
post.
B.6.4 Summary of the ex-ante estimation of emission reductions:
Emission Reductions:
To calculate the emission reductions the following equation is applied:
ERy = BEy – PEy – Ly
where:
ERy is the emissions reductions in year y (tCO2e);
BEy is the emissions in the baseline scenario in year y (tCO2e);
PEy is the emissions in the project scenario in year y (tCO2e); and
Ly is the leakage in year y (tCO2e).
Table 17. Emission reductions
Year
Baseline
emissions
(tCO2e)
Project
emissions
(tCO2e)
Baseline
emissions –
electricity
displacement
(tCO2e)
Leakag
e
(tCO2e)
ERs
(tCO2e)
(year 1)
1/08/2011- 31/07/2012 89,385 74,652
49,216 6,404
57,545
(year 2)
1/08/2012- 31/07/2013 99,714
74,652 49,216 6,404
67,874
(year 3)
1/08/2013- 31/07/2014 108,605
74,652 49,216 6,404
76,766
(year 4)
1/08/2014- 31/07/2015 116,285
74,652 49,216 6,404
84,445
(year 5)
1/08/2015- 31/07/2016 122,940
74,652 49,216 6,404
91,100
(year 6)
1/08/2016- 31/07/2017 128,728
74,652 49,216 6,404
96,887
(year 7)
1/08/2017- 31/07/2018 133,779
74,652 49,216 6,404
101,941
Total 799,437 522,564 344,512 44,828 576,558
B.7. Application of the monitoring methodology and description of the monitoring plan:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 48
B.7.1 Data and parameters monitored:
Data / Parameter: Fcons,y
Data unit: tonnes of fuel
Description: Diesel consumption on-site during year y of the crediting period.
Source of data to be
used:
Purchase invoices
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
100 tonnes
Description of
measurement methods
and procedures to be
applied:
Annually, based on actual consumption and invoices
QA/QC procedures to
be applied:
The amount of fuel will be derived from the paid fuel invoices (administrative
obligation).
Any comment: This parameter includes the auxiliary fossil fuel that is needed for start-up of
incineration process.
Data / Parameter: AMSW.y
Data unit: Tonnes / year
Description: Amount of waste fed into the waste incineration plant
Source of data to be
used:
Project developer
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
219,780 tonnes
Description of
measurement methods
and procedures to be
applied:
Measured with weighbridge continuously, aggregated quarterly
QA/QC procedures to
be applied:
Weighbridge will be subject to annual calibration
Any comment: N/A
Data / Parameter: Pn,i,y
Data unit: -
Description: Weight fraction of the waste type i in the sample n collected during the year y
Source of data to be
used:
Sample measurements by project participants
Value of data applied
for the purpose of Waste Type Percentage (%)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 49
calculating expected
emission reductions in
section B.5
Pulp, paper and
Cardboard 7.78
Wood & Straw
(excl. lignin) 0
Garden/Park Waste
(organic putrescibles) 0
Food, food waste,
beverages and tobacco 62.41
Textile 8.81
Total 79
Inorganic 21
Description of
measurement methods
and procedures to be
applied
Sample the waste prevented from disposal using the categories j, as provided in
the table for DOCj and kj, and weigh each waste fraction. Monitored quarterly
with uncertainty range of 20% at 95% confidence level.
QA/QC procedures to
be applied:
Statistically significant with a max uncertainty range of 20% at 95% confidence
level
Any comment: N/A
Data / Parameter: CCWi
Data unit Fraction
Description: Fraction of the carbon content in waste type i
Source of data to be
used:
IPCC 2006, Table 2.4, chapter 2, Volume 5 and table 5.2
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Content Total carbon content in
% of dry weight
Paper/cardboard 46
Textiles 50
Food waste 38
Wood 50
Garden and park waste 49
Diapers 70
Rubber and leather 67
Plastic 75
Metal NA
Glass NA
Other, inert waste 3
Description of
measurement methods
and procedures to be
applied:
Annually
QA/QC procedures to
be applied:
IPCC 2006, Volume 5, Chapter 2, Table 2.4
Any comment: N/A
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 50
Data / Parameter: FCFi
Data unit: Fraction
Description: Fraction of fossil carbon in total carbon of waste type i
Source of data to be
used:
Sample measurements by project participants
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
Content
Fossil carbon
fraction in % of
total carbon
Paper/cardboard 1
Textiles 20
Food waste -
Wood -
Garden and park
waste 0
Diapers 10
Rubber and leather 20
Plastic 100
Metal NA
Glass NA
Other, inert waste 100
Description of
measurement methods
and procedures to be
applied:
Quarterly. The size and frequency of sampling shall be statistically significant
with a maximum uncertainty range of 20% at a 95% confidence level. The
following standards shall be used:
• ASTM D6866-08: ―Standard Test Methods for Determining the Biobased
Content of Solid, Liquid, and Gaseous Samples Using Radiocarbon Analysis";
• ASTM D7459-08: ―Standard Practice for Collection of Integrated Samples for
the Speciation of Biomass (Biogenic) and Fossil- Derived Carbon Dioxide
Emitted from Stationary Emissions Sources".
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: SGi,y
Data unit: m3/year
Description: Total volume of stack gas from incineration
Source of data to be
used:
Project site
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
The stack gas flow rate will be measured directly quarterly.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 51
applied:
QA/QC procedures to
be applied:
Maintenance and calibration of equipment will be carried out annually.
Any comment: N/A
Data / Parameter: MCN2Oi,y
Data unit: tN2O/m3
Description: Monitored content of nitrous oxide in the stack gas from waste
incineration in year y
Source of data to be
used:
Project site
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
Quarterly. Sample of the stack gas will be taken to the laboratory to determine
the content of N2O.
QA/QC procedures to
be applied:
A laboratory which follows rigorous standards shall be selected.
Any comment: N/A
Data / Parameter: MCCH4,i,y
Data unit: tCH4/m3
Description: Monitored content of methane in the stack gas from waste incineration in year y
Source of data to be
used:
Project site
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
Quarterly. Sample of the stack gas will be taken to the laboratory to determine
the content of CH4.
QA/QC procedures to
be applied:
A laboratory which follows rigorous standards shall be selected.
Any comment: N/A
Data / Parameter: EGd,y
Data unit: MWh
Description: Amount of electricity generated utilizing the combustion heat from incineration
in the project activity displacing electricity in the baseline during the year y.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 52
Source of data to be
used:
Electricity meter
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
68,000 MWh
Description of
measurement methods
and procedures to be
applied:
Continuous. To be measured from electrical meters installed at the plant. The
proportion of data to be monitored is 100% and the data will be archived
electronically.
QA/QC procedures to
be applied:
Electricity meter will be maintained and calibrated annually to assure high
levels of accuracy. The amount of electricity exported will be matched with
electricity invoices.
Any comment: N/A
Data / Parameter: Qbiomass,y
Data unit: Tonne/year
Description: Amount of waste incinerated in year y
Source of data to be
used:
Project Developer
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
219,780 tonnes of waste.
Description of
measurement methods
and procedures to be
applied:
Daily and aggregated yearly. All trucks entering the site will be weighed
QA/QC procedures to
be applied:
Weighbridge will be subject to annual calibration.
Any comment: N/A
Data / Parameter: Aj,x
Data unit: Tonnes/year
Description: Amount of organic waste type j prevented from disposal in the landfill in the
year x (tonnes year)
Source of data to be
used:
Project participants
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
173,626 tonnes of waste
Description of Annually
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 53
measurement methods
and procedures to be
applied:
QA/QC procedures to
be applied:
Weighbridge will be subject to annual calibration.
