city of houston sylvester turner...c ity of houston george bush intercontinental ~ william p. hobby...

44
CITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council Members: Amy Peck Jerry Davis Abby Kamin Carolyn Evans-Shabazz Dave Martin Tiffanny D. Thomas Greg Travis Karla Cisneros Robert Gallegos Edward Pollard Martha Castex-Tatum Mike Knox David W. Robinson Michael Kubosh Leticia Plummer Sallie Alcorn Controller: Chris B. Brown July 8, 2020 SUBJECT: Addendum No. 3 REFERENCE: Invitation to Bid (ITB) for Runway 17-35, Demolition at William P. Hobby Airport; Solicitation No. H27-RR770B-2020-011; PN 770B To: All Prospective Respondents This Addendum is being issued to I) respond to questions, II) replace sections / documents and III) add attachments. I. Respond to Questions 1. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019, Project No. 770 is submitted without any warranty. How does the Contractor undertake finding information that it can rely on related to this plan? Response: The Construction Safety and Phasing Plan (CSPP) is a document prepared by the airport operator, that is submitted to and approved by the FAA, as a tool to ensure safety compliance when coordinating construction activities. The CSPP includes requirements that must be implemented by the contractor during construction to safely construct the work. The contractor is responsible for preparing a Safety Plan Compliance Document (SPCD) in accordance with the requirements of the CSPP and FAA AC 150/5370-2G. The SPCD may be relied upon once approved. 2. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019, Project No. 770, requires that revised to scope or schedule to the project may necessitate revisions to the construction safety phasing plan (“CSPP”). Are revisions to the CSPP and approvals accomplished through a Change Order? Response: Revisions to the CSPP are a matter between the airport operator and the FAA. Such changes may or may not require revisions to the SPCD, Safety and Phasing Plans, General Notes, or other contract documents, that may or may not result in the need for a change order being issued. 3. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019, Project No. 770, Appendix E, Under General Contractor Notes Nos. 3 and 9, who is responsible if the utility company makes an error in flagging and the contractor damages the utility? Response: There is insufficient information in this hypothetical situation to determine who might be responsible for damages to a utility. However, the contractor would only be responsible if the utilities are located on the drawings, markings by the utility owner, or other clear indicator that the utility is in that location. DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Upload: others

Post on 13-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

CITY OF HOUSTON

George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport

Sylvester Turner

Mayor

Mario C. Diaz

Director of Aviation

Council Members: Amy Peck Jerry Davis Abby Kamin Carolyn Evans-Shabazz Dave Martin Tiffanny D. Thomas Greg Travis Karla Cisneros

Robert Gallegos Edward Pollard Martha Castex-Tatum Mike Knox David W. Robinson Michael Kubosh Leticia Plummer Sallie Alcorn

Controller: Chris B. Brown

July 8, 2020

SUBJECT: Addendum No. 3

REFERENCE: Invitation to Bid (ITB) for Runway 17-35, Demolition at William P. Hobby Airport; Solicitation No. H27-RR770B-2020-011; PN 770B

To: All Prospective Respondents

This Addendum is being issued to I) respond to questions, II) replace sections / documents and III) add

attachments.

I. Respond to Questions

1. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019,Project No. 770 is submitted without any warranty. How does the Contractor undertake findinginformation that it can rely on related to this plan?

Response: The Construction Safety and Phasing Plan (CSPP) is a document prepared by the airport

operator, that is submitted to and approved by the FAA, as a tool to ensure safety compliance when

coordinating construction activities. The CSPP includes requirements that must be implemented by the

contractor during construction to safely construct the work. The contractor is responsible for preparing

a Safety Plan Compliance Document (SPCD) in accordance with the requirements of the CSPP and

FAA AC 150/5370-2G. The SPCD may be relied upon once approved.

2. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019,Project No. 770, requires that revised to scope or schedule to the project may necessitate revisions tothe construction safety phasing plan (“CSPP”). Are revisions to the CSPP and approvals accomplishedthrough a Change Order?

Response: Revisions to the CSPP are a matter between the airport operator and the FAA. Such

changes may or may not require revisions to the SPCD, Safety and Phasing Plans, General Notes, or

other contract documents, that may or may not result in the need for a change order being issued.

3. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019,Project No. 770, Appendix E, Under General Contractor Notes Nos. 3 and 9, who is responsible if theutility company makes an error in flagging and the contractor damages the utility?

Response: There is insufficient information in this hypothetical situation to determine who might be

responsible for damages to a utility. However, the contractor would only be responsible if the utilities

are located on the drawings, markings by the utility owner, or other clear indicator that the utility is in

that location.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 2: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

4. Question: Jacobs Runway 17-35 Demolition Construction and Safety Plan dated August 23, 2019,Project No. 770, Appendix E, Under General Contractor Note No. 13, who is responsible for notifyingthe Contractor of the location of the underground cables or is the Contractor’s only source ofinformation the contacts given under Security Requirements No. 8?

Response: The City is unable to provide specifications or details as to electronic safety and security

requirements. The electronic safety and security requirements will be determined by the selected

contractor.

5. Question: Under the 00700 General Conditions, Article 3.9.3, Contractor is required to restoredamaged property to its original condition. Does original condition mean its condition immediately priorto damage?

Response: For the purpose of this project, the original condition refers to the condition prior to

Contractor's Notice To Proceed. That condition includes current storm drainage patterns for regrading

the site.

6. Question: Under the 00700 General Conditions, Article 3.16.3, Contractor is required to provide theCity Attorney all documents and records necessary for the Contractor’s compliance with the Contract.What type of documents and records are customarily required and when?

Response: All documents related to the project and to the Contract. Document 0700 governs when

the City may request documents and the time by which Contractor must comply.

7. Question: How are the 00701 FAA General Contract Provisions interpreted with and harmonized withthe Contract between the City and the Contractor (00700 General Conditions) in light of Article 13.9 ofthe Contract? In particular, the warranty and indemnity obligations are different.

Response: Please provide example of conflict in the language.

8. Question: Under the 00700 General Conditions, Article 2.2.4 is “reasonable promptness” interpretedto be reasonably prompt in light of the demands of the project?

Response: The objective standard is intended.

9. Question: Under the 00700 General Conditions, Article 2, does the City make any warranty to theContractor on information provided?

Response: Any warranties made by the City would be expressly stated in the contract.

10. Question: Under the 00700 General Conditions, Article 3.25, who are intended to be the agents ofthe City that are not its employees, officers or legal representatives?

Response: The City does not name specific agents in its contract.

11. Question: Under the 00700 General Conditions, Article 3.25.1.1, who are intended to be agents ofthe Contractor that are not its employees, officers, directors, contractors or subcontractors?

Response: Please refer to response provided in Question #10.

12. Question: Is the City aware that under 00700 General Conditions, Articles 3.25.1.2 and 3.25.1.3 thatinsurance policies customarily provided to contractors do not provide insurance coverage for thenegligence or strict liability of the City (or any third party)?

Response: No.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 3: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

13. Question: Under 00700 General Conditions, Article 3.25 has a 4-year tail-end indemnity obligation onthe Contractor. The typical statute of limitations is 2 years after the cause of action occurs. This is inpart due to evidence becoming stale. Also, it is unknown on whether or not insurance coverage isprovided for obligations arising after the statute of limitations. In light of these factors, will the Citychange this obligation to the application statute of limitations for the cause of action alleged?

Response: No, this is the City's standard language.

14. Question: Under 00700 General Conditions, Article 3.25.2, in light of this likely being an uninsuredobligation, we request that the amount be reduced to $250,000.

Response: Requirements remain as stated.

15. Question: Does the City believe that the indemnity obligations in 00700 General Conditions andunder 00701 FAA General Contract Provisions, are subject to Article 151 of the Texas InsuranceCode?

Response: The City does not provide legal advice to bidders.

16. Question: Under 00700 General Conditions, Article 3.27.2.1, if the Contractor has financialresponsibility for the indemnified claim, then why does the Contractor need to seek approval from theCity for counsel?

Response: City requirement.

17. Question: Under 00700 General Conditions, Article 4.3.3, can a claim be timely filed in the 90-dayperiod if all of the information needed for the claim is not available in the 90-day time period, such asthe impacts of or a changing scope that is not final?

Response: The general conditions are as stated.

18. Question: Under 00700 General Conditions, Article 8.2.6.1, please confirm that the time period for filea claim for a delay is limited to no longer than 48 hours from the event giving rise to the delay?

Response: The general conditions are as stated.

19. Question: Under 00700 General Conditions, Article 8.2.6.1, can a claim be timely filed in the 48-hourperiod if all of the information needed for the claim is not available in the 48-hour time period, such asthe impacts of or a changing conditions or scope that is not final?

Response: In the case of scope changes, the "event" would be when the change order is executed.

Prior to an executed (finalized) change order, any work done by the contractor would be at risk.

20. Question: Under 00700 General Conditions, Article 4.3.5.1, please confirm that time period for filing aclaim for concealed conditions (as defined in this Article) is no later than 5 days from first observation?

Response: The general conditions are as stated.

21. Question: Under 00700 General Conditions, Article 4.5.1, please confirm that the condition precedentby the City Engineer applies to both the City and the Contractor?

Response: The condition precedent applies to the City and Contractor.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 4: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

22. Question: Please explain the equities of 00700 General Conditions, Article 5.2.4, requiring theContractor to release retainage to the Subcontractor before the Contractor has been paid suchamounts from the City?

Response: Please define "equities" for the purpose of this question.

23. Question: Does 00700 General Conditions, Article 8.2.1.6 intend to cover restrictions becausepersonnel are quarantined relative to COVID-19 and similar pandemics?

Response: The contract addresses additional days at no cost to the City for various events, including

epidemics.

24. Question: Will written notice to the Contractor be given if the City Engineer decides to withholdpayment under 00700 General Conditions, Article 9.7?

Response: If written notice is required under the Contract, written notice will be provided in

accordance with the terms of the Contract.

25. Question: Does 00700 General Conditions, Article 9.7.1.8 include bona fide disputes on the jobperformance of the subcontractor?

Response: HAS will abide by the conditions of the contract which will be between HAS and the Prime

Contractor.

26. Question: Does title and risk of loss transfer on date that warranties commence under 00700 GeneralConditions, Article 9.9.5?

Response: Warranties required by the Contract shall commence on the Date of Substantial

Completion unless otherwise provided by City Engineer in Certificate of Substantial Completion.

Warranties may not commence on items not substantially completed.

27. Question: When does title and risk of loss transfer under the partially occupied portions of the projectunder 00700 General Conditions, Article 9.10?

Response: Partial occupancy or use of a portion of the work does not constitute acceptance of work

not in compliance with requirements of the Contract.

28. Question: If under 00700 General Conditions, Article 10.3.7, damage is caused in part by 3rd partiesunrelated to Contractor and not Subcontractors, the City, the Design Consultant or other contractors,is Contractor required to pay for or correct damage caused by these unrelated 3rd parties

Response: Contractor is not required to remedy damage or loss attributable to the City, Design

Consultant, or other contractors.

29. Question: Are corrections under 00700 General Conditions Article 12.2.5, are corrections no longerrequired after the one-year period but for a claim still in the warranty period?

Response: The warranty period begins at substantial completion of the project or project phase. This

would be the same one-year period for claims.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 5: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

30. Question: Under 00700 General Conditions Article 14.1.1.1, should there be an expressed negativeconsequence stated to not having enough skilled workers such as not keeping the schedule?

Response: The contractor is responsible for providing all resources as needed, including equipment,

materials, labor, supervision, etcetera to meet the contract requirements.

31. Question: Under 00700 General Conditions Article 14.1.2.2, the remedy appears to be anexpropriation without compensation by a government authority. Is this correct?

Response: Please see Section 14.1.2 in its entirety for clarification.

32. Question: Under 00700 General Conditions Article 14.1.2.2, is the City responsible for all damages

and wear & tear caused by taking possession of Contractor’s equipment?

Response: This language does not appear in 14.1.2.2.

33. Question: Why is a condition of default under 00700 General Conditions Article 14.1.1.5 a failure toutilize low–sulfur diesel fuel, when under 00700 General Conditions Article 9.12.2 Contractor isassessed a penalty for high sulfur diesel fuel usage?

Response: A single use may be assessed a penalty; the on-going use of high sulfur fuels may invoke

Article 14.1.1.5.

34. Question: Item D-900 Underground Stormwater Storage Facility – Can you provide the schematicdrawings showing the footprint size and location? What is the minimum capacity, or the amount ofstorage required for the facility?

Response: Schematic drawings for Underground Stormwater Storage Facility are attached to this

Addendum (attachment #1). The contractor is expected to provide a system that will fit, into the

existing area being demolished. There are bid tab items to address cost of the additional installation,

cost of any "leveling course (excavation or fill), and a credit for fill not used due to the space occupied

by the system.

35. Question: Is it HAS's preference that the proposal, financial and pricing content be packagedindividually in separate envelopes at the time of submission?

Response: This is an Invitation to Bid, the 410B needs to be filled out in its entirety. No proposal or

financial data is required.

36. Question: On drawing E3.01 at radius on Taxiway E, Sign #SN105 is shown as new. Is a new padrequired? Provide the legends, # modules and Size required?

Response: Sign SN105 is an existing sign to be relocated, in conjunction with the holding position

marking relocation at the approach end of Runway 13R. It will require a new base. The legend is "E

13R-31L" on the primary side, with "E" on the reverse side. It is a Size 2, four-module sign.

37. Question: Specification Section L-100, Is the current ALCMS 100% functional?

Response: No insufficiencies have been identified.

38. Question: Specification Section L-100 Paragraph 100-1.6 calls for the ALCMS Manufacturer tosubmit ALCMS equipment specifications to the contractor. Is any new equipment required? Is thismodifications graphics only changes?

