Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page of 1 41 Jira tasks were added for each development subsystem for R2C2 and good progress has been made within each subsystem. The AS team continued their refactor Summary Progress: effort to use the new DM data retrieval functionality to generate google charts and matplotlib images based on requested timeframe. The CEI team worked on ways to speed up the ION system launch through a new release of Nimbus and the parallelization of the service launch launches. Additionally the CEI team continued to integrate their services to work within the pyon capability container. The COI team began working on porting the R1 scheduler service into the R2 infrastructure, improved the capability container bootstrap by making it more modular, and added functionality for user assigned queues for AS functionality. The DM team completed work on the user notification service, completed an initial version of the coverage API for storing science data, and began a refactoring of the transform infrastructure and ingestion/retrieval to utilize coverage API. The MI team prepared for and held a successful IDK IOC review, conducted numerous science profile meetings to capture detailed requirements for 5 instruments, continued work on 3 drivers (VEL3D, PRESF, NUTNR), and began updating the instrument driver/agent publishing infrastructure to utilize the new granule and packet publishing framework. Members of the SA team traveled to RSN to discuss details on the RSN OMS interface to enable design and development work to proceed on the platform agent. The team also began a base agent refactor to enable changes to the platform agent and started adding business logic to support the concept of dynamically computed resource attributes for SA managed resources. The integration team initiated and completed an effort to get an end-to-end test system running across all subsystems, including CEI launched capability containers. The team also improved the development environment for the dev team by creating a "smoke test" that quickly verifies if a delivery to the master code branch was OK or not. The UX team continued to work on formatting and laying out the face pages for instrument, platform, observatory, data product, user, resource, and information resource. CI System Administration Subsystem: 3 tasks, 0 In Progress, 2 Resolved Resolved Tasks: ( 1 Fixed, 0 Won't Fix, 1 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No Impact, 0 Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry ) Jira Key Task Status Task Title CISA-97 Adam Brust Resolved ( Fixed) Evaluate and upgrade collaboration tools (Confluence, Jira) CISA-98 John Graybeal Resolved ( Duplicate) Review use of VMWare with current IaaS technology suite CISA-101 Adam Brust Open Evaluate automated recovery operations when operating on the cloud. CI Development Analysis and Synthesis Subsystem: 10 tasks, 1 In Progress, 2 Resolved Resolved Tasks: ( 2 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No Impact, 0 Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry ) Jira Key Task Status Task Title CIDEVAS-50 Rajvkram Singh Resolved ( Fixed) Define objects in preload script CIDEVAS-51 Rajvkram Singh Resolved ( Fixed) Enhance preload code to include Vis Workflow objects defined in script CIDEVAS-48 Rajvkram Singh Open Indicate Data Product objects as Visualizations

Upload: others

Post on 24-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 1 41

Jira tasks were added for each development subsystem for R2C2 and good progress has been made within each subsystem. The AS team continued their refactorSummary Progress: effort to use the new DM data retrieval functionality to generate google charts and matplotlib images based on requested timeframe. The CEI team worked on ways to speed up the IONsystem launch through a new release of Nimbus and the parallelization of the service launch launches. Additionally the CEI team continued to integrate their services to work within thepyon capability container. The COI team began working on porting the R1 scheduler service into the R2 infrastructure, improved the capability container bootstrap by making it moremodular, and added functionality for user assigned queues for AS functionality. The DM team completed work on the user notification service, completed an initial version of the coverageAPI for storing science data, and began a refactoring of the transform infrastructure and ingestion/retrieval to utilize coverage API. The MI team prepared for and held a successful IDKIOC review, conducted numerous science profile meetings to capture detailed requirements for 5 instruments, continued work on 3 drivers (VEL3D, PRESF, NUTNR), and beganupdating the instrument driver/agent publishing infrastructure to utilize the new granule and packet publishing framework. Members of the SA team traveled to RSN to discuss details onthe RSN OMS interface to enable design and development work to proceed on the platform agent. The team also began a base agent refactor to enable changes to the platform agent andstarted adding business logic to support the concept of dynamically computed resource attributes for SA managed resources. The integration team initiated and completed an effort to getan end-to-end test system running across all subsystems, including CEI launched capability containers. The team also improved the development environment for the dev team by creatinga "smoke test" that quickly verifies if a delivery to the master code branch was OK or not. The UX team continued to work on formatting and laying out the face pages for instrument,platform, observatory, data product, user, resource, and information resource.