Any comment: N/A
Data / Parameter: Z
Data unit: -
Description: Number of samples collected during the year y
Source of data to be
used:
Project participants
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
At least quarterly, in accordance with measurement procedures in indicated in
this MP for FCFi and Pn,i,y
QA/QC procedures As above
Any comment: N/A
Data / Parameter: Aresidual
Data unit: Tonnes/year
Description: The amount of the residual waste from the incinerator
Source of data to be
used:
Project participants
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
59,605 tonnes
Description of
measurement methods
and procedures to be
applied:
Daily and aggregated monthly
QA/QC procedures to
be applied:
Weighbridge will be subject to annual calibration.
Any comment: N/A
Data / Parameter: FCresidual
Data unit: %
Description: Fraction of residual carbon in the residual waste of MSW incinerator
Source of data to be Sample measurements by the project participants
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 54
used:
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
2.93% based on actual lab test done by Environmental and Chemical
Engineering Department of Shanghai University.
Description of
measurement methods
and procedures to be
applied:
Quarterly test will be done in a laboratory. The size and frequency of sampling
should be statistically significant with a maximum uncertainty range of 20% at
a 95% confidence level.
QA/QC procedures to
be applied:
A laboratory which follows rigorous standards shall be selected.
Any comment: N/A
Data / Parameter: fi
Data unit: %
Description: fraction of waste diverted from the landfill to incinerator
Source of data to be
used:
Plant records
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
100%
Description of
measurement methods
and procedures to be
applied:
Daily and aggregated monthly. Weighbridge
QA/QC procedures to
be applied:
The weighbridge will be subject to annual calibration
Any comment: N/A
Data / Parameter: MBy
Data unit: tCH4
Description: Methane produced in the landfill in the absence of the project activity in year y.
Source of data to be
used:
Calculated as per the ―Tool to determine methane emissions avoided from
disposal of waste at a solid waste disposal site‖.
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
38,068 tCH4 for 7 years
Description of
measurement methods
and procedures to be
applied:
As per the ―Tool to determine methane emissions avoided from disposal of
waste at a solid waste disposal site‖
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 55
QA/QC procedures to
be applied:
As per the ―Tool to determine methane emissions avoided from disposal of
waste at a solid waste disposal site‖
Any comment: Calculated as per the ―Tool to determine methane emissions avoided from
disposal of waste at a solid waste disposal site‖
Data / Parameter: AF
Data unit: %
Description: Methane destroyed due to regulatory or other requirements
Source of data to be
used:
Local and national authorities
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0%
Description of
measurement methods
and procedures to be
applied:
At the renewal of the crediting period.
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: Rate compliance
Data unit: Number
Description: Rate of compliance
Source of data to be
used:
Municipal bodies
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
At the renewal of the crediting period
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: EFi
Data unit: Fraction
Description: Combustion efficiency for waste type ‗i‘.
Source of data to be
used:
Default values from 2006 IPCC Guidelines for National Greenhouse Gas
Inventories.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 56
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
1 for all waste types
Description of
measurement methods
and procedures to be
applied:
To be monitored annually.
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: GWPCH4
Data unit: tCO2e/tCH4
Description: Global warming potential of CH4
Source of data to be
used:
IPCC
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
21
Description of
measurement methods
and procedures to be
applied:
21 for the first commitment period. Shall be monitored annually.
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: GWPN2O
Data unit: tCO2e/tN2O
Description: Global warming potential of N2O
Source of data to be
used:
IPCC
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
310
Description of
measurement methods
and procedures to be
applied:
310 for the first commitment period. Shall be monitored annually.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 57
QA/QC procedures to
be applied:
N/A
Any comment: N/A
Data / Parameter: -
Data unit: MJ
Description: Energy generated by auxiliary fossil fuel added in the incinerator
Source of data to be
used:
Project site
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0.
Description of
measurement methods
and procedures to be
applied:
Estimated annually. This parameter will be estimated multiplying the amount of
auxiliary fossil fuel added in the incinerator to the net calorific value of this
auxiliary fossil fuel.
QA/QC procedures to
be applied:
N/A
Any comment: This parameter will be used to assess that the fraction of energy generated by
fossil fuel is no more than 50% of the total energy generated in the incinerator.
Energy generated by fossil fuel <0.50 x (Qy + EGd,y)
B.7.2. Description of the monitoring plan:
The Monitoring Plan (MP) details the actions necessary to record all the variables and factors required by
the AM0025, version 12, as explained in section B.7.1 above. All data will be archived electronically,
and backed up regularly. Moreover, this information will be kept for the full crediting period, plus two
years after the end of the crediting period or the last issuance of CERs for this project activity, whichever
occurs later.
The details of the Monitoring Plan is provided in Annex 4.
Project staff will be trained regularly in order to satisfactorily fulfil their monitoring obligations. The
authority and responsibility for project management, monitoring, measurement and reporting will be
agreed between the project participants and formalized.
Regular calibration will be performed according to the manufacturer‘s guidelines, or according to the
applicable regulations, by a suitably skilled technician at the required frequency (at least once a year). A
certificate of calibration will be provided for each piece of equipment after completion.
B.8. Date of completion of the application of the baseline study and monitoring methodology
and the name of the responsible person(s)/entity(ies):
The baseline study was completed on 27 February 2008 by:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 58
Francisco Fernández Asín
SECTION C. Duration of the project activity / crediting period
C.1. Duration of the project activity:
C.1.1. Starting date of the project activity:
31 March 2005. This is when the contract was signed for construction of the incinerator facility.
C.1.2. Expected operational lifetime of the project activity:
The Project is expected to have an operational lifetime of 30 years.
C.2. Choice of the crediting period and related information:
C.2.1. Renewable crediting period:
C.2.1.1. Starting date of the first crediting period:
01/08/2011 or the date of project registration.
C.2.1.2. Length of the first crediting period:
Seven (7) years with the option of two renewal periods.
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
>> N/A
C.2.2.2. Length:
>> N/A
SECTION D. Environmental impacts
>>
D.1. Documentation on the analysis of the environmental impacts, including transboundary
impacts:
The objectives of the Project are to minimize the environmental impact of current waste disposal
practices, to introduce proper waste handling in China, and to set an example of GHG reduction at
landfills through MSW incineration and valorization.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 59
The Project is in compliance with environmental standards and regulations, particularly the ―Technical
Policy on Urban Waste Disposal and Pollution Prevention‖ stipulated by the state. The Environmental
Impact Study (EIA) for the Project was completed in April 2004, and was approved by the Jiangsu
Province Environment Protection Bureau in October 2004. The EIA includes the following: (1) detailed
descriptions of the project phases, such as construction, and operations; (2) baseline environmental
parameters, such as topography, land use, soil, geology, hydrology, meteorology, air quality, noise, and
biological environment; (3) assessment of potential environmental impacts; (4) the environmental
management plan; and (4) social benefits. Copy of the EIA is made available to the DOE.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
The construction of the incineration power plant has a limited impact on surroundings because the major
emission is NOx, and the major pollutant is dioxin. The Project is located in a rural area and has little
impact on the Shanghu Scenic zone and Changshu urban areas, based on the monitoring of the most
frequent local wind direction and frequency. The Project not only has insignificant impact on the
environment, but rather, has positive environmental impacts. For example, waste incineration can reduce
the amount of waste by over 90%, such that through 30 years of operation of the plant, 3,720,000 m2
of
land will be saved from being used as a landfill whereas currently 4,120,000 m2 of land is being used for
piling waste up to 4 m high.