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 6: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Response: It is unknown if any new equipment is required to accomplish the reconfiguration. The

ALCMS manufacturer was Liberty, (now ADB) and they should be contacted to determine the

requirements for the graphics changes.

39. Question: Specification Section L-100, If graphics only changes are required, does paragraphs 100-1.08 thru 100-1.19 apply to this project?

Response: It should be determined by the ALCMS manufacturer if the change is graphics only.

40. Question: There are three conflicting dates

- On HAS Website, it’s showing Award Date of 9/16/2020

- Bid Form 00401A Part A Item C, shows Period for Bid Acceptance is 180 days.

- Specification 701 FAA General Provisions, 30-02 Award of Contract within 120 days.

Can you clarify the above three dates because vendors adjust their pricing based on contract award

date?

Response: Award dates are only estimates. Your pricing shall be valid for 180 days.

41. Question: Will the work under Allowance Item 2 be per FAA Specification or HAS Specification?

Response: The work described in the cash allowance table is to be performed according to FAA

standards, and only with the pre-approval of HAS.

42. Question: Can you provide drawings for Allowance Item 3 work?

Response: Please refer to HOU North Loop Fiber Map drawing (attachment #2) included in this

addendum.

43. Question: During what phase will Allowance 2 & 3 work be performed?

Response: The cash allowance work may be performed within the duration of the contract, subject to

restriction of FAA NAVAIDs moratorium during Thanksgiving, Christmas, and New Year’s Day

holidays.

44. Question: Would HAS be willing to extend the question deadline for ITB No. RR770B-2020-011,P770B Runway Demolition at William P. Hobby Airport to June 25, 2020?

Response: Question due date has been extended to June 25, 2020 through Addendum No. 2.

45. Question: If the Contract Start Date were to change from its estimated October 5, 2020 date, what

allowances will HAS make in regard to the schedule and Seasonal Restrictions identified for Phases 7,

8, and 9 as identified in Table 1 - Areas Affected by Construction Activity (page 11 in PDF) in the

provided Construction Safety and Phasing Plan?

Response: No adjustments to the seasonal restrictions are possible, however the Phases do not

have to be executed in numerical order.

46. Question: If a company is MWBE are they able to receive the full percentage? or must they be justMBE or WBE?

Response: No. This project is a DBE driven goal and not MBE or WBE.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 7: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

47. Question: Does the airport have a location onsite where removed concrete and asphalt could bestored and processed in order to be re-used on future projects?

Response: All material is to be removed from the airport and disposed of by the contractor at an

approved off-site location.

48. Question: Will a water source be provided at the on-site locations of sod placement in order to set upa watering system? a. If not, will concessions be made to get personnel to the different phases inorder to water the sod for a minimum of 7 days after placement?

Response: It is the contractor's responsibility to provide a water source. All normal access restrictions

to the airfield will apply. Concessions are not possible.

49. Question: The bid form has listed an alternate for underground storm water storage facility but, thecurrent drawings do not show this item of work. Can revised drawings be provided to show the itemslisted as alternates?

Response: Schematic Stormwater Storage Facility drawings (attachment #1) are attached to this

Addendum, however, it is the contractor's responsibility to produce an engineered design.

50. Question: In order to award this project is approval of the FAA Grant required? If so, when is theanticipated approval date?

Response: The FAA Grants have already been approved and accepted.

51. Question: What company currently holds the maintenance agreement with the airport for pavementmarking?

Response: There is no maintenance agreement with an outside vendor. HAS’s Maintenance

Division performs regular pavement marking maintenance.

52. Question: What company currently holds the maintenance agreement with the airport for securitypersonnel?

Response: There are no 3rd party security firms with HAS, security is provided by internal resources.

53. Question: Bid items 31 & 32 are used twice in the bid sheet. Which items are to be used?

Response: A revised bid sheet is attached to this Addendum as described below (Section II, Item No.

4).

54. Question: Bid item 59 is a lump sum price, however, it has 4 lump sums, do you want this to be 4 EAor 1 LS?

Response: This bid item is revised to "EA" in the attached Addendum.

55. Question: Alternate bid items, where can the drawings and information be found for the stormwaterstorage facility? We are unable to find any information on these items.

Response: Please refer to response provided in Question No. 49.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 8: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

56. Question: Alternate bid item #3 P-152-4.2 Embarkment Place CY (10,075), is this a typo that youwant people to bid a negative on your bid form?

Response: The intention is to bid a negative quantity, because there will be a reduction in material

required to fill the volume of the pavement being demolished.

57. Question: In almost all of the documents we are finding 9 phases, however, on sheet C1.07 you areshowing 10 Phases. What is correct and if 10 phases are correct, what are the contract days for thatphase?

Response: There are 9 phases in total.

58. Question: The period for acceptance per bid form part A, states that this offer is open to acceptance

and is irrevocable for 180 days from the bid date. However, in the FAA general provisions sheet

00701-14 section 30-02 award of contract shall be made within 120 calendar days. What time frame is

correct for acceptance of the bid?

Response: Please refer to response provided in Question No. 40.

59. Question: What is the classification of Bid item 24 Removal of foreign substances/ contaminates andwhat type of landfill classification will they fit for disposal?

Response: This is unknown and should be determined by the bidder.

60. Question: Per the pre-bid it was stated that seeding is not allowed on this project. How will this affect

bid item 7 c-102-5 .1a temporary seeding and mulching 32.5 acres? Will you be removing this bid

item?

Response: The contract documents clearly instructs the type of seed, if any, that is allowed, and not

allowed on Airport property. Your seeding mix will be closely monitored for bird attracting seeds. This

bid item will remain.

61. Question: The pre-bid stated that the alternate is not part of the base bid but sheet 01230-1 ver. 9-15-1999 states that the lowest Total Bid Price will be evaluated on the basis of base bid price plusalternates. How is the low bidder going to be determined?

Response: Only the Base Bid pricing will be tabulated and evaluated. Responsive bidder with the low

bid meeting the specifications and minimum qualifications described in Document 00210, paragraph

14.C will be considered for award.

62. Question: Will OCP be required per the contract on this project?

Response: All insurance requirements are contained in the bidding documents.

63. Question: General Conditions 00700 Paragraph 3.11.2 states “The City will pay the actual costs ofCash Allowance item exclusive of profit, overhead or administrative costs”. Can a line item be added toinclude profit, overhead or administrative costs for the FAA work and will be paid for on a proratedbasis as the work is completed?

Response: When Cash Allowances are used, and pre-approved by the owner, payment will be on

documented costs for Time and Material.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 9: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

64. Question: On the NAVAIDS demo, are all the power cables included in bid Item 29 – P-101.5.18(Removal of Electrical Cable)?

Response: Yes.

65. Question: On the NAVAIDS PAPI and VASI demo, are there existing electric racks with disconnectswitches, step-up transformer, Step-down transformer, CenterPoint Electric meter? During the fieldvisit, these areas were not visited

Response: Power cables and other equipment are the property of the FAA and will be removed

through a Reimbursable Agreement.

66. Question: Detail on sheet E3.09 shows 8” wide full depth removal of concrete pavement for the new

electrical conduit and base can installation. The 8” wide trench for conduit and 24” core for the base

cans will not dowels to be installed. This may require a minimum of 5 feet wide trench to preserve the

integrity of the shoulder pavement. Please review and provide addition details.

Response: Dowels will not be required. See revised Sheet E3.09 attached.

67. Question: Drawing E3.08, Elevated Fixture Note #19, calls for Base Cans to be extended. Can a biditem be added for this work?

Response: Note 19 does not call for any cans to be extended, but instead provides a methodology

should they need to be. It is not anticipated that any base cans will need to be extended.

68. Question: The drawings does not show any work to be done on existing Manholes, Handholes or PullBoxes near the demolished pavement. Will the demolished Runway or Taxiway be backfilled to theexisting elevation?

Response: Yes, the runway will be backfilled to existing elevation.

69. Question: On each phase closure, there will be additional work required other than temporary cable.Some of the additional work not covered under bid items are covering lights that lead into closedareas, signs around closed areas with directional arrow point to the closed areas. Can a bid item beadded to make ready for temporary closure?

Response: The work described in this question, and all other work which does not have a direct pay

item listed in 00410B Bid Form Part B, is considered incidental, per Section 00800 Supplementary

Conditions.

70. Question: Will new sign panels be required, or can the signs be covered?

Response: Signs may be covered.

71. Question: Can PVC tube be used to cover lights in and around closed taxiway?

Response: Yes.

72. Question: On Drawing E1.01 Note 4 and 5, requires the Contractor to field verify existing circuit

routing and make temporary connection/jumper to keep continuity of the circuit. Not providing any

drawings would make it impossible to estimate the number of manholes to complete this task to give a

Lump Sum Cost for Bid Item #53 (Circuit Investigation and Tracing). Can you provide drawings with

circuiting?

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 10: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Response: Any existing utility information currently within our database has been provided to our

Engineer of Record.

II. Replace the following Sections/Documents

1. Replace Section 01145 - Contractor’s Use of Premises with the latest version dated 7/6/20.

2. Replace Section C-105-1 Mobilization with the latest version dated 7/6/20.3. Replace Section P-101 Preparation/Removal of Existing Pavements with the latest version dated

7/6/20.

4. Replace Document 00410 Bid Form with the latest version dated 7/8/20.

5. Replace Sheet G1.01 Sheet Index/Quantities, with the latest version dated 7/8/20.

6. Replace Sheet E3-09 Airfield Electrical Details, with the latest version 7/6/20.7. Replace Sheet C1.07 Erosion and Sedimentation Control General Notes, with the latest version

7/6/20.

III. Attachments

1. Schematic Stormwater Storage Facility Drawings2. HOU North Loop Fiber Map

When issued, Addendum shall automatically become part of the solicitation documents and shall supersede any previous specification(s) and/or provision(s) in conflict with the Addendum. Addendum will be incorporated into the Agreement as applicable. It is the responsibility of the bidder(s) to ensure that it has obtained all such letter(s). By submitting a bid on this project, bidder(s) shall be deemed to have received all Addendum and to have incorporated them into their bid.

If further clarification is needed regarding this solicitation, please contact Al Oracion, Sr. Procurement Specialist, via email at [email protected].

___________________ Cathy Vander Plaats Procurement Officer Houston Airport System

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 11: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

CONTRACTOR'S USE OF PREMISES01145-1 ver. 12-15-2017

SECTION 01145 (REVISED 07/06/20)

CONTRACTOR'S USE OF PREMISES

PART 1- GENERAL

1.01 SECTION INCLUDES

A. Rights-of-way and access to the Work.

B. Property and Base Facility outside contract limits.

C. General requirements for exterior work.

D. Work in AOA, including electrical lockout/tagout program.

E. Interior work.

F. Control of access into security areas.

1.02 SUBMITTALS

A. Show start dates and duration of closures and impediments on construction schedulefollowing Section 01325 - Construction Schedules.

B. Prepare written requests, using Document 00931 - Request for Information, and submitrequests at least 7 days before access is required, for following:

1. Roadway, street, driveway, curbside and building main entrance/exit closures orimpediments. Do not close or impede emergency exits intended to remain.

2. Access to property outside contract limits, required to extend or connect work to utilitiesor environmental system controls in non-contract areas.

C. For work involving electrical energy or other hazardous energy sources, submit aLockout/Tagout Program.

1.03 RIGHTS-OF-WAY AND ACCESS TO THE WORK

A. Confine access and operations and storage areas to contract limits and other areas providedby City, following Document 00700. Do not trespass on non-City-owned property or on airportoccupants' spaces.

B. Airport operates "around the clock." In cases of conflicts with construction operations, airportoperations take precedence. Airport roads, streets, drives, curbsides and sidewalks, andticketing, baggage claim, security check points, concessions, restrooms, aircraft gates andsimilar passenger-related areas are intended for year-round uninterrupted use and access bythe public and airport operations. Maintain uninterrupted traffic movement.

1. Aircraft and emergency vehicles have right-of-way in AOA.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 12: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

CONTRACTOR'S USE OF PREMISES01145-2 ver. 12-15-2017

2. Private vehicles, public transportation and emergency vehicles have right-of-way onroads, streets, driveways and curbsides.

3. Passengers have right-of-way in public spaces. Occupants have right-of-way in otheroccupied areas.

C. Follow instructions of the City Engineer, Airport Manager and of ATCT. Follow FAAprocedures.

D. FAA will review Contractor's submittals for compliance with FAA requirements. Attendmeetings with FAA to assist the City Engineer in obtaining approvals.

E. Continued violations of or flagrant disregard for policies may be considered default, andindividuals disregarding requirements may be determined as objectionable by the CityEngineer, following provisions of Document 00700.

1. Do not close or impede rights-of-way without City Engineer approval.

F. Temporary storage of products, stockpiles, and waste materials shall be limited to areasshown on Drawings.

1.04 PROPERTY AND BASE FACILITY OUTSIDE CONTRACT LIMITS

A. Do not alter condition of property or Base Facility outside contract limits.

B. Means, methods, techniques, sequences, or procedures which may result in damage toproperty outside of contract limits are not permitted.

C. Repair or replace damage to property outside contract limits to condition existing at start ofthe Work, or better.

1.05 GENERAL REQUIREMENTS FOR EXTERIOR WORK

A. Obtain permits and City Engineer's approval prior to impeding or closing roadways, streets,driveways, Terminal curbsides and parking areas.

B. Maintain emergency vehicle access to the Work and to fire hydrants, following Section 01505- Temporary Facilities.

C. Do not obstruct drainage ditches or inlets. When obstruction is unavoidable due torequirements of the Work, provide grading and temporary drainage structures to maintainunimpeded flow.

D. Locate by Section 01726 - Base Facility Survey and protect by Section 01505 - TemporaryFacilities, drainage, water, wastewater, petroleum pipeline, power, and communicationsconduits, duct banks, and direct-buried lines which may exist. Repair or replace damagedsystems to condition existing at start of Work, or better.

