claytor hydroelectric project water quality study mark hutchins, project manager january 25, 2007
TRANSCRIPT
Claytor Hydroelectric Project
Water Quality Study
Mark Hutchins, Project Manager
January 25, 2007
About Normandeau Associates, Inc. New Hampshire-based natural resources
consulting firm founded in 1970
Employee-owned since 2001
13 fully-staffed offices nationwide
Known for managing complex field and impact assessment projects
Recognized as one of the largest natural resource management companies in the U.S. (EBJ)
Hydro Relicensing Services
FERC Relicensing and Compliance Fish Passage Wetlands, Endangered Species &
Wildlife Water Quality Monitoring and
Mitigation Instream Flow
Studies
Representative HydroPower Projects
Dozens of Hydro projects throughout the U.S. Yadkin Relicensing (NC) Tapoco Relicensing (NC/TN) Santee Cooper Relicensing (SC) TVA Reservoir Operations Study EIS (35
dams, 6 states)
Project Organization Chart
Mark HutchinsProject Manager
Rick SimmonsField Supervisor
Jeff WollisField Scientist
Claytor Lake Water Quality Study
Study Goals– Evaluate WQ within and downstream of Claytor
Lake– Determine how hydroelectric operations affect WQ– Determine how hydroelectric operations could be
modified to improve WQ, if necessary Study Methods
– Collect existing WQ data– Collect new WQ data– Characterize existing WQ conditions– Recommend measures to enhance WQ, as
appropriate
Specific Study Objectives
Objective 1: Assemble and Review Existing Data• All recent (last 15 years) data immediately
upstream, within and downstream of Claytor Lake will be retrieved.
• Know data sources are state agencies, colleges and universities and non-governmental agencies
• QA/QC data• VDEQ will determine data acceptability
Specific Study Objectives
Objective 8: Assess Adequacy of Existing Upriver and Downriver Temperature Data• Evaluate existing VDGIF continuous temp
data to determine completeness, deficiencies and additional data needs.
• Modify field collection study plan, if appropriate, to fill data gaps
Specific Study Objectives Objective 4: Collect Additional WQ Data
• Sampling period – generally, once weekly, June 15 to September 15• Four locations – inflow to Claytor Lake, lower Claytor Lake, Claytor Dam
tailrace and select downriver locations At an upriver mussel bed
• Temperature only Within Claytor Lake at three transects (forebay, 1km, 2km)
• Sampling will occur at 4 equi-spaced locations per transect• DO, temp, pH and conductivity by 1-meter vertical profile• Chlorophyll a by field meter at one center location per transect by 1-meter vertical
profile In Project tailrace – continuous monitoring
• Sampling will occur at one well-mixed location• DO, temp, pH and conductivity
3 downriver transects (Rt 11 bridge, upriver of Plum Creek, Pembroke area)• Sampling will occur at each quarter point on each transect in pre-dawn/early
dawn hours• DO, temp, pH and conductivity by 1-meter profile, if appropriate
Specific Study Objectives
• Objective 2: Characterize Existing Study Area WQ
• Use existing and new collected WQ data• Focus will be DO/temp, but other WQ parameters
will be included• Characterization will be 4 dimensional –
longitudinal (Allisonia to Glen Lyn), horizontal, vertical and temporal
• Temporal focus will be spring, summer, early fall
Specific Study Objectives
Objective 7: Identify Impact of Project Operations on Claytor Lake and Downriver WQ• Identify, where possible how peaking
operations, water level fluctuations, water residence times and turbine intake zones affect reservoir and New River WQ
Specific Study Objectives
Objective 3: Identify Measures that could Enhance Downriver DO under Normal and Drought River Flow Conditions• Determine the magnitude, frequency and
duration of low DO events downriver of the Project
• Conduct a literature survey of methods used to improve DO at hydroelectric facilities
• Assess applicability to Claytor Lake
Specific Study Objectives
Objective 6: Determine Effects of Sediments on Claytor Lake WQ• Conduct a literature review of activities that
may affect sediment/water/fish interactions• Review VDEQ fish tissue and sediment
analyses data• Assess relevance to Claytor Lake
Specific Study Objectives
Objective 5: Develop Protocols for Future WQ Monitoring, as Appropriate• Identify remaining WQ data deficiencies • Detail how future sampling efforts should be
undertaken, spatially and temporally, to eliminate these deficiencies
Project Deliverables
Periodic Progress Reports Draft Information Report Final Information Report Weekly spreadsheets of new data to VDEQ Draft Final Report Final Report
Schedule
Progress Reports – May, August and November 2007
Draft Informational Report – May 2007 Final Informational Report – June 2007 Stakeholders Meeting – May 2007 WQ Sampling Program – June 15-September
15, 2007 Draft Final Report – January 2008 Stakeholders Meeting – February 2008 Final Report – by May 30, 2008