The Project will also bring about social benefits. Building on the experience with the existing Pudong
Yuqiao Waste Incineration Power Plant, the Changshu City Project will set a positive early example for
China‘s fledgling SWM industry. It will also give impetus to improving the environmental status of
Changshu City by improving the outdated SWM practices that currently exist, matching SWM with the
pace of urbanization and economic development, and creating a comfortable investment and living
environment.
This Project employs advanced incineration technology that allows for the elimination of pollutants from
the waste gas and compliance with EU emission standards for flue gas, dust and dioxin, which are more
stringent than Chinese national standards. The leachate produced from waste, is high density organic
wastewater. It will be pre-treated with an Upflow Anaerobic Sludge Blanket (UASB) system and enters
the Sequencing Batch Reactor (SBR) treatment system together with other sewage water before
discharged into the municipal water supply upon reaching the acceptable levels of the Chengxi Sewage
Water Treatment Plant.
Noise pollution, which mainly results from the turbine generator, water pump and air compressor, can
meet the standards once measures are taken such as insulation and the installation of noise barriers. The
noise level slightly exceeds the standards at the western side of the plant bordering Nanhu Lake.
However, this is an area with no inhabitants within 500 m, therefore, noise is not an issue.
Odor is controlled through isolation, for example through the use of enclosed garbage trucks. With such
controls, the level of odor may drop to Class 2 of the ―Emission Standards for Odor Pollutants‖.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 60
According to the most recent monitoring results, the environmental quality of the air at the project
construction site is classified at Category II, which meets national air quality standards.45
Sewage water
and water quality can reach Category IV, which meets water quality standards, while noise levels at the
plant boundary are better than Category II, meeting noise level standards. Finally, the analysis of impact
on the ecological environment shows that the Project has little impact on soil quality, land plants and
water plants at the completion of construction.
Sulfur dioxide (SO2), flue gas and dust emitted by the Project all meet pollution standards. Various solid
wastes in the plant will be disposed of effectively such that there will be no negative environmental
impacts by the Project in this regard. It is, thus, feasible to control the amount of industrial solid wastes
and achieve zero solid waste output.
Design principles and adopted environmental standards for the Project are as follows:
Data on Process-Provided Pollutant Source;
Standards on Waste Incineration Pollution Control;
Standards on Comprehensive Treatment Discharge of Sewage;
Specifications on Sewage Recycling Projects;
Emission Standards for Odor ; and,
Standards on Plant Boundary Noise of Industrial Enterprise.
Regular reporting will provide periodic online monitoring of compliance with environmental standards.
SECTION E. Stakeholders’ comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
The Project Developer made information about the Project publicly available, held a consultation, and
conducted a questionnaire.
In order to inform local stakeholders of the details of the Project, the Project Developer posted the
relevant information on the website of the Changshu Construction Bureau at
http://www.csbuild.gov.cn/view.php?type=new&news_id=10002104, as well as on the Changshu
Construction Information website.
A notice regarding the public consultation was sent to all surrounding villages and towns in advance.
Representatives of residential committees also received invitations and were recommended to attend. In
addition, representatives of relevant government bodies and business enterprises were invited as well.
The consultation was held on 15 November 2007 at the Changshu Waste Incineration Plant. Attendees
included representatives from the Environmental Protection Office of Changshu City Construction
Bureau, Changshu City Municipal Waste Disposal Administration Station, Environmental Protection
Waste Industry Co., Ltd, Yisheng Blow Molding Factory, two local towns and six villages. In total, 37
45 Except that PM10 at the land planned for the construction and the landfill slightly exceeds standards.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 61
people attended the consultation, including representatives from Changshu Pufa Thermal Power Energy
Co., Ltd and Shanghai Pucheng Thermal Power Energy Co., Ltd. The consultation first provided an
introduction to the waste incineration plant and the proposed CDM project. Next, Mr. Li Ming, Director
of the Changshu City Waste Disposal Management Station spoke about the significance of the Project
from the point of the supervisory body. Subsequently, the floor was opened to questions and comments
from the attendees, which was followed by the administration of a questionnaire soliciting further input
from the attendees.
E.2. Summary of the comments received:
At the public consultation, 29 attendees received the questionnaire and 26 filled it out. The findings of
the questionnaire are as follows:
1. Satisfaction with the surroundings:
Very
satisfied
14 satisfied 11 Not satisfied 1
2. Knowledge about national standards on energy conservation and pollution reduction
during the 11th five year plan:
Quite clear 14 Heard of 12 Not clear 0
3. Knowledge about power generation from waste:
Clear 23 Heard of 3 Not clear 0
4. Approval of construction of the power generation project with the waste incinerator:
Approve 25 Not approve 0 Not clear 0
5. Will the construction of the Project improve local waste treatment practices?
Obvious
improvement
24 Little impact 1 Not clear 0
6. Impact on the surrounding water environment by the construction and operation of the
Project (More than one answer is allowed):
The
underground
water will be
improved
14 Little impact 12 Not clear 0
7. Has the Project reduced local air pollution ?
Yes 19 No 3 More
observation
is needed
4
8. Has the Project improved employment?
Yes 19 No 4 Not clear 2
9. Has the Project improved the economic situation of the local community?
Yes 6 No 11 Not clear 9
10. Do you have other opinions and suggestions?
23 answered ―no‖, 1 hoped to increase investment in technological innovations, 1 suggested
supplying the surplus heat to the surrounding enterprises, and 1 suggested the chimney be
built underground.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 62
The key questions raised at the consultation are listed below. All of these were clearly and thoroughly
answered by the Project Developer.
1. Are dioxin emissions regularly monitored? Could the Project Developer publicize the emission
levels as they are monitored and measured?
2. How will the Project Developer control odor from the plant? What results can be expected?
3. Does the chimney discharge black smoke? Do flue gas emissions pose harm to human health?
4. What measures are taken by the Project Developer to protect the environment?
5. Is it possible to supply the surplus heat to the neighbouring Shenbang Village?
6. Will there be noise from flushing the pipe in the future?
7. Do emissions from the plant reach or exceed national and local standards?
8. Is the sewage treated before being discharged? If so, where is it discharged? Will the sewage
have an adverse impact on the surrounding fish ponds?
9. What role does the construction of the plant play in the urbanization of Changshu City?
E.3. Report on how due account was taken of any comments received:
According to the results of the questionnaire, and as evident from the ensuing discussion, the
consultation was viewed by the participants as successful. Many valuable comments and suggestions
were raised during the discussion, and no major objections were voiced by any of the local stakeholders.
None of the participants were against the proposed project, which is due to the fact that many were
already familiar with waste incineration and power generation technologies. Most of the stakeholders
consider that the proposed project will bring a number of benefits to the community, especially in terms
of creating employment opportunities. They also believe that the few, if any, potential negative impacts
of the Project, can be mitigated through various measures to be taken by the Project Developer.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 63
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: Changshu Pufa Thermal Power Energy Co., Ltd.
Street/P.O. Box: Southern Nanhu Farm
Building:
City: Xinzhuang Town, Changshu
State/Region: Jiangsu Province
Postfix/ZIP: 215562
Country: China
Telephone: +86-512-52422702
FAX: +86-512-52444569
E-Mail: [email protected]
Represented by: Mr. Ruimin Jian
Title: President
Salutation: Mr.