E. Public, Temporary, and Construction Roads and Ramps:

1. Construct and maintain temporary detours, ramps, and roads to provide for normal publictraffic flow when use of public roads or streets is closed by necessities of the Work.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 13: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

CONTRACTOR'S USE OF PREMISES01145-3 ver. 12-15-2017

2. Provide mats or other means to prevent overloading or damage to existing airfieldpavements and roadways from tracked equipment, trucks, or other equipment.

3. Construct and maintain access roads and parking areas following Section 01505 -Temporary Facilities.

F. Provide barricades and signs following Sections 01505 - Temporary Facilities and 01507 -Temporary Signs.

G. Traffic Control: Follow Section 01555 - Traffic Control and Regulation.

H. Surface Restoration:

1. Restore site to condition existing before construction, following Section 01731 - Cuttingand Patching, to satisfaction of City Engineer.

2. Repair damaged turf areas, leveling to within 4 inches of pre-existing surface with selectfill material following Item P-101, apply 4 inches of topsoil following Item T-905, andresod following Item T-904, as shown in the drawings. Water and level newly soddedareas with adjoining turf using steel wheel rollers appropriate for sodding. Apply erosioncontrol blanket, per Item C-102, to seeded areas.

1.06 WORK IN AOA

A. Certain unforeseen conditions inherent to airfield operations may cause the City Engineer topreclude construction operations due to low visibility aircraft operations. In such an event, theCity Engineer will direct the contractor to stand down operations until such time as visibilityconditions permit safe construction operations. Payment for Stand-by time will be made atthe contract unit price, per hour of stand-by time actually incurred by the contractor, onlywhen so directed by the City Engineer.

B. Should work be precluded for an extended time for a superseding, intervening event orregulatory requirement of the airfield closure pursuant to federal, state, and local laws, or dueto an emergency declaration, the City Engineer will direct the contractor to stand downoperations until such time as conditions permit construction operations to resume. Paymentfor Extended Stand-by time will be made at the contract unit price, per day of extendedstand-by time actually incurred by the contractor, only when so directed by the City Engineer.Payment for extended stand-by time shall include compensation for all expenses related tothe extended stand-by time, including overhead and general conditions.

C. If construction requires closing of safety areas of runways, taxiways and aprons and thoseclosings are not already indicated on the Drawings, then submit such request in writing on aseparate document in the Safety Plan. Closings require NOTAMs (Section 01423 -References).

D. Open trenches are generally not permitted in areas of aircraft and GSE movement.Exceptions may be approved by the Airport Manager and by FAA. Barricade, light and markthe edges of permitted open trenches and excavations as directed.

E. Flares are not permitted in the AOA.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 14: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

CONTRACTOR'S USE OF PREMISES01145-4 ver. 12-15-2017

F. Do not obliterate runway and taxiway markings, unless required as part of the Work. Repairor replace damaged markings with matching color, material and copy where resulting fromwork of this contract.

G. Open-flame welding and cutting in the AOA is discouraged. When unavoidable, obtain case-by-case approval. Provide proper fire control equipment, approved by Fire Department/Aviation Section.

H. Hearing protection is recommended for persons in the AOA.

I. Do not store products in Object Free Areas of runways, taxiways or aprons or in runwayoverruns and clear zones for more than then-active one-day operation. Provide large andlong-term storage outside the AOA.

J. Follow lockout/tagout program below.

1. Electrical Lockout/Tagout for HAS Projects:

a. AOA has underground lighting and control cables. Known cables are shown(charted) on Drawings.

b. Survey area within contract limits following Section 01726 - Base Facility Survey,using proper equipment, to confirm location of charted cables and cables discoveredduring survey. Stake locations.

c. Notify City Engineer and Airport Manager in daily briefings (Section 01312 -Coordination and Meetings) before excavation in the vicinity of charted or discoveredcables. Make written request for deactivation and reactivation of circuits.

d. Deactivation and reactivation of circuits is the responsibility of the Airport Manager.

e. Furnish proper personnel, cable locating instruments, tools, splice kits, cable andother products at the time excavation work is underway, for cable repair as required.

f. Excavate, make cable repairs, cover repairs, and backfill excavation at repairedcables an only in presence of City Engineer and Airport Manager.

g. Immediately report discovered or detected outages to City Engineer and AirportManager.

h. Follow repair details shown on Drawings. If details are not consistent with existing ordiscovered conditions, or if required repairs cannot be properly made, submitDocument 00931 following Section 01255 - Modification Procedures.

i. Record repairs following Section 01770 - Contract Closeout.

j. Test proper operation of circuits, in presence of City Engineer and Airport Manager,before covering repairs. Follow Section 01450 - Contractor's Quality Control.Immediately correct failures.

k. Airport Manager will perform a daily check of circuits in vicinity of construction at1500 hours to confirm proper operation. Immediately correct failures.

I. Construction near NAVAIDS and ARFF:

1. Do not obstruct line of sight from ATCT or interfere with transmissions from NAVAIDS.

2. Do not obstruct exits or entrances to ARFF.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 15: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

CONTRACTOR'S USE OF PREMISES01145-5 ver. 12-15-2017

1.07 CONTROL OF SECURITY AREA ACCESS

A. Post one gatekeeper, employed by the Contractor, at each point of access throughbarricades or enclosures into security areas, during times when access points are not locked.Ensure persons entering are properly badged.

B. Provide signs following Section 01507 - Temporary Signs.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

END OF SECTION

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 16: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSC-105-1

ITEM C-105 MOBILIZATION (REVISED 07/06/20)

105-1 Description. This item of work shall consist of, but is not limited to, work and operationsnecessary for the movement of personnel, equipment, material and supplies to and from theproject site for work on the project except as provided in the contract as separate pay items.

105-2 Mobilization limit. Mobilization shall be limited to 5 percent of the total project cost.

105-3 Posted notices. Prior to commencement of construction activities, the Contractor mustpost the following documents in a prominent and accessible place where they may be easilyviewed by all employees of the prime Contractor and by all employees of subcontractors engagedby the prime Contractor: Equal Employment Opportunity (EEO) Poster “Equal EmploymentOpportunity is the Law” in accordance with the Office of Federal Contract Compliance ProgramsExecutive Order 11246, as amended; Davis Bacon Wage Poster (WH 1321) - DOL “Notice to AllEmployees” Poster; and Applicable Davis-Bacon Wage Rate Determination. These notices mustremain posted until final acceptance of the work by the Owner.

105-4 Engineer/RPR field office. The Contractor shall provide dedicated space for the use ofthe field RPR and inspectors, as a field office for the duration of the project. This space shall belocated conveniently near the construction and shall be separate from any space used by theContractor. The Contractor shall furnish water, sanitary facilities, heat, air conditioning, andelectricity in accordance with local building codes. The field office shall additionally meet therequirements contained in Section 01505.

METHOD OF MEASUREMENT

105-5 Basis of measurement and payment. Based upon the contract lump sum price for“Mobilization” partial payments will be allowed as follows:

a. With first pay request, 25%.

b. When 25% or more of the original contract is earned, an additional 25%.

c. When 50% or more of the original contract is earned, an additional 40%.

d. After Final Inspection, Staging area clean-up and delivery of all Project Closeout materialsas required by Section 90, paragraph 90-11, Contractor Final Project Documentation, the final10%.

BASIS OF PAYMENT

105-6 Payment will be made under:

Item C-105 Mobilization (Max 5% of Total Bid) – per lump sum

REFERENCES

The publications listed below form a part of this specification to the extent referenced. Thepublications are referred to within the text by the basic designation only.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 17: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-1

ITEM P-101 PREPARATION/REMOVAL OF EXISTING PAVEMENTS (REVISED 07/06/20)

DESCRIPTION

101-1 This item shall consist of preparation of existing pavement surfaces for overlay, surfacetreatments, removal of existing pavement, and other miscellaneous items. The work shall beaccomplished in accordance with these specifications and the applicable plans.

EQUIPMENT AND MATERIALS

101-2 All equipment and materials shall be specified here and in the following paragraphs orapproved by the Resident Project Representative (RPR). The equipment shall not causedamage to the pavement to remain in place.

CONSTRUCTION

101-3.1 Removal of existing pavement.

The Contractor’s removal operation shall be controlled to not damage adjacent pavementstructure, and base material, cables, utility ducts, pipelines, or drainage structures which are toremain under the pavement.

a. Concrete pavement removal. Full depth saw cuts shall be made perpendicular to the slabsurface. The Contractor shall saw through the full depth of the slab including any dowels at thejoint, removing the pavement and installing new dowels as shown on the plans and per thespecifications. Where the perimeter of the removal limits is not located on the joint and there areno dowels present, the perimeter shall be saw cut the full depth of the pavement. A second sawcut shall be made at 12 inches to 18 inches away from the pavement to remain, so that themajority of the pavement may be removed without damage. The pavement inside the saw cutshall be removed by methods which will not cause distress in the pavement which is to remain inplace. Concrete slabs that are damaged by under breaking shall be repaired or removed andreplaced as directed by the RPR.

The edge of existing concrete pavement against which new pavement abuts shall be protectedfrom damage at all times. Spall and underbreak repair shall be in accordance with the plans. Anyunderlaying material that is to remain in place, shall be recompacted and/or replaced as shownon the plans. Adjacent areas damaged during repair shall be repaired or replaced at theContractor’s expense.

b. Asphalt pavement removal. Asphalt pavement to be removed shall be cut to the full depthof the asphalt pavement around the perimeter of the area to be removed.

c. Removal of Base, Subbase, and/or Subgrade. All stabilized base and/or subbasematerial beneath concrete or asphalt pavements to be removed shall be removed. Stabilized baseshall mean any cemented material, including, but not limited to cement-treated base, bituminousbase, lean concrete base, or soil-cement base.

101-3.2 Preparation of joints and cracks prior to overlay/surface treatment. Remove allvegetation and debris from cracks to a minimum depth of 1 inch (25 mm). If extensive vegetationexists, treat the specific area with a concentrated solution of a water-based herbicide approvedby the RPR. Fill all cracks greater than 1/4 inch (6 mm) wide) with a crack sealant per ASTM

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 18: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-2

D6690. The crack sealant, preparation, and application shall be compatible with the surfacetreatment/overlay to be used. To minimize contamination of the asphalt with the crack sealant,underfill the crack sealant a minimum of 1/8 inch (3 mm), not to exceed ¼ inch (6 mm). Anyexcess joint or crack sealer shall be removed from the pavement surface.

Wider cracks (over 1-1/2 inch wide (38 mm)), along with soft or sunken spots, indicate that thepavement or the pavement base should be repaired or replaced as stated below.

Cracks and joints may be filled with a mixture of emulsified asphalt and aggregate. The aggregateshall consist of limestone, volcanic ash, sand, or other material that will cure to form a hardsubstance. The combined gradation shall be as shown in the following table.

Gradation

Sieve Size Percent Passing

No. 4 (4.75 mm) 100

No. 8 (2.36 mm) 90-100

No. 16 (1.18 mm) 65-90

No. 30 (600 µm) 40-60

No. 50 (300 µm) 25-42

No. 100 (150 µm) 15-30

No. 200 (75 µm) 10-20

Up to 3% cement can be added to accelerate the set time. The mixture shall not contain morethan 20% natural sand without approval in writing from the RPR.

The proportions of asphalt emulsion and aggregate shall be determined in the field and may bevaried to facilitate construction requirements. Normally, these proportions will be approximatelyone part asphalt emulsion to five parts aggregate by volume. The material shall be poured orplaced into the joints or cracks and compacted to form a voidless mass. The joint or crack shallbe filled to within +0 to -1/8 inches (+0 to -3 mm) of the surface. Any material spilled outside thewidth of the joint shall be removed from the pavement surface prior to constructing the overlay.Where concrete overlays are to be constructed, only the excess joint material on the pavementsurface and vegetation in the joints need to be removed.

101-3.3 Removal of Foreign Substances/contaminates prior to seal-coat and/or remarking.Removal of foreign substances/contaminates from existing pavement that will affect the bond ofthe new treatment shall consist of removal of rubber, fuel spills, oil, crack sealer, at least 90% ofpaint, and other foreign substances from the surface of the pavement. Areas that require removalare designated on the plans and as directed by the RPR in the field during construction.

Chemicals, high-pressure water, or sandblasting may be used. If chemicals are used, they shallcomply with the state’s environmental protection regulations. Removal methods used shall notcause major damage to the pavement, or to any structure or utility within or adjacent to the workarea. Major damage is defined as changing the properties of the pavement, removal of asphaltcausing the aggregate to ravel, or removing pavement over 1/8 inch (3 mm) deep. If it is deemedby the RPR that damage to the existing pavement is caused by operational error, such aspermitting the application method to dwell in one location for too long, the Contractor shall repairthe damaged area without compensation and as directed by the RPR.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 19: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-3

Removal of foreign substances shall not proceed until approved by the RPR. Water used for high-pressure water equipment shall be provided by the Contractor at the Contractor's expense. Nomaterial shall be deposited on the pavement shoulders. All wastes shall be disposed of in areasindicated in this specification or shown on the plans.

101-3.4 Concrete spall or failed asphaltic concrete pavement repair. (Not Used)

101-3.5 Cold milling. (Not Used)

101-3.6. Preparation of asphalt pavement surfaces prior to surface treatment. Existingasphalt pavements to be treated with a surface treatment shall be prepared as follows:

a. Patch asphalt pavement surfaces that have been softened by petroleum derivatives or havefailed due to any other cause. Remove damaged pavement to the full depth of the damage andreplace with new asphalt pavement similar to that of the existing pavement.

b. Repair joints and cracks in accordance with paragraph 101-3.2.

c. Remove oil or grease that has not penetrated the asphalt pavement by scrubbing with adetergent and washing thoroughly with clean water. After cleaning, treat these areas with an oilspot primer.

d. Clean pavement surface immediately prior to placing the surface treatment so that it is freeof dust, dirt, grease, vegetation, oil or any type of objectionable surface film.

