city council april 5, 2011 lone wolf bridge presentation
TRANSCRIPT
Donald A. Peterson, P.E.Donald A. Peterson, P.E.Project Engineer/ Project Engineer/
San Angelo Area EngineerSan Angelo Area Engineer
TexasDepartment
of Transportation
TexasDepartment
of Transportation
Lone Wolf Historic Bridge Lone Wolf Historic Bridge ProjectProject
TexasDepartment
of Transportation
Lone Wolf Historic Bridge Project
Limits: On Avenue K at the South Concho River
The Proposed Work Consists:Refurbishing a Historic City Street Bridge to a Pedestrian/ Bike Path Bridge.
Project Length:Roadway = 1,289 Feet.Bridge = 585 Feet.Total Length = 1,874 Feet.
TexasDepartment
of Transportation
Funding:100% Federal Funding Funds from American Recovery and Reinvestment Act (ARRA) of 2009, Economic Stimulus Package Enacted by Congress.
Any additional work requested would required funding be provided bythe City Of San Angelo.
Lowest Bid was $ $1,399,601.86.
TexasDepartment
of Transportation
Contractor : SCR Construction Company, Inc.
We have paid Contractor the amount of $695,964.22
Time set for project = 210 working days.Contractor has used = 167 working days.
Project is 61.22 percent complete.Contractor has used 79.52 percent of time set for the project.Project is behind of schedule by 18.30 percent.
Project is behind of schedule by 38 working days.As of February 28, 2011.