Last Name: Jian
Middle Name:
First Name: Ruimin
Department:
Mobile: 13901770645
Direct FAX: +86-21-68932303
Direct tel: +86-21-68932303
Personal E-Mail: [email protected]
Organization: Endesa Generación S.A.
Street/P.O.Box: Ribeira del Loira, 60
Building:
City: Madrid
State/Region:
Postfix/ZIP: 28042
Country: Spain
Telephone: +34.91.213.1414
FAX: +34.91.213.1052
E-Mail: [email protected]
URL:
Represented by: Mr. Jesús Abadía Ibanez
Title: Director Environment and Sustainable Development Department
Salutation: Mr.
Last Name: Abadía Ibanez
First Name: Jesús
Department:
Mobile:
Direct FAX: +34.91.213.1052
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 64
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
There is no public funding involved in the projects.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 65
Annex 3
BASELINE INFORMATION
Step1. Identify the relevant electric power system
Using the boundary definitions of the Chinese NDRC46
, The spatial extent of the project boundary
includes the proposed project and all power plants connected physically to the East China Power Grid
that the CDM project power plant is connected to.
Step 2.Choose whether to include off-grid power plants in the project electricity systems (optional)
The project chose not to choose this option.
Step 3. Select an operating margin (OM) method
The calculation of the operating margin emission factor (EFgrid,OM,y) is based on one of the following
methods:
(a) Simple OM; or
(b) Simple adjusted OM; or
(c) Dispatch data analysis OM; or
(d) Average OM.
Dispatch data is unavailable for the East China Power Grid; therefore, this PDD selects option (a), the
Simple OM method, to calculate this parameter. The low-cost/must-run resources constitute less than
50% of total East China Power Grid generation in each of the five most recent years for which data is
available. Therefore, the option a) Simple OM is applicable.
Step 4. Calculate the operating margin emission factor according to the selected method
The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per
unit net electricity generation (tCO2/MWh) of all generation power plants serving the system, not
including low-cost/must-run power plants/units. It is calculated based on data on the total net
electricity generation of all power plants serving the system and the fuel types and total fuel
consumption of the project electricity system (option B) because (a) the necessary data for option A is
not available, (b) nuclear and renewable power generation are considered as low-cost/ must-run power
sources and the quantity of electricity supplied to the grid by these sources is known and (c) off-grid
power plants are not included in the calculation. Electricity imports are treated as one power plant m.
y
i
yiCOyiyi
yOMsimplegridEG
EFxNCVxFC
EF
)....( ,,2,,
,, (7)
46 http://cdm.ccchina.gov.cn/web/index.asp.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 66
Table A.1. Thermal Power Generation Capacity of the Eastern Power Grid in 2003
Province Power generation Power consumption
rate Power supply
MWh % MWh
Shanghai 69,444,000.00 5.14 65,874,578.40
Jiangsu 133,277,000.00 5.9 125,413,657.00
Zhejiang 83,089,000.00 5.31 78,676,974.10
Anhui 54,156,000.00 6.06 50,874,146.40
Fujian 42,146,000.00 5.07 40,009,197.80
Total 360,848,553.70
Source: China Electric Power Yearbook 2004
Table A.2. Thermal Power Generation Capacity of Eastern Power Grid in 2004
Province Power generation Power consumption
rate Power supply
MWh % MWh
Shanghai 71,127,000 5.22 67,414,170.60
Jiangsu 163,545,000 5.93 153,846,781.50
Zhejiang 95,255,000 5.68 89,844,516.00
Anhui 59,875,000 6.03 56,264,537.50
Fujian 50,490,000 6.07 47,425,257.00
Total 414,795,262.60
Source: China Electric Power Yearbook 2005
Table A.3. Thermal Power Generation Capacity of the Eastern Power Grid in 2005
Province Power generation Power consumption
rate Power supply
MWh % MWh
Shanghai 74,606,000 5.05 70,838,397
Jiangsu 211,429,000 5.96 198,827,832
Zhejiang 108,110,000 5.59 102,066,651
Anhui 62,918,000 5.9 59,205,838
Fujian 48,600,000 4.57 46,378,980
Total 477,317,698
Source: China Electric Power Yearbook 2006
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 67
Table A.4. Marginal Emission Factor Calculation for the Eastern Power Grid in 2003
Fuel Type Unit Shanghai Jiangsu Zhejian
g Anhui Fujian Total
Emission
factor
(tC/TJ)
Carbon
oxidation
rate (%)
Average low
heating
value
(MJ/t,km3)
CO2 Emissions
tCO2eJ=G*H*I*F*4
4/12/10000mass unit
A B C D E
F=A+B+
C+D+E G H I
J=G*H*I*F*44/12/1
000 (volume unit)
Coal
10
kT 2618
6417.7
4 3442.4
2669.6
7 1754 16901.81 25.8 100 20908 334,300,359.13
Refined coal
10
kT 0 25.8 100 26344 - Other
washed coal
10
kT 0 25.8 100 8363 -
Coke
10
kT 0 25.8 100 28435 -
Coke gas
100
million
m3 1.99 0.06 2.05 12.1 100 16726 152,125.76
Other gases
100
million
m3 66.34 66.34 12.1 100 5227 1,538,454.90
Oil
10
kT 0 20 100 41816 -
Gasoline
10
kT 18.9 100 43070 -
Diesel fuel
10
kT 1.26 14.71 13.99 29.96 20.2 100 42652
946,463.80
Fuel oil
10
kT 95.49 0.76 174.48 18.89 289.62 21.1 100 41816
9,369,683.52 Liquid
petroleum
gas
10
kT
0 17.2 100 50179
-
Refinery dry
gas
10
kT 0.49 0.96 1.45 18.2 100 46055
44,564.35
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 68
Natural gas
100
million
m3 0 15.3 100 38931
- Other
petroleum
products
10
kT 18.91 5.3 15.04 39.25 20 100 38369
1,104,387.72
Other coke
products
10
kT 0 25.8 100 28435
- Other
energy
sources
10,000
tce 5.68 7.08 12.76 0 100 0
-
347,456,039.18
Source: China Energy Statistical Yearbook 2004
Table A.5. Marginal Emission Factor Calculation for the Eastern Power Grid in 2004
Fuel
Type Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total
Emission
factor
(tC/TJ)
Carbon
oxidation
rate (%)
Average low
heating
value
(MJ/t,km3)
CO2 Emissions
tCO2e
J=G*H*I*F*44/12/10000
mass unit
A B C D E
F=A+B+C+
D+E G H I
J=G*H*I*F*44/12/1000
(volume unit)
Coal
10
kT 2779.6 7601.9 4008.9 2906.2 2183.7 19480.3 25.8 100 20908
385,300,230.33
Refined
coal
10
kT 0 25.8 100 26344
-
Other
washed
coal
10
kT
5.46 4.63 10.09 25.8 100 8363
79,826.01
Coke
10
kT 0 25.8 100 28435
-
Coke gas
100
million
m3 2.59 2.59 12.1 100 16726
192,197.91
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 69
Other
gases
100
million
m3 72.46 72.46 12.1 100 5227
1,680,380.49
Oil
10
kT 0 20 100 41816
-
Gasoline
10
kT 0 18.9 100 43070
-
Diesel
fuel
10
kT 2.69 27.17 6.23 36.09 20.2 100 42652
1,140,116.11
Fuel oil
10
kT 58.52 55.07 202.89 23.26 339.74 21.1 100 41816
10,991,147.99
Liquid
petroleu
m gas