101-3.7 Maintenance. The Contractor shall perform all maintenance work necessary to keep thepavement in a satisfactory condition until the full section is complete and accepted by the RPR.The surface shall be kept clean and free from foreign material. The pavement shall be properlydrained at all times. If cleaning is necessary or if the pavement becomes disturbed, any workrepairs necessary shall be performed at the Contractor’s expense.

101-3.8 Preparation of Joints in Rigid Pavement prior to resealing. (Not Used)

101-3.9 Preparation of Cracks in Flexible Pavement prior to sealing. Prior to application ofsealant material, clean and dry the joints of all scale, dirt, dust, old sealant, curing compound,moisture and other foreign matter. The Contractor shall demonstrate, in the presence of the RPR,that the method used cleans the cracks and does not damage the pavement.

101-3.9.1 Preparation of Crack. Widen crack with router by removing a minimum of 1/16 inch (2mm) from each side of crack. Immediately before sealing, cracks will be blown out with a hot airlance combined with oil and water-free compressed air.

101-3.9.2 Removal of Existing Crack Sealant. Existing sealants will be removed by routing.Following routing, any remaining debris will be removed by use of a hot lance combined with oiland water-free compressed air.

101-3.9.3 Crack Sealant. Crack sealant material and installation will be in accordance with ItemP-605.

101-3.10 Removal of Pipe and other Buried Structures. (Not Used)

101-3.11 Removal of Electrical Conduit, Duct Banks, and other Buried Structures.

a. Removal of Existing Electrical Conduits and Duct Banks. Remove the electricalconduits and duct banks as indicated on the plans. The conduit material and concrete, if present,shall be legally disposed of off-site in a timely manner following removal. Trenches shall bebackfilled with material equal to or better in quality than adjacent embankment. Trenches underpaved areas must be compacted to 95% of ASTM D698.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 20: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-4

b. Removal of Electrical Manholes and Light Base Cans. Where indicated on the plansor as directed by the RPR, electrical manholes, light base cans, and surrounding concrete shallbe removed and legally disposed of off-site in a timely fashion after removal. Excavations afterremoval shall be backfilled with material equal or better in quality than adjacent embankment.Voids shall be backfilled with material equal to or better in quality than adjacent embankment.Trenches under paved areas must be compacted to 95% of ASTM D698.

c. Removal of Lighting Fixtures. Light fixtures shall be removed and stockpiled as shownon the drawings. Light fixtures removed shall be handled gently to avoid damage. Airport staffshall have the right to review all lighting fixtures and select those they wish to retain. Any productsthe airport does not wish to retain must be disposed of legally offsite by the contractor in a timelymanner. Stockpile location shall be determined by the RPR.

d. Removal of Existing Signage. Existing signage shall be removed as shown on thecontract drawings. Removal of a sign includes the above ground sign cabinet, concretefoundation and base can, any grounding elements, and any other ancillary items associated withthe sign installation. Backfill of the void created by the sign foundation shall be with material equalor better in quality than adjacent embankment.

e. Removal of Existing Navigational Aids. Existing navigation aids shall be removed asshown on the contract drawings. These include the Runway 17 VASI (4 boxes and a controlpanel), Runway 35 PAPI (4 boxes and a control panel), and the Runway 35 REIL (2 boxes and acontrol panel). The equipment to be removed shall be turned over to the owner as noted on thecontract drawings. Backfill of the void created by any foundation removals shall be with materialequal or better in quality than adjacent embankment.

f. Removal of Existing Cable. All cable removed from trench, conduit, or duct bank as apart of this project shall be disposed of legally offsite by the contractor in a timely fashion.

METHOD OF MEASUREMENT

101-4.1 Pavement removal. The unit of measurement for pavement removal shall be the numberof square yards (square meters) removed by the Contractor. Any pavement removed outside thelimits of removal because the pavement was damaged by negligence on the part of the Contractorshall not be included in the measurement for payment. No direct measurement or payment shallbe made for saw cutting. Saw cutting shall be incidental to pavement removal. No separatemeasurement will be made for removal of base and/or subbase course(s). All hauling and disposaloff-site will be considered a necessary and incidental part of the work. The Contractor shall includethe cost in the contract unit price for the pay of items of work involved. No payment will be madeseparately or directly for hauling or disposal on any part of the work.

101-4.2 Joint and crack repair. The unit of measurement for joint and crack repair shall be thelinear foot (meter) of joint.

101-4.3 Removal of Foreign Substances/contaminates. The unit of measurement for foreignSubstances/contaminates removal shall be the square foot (meter).

101-4.4 Removal of Existing Pavement Markings. The unit of measurement for removingexisting pavement markings shall be the number of square feet (square meters) removed by theContractor on existing pavement surfaces to remain. No measurement will be made of pavementmarkings removed on pavements to be demolished. No separate measurement will be made forthe fog seal or seal coat applied to block out areas where existing markings were removed.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 21: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-5

101-4.5 Removal of Electrical Conduit, Duct Banks, and other Buried Structures.Measurement for removal of existing fixtures and their associated base cans shall be on a per-each basis, and shall include the fixture, base can, concrete anchor, and any cabling within thebase can, in addition to the backfill of the void created by the demolition to proposed grade.

Removal of electrical conduit, duct banks, cabling and other buried structures shall be by thelinear foot. The linear foot cost shall include removal of all material associated with theconduit/duct and cable regardless of the size, including any concrete encasement, and the backfillof the void created by the conduit/duct installation. The price per each or per foot shall be fullcompensation for all labor, equipment, tools, and incidentals necessary to complete this item inaccordance with paragraph 100-3.2. In locations where the conduit enters under pavement thatis to remain, the conduit shall be capped and have a pull string installed. This work shall beincidental to the termination of the demolition of the conduit.

Removal of navigational aids shall be paid on a lump sum basis. The lump sum cost shall includeremoval of all above ground navigational aid equipment and storage at location of RPR’s choosingfor owner to take possession, the removal of all concrete foundations, grounding, and anyancillary power supply infrastructure associated at the aid installation site. Backfill of the voidcreated by the foundations shall be included in the lump sum cost.

Removal of airfield signage shall be paid on a per-each basis. The cost shall include the removalof all above ground signage elements, the removal of the concrete foundation including the basecan, any grounding elements or other associated items integral to the signage installation. Backfillof the sign foundation void shall be included in the line item cost.

Removal of airfield electrical structures, such as handholes or other buried structures, shall be ona per-each basis. The cost shall include the removal of the concrete structure, and any groundingelements or other associated items integral to the structure installation. Backfill of the structurevoid once demolished shall be included in the line item cost.

BASIS OF PAYMENT

100-5.1 Payment. Payment shall be made at contract unit price for the unit of measurement asspecified above. This price shall be full compensation for furnishing all materials and for allpreparation, hauling, and placing of the material and for all labor, equipment, tools, and incidentalsnecessary to complete this item.

Item P-101-5.1 Pavement Removal – Portland Cement Concrete - per square yard(square meter)

Item P-101-5.2 Pavement Removal – Polymer Modified Asphalt - per square yard(square meter)

Item P-101-5.3 Pavement Removal, Greater Than 48-inches, Including OSHACompliant Trench Safety - per square yard (square meter)

Item P-101-5.4 Joint and crack repair – per linear foot (meter)

Item P-101-5.5 Removal of Foreign Substances/contaminates – per square foot(square meter)

Item P-101-5.6 Removal of Existing Pavement Markings – per square foot (squaremeter)

Item P-100-5.7 Removal of Elevated Light and Associated Base Can – Per Each

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 22: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770

FAA TECHNICAL SPECIFICATIONSP-101-6

Item P-100-5.8 Removal of In-Pavement Light and Associated Base Can – Per Each

Item P-100-5.9 Removal of Electrical Conduit or Duct – Per Linear Foot

Item P-100-5.10 Removal of Electrical Cable – Per Linear Foot

Item P-100-5.11 Removal of Airfield Sign and Foundation – Per Each

Item P-100-5.12 Removal of Airfield Navigational Aids – Per Lump Sum

Item P-100-5.13 Removal of Lighting Fixture from Base Can to Remain – Per Each

Item P-100-5.14 Removal of Airfield Electrical Structure – Per Each

REFERENCES

The publications listed below form a part of this specification to the extent referenced. Thepublications are referred to within the text by the basic designation only.

Advisory Circulars (AC)

AC 150/5380-6 Guidelines and Procedures for Maintenance of Airport Pavements.

ASTM International (ASTM)

ASTM D6690 Standard Specification for Joint and Crack Sealants, Hot Applied,for Concrete and Asphalt Pavements

END OF ITEM P-101

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 23: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART A00410A-1 ver. 06-18-2019

DOCUMENT 00410A (REVISED 07/08/20)

BID FORM – PART A

To: The Honorable Mayor and City Council of the City of Houston

City Hall Annex

900 Bagby Street

Houston, Texas 77002

Project: Runway 17-35 DemolitionProject No.: 770BBidder:

(Print or type full name of business entity, such as corporation, LLC, etc)

OFFER

A. Total Bid Price: Having examined the Project location and all matters referred to in BidDocuments for the Project, we, the undersigned, offer to enter into a Contract to performthe Work for the Total Bid Price shown on the signature page of this Document

B. Security Deposit: Included with the Bid is a Security Deposit in the amount of 10 percentof the Total Bid Price subject to terms described in Document 00200 – Instructions toBidders.

C. Period for Bid Acceptance: This offer is open to acceptance and is irrevocable for 180days from Bid Date. That period may be extended by mutual written agreement of the Cityand Bidder.

D. Addenda: All Addenda have been received. Modifications to Bid Documents have beenconsidered and all related costs are included in the Total Bid Price.

E. Bid Supplements: The following documents are attached:

[X] Security Deposit (as defined in Document 00200 – Instructions to Bidders)[X] Document 00450 - Bidder's Statement of MWSBE Status[X] Document 00452 – Contractor Submission List COH Fair Campaign Ordinance

Form A[ ] Document 00453 – Bidder’s Statement of Residency[X] Document 00454 - Affidavit of Non-interest[X] Document 00455 - Ownership Information Form[X] Document 00456 - Bidder’s Certificate of Compliance with Buy American Program

(required for AIP funded project)[X] Document 00457 – Conflicts of Interest Questionnaire (CIQ)[X] Document 00458 - Bidder’s Certificate Regarding Foreign Trade Restriction

(required for AIP funded project)[X] Document 00459 - Contractor’s Statement Regarding Previous Contracts Subject to

EEO (required for AIP funded project)[X] Document 00460 – Pay or Play Acknowledgement Form (POP 1-A)[ ] Document 00461 – Hire Houston First Affidavit[X] Document 00470D - Bidder’s DBE Participation Plan (required for AIP funded

project)[X] Document 00480 – Form SCM-1 Reference Verification[ ] Document 00481 – Non-Collusion Statement[ ] Others as listed:

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 24: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART A00410A-2 ver. 06-18-2019

CONTRACT TIME

A. If offer is accepted, Contractor shall achieve Date of Substantial Completion within 234calendar days after Date of Commencement of the Work, subject to adjustments ofContract Time as provided in the Contract.

END OF DOCUMENT

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 25: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-3 ver. 06-18-2019

DOCUMENT 00410B (REVISED 07/09/20)

BID FORM – PART B

1.0 TOTAL BID PRICE HAS BEEN CALCULATED BY BIDDER, USING THE FOLLOWING

COMPONENT PRICES AND PROCESS (PRINT OR TYPE NUMERICAL AMOUNTS):

A. BASE UNIT PRICE TABLE:

ItemNo.

SpecRef.

Base Unit Short TitleUnit of

MeasureEstimatedQuantity

Unit Price(this

columncontrols)

Total infigures

1 01410 TPDES Requirements LS 1

2 01505 Temporary Facilities LS 1

3 01506 Airport Temporary Controls LS 1

401555-1.04 A.

Traffic Control and Regulation,Excluding Flagmen

LS 1

501555-1.04 B.

Flagmen LS 1

6 C-100Contractor Quality ControlProgram (CQCP)

LS 1

7C-102-5.1A

Temporary Seeding andMulching

SY 157,300

8C-102-5.1C

Installation and Removal ofErosion Control Sediment Logs

LF 1,320

9C-102-5.1E

Installation and Removal ofStabilized Construction Exits

EA 10

10 C-105Mobilization (Max 5% of TotalBid)

LS 1

11 01145Stand-By Time for Low VisibilityOperations

HR 40

12 01145

Extended Standby Time, for asuperseding, intervening eventor regulatory requirement ofthe airfield closure pursuant tofederal, state, and local laws,or due to an emergencydeclaration.

DAY 5

13P-101-

5.1Pavement Removal – PortlandCement Concrete

SY 64,205

14P-101-

5.2Pavement Removal – PolymerModified Asphalt

SY 40,275

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 26: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-4 ver. 06-18-2019

ItemNo.

SpecRef.

