City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012. Agenda Past Flood Fight Strategy (i.e. 2009,2010,…) Assessment of Flood Risk Overview of Project Objectives Recommended Plan Project Schedule / Financing Questions. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/1.jpg)
City of FargoMickelson Field Area Flood
Risk Management – Project 5902
Public Information Meeting
July 12, 2012
![Page 2: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/2.jpg)
Agenda Past Flood Fight Strategy (i.e. 2009,2010,
…) Assessment of Flood Risk Overview of Project Objectives Recommended Plan Project Schedule / Financing Questions
Mickelson Flood Risk Management
![Page 3: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/3.jpg)
2009 Spring Flood – Mickelson Area
![Page 4: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/4.jpg)
2009 Spring Flood – Mickelson Area
![Page 5: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/5.jpg)
2010 Spring Flood – Mickelson Area
![Page 6: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/6.jpg)
Existing vs. Preliminary FEMA Floodplain
EXISTING – RS 38.3±
PROPOSED – RS 39.5±
![Page 7: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/7.jpg)
Assessment of Flood Risk
River Stage 25.0ft
![Page 8: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/8.jpg)
River Stage 35.0ft
Assessment of Flood Risk
Oak Street Dike – Action Stage RS 30 –
Inundation 34.6
![Page 9: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/9.jpg)
River Stage 37.0ft
Assessment of Flood Risk
Emergency Dike Closure – Action Stage RS 31 –
Inundation 36.0±
![Page 10: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/10.jpg)
River Stage 38.0ft
Assessment of Flood Risk
![Page 11: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/11.jpg)
River Stage 39.0ft
Assessment of Flood Risk
![Page 12: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/12.jpg)
River Stage 40.0ft
Assessment of Flood Risk
FEMA 100-yr Flood Stage 39.5
![Page 13: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/13.jpg)
River Stage 41.0ft
Assessment of Flood Risk
2009 Spring Flood – RS 40.8
![Page 14: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/14.jpg)
River Stage 42.0ft
Assessment of Flood Risk
![Page 15: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/15.jpg)
River Stage 42.5ft
Assessment of Flood Risk
USACE Recent Evaluation – 1% Flood in Fargo is 42.4?
![Page 16: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/16.jpg)
Reduced Reliance on Temporary Flood Protection
– Clay levees, closures, and etc. Existing Storm Sewer Lift Station
Improvement – Reduce Internal Flooding Potential– Redundant Pumping Capacity
Overview of Project Objectives
![Page 17: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/17.jpg)
Construct Earthen Levee (RS 39.5+4.5’) Abandon Lift Stations 29, 37, and 38 Construct New Combined Lift Station Storm Sewer Outlet Structure Storm Sewer Improvements Dry Stormwater Pond General Landscaping / Grading Impacts to Existing Park Facility – Fargo
Park District Future Modifications
Recommended Plan
![Page 18: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/18.jpg)
Mickelson Flood Risk Management
![Page 19: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/19.jpg)
Mickelson Flood Risk Management
![Page 20: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/20.jpg)
Mickelson Flood Risk Management
FENCED RECYCLE AREA
![Page 21: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/21.jpg)
Mickelson Flood Risk Management
![Page 22: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/22.jpg)
Mickelson Flood Risk Management
NEW LIFT STATION
![Page 23: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/23.jpg)
Mickelson Flood Risk Management
![Page 24: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/24.jpg)
Recommended Plan– Approximately $4.5 M± (Construction)
Preliminary Funding Plan – FEMA – HMGP Funding – Pending (75%)– Local Cost Share – City (25%)
Project Schedule / Financing
![Page 25: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/25.jpg)
Project Schedule / Financing Schedule
– HMGP Grant Submittal Application Submitted (April 2012) Anticipated Decision (March 2013)
– Recommended Project Design– Public Informational Meeting (tonight)
Public Comment Period (Until 7/20)– Final Plans / Specifications / Cost Estimates (8/10)– Right-of-way / Park District Approval (TBD – Aug/Sept?)– Recommendation to City Commission (Spring 2013) – Permitting/Construction Bidding/Award Contract
(TBD)– Anticipated Construction Begins (TBD – Summer
2013?)– Anticipated Construction Ends (TBD - Fall 2014?)
![Page 26: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/26.jpg)
Comment Form
![Page 27: City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012](https://reader035.vdocuments.us/reader035/viewer/2022070500/56816865550346895ddebcf1/html5/thumbnails/27.jpg)
Questions / Discussion
www.cityoffargo.com\Engineering