10
kT 0 17.2 100 50179
-
Refinery
dry gas
10
kT 0.77 0.55 1.32 18.2 100 46055
40,568.93
Natural
gas
100
million
m3 0.14 0.14 15.3 100 38931
30,576.41
Other
petrol
products
10
kT 21.22 1.37 24.89 47.48 20 100 38369
1,335,957.42
Other
coke
products
10
kT 0 25.8 100 28435
-
Other
energy
sources
10,000
tce 6.43 15.48 21.91 0 100 0
-
400,791,001.59
Source: China Energy Statistical Yearbook 2005
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 70
Table A.6. Marginal Emission Factor Calculation for the Eastern Power Grid in 2005
Fuel
Type Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total
Emission
factor
(tC/TJ)
Carbon
oxidation
rate (%)
Average
low
heating
value
(MJ/t,km3)
CO2 Emissions
tCO2e
J=G*H*I*F*4
4/12/10000
mass unit
A B C D E F=A+B+C
+D+E G H I
J=G*H*I*F*4
4/12/1000
(volume unit)
Coal
10
kT 2847.31 9888.06 4801.52 3082.9 2107.69 22727.48 25.8 100 20908
449,526,099.6
4
Refined
coal
10
kT 0 25.8 100 26344
-
Other
washed
coal
10
kT
0 25.8 100 8363
-
Coke
10
kT 0.03 0.03 25.8 100 28435
806.99
Coke gas
100
million m3 1.68 1.38 1.71 4.77 12.1 100 16726
353,970.67
Other
gases
100
million m3 83.72 24.97 0.06 30 138.75 12.1 100 5227
3,217,675.86
Oil
10
kT 27.01 27.01 20 100 41816
828,263.45
Gasoline
10
kT 0 18.9 100 43070
-
Diesel
fuel
10
kT 1.25 16 4.52 1.67 23.44 20.2 100 42652
740,491.04
Fuel oil
10
kT 59.39 13.22 153.22 7.45 233.28 21.1 100 41816
7,546,991.82
Liquid
petroleu
m gas
10
kT 0 17.2 100 50179
-
Refinery 10 0.57 0.83 1.4 18.2 100 46055
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 71
dry gas kT 43,027.65
Natural
gas
100
million m3 1.09 1.85 0.62 3.56 15.3 100 38931
777,514.36
Other
petroleu
m
products
10
kT
21 8.38 34.8 64.18 20 100 38369
1,805,849.77
Other
coke
products
10
kT 0 25.8 100 28435
-
Other
energy
sources
10,000 tce
12.36 15.29 27.65 0 100 0
-
464,840,691.2
5
Source: China Energy Statistical Yearbook 2006
Table A.7. Emission Factor of the Eastern China Power Grid in 2003
Total electricity to the grid
(MWh)
Total emission
(tCO2e)
Emission factor
(tCO2e/ MWh)
385,310,464 368,593,903 0.956615
Table A. 8. Emission Factor for the Eastern China Power Grid in 2004
Total electricity to the grid
(MWh)
Total emission
(tCO2e)
Emission factor
(tCO2e/ MWh)
453,378,723 434,050,485 0.957368
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board page 72
Table A. 9. Emission Factor of the Eastern China Power Grid in 2005
Total electricity to the grid
(MWh)
Total emission
(tCO2e)
Emission factor
(tCO2e/ MWh)
714,971,698 661,062,081 0.924599
And therefore the three-year weighted average emission factor is: 0.942102tCO2e/ MWh
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 73
Table 1-1: Parameters for the low calorific value, oxidation rate and potential emission factor of
individual fuels
Fuel Type Low calorific
value
Emission factor
(tc/TJ) Oxidation rate
Raw coal 20908 kJ/kg 25.80 1
Refined coal 26344 kJ/kg 25.80 1
Other washed coal1 8363 kJ/kg 25.80 1
Coke 28435 kJ/kg 29.50 1
Crude oil 41816 kJ/kg 20.00 1
Gasoline 43070 kJ/kg 18.90 1
Kerosene 43070 kJ/kg 19.60 1
Diesel oil 42652 kJ/kg 20.20 1
Fuel oil 41816 kJ/kg 21.10 1
Other petroleum
products2
38369 kJ/kg 20.00 1
Natural gas 38931 kJ/m3 15.30 1
Coke-oven gas3 16726 kJ/m
3 12.10 1
Other gases4 5227 kJ/m
3 12.10 1
Liquefied petroleum
gas 50179 kJ/kg 17.20 1
Refinery day gas 46055 kJ/kg 18.20 1
Source: The caloric value of each kind of fuel is from p.287 of China Energy Statistical Yearbook 2006.
The potential emission factor of each kind of fuel is sourced from the Table 1.3 and Table 1.4,
p.1.21,1.24, Chapter 1 of ―2006 IPCC Guidelines for National Greenhouse Gas Inventories‖ Volume2
Energy.
____________________________
1. The calculation is carried out based on the low calorific values of middlings stated in p.287 of China
Energy Statistical Yearbook 2006. Since the average low calorific value of coal sludge is higher than
that of middlings, such handling is conservative.
2. Low calorific values of other petroleum products are not provided in the China Energy Statistical
Yearbook of each year. In this appendix, the low calorific value obtained by converting the actual values
and standard values in the energy balance sheet of each year is 38,369 kJ/kg, i.e.1.3108 tce/t.
3. The calculation is carried out based on the lower value in the caloric value range of 16,726-17,981
kJ/m3 of coke-oven gas provided in p.287 of China Energy Statistical Yearbook 2006.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 74
The calculation is carried out based on the lowest values of the low calorific values of generator gas,
heavy oil catalytic cracking gas, heavy oil thermal cracking gas, pressure gasified gas or water gas
provided in p.287 of China Energy Statistical Yearbook 2006.
According to data for the new thermal power projects during the 10th Five-Year Plan period issued by the
State Electricity Regulatory Commission, among the new thermal power projects during 2000-2005,
units with the capacity of 600 MW or above per machine account for 24%; units with the capacity of
300MW per machine account for 60%; and the rest are the units with the capacity of 300 MW or below
per machine. The capacity of power generated by new large-medium thermal power projects in 2005
total 54 GW, where 600 MW units total 15 sets, accounting for 17% of the power generated by the new
large-medium thermal power projects of that year. Based on the analysis above, in this calculation, the
domestic sub-critical unit of 600 MW is adopted as the technology for identifying the commercialized
optimal efficiency of coal-fired electricity. In this calculation, the weighted average of the net coal
consumption rate of the 15 sets of new 600 MW units in 2005 is used as the approximation of the
technology of commercialized optimal efficiency. The net coal consumption rate of the 600 MW
domestic sub-critical unit is 343.33 gce/kWh, i.e. the power supply efficiency is 35.82%.
According to data on gas turbine power plants in 2004, 200 MW combined cycle (9E type units of
technology level equal to GE) is determined as the technology of commercialized optimal efficiency of
gas turbine power plant (including oil- and gas-burning). The gas turbine power plant of the highest
actual power supply efficiency is taken as the approximation of the technology of commercialized
optimal efficiency. The net coal consumption rate (converted according to caloric value) of the gas
turbine power plant is estimated as 258 gce/kWh, i.e. the power supply efficiency is 47.67%.