Base Unit Short TitleUnit of

MeasureEstimatedQuantity

Unit Price(this

columncontrols)

Total infigures

15P-101-

5.3

Pavement Removal, GreaterThan 48-inches, IncludingOSHA Compliant TrenchSafety

SY 1,000

16P-101-

5.4Joint and Crack Repair LF 5,600

17P-101-

5.5Removal of ForeignSubstances/Contaminates

SF 3,465

18P-101-

5.6Removal of Existing PavementMarkings

SF 58,300

19P-101-

5.7Removal of Elevated Light andAssociated Base Can

EA 33

20P-101-

5.8Removal of In-Pavement Lightand Associated Base Can

EA 105

21P-101-

5.9Removal of Electrical Conduitor Duct

LF 22,000

22P-101-5.10

Removal of Electrical Cable LF 60,000

23P-101-5.11

Removal of Airfield Sign andFoundation

EA 45

24P-101-5.12

Removal of AirfieldNavigational Aids

LS 1

25P-101-5.13

Removal of Lighting Fixturefrom Base Can to Remain

EA 1

26P-101-5.14

Removal of Airfield ElectricalStructure

EA 1

27P-152-

4.2Embankment in Place CY 48,646

28P-608-

8.1Asphalt Surface Treatment SY 40,400

29P-620-5.1A

Surface Preparation SF 26,400

30P-620-5.2B

Marking SF 27,200

31P-620-5.3C

Reflective Media, Tt-B-1325DType I

LB 50

32P-620-5.3D

Reflective Media, Tt-B-1325DType III

LB 1,200

33P-620-5.3E

Temporary Markings SF 19,835

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 27: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-5 ver. 06-18-2019

ItemNo.

SpecRef.

Base Unit Short TitleUnit of

MeasureEstimatedQuantity

Unit Price(this

columncontrols)

Total infigures

34T-900-

9.1Temporary Irrigation SystemInstallation and Removal

LS 1

35T-900-

9.2Water for Irrigation KGAL 37,500

36T-904-

5.1Sodding SY 167,074

37T-905-

5.1Topsoil (Furnished from Off-Site)

CY 11,669

38L-100-

5.1Modifications to ALCMSEquipment

LS 1

39L-100-

5.2Contractor Support of ALCMSInstallation

LS 1

40L-108-

5.1No. 8 AWG Cable, Installed inTrench, Duct Bank or Conduit

LF 9,000

41L-108-

5.2

No. 6 AWG, Solid, BareCopper Counterpoise Wire,Installed in Trench

LF 4,100

42L-110-

5.1Direct Buried 1-Way, 2" PVCConduit - Installed in Turf

LF 2,300

43L-110-

5.2

Concrete Encased 1-Way, 2"PVC Conduit - Installed inConcrete

LF 1,800

44L-115-

5.1Tie Proposed Conduit toExisting L-867 Base Can

EA 14

45L-115-

5.2Tie Proposed L-867 Base Canto Existing Conduit

EA 22

46L-115-

5.3Install New L-867 Base Canwith Steel Cover

EA 3

47L-120-

5.1Temporary Lighting Cable LF 20,000

48L-120-

5.2Circuit Investigation andTracing

LS 1

49L-125-

5.1Install New 3/8" Steel Plate onExisting L-867 Base Can

EA 7

50L-125-

5.2Install New 3/4" Steel Plate onExisting L-868 Base Can

EA 57

51L-125-

5.3

Install New L-861T TaxiwayEdge Light on New L-867 BaseCan in Turf

EA 27

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 28: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-6 ver. 06-18-2019

ItemNo.

SpecRef.

Base Unit Short TitleUnit of

MeasureEstimatedQuantity

Unit Price(this

columncontrols)

Total infigures

52L-125-

5.4

Install New L-861T TaxiwayEdge Light on New L-867 BaseCan in Concrete

EA 25

53L-125-

5.5

Install New L-852C/D TaxiwayCenterline Light on Existing L-868 Base Can

EA 13

54L-125-

5.6Procure and Install NewGuidance Sign Panels

EA 4

55L-125-

5.7Install New L-853 Type IIRetroreflective Marker

EA 173

56L-125-

5.810% Spare Parts (Not toExceed $10,000)

LS 1

57L-125-

5.9

Relocate Existing Sign SN105,Including New Base, Base Can,Conduit, and Cable.

LS 1

TOTAL BASE UNIT PRICES $_________

REST OF PAGE INTENTIONALLY LEFT BLANK

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 29: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-7 ver. 06-18-2019

B. CASH ALLOWANCE TABLE:

REST OF PAGE INTENTIONALLY LEFT BLANK

ItemNo.

SpecRef.

Cash Allowance Short Title(See Footnote 1)

CashAllowance in

figures (1)

101210,1.02 A.

A. Existing Utility Line Relocation, Abandonment, or RemovalB. Site Condition Specific Safety ConditionsC. Airfield Safety Controls AllowanceD. Contaminated Material HandlingE. Additional Flagger and Barricades Associated with Phasing /

OperationsF. Building Permit: For obtaining the Building Permit from City of

Houston

$300,000.00

201210,1.02 B.

Provide and install 1-24 strand Single mode corning fiber from NewRTR-D site to the FAA tower along the north route through the MDF.

$59,250.00

301210,1.02 C.

Provide and install Maxcell (3) 3” 3 cell innerduct in (1) conduit of theexisting duct bank from the NEW RTR-D to the FAA tower around theNorth side of the Airport. Provide and install 4” Maxcell wolfbags inexisting pull boxes to seal conduits after cable installation.

$250,392.00

401210,1.02 D.

Researching and establishing a clear pathway in the existing ductbank from the NEW RTR-D to the FAA tower utilizing a north routearound the Airport. Pathway will go through the MDF and the tunnelin the new terminal.

$17,886.50

TOTAL CASH ALLOWANCES $627,528.50

(1) Fixed Unit Price determined prior to Bid. Cannot be adjusted by the Bidder.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 30: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-8 ver. 06-18-2019

C. ALTERNATES TABLE:

REST OF PAGE INTENTIONALLY LEFT BLANK

ItemNo.

SpecRef.

Alternate Short TitleUnit of

MeasureEstimatedQuantity

Unit Price(this column

controls)

Total Pricefor Alternate

in figures

1D-900-

5.1Underground StormwaterStorage Facility

LS 1

2P-152-

4.1Unclassified Excavation CY 23,508

3P-152-

4.2Embankment in Place CY (10,075)

TOTAL ALTERNATES $________

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 31: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

Runway 17-35 DemolitionHouston, Texas HOU/Project No. 770B

BID FORM PART B00410B-9 ver. 06-18-2019

D. TOTAL BID PRICE: $(Add Totals for Stipulated Price, Base Unit Price, Extra Unit Price, Cash Allowance, and All Alternates, if any)

2.0 SIGNATURES: By signing this Document, I agree that I have received and reviewed allAddenda and considered all costs associated with the Addenda in calculating the Total BidPrice.

Bidder:(Print or type full name of your proprietorship, partnership, corporation, or joint venture.*)

** By:Signature Date

Name:(Print or type name) Title

Address:(Mailing)

(Street, if different)

Telephone and Fax Number:(Print or type numbers)

* If Bid is a joint venture, add additional Bid Form signature sheets for each member of thejoint venture.

** Bidder certifies that the only person or parties interested in this offer as principals are thosenamed above. Bidder has not directly or indirectly entered into any agreement, participatedin any collusion, or otherwise taken any action in restraint of free competitive bidding.

Note: This document constitutes a government record, as defined by § 37.01 of the Texas PenalCode. Submission of a false government record is punishable as provided in § 37.10 of theTexas Penal Code.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 32: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

SHEE

T IN

DEX

/ Q

UAN

TITI

ES

NO

N-S

TAN

DAR

D T

AXIW

AYS

PRO

JEC

T

WILLIAM P. HOBBY AIRPORT

TEXASHOUSTON

REVISIONS

BYNO. DESCRIPTION DATE

RGSPROJECT MGR:

RGSDESIGNER:

RGSDRAWN BY:

JNPCHECKED BY:

AS SHOWNSCALE:

JANUARY 24, 2020DATE:

DATE:APPROVED BY:

PROJECT NO:

C.I.P. NO:

H.A.S. NO:

SHEET NO:

DIRECTORHOUSTON AIRPORT SYSTEM

770B

N/A

N/A

JACOBS ENGINEERING GROUP INC.5995 ROGERDALE ROADHOUSTON, TEXAS 77072

+1-832-351-6000WWW.JACOBS.COM

TEXAS P.E. FIRM F-2966

RU

NW

AY 1

7-35

DEM

OLI

TIO

N

SHEET INDEX

DRAWING NO. SHEET NO. SHEET NAME

1 G0.00 COVER

2 G1.01 INDEX AND QUANTITIES

3 G2.01 CONTRACT LAYOUT PLAN

4 G3.01 PHASING PLAN - GENERAL NOTES (1 OF 2)

5 G3.02 PHASING PLAN - GENERAL NOTES (2 OF 2)

6 G3.03 PHASING PLAN - PHASE 1 (1 OF 2)

7 G3.04 PHASING PLAN - PHASE 1 (2 OF 2)

8 G3.05 PHASING PLAN - PHASE 2

9 G3.06 PHASING PLAN - PHASE 3

10 G3.07 PHASING PLAN - PHASE 4

11 G3.08 PHASING PLAN - PHASE 5

12 G3.09 PHASING PLAN - PHASE 6 (1 OF 2)

13 G3.10 PHASING PLAN - PHASE 6 (2 OF 2)

14 G3.11 PHASING PLAN - PHASE 7

15 G3.12 PHASING PLAN - PHASE 8 (1 OF 2)

16 G3.13 PHASING PLAN - PHASE 8 (2 OF 2)

17 G3.14 PHASING PLAN - PHASE 9

18 G4.01 SAFETY AND SECURITY DETAILS

19 C1.01 EROSION AND SEDIMENTATION CONTROL PLAN (1 OF 6)

20 C1.02 EROSION AND SEDIMENTATION CONTROL PLAN (2 OF 6)

21 C1.03 EROSION AND SEDIMENTATION CONTROL PLAN (3 OF 6)

22 C1.04 EROSION AND SEDIMENTATION CONTROL PLAN (4 OF 6)

23 C1.05 EROSION AND SEDIMENTATION CONTROL PLAN (5 OF 6)

24 C1.06 EROSION AND SEDIMENTATION CONTROL PLAN (6 OF 6)

25 C1.07 EROSION AND SEDIMENTATION CONTROL GENERAL NOTES

26 C1.08 EROSION AND SEDIMENTATION CONTROL DETAILS

27 C2.01 CIVIL DEMOLITION PLAN (1 OF 6)

28 C2.02 CIVIL DEMOLITION PLAN (2 OF 6)

29 C2.03 CIVIL DEMOLITION PLAN (3 OF 6)

30 C2.04 CIVIL DEMOLITION PLAN (4 OF 6)

31 C2.05 CIVIL DEMOLITION PLAN (5 OF 6)

32 C2.06 CIVIL DEMOLITION PLAN (6 OF 6)

33 C2.07 DEMOLITION DETAILS

34 C3.01 PAVEMENT MARKING PLAN (1 OF 6)

35 C3.02 PAVEMENT MARKING PLAN (2 OF 6)

36 C3.03 PAVEMENT MARKING PLAN (3 OF 6)

37 C3.04 PAVEMENT MARKING PLAN (4 OF 6)

38 C3.05 PAVEMENT MARKING PLAN (5 OF 6)

39 C3.06 PAVEMENT MARKING PLAN (6 OF 6)

40 C3.07 PAVEMENT MARKING DETAILS

41 C4.01 TEMPORARY REFLECTOR PLAN (1 OF 6)

42 C4.02 TEMPORARY REFLECTOR PLAN (2 OF 6)

43 C4.03 TEMPORARY REFLECTOR PLAN (3 OF 6)

44 C4.04 TEMPORARY REFLECTOR PLAN (4 OF 6)

45 C4.05 TEMPORARY REFLECTOR PLAN (5 OF 6)

46 C4.06 TEMPORARY REFLECTOR PLAN (6 OF 6)

47 C4.07 TEMPORARY REFLECTOR LOCATION CHART AND DETAIL

48 E1.00 AIRFIELD ELECTRICAL LIGHTING, SIGNAGE, ELECTRICAL LEGEND AND NOTES

49 E1.01 AIRFIELD ELECTRICAL PHASING PLAN - GENERAL NOTES

50 E1.02 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 1 (1 OF 2)

51 E1.03 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 1 (2 OF 2)

52 E1.04 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 2

53 E1.05 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 3

54 E1.06 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 4

55 E1.07 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 5

56 E1.08 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 6 (1 OF 2)

57 E1.09 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 6 (2 OF 2)

58 E1.10 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 7

59 E1.11 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 8 (1 OF 2)

60 E1.12 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 8 (2 OF 2)

61 E1.13 AIRFIELD ELECTRICAL PHASING PLAN - PHASE 9

62 E2.01 AIRFIELD ELECTRICAL DEMOLITION PLAN (1 OF 6)

63 E2.02 AIRFIELD ELECTRICAL DEMOLITION PLAN (2 OF 6)

64 E2.03 AIRFIELD ELECTRICAL DEMOLITION PLAN (3 OF 6)

65 E2.04 AIRFIELD ELECTRICAL DEMOLITION PLAN (4 OF 6)

66 E2.05 AIRFIELD ELECTRICAL DEMOLITION PLAN (5 OF 6)

67 E2.06 AIRFIELD ELECTRICAL DEMOLITION PLAN (6 OF 6)

68 E3.01 AIRFIELD ELECTRICAL PLAN (1 OF 6)

69 E3.02 AIRFIELD ELECTRICAL PLAN (2 OF 6)

70 E3.03 AIRFIELD ELECTRICAL PLAN (3 OF 6)

71 E3.04 AIRFIELD ELECTRICAL PLAN (4 OF 6)

72 E3.05 AIRFIELD ELECTRICAL PLAN (5 OF 6)

73 E3.06 AIRFIELD ELECTRICAL PLAN (6 OF 6)

74 E3.07 AIRFIELD ELECTRICAL DETAILS

75 E3.08 AIRFIELD ELECTRICAL DETAILS

76 E3.09 AIRFIELD ELECTRICAL DETAILS

77 E3.10 AIRFIELD ELECTRICAL DETAILS

G1.01

RUNWAY 17-35 DEMOLITION - ESTIMATED QUANTITIES

ITEM # SPEC. # BASE UNIT SHORT TITLE

UNIT OF

MEASURE

ESTIMATED

QUANTITY

1 01410 TPDES REQUIREMENTS LS 1

2 01505 TEMPORARY FACILITIES LS 1

3 01506 AIRPORT TEMPORARY CONTROLS LS 1

4 01555-1.04 A. TRAFFIC CONTROL AND REGULATION, EXCLUDING FLAGMEN LS 1

5 01555-1.04 B. FLAGMEN LS 1

6 C-100 CONTRACTOR QUALITY CONTROL PROGRAM (CQCP) LS 1

7 C-102-5.1A TEMPORARY SEEDING AND MULCHING SY 157,300

8 C-102-5.1C INSTALLATION AND REMOVAL OF EROSION CONTROL SEDIMENT LOGS LF 1,320

9 C-102-5.1E INSTALLATION AND REMOVAL OF STABILIZED CONSTRUCTION EXITS EA 10

10 C-105 MOBILIZATION (MAX 5% OF TOTAL BID) LS 1

11 01145 STAND-BY TIME FOR LOW VISIBILITY OPERATIONS HR 40

12 01145EXTENDED STANDBY TIME FOR A SUPERSEDING, INTERVENING EVENT OR REGULATORY REQUIREMENT OF THE AIRFIELD CLOSURE PURSUANT TO FEDERAL, STATE, AND LOCAL LAWS,OR DUE TO AN EMERGENCY DECLARATION.