 

CI System Administration Subsystem: 3 tasks, 0 In Progress, 2 Resolved Resolved Tasks: ( 1 Fixed, 0 Won't Fix, 1 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No Impact, 0

Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CISA-97Adam Brust

Resolved ( Fixed) Evaluate and upgrade collaboration tools (Confluence, Jira)

CISA-98John Graybeal

Resolved ( Duplicate) Review use of VMWare with current IaaS technology suite

CISA-101Adam Brust

Open Evaluate automated recovery operations when operating on the cloud.

 

 

CI Development Analysis and Synthesis Subsystem: 10 tasks, 1 In Progress, 2 Resolved Resolved Tasks: ( 2 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0

Dropped-No Impact, 0 Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVAS-50Rajvkram Singh

Resolved ( Fixed) Define objects in preload script

CIDEVAS-51Rajvkram Singh

Resolved ( Fixed) Enhance preload code to include Vis Workflow objects defined in script

CIDEVAS-48Rajvkram Singh

Open Indicate Data Product objects as Visualizations

Page 2: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 2 41

CIDEVAS-57Rajvkram Singh

Open Refactor service to use workflow data product objects

CIDEVAS-54Rajvkram Singh

In Progress Consolidate viz manager into framework service

CIDEVAS-59Rajvkram Singh

Open Create Matplotlib workflow

CIDEVAS-60Rajvkram Singh

Open Ingest and cache matplotlib images

CIDEVAS-61Rajvkram Singh

Open Refactor Vis Service to retrieve images

CIDEVAS-62Rajvkram Singh

Open Implement on-demand execution of transform

CIDEVAS-63Rajvkram Singh

Open Implement real-time with user queues

 

 

Common Operating Infrastructure Subsystem: 40 tasks, 10 In Progress, 11 Resolved Resolved Tasks: ( 8 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0

Dropped-No Impact, 0 Dropped-May Impact, 3 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVCOI-480Thomas Lennan

Resolved ( Fixed) Provide container certificate

CIDEVCOI-505David Foster

Resolved ( Work Remains) Automatic COI performance tests

CIDEVCOI-551David Foster

Resolved ( Work Remains) Container robust to broker failover

CIDEVCOI-577Thomas Lennan

Resolved ( Fixed) Get CILogon working on Alpha machine

CIDEVCOI-583Michael Meisinger

Resolved ( Fixed) Make bootstrap modular, idempotant and support different boot modes

