City of Marshall Development Proposal
to Action Manufacturing, Inc.
November 26, 2013
![Page 2: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/2.jpg)
Evolution of Trackchair
http://youtu.be/Cz9vutYMjuE
![Page 3: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/3.jpg)
City Provided Ground Lease/Infrastructure
• Airpark East Development Area:o 1560 Madrid Circle
• 99 year ground lease for $1/yearo 5 Acres: Market Value of $125,000
• All public utilities completed (water, sanitary sewer, stormwater, electric, streetlighting).
• Special Assessments o Waive $325,000
![Page 4: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/4.jpg)
Minnesota Investment Fund Loan• $240,000 Loan:o 2% Interest for 7 yearso Job Retention of 13 FTE’so Job Creation of 10 FTE’so$13.00/hour with $2.00/hour benefits
![Page 5: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/5.jpg)
Airpark East Development Area
![Page 6: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/6.jpg)
Development Plan• Action Manufacturing Construction DetailsoApproximately 20,000 square foot
warehouse 18K SF: manufacturing, welding, fabrication,
assembly 2K SF: office space/restrooms
![Page 7: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/7.jpg)
Site Plan
![Page 8: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/8.jpg)
Floor Plan
![Page 9: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/9.jpg)
Future Development
![Page 10: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/10.jpg)
Recap of Obligations• City of Marshall Obligationso99 year lease for $1/year ($125,000)oWaive special assessments ($325,000)oMIF Loan ($240,000)oSite Grading
• Action Manufacturing Obligationso 20,000 square foot warehouseo Job Retention of 13 FTE’so Job Creation of 10 FTE’s o $13.00/hour with $2.00/hour benefits
![Page 11: City of Marshall Development Proposal to Action Manufacturing, Inc. November 26, 2013](https://reader034.vdocuments.us/reader034/viewer/2022051216/5697bf851a28abf838c87822/html5/thumbnails/11.jpg)
Recommendation• Approve Contract for Private Development
Including Ground Lease and Business Subsidy Agreement for Action Manufacturing, Inc.