DAY 5

13 P-101-5.1 PAVEMENT REMOVAL – PORTLAND CEMENT CONCRETE SY 64,205

14 P-101-5.2 PAVEMENT REMOVAL – POLYMER MODIFIED ASPHALT SY 40,275

15 P-101-5.3 PAVEMENT REMOVAL, GREATER THAN 48-INCHES, INCLUDING OSHA COMPLIANT TRENCHSAFETY SY 1,000

16 P-101-5.4 JOINT AND CRACK REPAIR LF 5,600

17 P-101-5.5 REMOVAL OF FOREIGN SUBSTANCES/CONTAMINATES SF 3,465

18 P-101-5.6 REMOVAL OF EXISTING PAVEMENT MARKINGS SF 58,300

19 P-101-5.7 REMOVAL OF ELEVATED LIGHT AND ASSOCIATED BASE CAN EA 33

20 P-101-5.8 REMOVAL OF IN-PAVEMENT LIGHT AND ASSOCIATED BASE CAN EA 105

21 P-101-5.9 REMOVAL OF ELECTRICAL CONDUIT OR DUCT LF 22,000

22 P-101-5.10 REMOVAL OF ELECTRICAL CABLE LF 60,000

23 P-101-5.11 REMOVAL OF AIRFIELD SIGN AND FOUNDATION EA 45

24 P-101-5.12 REMOVAL OF AIRFIELD NAVIGATIONAL AIDS LS 1

25 P-101-5.13 REMOVAL OF LIGHTING FIXTURE FROM BASE CAN TO REMAIN EA 1

26 P-101-5.14 REMOVAL OF AIRFIELD ELECTRICAL STRUCTURE EA 1

27 P-152-4.2 EMBANKMENT IN PLACE CY 48,646

28 P-608-8.1 ASPHALT SURFACE TREATMENT SY 40,400

29 P-620-5.1A SURFACE PREPARATION SF 26,400

30 P-620-5.2B MARKING SF 27,200

31 P-620-5.3C REFLECTIVE MEDIA, TT-B-1325D TYPE I LB 50

32 P-620-5.3D REFLECTIVE MEDIA, TT-B-1325D TYPE III LB 1,200

33 P-620-5.3E TEMPORARY MARKINGS SF 19,835

34 T-900-9.1 TEMPORARY IRRIGATION SYSTEM INSTALLATIONS AND REMOVAL LS 1

35 T-900-9.2 WATER FOR IRRIGATION KGAL 37,500

36 T-904-5.1 SODDING SY 167,074

37 T-905-5.1 TOPSOIL (FURNISHED FROM OFF THE SITE) CY 11,669

38 L-100-5.1 MODIFICATIONS TO ALCMS EQUIPMENT LS 1

39 L-100-5.2 CONTRACTOR SUPPORT OF ALCMS INSTALLATION LS 1

40 L-108-5.1 NO. 8 AWG CABLE, INSTALLED IN TRENCH, DUCT BANK OR CONDUIT LF 9,000

41 L-108-5.2 NO. 6 AWG, SOLID, BARE COPPER COUNTERPOISE WIRE, INSTALLED IN TRENCH LF 4,100

42 L-110-5.1 DIRECT BURIED 1-WAY, 2" PVC CONDUIT - INSTALLED IN TURF LF 2,300

43 L-110-5.2 CONCRETE ENCASED 1-WAY, 2" PVC CONDUIT - INSTALLED IN CONCRETE LF 1,800

44 L-115-5.1 TIE PROPOSED CONDUIT TO EXISTING L-867 BASE CAN EA 14

45 L-115-5.2 TIE PROPOSED L-867 BASE CAN TO EXISTING CONDUIT EA 22

46 L-115-5.3 INSTALL NEW L-867 BASE CAN WITH STEEL COVER EA 3

47 L-120-5.1 TEMPORARY LIGHTING CABLE LF 20,000

48 L-120-5.2 CIRCUIT INVESTIGATION AND TRACING LS 1

49 L-125-5.1 INSTALL NEW 3/8" STEEL PLATE ON EXISTING L-867 BASE CAN EA 7

50 L-125-5.2 INSTALL NEW 3/4" STEEL PLATE ON EXISTING L-868 BASE CAN EA 57

51 L-125-5.3 INSTALL NEW L-861T TAXIWAY EDGE LIGHT ON NEW L-867 BASE CAN IN TURF EA 27

52 L-125-5.4 INSTALL NEW L-861T TAXIWAY EDGE LIGHT ON NEW L-867 BASE CAN IN CONCRETE EA 25

53 L-125-5.5 INSTALL NEW L-852C/D TAXIWAY CENTERLINE LIGHT ON EXISTING L-868 BASE CAN EA 13

54 L-125-5.6 PROCURE AND INSTALL NEW GUIDANCE SIGN PANELS LS 4

55 L-125-5.7 INSTALL NEW L-853 TYPE II RETROREFLECTIVE MARKER EA 17356 L-125-5.8 10% SPARE PARTS (NOT TO EXCEED $10,000) LS 1

57 L-125-5.9 RELOCATE EXISTING SIGN SN105, INCLUDING NEW BASE, BASE CAN, CONDUIT, AND CABLE. LS 1

REVISED 07/08/20

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

AutoCAD SHX Text
P
AutoCAD SHX Text
R
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
E
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
D
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
X
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
62314
AutoCAD SHX Text
ROBERT SCHMIDT
Page 33: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

E3.09

AIR

FIE

LD

E

LE

CT

RIC

AL D

ET

AILS

NO

N-S

TA

ND

AR

D T

AX

IW

AY

S P

RO

JE

CT

WILLIAM P. HOBBY AIRPORT

TEXASHOUSTON

REVISIONS

BYNO. DESCRIPTION DATE

RGSPROJECT MGR:

DESIGNER:

DRAWN BY:

CHECKED BY:

AS SHOWNSCALE:

JANUARY 24, 2020DATE:

DATE:APPROVED BY:

PROJECT NO:

C.I.P. NO:

H.A.S. NO:

SHEET NO:

DIRECTOR

HOUSTON AIRPORT SYSTEM

770B

N/A

N/A

JACOBS ENGINEERING GROUP INC.

5995 ROGERDALE ROAD

HOUSTON, TEXAS 77072

+1-832-351-6000

WWW.JACOBS.COM

TEXAS P.E. FIRM F-2966

RU

NW

AY

1

7-3

5 D

EM

OL

IT

IO

N

NBD

KWA

JAM

CABLE DIAMETER

AMERACE SIZE NUMBER

54 SUPER-D4-D4

MIN.

0.320

MAX.

0.430

SPLICE KIT SPECIFICATIONS:

1. WORKERS PERFORMING SPLICING WORK MUST BE TRAINED AND CERTIFIED BY THE CONNECTOR KIT MANUFACTURER TO

POSSES THE PROPER SPLICING ABILITIES. CERTIFICATION DOCUMENTATION SHALL BE SUBMITTED TO THE ENGINEER.

2. VERIFY THAT ALL SPLICERS DISPLAY A VISIBLE BADGE TO INDICATE SPLICING CERTIFICATION AND HAVE AT LEAST FIVE

YEARS OF HIGH VOLTAGE SPLICING EXPERIENCE AND HAVE BEEN TRAINED BY THE KIT MANUFACTURER.

3. CONNECTORS SHALL BE PLUG AND RECEPTACLE TYPE IN ACCORDANCE WITH FAA SPECIFICATIONS, AND SHALL BE

APPLIED IN ACCORDANCE WITH SERIES LIGHTING CABLE MANUFACTURER INSTRUCTIONS.

CONNECTOR SHALL BE PLUG AND RECEPTACLE TYPE, AMERACE 54 SUPER SERIES, INTEGRO KIT, OR APPROVED EQUAL, IN

ACCORDANCE WITH FAA SPECIFICATION. SUBMIT CATALOG CUT SHEET AND PRODUCT SAMPLE FOR APPROVAL AND TESTING.

CONNECTOR KIT SHALL BE APPLIED IN ACCORDANCE WITH SERIES LIGHTING CABLE MANUFACTURERS WRITTEN INSTRUCTIONS.

ACTUAL OUTSIDE DIAMETER (OVER JACKET) OF SERIES LIGHTING CABLE SHALL BE USED TO DETERMINE CONNECTOR KIT SIZE

REQUIREMENT.

CABLE DIAMETER

INTEGRO SIZE NUMBER

INTEGRO COMPLETE KIT

MIN.

0.320

MAX.

0.430

SCALE

BASE CAN IDENTIFICATION MARKER

1

N.T.S.

SCALE

STAINLESS STEEL CABLE ID TAG DETAIL

2

N.T.S.

TYPICAL DETAILS FOR SPLICING OF 1/C #8, 5KV

SERIES LIGHTING CABLE VIA L-823 CONNECTOR KIT

SCALE

(FOR LIGHTING BASES, HANDHOLES AND MANHOLES)

3

N.T.S.

AMERACE SIZE SYMBOL

D

INTEGRO SIZE SYMBOL

11805-01 OR 11805-05

TYPICAL CONDUIT INSTALLATIONS

SCALE

IN EXISTING SHOULDER PAVEMENT

4

N.T.S.

SCALE

INSTALLATIONS IN EARTH

5

N.T.S.

SCALE

TRANSFORMER CONNECTION DETAIL

6

N.T.S.

TYPICAL ISOLATIONTYPICAL CONDUIT

CENTER OF LIGHT BASE OR JUNCTION CAN

9"

2" DIA. DOMED BRONZE

MARKER (BERNTSEN CD2B

OR EQIVALENT)

TOP OF CONCRETE

3/4" DIA. NOTCHED STEM

NOTES FOR IDENTIFICATION MARKER:

1. IDENTIFICATION SHALL BE STAMPED USING 1/4" FIGURES AND

LETTERS UNIFORMLY SPACED ON THE BRONZE MARKER.

2. IDENTIFICATION MARKERS SHALL BE UNIFORMLY INSTALLED

ADJACENT TO TAXIWAY AND RUNWAY ELEVATED EDGE LIGHTS.

PREFERRED LOCATION IS ON A LINE PERPENDICULAR TO

RUNWAY OR TAXIWAY CENTERLINE, INBOARD OF LIGHT

FIXTURE.

3/16" DIA. HOLE ATTACHED TO

L-824 CABLE USING TIE WRAPS

2" DIA. CABLE TAG WITH

1/2" STAMPED TEXT

CIRCUIT IDENTIFICATION

MOLDED PLUG

MOLDED RECEPTACLE

EXISTING GRADE

24

" (M

IN

)

3/4" DIA. x 10' COPPER CLAD

GROUND ROD, 1 PER TRENCH

AT MIDPOINT (TYP)

INSTALL CONDUIT CHAIR AS

NEEDED. AFFIX CHAIR TO

TRENCH BOTTOM AND SECURE

CONDUIT TO PREVENT FLOAT.

8" (MIN)

3"

EXISTING SHOULDER

PAVEMENT

1 #6 AWG BARE SOLID COUNTERPOISE.

LOCATE COUNTERPOISE ABOVE

CONDUIT.

SCH 40 PVC CONDUIT

BACKFILL TRENCH WITH P-610 CONCRETE,

VIBRATE TO ENSURE CONSOLIDATION

BELOW CONDUIT AND CHAIRS.

8"

FINISHED GRADE

6"

3"

4"

24

" (M

IN

)

4"

3/4" DIA. x 10' COPPER CLAD

GROUND ROD, 1 PER TRENCH

AT MIDPOINT (TYP)

BACKFILL TRENCH WITH SAND

OR NATIVE MATERIAL PER

SPECIFICATION L-108.

SCH 40 PVC CONDUIT

1 #6 AWG BARE SOLID COUNTERPOISE.

LOCATE COUNTERPOISE ABOVE

CONDUIT.

PLASTIC 6" WIDE LOCATABLE TAPE

MARKED 'ELECTRICAL' OVER ALL

DIRECT BURIED CONDUIT (TYP)

EARTH

NOTE:

1. INSTALL ISOLATION TRANSFORMER IN ACCORDANCE

WITH MANUFACTURER'S INSTRUCTIONS.