Variables
Power
supply
efficiency
Fuel
emission
factor
(tc/TJ)
Oxidation
rate
Emission factor
(tCO2/MWh)
A B C
D=3.6/A/1000*B*C*44/
12
Coal-fired
power plant EFCoal,Adv 35.82% 25.8 1 0.9508
Gas-fired
power plant EFGas,Adv 47.67% 15.3 1 0.4237
Oil-fired
power plant EFOil,Adv 47.67% 21.1 1 0.5843
Step 5. Identify the group of power units to be included in the build margin
The sample group of power units m used to calculate the build margin consists of either:
a. The set of five power units that have been built most recently; or
b. The set of power capacity additions in the electricity system that comprise 20% of the system
generation in (MWh) and that have been built most recently.
However, due to the fact that data on electricity generation of each power plant / unit in the grid is
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 75
currently not available in P. R. China option (b) the set of power capacity additions in the electricity
system that comprises 20% of the system generation capacity (in MW) and that have been built most
recently is selected.
Step 6. Calculate the build margin emission factor
According to the ―Tool to calculate the emission factor for an electricity system‖, EFgrid,BM,y is the
generation-weighted average emission factor of all power units m during the most recent year y for
which power generation data is available. However, due to the fact that data on both electricity
generation and emission factor of each power plant / unit in the grid is currently not available in P. R.
China (see Step 3), EB guidance on the estimation of the build margin in P.R. China can also be
applied for the purpose of estimating the BM emission factor and EFgrid, BM, y is calculated as follows:
m
ym
mi
ymELym
EG
EFEG
,
,
,,,
yBM, gridEF (13)
Calculate the proportions of CO2 emissions corresponding to solid, fluid and gas fuels used for power generation
to the total emissions.
Fuel Type Unit Shangh
ai Zhejiang
Jiangs
u Anhui Fujian Total
Caloric
value
Emission
factor
Oxida
tion
rate
Emissi
on
A B C D E
F=A+
…+D
+E
G H I
J=F*G
*H*I*4
4/12/10
0
Raw coal 10 kT 2847.3
1 4801.52
9888.
06 3082.9
2107.6
9
2272
7.48
20908
kJ/kg 25.80 1
449,52
6,100
Refined
coal
10 kT 0 0 0 0 0 0
26344
kJ/kg 25.80 1 0
Other
washed
coal
10 kT
0 0 0 0 0 0 8363
kJ/kg 25.80 1 0
Coke 10 kT
0 0.03 0 0 0 0.03 28435
kJ/kg 29.50 1 807
Sum
449,52
6,907
Crude oil 10 kT
0 27.01 0 0 0 27.01 41816
kJ/kg 20.00 1
828,26
3
Gasoline 10 kT
0 0 0 0 0 0 43070
kJ/kg 18.90 1 0
Kerosene 10 kT
0 0 0 0 0 0 43070
kJ/kg 19.60 1 0
Diesel oil 10 kT
1.25 4.52 16 0 1.67 23.44 42652
kJ/kg 20.20 1
740,49
1
Fuel oil 10 kT
59.39 153.22 13.22 0 7.45 233.2
8
41816
kJ/kg 21.10 1
7,546,9
92
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 76
Other
petroleum
products
10 kT
21 34.8 8.38 0 0 64.18 38369
kJ/kg 20.00 1
1,805,8
50
Sum
10,921,
596
Natural
gas
10
millio
n m3
10.9 6.2 18.5 0 0 35.6 38931
kJ/m3
15.30 1 777,51
4
Coke-
oven gas
10
millio
n m3
16.8 0 13.8 17.1 0 47.7 16726
kJ/m3
13.00 1 353,97
1
Other
gases
10
millio
n m3
837.2 0.6 249.7 300 0 1387.
5
5227
kJ/m3
13.00 1 3,217,6
76
Liquefied
petroleum
gas
10
kiloto
nne
0 0 0 0 0 0 50179
kJ/kg 17.20 1 0
Refinery
day gas
10
kiloto
nne
0.57 0 0.83 0 0 1.4 46055
kJ/kg 18.20 1 43,028
Sum
4,392,1
89
Total
464,84
0,691
Source: China Energy Statistical Yearbook 2006
Adopting tables above and formula (2), (3) and (4): Coal=96.71%, Oil
=2.35%, Gas=0.94%.
Step 2: Calculate the corresponding thermal power emission factor.
Step 3: Calculate the grid BM.
Installed capacity of East China Grid in 2005
Installed
capacity Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total
%
Thermal power MW 13113.5 42506.4 27688.1 11423.2 9345.4 104076.6 84.2%
Hydro power MW 0 142.6 6952.1 749.8 8224.9 16069.4 13%
Nuclear power MW 0 0 3066 0 0 3066 2.5%
Wind power and
others MW 253.3 58.8 37.2 0 52 401.3
0.3%
Total LCMR MW 15.8%
Total MW 13366.8 42707.8 37743.4 12173 17622.3 123613.3
Data source: China Electricity Yearbook 2006
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 77
Installed capacity of East China Grid in 2004
Installed capacity Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total %
Thermal power MW 12014.9 28289.5 21439.8 9364.5 8315.4 79424.1 81.9%
Hydro power MW 0 126.5 6418.4 692.8 7180.1 14417.8 14.9%
Nuclear power MW 0 0 3056 0 0 3056 3.2%
Wind power and others MW 3.4 17.6 39.7 0 12 72.7 0.1%
Total LCMR MW 18.1 %
Total MW 12018.3 28433.6 30953.9 10057.3 15507.5 96970.6
Data source: China Electricity Yearbook 2005
Installed capacity of East China Grid in 2003
Installed capacity Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total %
Thermal power MW 11092.6 22245 15321.2 9284.9 7092.8 65036.5 80.2%
Hydro power MW 0 137.8 6054.5 649.1 6761.1 13602.5 16.8%
Nuclear power MW 0 0 2406 0 0 2406 3%
Wind power and
others MW 0 0 39.7 0 12 51.7
0.1%
Total LCMR MW 19.8%
Total MW 11092.6 22382.7 23821.4 9934 13865.8 81096.5
Data source: China Electricity Yearbook 2004
Installed capacity of East China Grid in 2002
Installed capacity Unit Shanghai Jiangsu Zhejiang Anhui Fujian Total %
Thermal power MW 11382.6 20599 13082.4 9056.3 6999.9 61120.2 80.4%
Hydro power MW 0 137.2 5866.8 649.1 6512 13165.1 17.3%
Nuclear power MW 0 0 1678 0 0 1678 2.2%
Wind power and
others MW 0 0 50.2 0 12 62.2
0.1%
LCMR MW 19.6%
Total MW 11382.6 20736.2 20677.4 9705.4 13523.9 76025.5
Data source: China Electricity Yearbook 2003
Installed capacity of East China Grid in 2001
Installed capacity
(in MW) Shanghai Jiangsu Zhejiang Anhui Fujian Total
%
Thermal 57967 104062 65691 40816 21170 289436 86%
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 78
Hydroelectric 0 57 10513 926 23433 34999 11%
Nuclear 0 0 2472 0 0 2472 0.01%
Wind and others 0 0 0 0 0
Total LCMR 11%
Total 57967 104119 78676 41742 44603 326907
Data source: China Electricity Yearbook 2002
EFBM,y= 0.9372×92.53%=0.8672 tCO2/MWh.
