TECHNICAL CLARIFICATION SHEET
CANTILEVER AND DRILL FLOOR SKIDDING SYSTEM UNDER JU 2000E PROJECT
Time : 01/Aug/2012
Place : PVShipyard head office – 65A2, 30/4 Road, Vung Tau city
Bidder Name EMS
Clarification No. 01
Prepared by Huynh Phat Huy – Mechanical Engineer
Bidder shall clarify base on Bidder’s proposal
No. DESCRIPTIONS PVSHIPYARD’S CLARIFICATION BIDDER’S REPLIES EVALUATION
1 GA DrawingBidder’s to provide GA drawing of Hilman Roller c/w Tapered FABREEKA Pad for PV Shipyard review.
2 P&IDBidder to provide P&ID of Cantilever and Drill floor skidding system.
3 Design RulesBidder to update design rule follow ABS rule for Building and Classing MODU 2012 (not 2008 as BIDDER’s proposal)
4 Project reference listBidder to provide Project reference list for PV Shipyard review.
5
6
7
8
Page 1 of 1