CIDEVCOI-584Seman Said

Resolved ( Fixed) Create tests for generate_interfaces Integration Points

CIDEVCOI-587Thomas Lennan

Resolved ( Fixed) Support the release pyon as a versioned package

CIDEVCOI-589Thomas Lennan

Resolved ( Fixed) gevent upgrade

Page 3: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 3 41

CIDEVCOI-591Jonathan Newbrough

Resolved ( Work Remains) Investigate BigCouch cluster

CIDEVCOI-594Stephen Henrie

Resolved ( Fixed) Framework support for computed resource attributes

CIDEVCOI-596David Foster

Resolved ( Fixed) User Queues for AS improvements

CIDEVCOI-527Stephen Henrie

Open Agent functionality for non-taskable resources

CIDEVCOI-528Stephen Henrie

Open Governance agent consolidation and extensible framework

CIDEVCOI-529Stephen Henrie

Open Exchange space with governance

CIDEVCOI-535David Foster

Open Enhanced Service Request PrototcolDesign Doc

CIDEVCOI-544Jonathan Newbrough

Open Profile and improve resource registry and CouchDB performance

CIDEVCOI-545Thomas Lennan

Open Service definition extension

CIDEVCOI-548David Foster

Open Integrate a broker management plugin

CIDEVCOI-552Jonathan Newbrough

Open Profile messaging performance

CIDEVCOI-556Thomas Lennan

Open Resource life cycle change protected by policy

CIDEVCOI-508Stephen Henrie

In Progress Resource agent integrated with governance, Org and Policy services

CIDEVCOI-524Stephen Henrie

In Progress Document the policy specification format in the architecture

CIDEVCOI-525Stephen Henrie

In Progress Define essential types of policy in Policy MS

CIDEVCOI-542Thomas Lennan

In Progress Object definition extension

CIDEVCOI-543Michael Meisinger

In Progress Container saves process in state repository

CIDEVCOI-576Thomas Lennan

In Progress COI Requirements verification

CIDEVCOI-580Stephen Henrie

In Progress Conversation type definition in Conversation MS (integration)

CIDEVCOI-585

Page 4: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 4 41

Thomas Lennan In Progress Container stabilization and integration

CIDEVCOI-586Michael Meisinger

In Progress Pyon stability refactoring

CIDEVCOI-592David Foster

In Progress Exchange system bootstrap

CIDEVCOI-550Jonathan Newbrough

Open Set up Rabbit broker failover pairsDesign Doc

CIDEVCOI-578Stephen Henrie

Open Full negotiation conversation with offer, counter-offer and accept

CIDEVCOI-579David Foster

Open EE agent interaction

CIDEVCOI-581Seman Said

Open Add service, object type, resource type and association to running system in Service MS

CIDEVCOI-582Thomas Lennan

Open Support restart system from saved state

CIDEVCOI-588Seman Said

Open Address issue of lingering queues in test builders

CIDEVCOI-590Jonathan Newbrough

Open Container robust to common CouchDB/BigCouch errors

CIDEVCOI-593David Foster

Open Exchange system restart

CIDEVCOI-595David Foster

Open Non-AMQP transport

CIDEVCOI-597Seman Said

Open Scheduler Service

 

 

Common Execution Infrastructure Subsystem: 23 tasks, 6 In Progress, 4 Resolved Resolved Tasks: ( 4 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0

Dropped-No Impact, 0 Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVCEI-271Pierre Riteau

Resolved ( Fixed) Add qcow2 and copy-on-write support to Nimbus IaaS

CIDEVCEI-279David LaBissoniere

Resolved ( Fixed) Parallelize Pyon service launches where appropriate

Page 5: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 5 41

CIDEVCEI-282David LaBissoniere

Resolved ( Fixed) Integrate pre-built packages into launch

CIDEVCEI-283Patrick Armstrong

Resolved ( Fixed) Support multiple statically-defined Execution Engines

CIDEVCEI-258David LaBissoniere

Open Design and implement strategy for populating Resource Registry with CEI objects

CIDEVCEI-270David LaBissoniere

In Progress Integrate Process Dispatcher as Pyon Service

CIDEVCEI-272Pierre Riteau

In Progress Finalize and release Nimbus IaaS 2.10

CIDEVCEI-275David LaBissoniere

In Progress Support System Requirements Verification

CIDEVCEI-278David LaBissoniere

In Progress Add ZooKeeper to launch

CIDEVCEI-281David LaBissoniere

In Progress Enable communications between Apache/Flask and Service Gateway

CIDEVCEI-289David LaBissoniere

In Progress Assist port of base image to EC2

CIDEVCEI-261David LaBissoniere

Open Support integration of launch plans using Pyon CEI components

CIDEVCEI-269David LaBissoniere

Open HA service agent monitoring service workers

CIDEVCEI-273Pierre Riteau

Open Add EPU definition support to EPU Management Service

CIDEVCEI-274John Bresnahan

Open Add EPUM/Provisioner diagnostic and integration tests

CIDEVCEI-276Patrick Armstrong

Open Support system launch

CIDEVCEI-277David LaBissoniere

Open Add centralized logging to launch

CIDEVCEI-280John Bresnahan

Open Improve per-EPU logging

CIDEVCEI-284Patrick Armstrong

Open Integrate the HA service agent as a Pyon agent

CIDEVCEI-285Patrick Armstrong

Open Prototype pulling sensor data into an HA Agent

CIDEVCEI-286Patrick Armstrong

Open Process Dispatcher scheduling API

CIDEVCEI-287

Page 6: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 6 41

David LaBissoniere Open Start containers with security credentials

CIDEVCEI-288Patrick Armstrong

Open Prototype installing process packages from repository

 