Step 7. Calculate the combined margin emission factor
The combined margin emission factor is calculated as follows:
EFgrid, CM,y = EFgrid, OM,y × wOM,y + EFgrid,,BM,y × wBM,y (14)
Electricity baseline emission factor is calculated as the weighted average of the Operating Margin
emission factor (EFOM,y) and the Build Margin emission factor (EFBM,y) where the weights wOM and wBM,
by default, are 50% (i.e., wOM = wBM = 0.5). This is presented below.
Eastern China Grid OM Ex Ante (tCO2/MWh) 0.942102
Eastern China Grid BM Ex Ante (tCO2/MWh) 0.8672
Eastern China Grid CM Ex Ante (tCO2/MWh) 0.9047
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 79
Annex 4
MONITORING INFORMATION
TABLE OF CONTENTS
I. Background information
II. Organizational, Operational and Monitoring Obligations
A. Obligations of the Operator
B. Emissions Reductions Calculation Spreadsheets
III. Annexes
I. Background Information
The baseline and monitoring methodologies for the Project are in accordance with the approved baseline
methodology, AM0025, the Tool to Calculate the Emission Factor for an Electricity System and the Tool
to avoid methane emissions from dumping waste at a solid waste disposal site. They are applicable to the
project activity, which consists of the diversion of MSW from a landfill and its controlled incineration,
i.e. Option (e) of AM0025, as well as renewable electricity generation for a grid.
The Project will be comprised of two different components: (i) the installation of a waste incinerator
system with a total capacity for 660 tonnes of waste per day; and, (ii) the generation of electricity using
heat from the incineration as fuel in a 12 MW generator. The total ERs from the Project are estimated ex-
ante at an annual average of 82,365 tCO2e. A total reduction of approximately 576,558 tCO2e is
projected for the first 7-year crediting period. The spatial extent of the project boundary is the site of the
project activity where the waste is treated. This includes the facilities for processing the waste, on-site
electricity generation and/or consumption, on-site fuel use and the landfill site. The project boundary
does not include facilities for waste collection, sorting and transport to the project site, but it does
include the Eastern China Power Grid, to which the on-site generation plant will be connected. Since the
Project provides electricity to a grid, the spatial extent of the project boundary will also include those
plants connected to the energy system to which the plant is connected.
II. Organizational, Operational and Monitoring Obligations
A. Obligations of the Operator
Monitoring the Project‘s ER performance requires proper data collection and processing by the Project
Operator. The Project Operator has the primary obligation to calculate ERs based on the most recent
available information, following the Emission Reduction Calculation Procedure (ERCP), and to abide by
the ERCP Organizational Structure as well as the ERCP Quality Control provisions presented in the
Annex to this MP.
The ERCP Organizational Structure dictates that the ERCP Manager will be responsible for performing
the ERCP (monthly), and the MP Steering Committee will be responsible for supervising the ERCP
Manager‘s monitoring work (monthly). The ERCP Manager will report to the MP Steering Committee
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 80
(monthly), and the ERCP Manager and MP Steering Committee will coordinate in reporting to the DOE
at Verification. The ERCP Quality Control provisions will offer additional guidance to the Monitoring Plan on how to
handle monitoring data to ensure that sufficient and accurate information is made available to the DOE.
Specifically, the ERCP Quality Control demonstrates how to trace back the avoided emissions from the
Nanhu landfill, as well as the electricity produced by the Project from the off-taker of the surplus power.
All data required for the MP will come from the Project Operator‘s information system, and it is the
responsibility of the Project Operator to ensure that this data is made available monthly to the ERCP
Manager.
It is believed that the monitoring approach presented in this MP will result in an accurate, yet
conservative calculation of ERs. However some uncertainties, especially errors in the data monitoring
and processing system, may result in a discrepancy between the monitored ERs and the verified ERs. The
Project Operator is expected to prevent such errors, and the verification audits are expected to uncover
any potential ones. Given that CERs can only be certified after Verification, there is a significant internal
incentive for the Project Operator to perform all steps related to data collection and calculations as
accurately as possible.
The ERCP Manager will seek to establish and maintain a positive and efficient relationship with the
DOE verifying the Project‘s ERs so as ensure a dependable and transparent outcome. In doing so, the
ERCP Manager will:
provide all necessary monitoring information to facilitate the Verification, and cooperate with the
DOE in a timely manner on all data requests and questions;
during the crediting period, always take into account requests by the CDM Executive Board and
conduct preparatory work for the verification to obtain high quality and efficient results; and,
ensure that all monitoring reports are reviewed by the ERCP Manager and the MP Steering
Committee before they are transmitted to the DOE.
Training is an important element in successful monitoring of ERs. The MP and associated training on it
will build the capability of the MP Steering Committee and the ERCP Manager to replicate - on an ex-
post basis – an equivalent process that has been demonstrated in this PDD for an ex-ante emissions
avoidance calculation as if the plant were in operation in 2005. All relevant personnel will be trained by
ENDESA Carbono at a one- day workshop on a comprehensive set of tools and knowledge required to
implement the MP, including: (a) accurate monitoring of the performance and output characteristics of
the plant for recording and keeping accurate data; (b) collection and integration of utility data for the
current year; (c) incorporation of these data sets into Excel spreadsheets pre-prepared by ENDESA
Carbono, and (d) consistently calculating verifiable CERs as a function of measured plant output against
a current-year emission factor that serves as a recognized proxy for emissions displaced from the grid.
Adequate equipment will be defined and procured during project construction, which will be used for
monitoring MSW treated, fuel consumption, and electricity that is generated, consumed on-site, and
dispatched to the grid. Procedures for maintenance and installation of equipment, as well as calibration,
will be performed according to manufacturer‘s specifications. All measurements, data gathering, record
keeping, and procedures for dealing with possible data adjustments will be performed taking into
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 81
consideration the specific data gathering requirements of the MP, and will also meet the requirements of
both AM0025 and the Tool to Calculate the Emission Factor for an Electricity System.
The ERCP is designed for performing quality control on the ER calculation, and provides procedures to
guarantee the accuracy of the results. The quality control procedures deal with data collection,
processing, record keeping, and cross-checking. It is therefore, expected that the MP approach presented
in this PDD will result in an accurate, yet conservative calculation of ERs.
Table A4-1: Monthly Data Collection: Division of Labor
Electricity distributor
final client(s)
(Data Provider)
provide the Project Operator with written proof of the
Project‘s hourly generation purchased/sold.
Frequency: Monthly
Grid Operator
(Data Provider)
provide the Project Operator with written proof of the
Project‘s hourly generation registered.
Frequency: Monthly
Project Operator
(Data Processor)
directly measure the MSW incinerated in the project facilities
following AM0025.
estimate ERs for electricity displacement following Tool to
Calculate the Emission Factor for an Electricity System.
estimate the project emissions following AM0025.
perform the monthly calculation of ERs following the ERCP.
keep receipt of sales of electricity.
prepare and submit the annual report of the total project ERs
to the DOE.
establish the necessary agreements with the Grid Operator and
final clients to assure that they all provide a monthly written
report of the Project‘s hourly generation registered/bought.