(M

IN

)

(M

IN

)

TO

LIGHT

FIXTURE

L-830 ISOLATION

TRANSFORMER

MALE CONNECTOR

(PLUG)

TO NEXT ISOLATION

TRANSFORMER OR

RETURN PATH

L-823 SINGLE

CONNECTOR (TYP)

FEMALE CONNECTOR

(RECEPTACLE)

SECONDARY CABLE

MALE CONNECTOR

(PLUG)

FEMALE CONNECTOR

(RECEPTACLE)

TO

PRIMARY

FEED

INSTALL ENOUGH

CABLE TO ALLOW

SLACK FOR SEVERAL

SPLICINGS (TYP)

NOTES:

1. ENGRAVE EACH TAG WITH THE CIRCUIT ID AS ORDERED BY

THE ENGINEER.

2. ATTACH EACH TAG WITH A #16 BRASS JACK CHAIN.

REVISED 07/06/20

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

AutoCAD SHX Text
P
AutoCAD SHX Text
R
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
E
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
D
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
X
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
62314
AutoCAD SHX Text
ROBERT SCHMIDT
AutoCAD SHX Text
5000V
AutoCAD SHX Text
T/W
AutoCAD SHX Text
*
Page 34: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

C1.07

ER

OS

IO

N A

ND

S

ED

IM

EN

TA

TIO

N C

ON

TR

OL

GE

NE

RA

L N

OT

ES

NO

N-S

TA

ND

AR

D T

AX

IW

AY

S P

RO

JE

CT

WILLIAM P. HOBBY AIRPORT

TEXASHOUSTON

REVISIONS

BYNO. DESCRIPTION DATE

RGSPROJECT MGR:

DESIGNER:

DRAWN BY:

CHECKED BY:

AS SHOWNSCALE:

JANUARY 24, 2020DATE:

DATE:APPROVED BY:

PROJECT NO:

C.I.P. NO:

H.A.S. NO:

SHEET NO:

DIRECTOR

HOUSTON AIRPORT SYSTEM

770B

N/A

N/A

JACOBS ENGINEERING GROUP INC.

5995 ROGERDALE ROAD

HOUSTON, TEXAS 77072

+1-832-351-6000

WWW.JACOBS.COM

TEXAS P.E. FIRM F-2966

RU

NW

AY

1

7-3

5 D

EM

OL

IT

IO

N

RGS

DLC

DLC

1. THE IMPLEMENTATION OF THE EROSION CONTROL PLAN SHALL BE COORDINATED BY THE

CONTRACTOR WITH THE PROJECT CONSTRUCTION SEQUENCING. CHANGES ARE TO BE

REVIEWED AND APPROVED PRIOR TO IMPLEMENTATION.

2. CONTRACTOR SHALL RESTORE ALL AREAS DISTRIBUTED WITHIN THE PROJECT LIMITS BY

CONSTRUCTION WITH SOD, SEED, TOPSOIL, MULCH & MAT.

3. CONTRACTOR SHALL IMPLEMENT INLET PROTECTION DEVICES AT LOCATIONS SHOWN ON

THE EROSION CONTROL PLANS TO KEEP KEEP SILT AND/OR EXCAVATED MATERIALS FROM

ENTERING INTO THE STORM WATER INLETS.

4. DURING EXCAVATION PHASE OF THE PROJECT, CONTRACTOR SHALL SCHEDULE THE WORK

IN SHORT SEGMENTS SO THAT EXCAVATED MATERIAL CAN BE QUICKLY HAULED AWAY

FROM THE SITE AND TO PREVENT IT FROM STAYING UNCOLLECTED ON THE EXISTING

PAVEMENT. ANY LOOSE EXCAVATED MATERIAL WHICH FALLS ON PAVEMENTS OR

DRIVEWAYS SHALL BE SWEPT BACK INTO THE EXCAVATED AREA.

5. CONTRACTOR SHALL CLEAN UP THE EXISTING STREET INTERSECTIONS AND DRIVEWAYS

DAILY, AS NECESSARY, TO REMOVE ANY EXCESS MUD, SILT, OR ROCK TRACKED FROM THE

EXCAVATED AREA.

6. CONTRACTOR SHALL FOLLOW GOOD HOUSE KEEPING PRACTICES DURING THE

CONSTRUCTION OF THE PROJECT, ALWAYS CLEANING UP DIRT AND LOOSE MATERIAL AS

CONSTRUCTION PROGRESSES.

7. THE CONTRACTOR SHALL UTILIZE STABILIZED CONSTRUCTION EXITS IN CONJUNCTION WITH

THE PROJECT PHASING AND CONTRACTOR HAUL ROUTES. NO SEPARATE PAY FOR

STABILIZED CONSTRUCTION EXITS - INCIDENTAL TO THE APPLICABLE MAJOR WORK ITEM IN

THE AREA.

8. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING STOCKPILE AREAS AND PREVENTING

ANY MATERIAL RUNOFF FROM THE DESIGNATED AREAS.

9. CONTRACTORS OPERATING CONSTRUCTION VEHICLES AND EQUIPMENT ON THE AIRPORT

MUST BE PREPARED TO EXPEDITIOUSLY CONTAIN AND CLEAN-UP SPILLS RESULTING FROM

FUEL, HYDRAULIC FLUID, OR OTHER CHEMICAL FLUID LEAKS. TRANSPORT AND HANDLING OF

OTHER HAZARDOUS MATERIALS ON AN AIRPORT ALSO REQUIRES SPECIAL PROCEDURES.

TO THAT END, THE CONTRACTOR IS REQUIRED TO DEVELOP AND IMPLEMENT SPILL

PREVENTION AND RESPONSE PROCEDURES FOR VEHICLE OPERATIONS. THE CONTRACTOR

SHALL INCORPORATE THESE PROCEDURES INTO THE SPCD. THIS INCLUDES MAINTENANCE

OF APPROPRIATE MSDS DATA AND APPROPRIATE PREVENTION AND RESPONSE EQUIPMENT

ON-SITE.

10. THE CONTRACTOR SHALL IMPLEMENT AND MAINTAIN ACCEPTABLE SOIL EROSION AND

SEDIMENT CONTROL MEASURES INCLUDING BEST MANAGEMENT PRACTICES (BMPS) IN

CONFORMANCE WITH THE EROSION CONTROL TECHNICAL STANDARDS OF THE MOST

CURRENT TPDES CGP.

11. CONTRACTOR SHALL GRADE AND COMPACT THE AREA OF EROSION CONTROL BLANKET

INSTALLATION AS DIRECTED IN THE PLANS. THE SEED-BED SHALL BE PREPARED BY

LOOSENING THE TOP 2-3 INCHES MINIMUM OF SOIL AND SHALL BE UNIFORM & SMOOTH AND

FREE FROM ROCKS, CLODS, VEGETATION OR OTHER OBJECTS. CONTRACTOR SHALL APPLY

SEED TO SOIL SURFACE BEFORE INSTALLING BLANKET & DISTURBED AREAS SHALL BE

RE-SEEDED.

12. CONTRACTOR SHALL USE TURF REINFORCEMENT MATTING MATERIAL WHICH SHALL BE

RATED 6.0 FT/SEC AND WITHSTAND A SHEAR STRESS OF 2.0 LB/SQ.FT.

13. CONTRACTOR TO INSPECT AND MAINTAIN THE AREAS LISTED BELOW AT LEAST ONCE EVERY

FOURTEEN (14) CALENDAR DAYS AND WITHIN 24 HOURS OF THE END OF A STORM EVENT OF

0.5 INCHES OR GREATER.

- DISTURBED AREAS OF THE CONSTRUCTION SITE THAT HAVE NOT BEEN FINALLY

STABILIZED.

- AREAS USED FOR STORAGE OF MATERIALS THAT ARE EXPOSED TO PRECIPITATION.

- STRUCTURAL CONTROL MEASURES.

- LOCATIONS WHERE VEHICLES ENTER OR EXIT THE SITE.

14. CONTRACTOR TO BE RESPONSIBLE TO MAINTAIN EXISTING DITCHES AND/OR CULVERTS FOR

UNOBSTRUCTED DRAINAGE AT ALL TIMES. WHERE SODDING IS DISTURBED BY EXCAVATION

ON BACKFILLING OPERATIONS, SUCH AREAS SHALL BE REPLACED BY SODDING. SLOPES 4:1

OR STEEPER SHALL BE REPLACED BY BLOCK SODDING.

15. STABILIZATION OF DISTURBED GRADE, WHETHER BY SODDING OR EROSION CONTROL

MATTING AND SEEDING WILL BE PAID FOR AT THE LIMITS SHOWN IN THESE PLANS. NO

SEPARATE PAYMENT WILL BE MADE FOR ANY OTHER STABILIZATION NECESSARY FOR

GROUND DISTURBED OUTSIDE THESE LIMITS, STABILIZED AREAS DISTURBED AGAIN IN

LATER PHASES, AND GROUND DISTURBED FOR ACCESS TO THE WORK AREAS. THAT WORK

SHALL BE CONSIDERED INCIDENTAL TO THE GENERAL EROSION AND SEDIMENTATION

CONTROL.

PHASE 1

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 1 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 2

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 2 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 3

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 3 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 4

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 4 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 5

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 5 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 6

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 6 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 7

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 7 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 8

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 8 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

PHASE 9

· THIS PHASE IS CONSTRUCTED DURING THE RUNWAY DEMOLITION PERIOD.

· PROVIDE INLET PROTECTION FOR EXISTING INLETS.

· CONDUCT CLEARING, GRUBBING, PAVEMENT REMOVAL, & GRADING OPERATIONS.

· PROVIDE SODDING.

· PROVIDE TOPSOIL.

· PROVIDE SEEDING AND EROSION CONTROL BLANKETS.

· WATERING AND MAINTENANCE OF SOD UNTIL ESTABLISHED.

· PHASE 9 MEASURES TO REMAIN UNTIL SOD IS ESTABLISHED.

SEQUENCE OF CONSTRUCTION (SOC):GENERAL NOTES:

1

1

1

1

1

1

1

1

1

1

1 REVISED NOTES 7/6/20 RGS

REVISED 07/06/20

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

AutoCAD SHX Text
P
AutoCAD SHX Text
R
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
E
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
O
AutoCAD SHX Text
N
AutoCAD SHX Text
A
AutoCAD SHX Text
L
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
G
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
D
AutoCAD SHX Text
S
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
T
AutoCAD SHX Text
E
AutoCAD SHX Text
X
AutoCAD SHX Text
A
AutoCAD SHX Text
S
AutoCAD SHX Text
62314
AutoCAD SHX Text
ROBERT SCHMIDT
Page 35: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

SC

ALE

=

1 : 200

NOTES

· MANIFOLD SIZE TO BE DETERMINED BY DESIGN ENGINEER.

· IT MAY BE NECESSARY TO CUT AND COUPLE ADDITIONAL PIPE TO STANDARD MANIFOLD COMPONENTS IN THE FIELD.

· THE DESIGN ENGINEER MUST REVIEW ELEVATIONS AND IF NECESSARY ADJUST GRADING TO ENSURE THE CHAMBER

COVER REQUIREMENTS ARE MET.

· THIS CHAMBER SYSTEM WAS DESIGNED WITHOUT SITE-SPECIFIC INFORMATION ON SOIL CONDITIONS OR BEARING

CAPACITY. THE DESIGN ENGINEER IS RESPONSIBLE FOR DETERMINING THE SUITABILITY OF THE SOIL AND PROVIDING

THE BEARING CAPACITY OF THE INSITU SOILS. THE BASE STONE DEPTH MAY BE INCREASED OR DECREASED ONCE THIS

INFORMATION IS PROVIDED.

· NOT FOR CONSTRUCTION: THIS LAYOUT IS FOR DIMENSIONAL PURPOSES ONLY TO PROVE CONCEPT & THE

REQUIRED STORAGE VOLUME CAN BE ACHIEVED ON SITE.

DUAL WALL PERFORATED HDPE

UNDERDRAIN (SIZE TBD BY

ENGINEER)

INSPECTION PORT (TYP 20 PLACES)

PROPOSED STRUCTURE

(TYP 19 PLACES)

OUTLET CONTROL STRUCTURE

ISOLATOR ROW

(SEE DETAIL / TYP 20 PLACES)

PLACE MINIMUM 12.5' OF WOVEN

GEOTEXTILE OVER BEDDING STONE AND

UNDERNEATH CHAMBER FEET FOR SCOUR

PROTECTION AT ALL CHAMBER INLET ROWS

24" PREFABRICATED END CAP, TYP OF ALL

24" CONNECTIONS AND ISOLATOR ROWS

BOTTOM CONNECTION

(TYP 14 PLACES)

(SEE NOTES)

TOP CONNECTION

(SEE NOTES)

BOTTOM CONNECTION

(SEE NOTES)

BOTTOM MANIFOLD

(SEE NOTES)

TOP MANIFOLD

(TYP 19 PLACES)

(SEE NOTES)

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 36: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

SC

ALE

=

1 : 200

1627.29'

165.29'172.41'165.29'172.41'165.29'165.29'172.41'122.59'172.41'

37.19'

79

.0

7'

75

.5

0'

1677.10'

37.19'

26

.8

2'

23

.2

5'

18

.9

9'

10.13'

11.22'

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 37: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

006

0'

12

0'

NOTES

· MANIFOLD SIZE TO BE DETERMINED BY DESIGN ENGINEER.

· DUE TO THE ADAPTATION OF THIS CHAMBER SYSTEM TO SPECIFIC SITE AND DESIGN CONSTRAINTS, IT MAY BE

NECESSARY TO CUT AND COUPLE ADDITIONAL PIPE TO STANDARD MANIFOLD COMPONENTS IN THE FIELD.

· THE DESIGN ENGINEER MUST REVIEW ELEVATIONS AND IF NECESSARY ADJUST GRADING TO ENSURE THE CHAMBER

COVER REQUIREMENTS ARE MET.