 

Data Management Subsystem: 52 tasks, 11 In Progress, 13 Resolved Resolved Tasks: ( 5 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 7 Dropped-No Impact, 0

Dropped-May Impact, 1 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVDM-455Christopher Mueller

Resolved ( Dropped-NoImpact)

Specify Domain of Application

CIDEVDM-456Christopher Mueller

Resolved ( Dropped-NoImpact)

Define Coverage Object Model including Granule, Record Set and Value Set

CIDEVDM-457Christopher Mueller

Resolved ( Dropped-NoImpact)

Complete Coverage Object Model including Granule, Record Set and Value Set

CIDEVDM-463Christopher Mueller

Resolved ( Dropped-NoImpact)

Define API for coverage objects, domain and range

CIDEVDM-464Christopher Mueller

Resolved ( Dropped-NoImpact)

Implement API for coverage objects, domain and range

CIDEVDM-470Christopher Mueller

Resolved ( Dropped-NoImpact)

Persistence API for Coverages

CIDEVDM-474Christopher Mueller

Resolved ( Dropped-NoImpact)

Coverage persistence implementation

CIDEVDM-508David Foster

Resolved ( Fixed) Refactor pubsub code to use Exchange Objects

CIDEVDM-528Luke Campbell

Resolved ( Fixed) Primitive Ingestion

CIDEVDM-529Luke Campbell

Resolved ( Fixed) Primitive Replay

CIDEVDM-530Christopher Mueller

Resolved ( Work Remains) Refactor of Resource Agent Framework

CIDEVDM-532Christopher Mueller

Resolved ( Fixed) Initial Coverage API Design and Implementation

CIDEVDM-533Christopher Mueller

Resolved ( Fixed) Primitive Coverage Model and Persistence Implementation

Page 7: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 7 41

CIDEVDM-466Maurice Manning

Open Define Stream API extensions to publish and subscribe to Coverages

CIDEVDM-467Tim Giguere

Open Extend Stream API to publish and subscribe to Coverages

CIDEVDM-469Maurice Manning

Open Refine the Service Interfaces and system resources for coverage registration and streaming

CIDEVDM-471Tim Giguere

Open Implementation of service interface changes

CIDEVDM-472Luke Campbell

Open Implementation of coverage ingestion/insertion

CIDEVDM-473Luke Campbell

Open Implementation of coverage retriever/replay

CIDEVDM-475Maurice Manning

Open Create provenance and workflow schema

CIDEVDM-499Maurice Manning

Open Design notification repository to support R2 capabilities.

CIDEVDM-503Maurice Manning

Open Event processing design

CIDEVDM-506Swarbhanu Chatterjee

In Progress Implement aggregated notifications

CIDEVDM-512Luke Campbell

In Progress More flexible replay

CIDEVDM-517Swarbhanu Chatterjee

In Progress Refactor UNS

CIDEVDM-518Swarbhanu Chatterjee

In Progress Notification Workers

CIDEVDM-519Swarbhanu Chatterjee

In Progress Unit and Integration Testing

CIDEVDM-520Swarbhanu Chatterjee

In Progress Advanced user notification requests

CIDEVDM-525Luke Campbell

In Progress Resolve temporal searching issues

CIDEVDM-534Christopher Mueller

In Progress Initial Coverage Model Design and Implementation

CIDEVDM-535Christopher Mueller

In Progress Initial Persistence Layer Design and Implementation

CIDEVDM-536Christopher Mueller

In Progress Refinement of Coverage API

CIDEVDM-539

Page 8: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 8 41

Christopher Mueller In Progress Refinement of Granule

CIDEVDM-509Tim Giguere

Open Refactor TopicTopologies

CIDEVDM-510Tim Giguere

Open Add capability to define assignment of stream to exchange points via configuration.

