City of Raleigh
Pleasant Valley Road Widening Project October 11, 2016
City Manager Presentation
Pleasant Valley RD 2016
Pleasant Valley Rd. Widening Project
Project Location
Purpose of Project Pleasant Valley RD 2016
• Reconstruct Damaged Pavement
• Widen to a Three-Lane Section (According to Comprehensive Plan)
• Add Facilities For Pedestrians and Bicycles on both sides of the road
• Add pedestrian refuge at signalized intersections (Duraleigh and Glenwood)
Project Challenges Pleasant Valley RD 2016
• Minimize Property Encroachment
• Proximity Parking Lots
• Existing Utilities
• Stormwater
Proposed Design Pleasant Valley RD 2016
6’ CONCRETE
SIDEWALK
VARIABLE WIDTH
PLANTING STRIP
TWO-WAY LEFT TURN
CENTER LANE
6’ CONCRETE
SIDEWALK
5’ BIKE LANE
Typical Section Pleasant Valley RD 2016
76’ (Varies) RIGHT-OF-WAY
6’ 2’ 6’ 2.5’ 5’ 11’ 11’ 11’
Note: Dimensions shown on right side of the road apply also to left side.
VA
RIE
S
Stormwater Design Pleasant Valley RD 2016
Water Quality Management • Nitrogen Treatment handled through City of Raleigh
credit bank from other projects
Water Quantity Management • Approximately 1000 ft3 of storage provided in
oversized pipes along Pleasant Valley Road
Funding & Schedule Pleasant Valley RD 2016
On December 8, 2015 the Raleigh City Council approved a $398,533 contract agreement with AMT for design , SUE, survey, landscaping, and geotechnical services.
Estimated Project Cost
$3.7 Million Including Construction and Right of Way
Project Schedule:
• Complete Right of Way Acquisition – Early 2018 (4-6 Month Duration)
• Award Construction Contract – Spring 2018
• Complete Construction – Spring 2019