City CouncilJune 7, 2011

Page 2: City Council June 7, 2011 CIP

2011-2016Capital Improvement Plan

Page 3: City Council June 7, 2011 CIP

CIP Overview• City Charter requirement

• Definition of a capital project

Land, facilities, parks, streets, water, waste water, technology, and transportation devices

Typically, total cost in excess of $100,000

Investments which yield a useful life of at least 5 years

Page 4: City Council June 7, 2011 CIP

CIP Calendar

2/4/2011 CIP forms & instructions sent out

2/18/2011 CIP projects due from departments

3/22/2011 Introduce CIP to City Council

4/20/2011 CIP Committee review of projects5/16-17/11 CIP Public Meetings

6/7/2011 CIP discussion with City Council

6/28/2011 CIP resolution approval by City Council

Page 5: City Council June 7, 2011 CIP

Project Identity

Stormwater Quantity Projects

Street Construction Projects

Page 6: City Council June 7, 2011 CIP

Public Meetings

Public meetings regarding the 2011-2016 Capital Improvement Plan (CIP) were held on May 16th and 17th.

The meetings took place at the Public Housing Authority and Fort Concho, respectively.

Page 7: City Council June 7, 2011 CIP

Promotion of CIP Public Meetings

Meetings were publicized with the help of theCity’s Public Information Office in following ways:

March 22nd, 2011 City Council MeetingCity’s websiteChannel 17Social networking ( acebook & witter)Local media outlets

TelevisionRadio Newspaper

Page 8: City Council June 7, 2011 CIP

Public Meeting # 1

Location: Public Housing Authority Time: Monday, May 16th at 6 p.m.Number of Attendees: 7

Summary of Public Comments:Lone Wolf Dog ParkMeadowcreek ParkFiscal ResponsibilityStreet Projects30-60 Day Public Comment Period

Page 9: City Council June 7, 2011 CIP

Public Meeting # 2

Location: Fort Concho Officer’s Quarters #8Time: Tuesday, May 17th at 6 p.m.Number of Attendees: 4

Summary of Public Comments:Hotel TaxStreet ReconstructionPublic SafetyFiscal Responsibility

Page 10: City Council June 7, 2011 CIP

Planning vs. Funding

CIP = Planning Document

Identification of Project Needs

Funding discussed during the Budget Process

Page 11: City Council June 7, 2011 CIP

Removed Projects

Fire Truck Shop Addition

Signal Re-lamping

Page 12: City Council June 7, 2011 CIP

Summary of Proposed ProjectsProject Type Number of

ProjectsProject Cost

Airport 21 23,858,644

Environmental 3 18,394,264

Equipment 10 6,611,952

Facility – Buildings,etc. 43 64,305,954

Facility – Parks & Recreation 30 20,262,850

Pedestrian 3 3,030,000

Stormwater 26 76,568,925

Streets/Traffic 68 163,007,235

Technology 7 3,295,696

Water/Wastewater 10 367,151,509

221 $ 746,437,029

Page 13: City Council June 7, 2011 CIP

Proposed Projects for FY 2011-2012Proposed/Committed Funding Source

Number of Projects

Project Cost

Airport 3 1,643,000

Environmental 1 100,000

Equipment 2 268,000

Facility – Buildings, etc. 13 4,999,500

Facility – Parks & Recreations 7 5,038,000

Stormwater 1 1,000,000

Streets/Traffic 4 1,931,000

Technology 7 906,387

Water/Wastewater 7 62,050,000

45 $ 77,935,887

Page 14: City Council June 7, 2011 CIP

CIP Calendar

2/4/2011 CIP forms & instructions sent out

2/18/2011 CIP projects due from departments

3/22/2011 Introduce CIP to City Council

4/20/2011 CIP Committee review of projects5/16-17/11 CIP Public Meetings

6/7/2011 CIP discussion with City Council

6/28/2011 CIP resolution approval by City Council