CIDEVDM-511Tim Giguere

Open Robust multi-input data transforms

CIDEVDM-514Tim Giguere

Open Refactor Example Transforms

CIDEVDM-515Tim Giguere

Open Refactor Transforms

CIDEVDM-516Tim Giguere

Open Refactor Transform Management Service

CIDEVDM-521Christopher Mueller

Open Design granule API to include metadata

CIDEVDM-522Christopher Mueller

Open Implement granule API to include metadata

CIDEVDM-523Swarbhanu Chatterjee

Open Refine provenance schema design and create impl plan

CIDEVDM-524Luke Campbell

Open Stream Definition

CIDEVDM-526Luke Campbell

Open Prototype GeoPortal

CIDEVDM-527Luke Campbell

Open Search and Navigation

CIDEVDM-531Maurice Manning

Open Define storage mechanism for process definitions

CIDEVDM-537Christopher Mueller

Open Refinement of Coverage Model

CIDEVDM-538Christopher Mueller

Open Refinement of Persistence Layer

CIDEVDM-540Tim Giguere

Open Install ERDDAP and PyDAP

CIDEVDM-541Tim Giguere

Open Validate interaction pattern between ERDDAP and PyDAP

CIDEVDM-542Tim Giguere

Open Package PyDAP in an ION Agent

CIDEVDM-543Tim Giguere

Open Write prototype PyDAP handler plugin

Page 9: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 9 41

 

 

External Observatory Integration Subsystem: 3 tasks, 0 In Progress, 2 Resolved Resolved Tasks: ( 0 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No

Impact, 0 Dropped-May Impact, 2 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVEOI-114Christopher Mueller

Resolved ( Work Remains) Refinement of SlocumDataHandler

CIDEVEOI-115Christopher Mueller

Resolved ( Work Remains) Register sample Glider datasets

CIDEVEOI-104Christopher Mueller

Open Ingest via iRODS

 

 

CI Development Marine Integration Subsystem: 13 tasks, 2 In Progress, 2 Resolved Resolved Tasks: ( 0 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0

Dropped-No Impact, 0 Dropped-May Impact, 2 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVMI-501Bill French

Resolved ( Work Remains) Complete C++ port agent for serial devices

CIDEVMI-502Bill French

Resolved ( Work Remains) Complete port agent for digi devices

CIDEVMI-61David Everett

In Progress ISUS (NUTNR)

CIDEVMI-499Steve Foley

In Progress Update Instrument Driver/Agent publishing

CIDEVMI-251Bill Bollenbacher

Open NOBSKAMAVS (VEL3D)

CIDEVMI-321Roger Unwin

Open PRESF

CIDEVMI-500Bill French

Open Complete C++ port agent for ethernet devices

CIDEVMI-503

Page 10: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 10 41

Bill French Open Complete Science Profiles

CIDEVMI-504Bill French

Open Transform Deployment Process

CIDEVMI-505Steve Foley

Open Driver publication process

CIDEVMI-506Bill French

Open Driver Egg Eggsecutable

CIDEVMI-507Bill French

Open TRHPH - Complete for publication

CIDEVMI-508Bill French

Open PARAD-SA - Complete for publication

 

 

Sensing & Acquisition Subsystem: 34 tasks, 12 In Progress, 3 Resolved Resolved Tasks: ( 1 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No Impact, 0

Dropped-May Impact, 2 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIDEVSA-337Edward Hunter