B. Emissions Reductions Calculation Procedure and Required Spreadsheets
The ERCP is the basic instrument for gathering, recording and processing information that will result in
the measured ERs. The Project Operator shall consider the Project‘s ERCP as a manual. The ERCP
should contain: (i) data gathered from the Grid Operator information system, (ii) data processed by the
Project Operator, and (iii) data gathered from the equipment installed for the monitoring of the MSW
incinerated. All data processing should be done using Excel software. The ERCP is designed for
monthly and yearly calculation, based on final monthly Grid Operator reports and monthly recording and
continuous recording of the meters installed. Entering the data monthly in the required spreadsheets will
provide the opportunity to review formulas, minimize errors and have data readily available for the DOE
at any time during the year.
For effective data management, ENDESA Carbono will provide the Project Developer with an MP and
pre-programmed spreadsheets such that the Project Developer will only need to collect the information as
described and apply the formulas as instructed in the MP.
The Project Operator will calculate the ERs on the basis of the MP, following the ERCP. Calculations
will follow AM0025 to calculate ERs from the avoided methane emissions by the Project, and the Tool
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 82
to Calculate the Emission Factor for an Electricity System to calculate the ERs from electricity
displacement when the Project provides renewable electricity to the grid.
There will only be two spreadsheets to be reviewed by the DOE, namely, ―changshu ACM0002 ERs at
‗yearly period in question‘.xls‖ and ―changshu AM0025 ERs at ‗yearly period in question‘.xls‖.
However, as the DOE may require preliminary calculations, the staff person designated as the ERCP
Manager should keep the name of the files, and every time he/she works on the files, should follow by
the date when the latest adjustment was made. Doing so would allow old versions to be saved on disk
and kept as a record to show to the verifier, if the need arises.
When the ER calculation for the month is completed, the files should be named ―changshu ACM0002
ERs at ‗month in question‘.xls‖ and ―changshu AM0025 ERs at ‗month in question‘.xls‖, in order to
differentiate drafts from final monthly calculations. Likewise, after the calculation of the ERs of the last
month of the year, the file name should be changed to ―changshu ACM0002 ERs at ‗yearly period in
question‘.xls‖ and ―changshu AM0025 ERs at ‗yearly period in question‘.xls‖.
The year for the MP will run from 1 January through 31 December of the following year.
Spreadsheet 1, ―changshu ACM0002 ERs at ‗yearly period in question‘.xls‖ will be composed of two
worksheets: Worksheet # 1: Original Data from Grid operator, and Worksheet # 2: Organized Data,
Processed Data and Result.
Worksheet # 1 should contain data as it was provided by the Grid Operator, on a CD or in email,
arranged in months. The ERCP Manager should not manipulate this data other than to copy and paste it
from the file in which it was handed. The CD or e-mail through which the data comes from the provider
should also be kept as proof for the DOE.
For Worksheet # 2, the ERCP Manager should put in one column per month the monthly project
generation. In this same Worksheet, the ERCP Manager should calculate monthly ERs in tCO2e by
multiplying the generation in MWh times 0.8672 in tCO2e/MWh (the Baseline Emissions Factor for
China‘s Eastern Power Grid calculated ex-ante as described in Annex 3), and which will be used for the
first 7-yr crediting period. Rounding off is not necessary when calculating monthly ERs since the
monthly calculation is only for measuring progress. At the end of the year, the ERCP Manager should
sum up the resulting monthly ERs from electricity displacement to obtain the yearly project ERs from
electricity displacement ready for Verification. Resulting yearly ERs from electricity displacement must
be rounded off to the nearest integer. Once the calculation of yearly ERs from electricity displacement is
completed in the ―Changshu ACM0002 ERs at November.xls‖47
, this file should become ―changshu
ACM0002 ERs at ‗yearly period in question‘.xls‖.
Worksheet # 2 also allows the ERCP Manager to calculate the cumulative generation and cumulative
ERs from electricity displacement throughout the year and be aware of the progress of the Project‘s
environmental benefits accrued due to ERs from electricity displacement.
47 November is the last month of the year for the MP.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 83
Spreadsheet 2 ―Changshu AM0025 ERs at ‗month in question‘.xls‖ will be composed of four
worksheets.48
It is necessary for the data gathered from the equipment installed to the MSW to be
processed monthly such that the worksheets can be annualized at the end of the year, and the results
coming out from the application of the ―Tool to determine methane emissions avoided from disposal of
waste at a solid waste disposal site‖.
Worksheet # 1 should contain the ERs from avoided CH4 emissions calculated as per Tool to Determine
Methane Emissions Avoided from Disposal of Waste at a Solid Waste Disposal Site before discounting
project emissions, as per AM0025. Worksheet # 2 should contain project emissions from the
incineration project activity as per AM0025. Worksheet # 3 should contain methane emissions from
wastewater treatment if any. Worksheet 4 should contain ERs from avoided CH4 emissions after
discounting project emissions.
During all stages of monitoring, the project entity will assign a primary, secondary and a support stuff to
ensure that there is a qualified and trained person available at all times to implement the monitoring plan
properly.
Regular calibration will be performed according to the manufacturer‘s guidelines, or according to the
applicable regulations, by a suitably skilled technician at the required frequency (at least once a year). A
certificate of calibration will be provided for each piece of equipment after completion.
48 Spreadsheet 2 should always take the latest data of Spreadsheet 1, but no Excel links are to be made since they could overload both files.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 84
Monitoring Plan
Emission reductions Calculation procedure (ERCP)
Quality Control for Electricity Displacement
Grid Operator
Data:
Project´s monthly generation registered by Grid operator, provided in excel by Grid Operator via email or
CD to the Project Operator.
Project Operator
Data:
Net electricity sold to Grid Operator
The Project Operator will perform monthly recording and calibration check of electric meters
periodically. Only one person will be responsible for the ERCP: Mr. Lu Jiqing
Quality of Data Collection:
Data: Monthly generation from Grid Operator, remaining information from the Project Operator.
Format: Summarized in Excel
Frequency: monthly
Quality of Data Processing:
Original data
Organized data
Entered data
Processed data
Results
Quality of Data Delivery:
Provide to the DOE the emails/CDs through which Data Provider delivered the original data
Provide to the DOE the sales receipts
Provide to the DOE evidence of all calculations made showing all preliminary versions of
spreadsheets saved on disc.
Monthly calculations involve 5 data points.
All must be recorded and manipulated in
excel with records of data points and
electricity sales receipts.
Yearly consolidation of monthly
calculations.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 85
Monitoring Plan
Emission reductions Calculation procedure (ERCP)
Quality Control for Methane Avoidance
MSW Data:
MSW processed registered by the scale/load cells (continuous measurement of waste
composition percentages)
PE measurement according to the AM0025
The Operator will perform monthly recording and calibration check of flow meters periodically. Only
one person will be responsible for the ERCP: Mr. Lu Jiqing
Quality of Data Collection:
Data: All the above from measurement devices.
Format: Summarized in excel
Frequency: monthly
Quality of Data processing:
Original data
Organized data
Entered data
Processed data
Results
Quality of Data storage:
Prevent excel version problems by updating excel software packages every year in PCs used for
the ER calculations;
Keep all data for 2 years after the first crediting period, i.e for a total of 9 years;
Assign a password to Excel spreadsheets used for ERCP;
Save the document with the last date in which an alteration was made so that old versions are
kept on disc;
Keep all written documentation in a folder that will be provided to the DOE together with the
data collected in Excel.
Quality of data Delivery:
Provide to the DOE the emails/CDs through which Data provider delivered the original data
Provide to the DOE evidence of all calculations made showing all preliminary versions of
spreadsheets saved on disc.