· THIS CHAMBER SYSTEM WAS DESIGNED WITHOUT SITE-SPECIFIC INFORMATION ON SOIL CONDITIONS OR BEARING

CAPACITY. THE SITE DESIGN ENGINEER IS RESPONSIBLE FOR DETERMINING THE SUITABILITY OF THE SOIL AND

PROVIDING THE BEARING CAPACITY OF THE INSITU SOILS. THE BASE STONE DEPTH MAY BE INCREASED OR DECREASED

ONCE THIS INFORMATION IS PROVIDED.

· NOT FOR CONSTRUCTION: THIS LAYOUT IS FOR DIMENSIONAL PURPOSES ONLY TO PROVE CONCEPT & THE

REQUIRED STORAGE VOLUME CAN BE ACHIEVED ON SITE.

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

759.06'

773.29'

53

.7

5'

24

.7

6'

35.58'

122.59'

30.07'

65.66' 172.41' 165.29' 101.24'

30.07'

94.12' 165.29' 172.41' 165.29' 94.12'

18

.9

5'

17.25'

29

.5

7'

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 38: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

006

0'

12

0'

NOTES

· MANIFOLD SIZE TO BE DETERMINED BY DESIGN ENGINEER.

· DUE TO THE ADAPTATION OF THIS CHAMBER SYSTEM TO SPECIFIC SITE AND DESIGN CONSTRAINTS, IT MAY BE

NECESSARY TO CUT AND COUPLE ADDITIONAL PIPE TO STANDARD MANIFOLD COMPONENTS IN THE FIELD.

· THE DESIGN ENGINEER MUST REVIEW ELEVATIONS AND IF NECESSARY ADJUST GRADING TO ENSURE THE CHAMBER

COVER REQUIREMENTS ARE MET.

· THIS CHAMBER SYSTEM WAS DESIGNED WITHOUT SITE-SPECIFIC INFORMATION ON SOIL CONDITIONS OR BEARING

CAPACITY. THE SITE DESIGN ENGINEER IS RESPONSIBLE FOR DETERMINING THE SUITABILITY OF THE SOIL AND

PROVIDING THE BEARING CAPACITY OF THE INSITU SOILS. THE BASE STONE DEPTH MAY BE INCREASED OR DECREASED

ONCE THIS INFORMATION IS PROVIDED.

· NOT FOR CONSTRUCTION: THIS LAYOUT IS FOR DIMENSIONAL PURPOSES ONLY TO PROVE CONCEPT & THE

REQUIRED STORAGE VOLUME CAN BE ACHIEVED ON SITE.

DUAL WALL PERFORATED

HDPE UNDERDRAIN

(SIZE TBD BY ENGINEER)

INSPECTION PORT (TYP 11 PLACES)

PROPOSED STRUCTURE

(TYP 10 PLACES)

PROPOSED OUTLET CONTROL STRUCTURE

ISOLATOR ROW

(SEE DETAIL / TYP 11 PLACES)

PLACE MINIMUM 12.5' OF WOVEN

GEOTEXTILE OVER BEDDING STONE AND

UNDERNEATH CHAMBER FEET FOR SCOUR

PROTECTION AT ALL CHAMBER INLET ROWS

24" PREFABRICATED END CAP, TYP OF ALL 24"

CONNECTIONS AND ISOLATOR ROWS

TOP CONNECTION

(SEE NOTES)

BOTTOM CONNECTION

(SEE NOTES)

BOTTOM MANIFOLD

(SEE NOTES)

TOP MANIFOLD

(TYP 11 PLACES)

(SEE NOTES)

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 39: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

ACCEPTABLE FILL MATERIALS: POLYPROPYLENE CORRUGATED WALL STORMWATER COLLECTION CHAMBERS

PLEASE NOTE:

1. THE LISTED AASHTO DESIGNATIONS ARE FOR GRADATIONS ONLY. THE STONE MUST ALSO BE CLEAN, CRUSHED, ANGULAR. FOR EXAMPLE, A SPECIFICATION FOR #4 STONE WOULD STATE: "CLEAN, CRUSHED, ANGULAR NO. 4 (AASHTO M43) STONE".

2. STORMTECH COMPACTION REQUIREMENTS ARE MET FOR 'A' LOCATION MATERIALS WHEN PLACED AND COMPACTED IN 6" (150 mm) (MAX) LIFTS USING TWO FULL COVERAGES WITH A VIBRATORY COMPACTOR.

3. WHERE INFILTRATION SURFACES MAY BE COMPROMISED BY COMPACTION, FOR STANDARD DESIGN LOAD CONDITIONS, A FLAT SURFACE MAY BE ACHIEVED BY RAKING OR DRAGGING WITHOUT COMPACTION EQUIPMENT. FOR SPECIAL LOAD DESIGNS, CONTACT STORMTECH FOR

COMPACTION REQUIREMENTS.

4. ONCE LAYER 'C' IS PLACED, ANY SOIL/MATERIAL CAN BE PLACED IN LAYER 'D' UP TO THE FINISHED GRADE. MOST PAVEMENT SUBBASE SOILS CAN BE USED TO REPLACE THE MATERIAL REQUIREMENTS OF LAYER 'C' OR 'D' AT THE SITE DESIGN ENGINEER'S DISCRETION.

NOTES:

1. CHAMBERS SHALL MEET THE REQUIREMENTS OF ASTM F2418-16a, "STANDARD SPECIFICATION FOR POLYPROPYLENE (PP) CORRUGATED WALL STORMWATER

COLLECTION CHAMBERS".

2. CHAMBERS SHALL BE DESIGNED IN ACCORDANCE WITH ASTM F2787 "STANDARD PRACTICE FOR STRUCTURAL DESIGN OF THERMOPLASTIC CORRUGATED WALL

STORMWATER COLLECTION CHAMBERS".

3. THE DESIGN ENGINEER IS RESPONSIBLE FOR ASSESSING THE BEARING RESISTANCE (ALLOWABLE BEARING CAPACITY) OF THE SUBGRADE SOILS AND THE DEPTH OF

FOUNDATION STONE WITH CONSIDERATION FOR THE RANGE OF EXPECTED SOIL MOISTURE CONDITIONS.

4. PERIMETER STONE MUST BE EXTENDED HORIZONTALLY TO THE EXCAVATION WALL FOR BOTH VERTICAL AND SLOPED EXCAVATION WALLS.

5. REQUIREMENTS FOR HANDLING AND INSTALLATION:

· TO MAINTAIN THE WIDTH OF CHAMBERS DURING SHIPPING AND HANDLING, CHAMBERS SHALL HAVE INTEGRAL, INTERLOCKING STACKING LUGS.

· TO ENSURE A SECURE JOINT DURING INSTALLATION AND BACKFILL, THE HEIGHT OF THE CHAMBER JOINT SHALL NOT BE LESS THAN 2”.

· TO ENSURE THE INTEGRITY OF THE ARCH SHAPE DURING INSTALLATION, a) THE ARCH STIFFNESS CONSTANT AS DEFINED IN SECTION 6.2.8 OF ASTM F2418 SHALL

BE GREATER THAN OR EQUAL TO 550 LBS/IN/IN. AND b) TO RESIST CHAMBER DEFORMATION DURING INSTALLATION AT ELEVATED TEMPERATURES (ABOVE 73° F /

23° C), CHAMBERS SHALL BE PRODUCED FROM REFLECTIVE GOLD OR YELLOW COLORS.

MATERIAL LOCATION DESCRIPTION

AASHTO MATERIAL

CLASSIFICATIONS

COMPACTION / DENSITY REQUIREMENT

D

FINAL FILL: FILL MATERIAL FOR LAYER 'D' STARTS FROM THE

TOP OF THE 'C' LAYER TO THE BOTTOM OF FINISHED GRADE

ABOVE.

ANY SOIL/ROCK MATERIALS, NATIVE SOILS, OR TOPSOIL.N/A PREPARE PER DESIGN ENGINEER'S PLANS.

C

INITIAL FILL: FILL MATERIAL FOR LAYER 'C' STARTS FROM THE

TOP OF THE EMBEDMENT STONE ('B' LAYER) TO 24" (600 mm)

ABOVE THE TOP OF THE CHAMBER.

GRANULAR WELL-GRADED SOIL/AGGREGATE MIXTURES, <35% FINES OR

PROCESSED AGGREGATE.

MOST PAVEMENT SUBBASE MATERIALS CAN BE USED IN LIEU OF THIS

LAYER.

AASHTO M145¹

A-1, A-2-4, A-3

OR

AASHTO M43¹

3, 357, 4, 467, 5, 56, 57, 6, 67, 68, 7, 78, 8, 89, 9, 10

BEGIN COMPACTIONS AFTER 12" (300 mm) OF MATERIAL OVER

THE CHAMBERS IS REACHED. COMPACT ADDITIONAL LAYERS IN

6" (150 mm) MAX LIFTS TO A MIN. 95% PROCTOR DENSITY FOR

WELL GRADED MATERIAL AND 95% RELATIVE DENSITY FOR

PROCESSED AGGREGATE MATERIALS. ROLLER GROSS

VEHICLE WEIGHT NOT TO EXCEED 12,000 lbs (53 kN). DYNAMIC

FORCE NOT TO EXCEED 20,000 lbs (89 kN).

B

EMBEDMENT STONE: FILL SURROUNDING THE CHAMBERS

FROM THE FOUNDATION STONE ('A' LAYER) TO THE 'C' LAYER

ABOVE.

CLEAN, CRUSHED, ANGULAR STONE

AASHTO M43¹

3, 357, 4, 467, 5, 56, 57

NO COMPACTION REQUIRED.

A

FOUNDATION STONE: FILL BELOW CHAMBERS FROM THE

SUBGRADE UP TO THE FOOT (BOTTOM) OF THE CHAMBER.

CLEAN, CRUSHED, ANGULAR STONE

AASHTO M43¹

3, 357, 4, 467, 5, 56, 57

PLATE COMPACT OR ROLL TO ACHIEVE A FLAT SURFACE.

2,3

TO BE DETERMINED BY ENGINEER

24" (600 mm) MIN

8'

(2.4 m)

MAX

D

C

B

A

12" (300 mm) MIN

NON-WOVEN GEOTEXTILE ALL AROUND CLEAN,

CRUSHED, ANGULAR STONE IN A & B LAYERS

12" (300 mm) MIN51" (1295 mm)6" (150 mm) MIN

30"

(762 mm)

DEPTH OF STONE TO BE DETERMINED

BY SITE DESIGN ENGINEER 6" (150 mm) MIN

EXCAVATION WALL

(CAN BE SLOPED OR VERTICAL)

PERIMETER STONE

(SEE NOTE 4)

END CAP

SUBGRADE SOILS

(SEE NOTE 3)

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 40: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

SUMP DEPTH TBD BY

DESIGN ENGINEER

(24" [600 mm] MIN RECOMMENDED)

CATCH BASIN

OR MANHOLE

ISOLATOR ROW DETAIL

NTS

END CAP

INSPECTION PORT

POLYPROPYLENE (PP) CORRUGATED WALL

STORMWATER COLLECTION CHAMBERS

COVER ENTIRE ISOLATOR ROW WITH ADS

GEOSYNTHETICS 601T NON-WOVEN GEOTEXTILE

8' (2.4 m) MIN WIDE

24" (600 mm) HDPE ACCESS PIPE REQUIRED

USE FACTORY PRE-FABRICATED END CAP

TWO LAYERS OF WOVEN GEOTEXTILE BETWEEN FOUNDATION

STONE AND CHAMBERS 5' (1.5 m) MIN WIDE CONTINUOUS

FABRIC WITHOUT SEAMS

ELEVATED BYPASS MANIFOLD

NOTES:

1. INSPECTION PORTS MAY BE CONNECTED THROUGH ANY CHAMBER

CORRUGATION VALLEY.

2. ALL SCHEDULE 40 FITTINGS TO BE SOLVENT CEMENTED.

CONNECTION DETAIL

NTS

8"

(200 mm)

4" (100 mm)

SCHED 40 PVC

COUPLING

4" (100 mm)

SCHED 40 PVC

4" (100 mm)

SCHED 40 PVC

CORE 4.5" (114 mm) Ø

HOLE IN CHAMBER

(4.5" HOLE SAW REQ'D)

ANY VALLEY

LOCATION

POLYPROPYLENE (PP) CORRUGATED WALL

STORMWATER COLLECTION CHAMBER

4" PVC INSPECTION PORT DETAIL

NTS

8" INSPECTION PORT BODY

4" (100 mm)

SCHED 40 PVC

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 41: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

UNDERDRAIN DETAIL

NTS

A

A

B B

SECTION A-A

SECTION B-B

NUMBER AND SIZE OF UNDERDRAINS PER DESIGN ENGINEER

OUTLET MANIFOLD

END CAP

STORMWATER

COLLECTION

CHAMBERS

STORMWATER

COLLECTION

CHAMBER

END CAP

DUAL WALL

PERFORATED

HDPE

UNDERDRAIN

NON-WOVEN GEOTEXTILE

NON-WOVEN GEOTEXTILE

FOUNDATION STONE

BENEATH CHAMBERS

FOUNDATION STONE

BENEATH CHAMBERS

THIS DRAWING WAS PROVIDED BY THE HOUSTON AIRPORT SYSTEM AND

IS FOR CONCEPTUAL PURPOSES ONLY. IT IS NOT INTENDED FOR

BIDDING, ESTIMATING OR CONSTRUCTION. IT DOES NOT INCLUDE

ELEVATIONS, FLOW RATES OR SURROUNDING TOPOGRAPHY, NOR HAS

IT BEEN REVIEWED BY JACOBS ENGINEERING.

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 42: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

NORTH BED

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 43: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

SOUTH BED

DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3

Page 44: CITY OF HOUSTON Sylvester Turner...C ITY OF HOUSTON George Bush Intercontinental ~ William P. Hobby ~ Ellington Airport Sylvester Turner Mayor Mario C. Diaz Director of Aviation Council

REVISED 07/06/20DocuSign Envelope ID: 09FBA331-CFB3-49CA-8B2D-217328271DF3