Resolved ( Fixed) 2CAA technology investigation

CIDEVSA-354Carlos Rueda

Resolved ( Work Remains) Distinguish internal vs user visible data products

CIDEVSA-365Edward Hunter

Resolved ( Work Remains) 2CAA Component Implementation

CIDEVSA-245Maurice Manning

Open Define Marine observatory facility policy model

CIDEVSA-315Maurice Manning

Open Define platform services

CIDEVSA-344Carlos Rueda

In Progress Design management of raw data

CIDEVSA-357Carlos Rueda

In Progress Platform agent detailed design

CIDEVSA-358Carlos Rueda

In Progress Platform agent initial implementation

CIDEVSA-359Carlos Rueda

In Progress OMS Simulator

Page 11: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 11 41

CIDEVSA-368Ian Katz

In Progress Add support for extended resource calcuations

CIDEVSA-370Carlos Rueda

In Progress Implement management of raw data design

CIDEVSA-373Ian Katz

In Progress Sync OOI asset database with ION

CIDEVSA-375Maurice Manning

In Progress Design data processes with more than one inputDesign Doc

CIDEVSA-379Maurice Manning

In Progress Add capabilities to validate workflow

CIDEVSA-380Ian Katz

In Progress Data product life cycle and visibility

CIDEVSA-381Maurice Manning

In Progress Refine provenance schema design and create impl plan

CIDEVSA-383Maurice Manning

In Progress Implement data product versioning capabilities for R2.Design Doc

CIDEVSA-355Edward Hunter

Open Base Agent Refactor

CIDEVSA-356Edward Hunter

Open Instrument Agent Improvements

CIDEVSA-360Carlos Rueda

Open Design and Implement Platform Driver Framework

CIDEVSA-361Carlos Rueda

Open Add PA startup/shutdown functionality

CIDEVSA-362Carlos Rueda

Open Add PA Resource Monitoring and Resource Provisioning

CIDEVSA-363Edward Hunter

Open Refine 2CAA Design

CIDEVSA-364Edward Hunter

Open End-to-end 2CAA Prototype

CIDEVSA-366Edward Hunter

Open Time management concept of operations and design candidate

CIDEVSA-367Ian Katz

Open Add support for model specific device attributesDesign Doc

CIDEVSA-369Ian Katz

Open Basic instrument test and reset in Instrument MS

CIDEVSA-371Maurice Manning

Open Design bulk data acquisition workflow, organization and applicable policies.

CIDEVSA-372

Page 12: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 12 41

Maurice Manning Open Implement bulk data acquisition processing

CIDEVSA-374Ian Katz

Open Implement basic service capabilities - Marine platform resource services

CIDEVSA-376Maurice Manning

Open Implement Data processes with more than one inputDesign Doc

CIDEVSA-377Maurice Manning

Open Design data processes with complex subscriptionDesign Doc

CIDEVSA-378Maurice Manning

Open Implement data processes with complex subscriptionDesign Doc

CIDEVSA-382Maurice Manning

Open Implement data provenance extraction and metadata

 

 

System Integration, Test, and Validation Subsystem: 26 tasks, 12 In Progress, 2 Resolved Resolved Tasks: ( 1 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0

Dropped-No Impact, 0 Dropped-May Impact, 1 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIINT-186Jamie Chen

Resolved ( Work Remains) developer centos image

CIINT-196Jonathan Newbrough

Resolved ( Fixed) Assist with End-to-End System Integration

CIINT-166Jamie Chen

In Progress Improve integration test infrastructure (pycc plugin)

CIINT-169Jamie Chen

In Progress pycc nose integration test runner using CEI

CIINT-173Jonathan Newbrough

In Progress Stress testing framework

CIINT-174Jamie Chen

In Progress Better documentation for "best practicies" for integration tests

CIINT-175Jamie Chen

In Progress full integration test runner using CEI

CIINT-176Jamie Chen

In Progress CEI builder to pre package buildout

CIINT-177Jamie Chen

In Progress r2testsystem1 runner

Page 13: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 13 41

CIINT-178Jamie Chen

In Progress Add build info to each builder

CIINT-179Jamie Chen

In Progress cei light launch integration test runner

CIINT-182Jamie Chen

In Progress Formalize what tests will be run as INT_LONG

CIINT-183Jamie Chen

In Progress Integrate elastic search tests into coi_testbc

CIINT-190Jamie Chen

In Progress Track Integration tests for all subsystems

CIINT-180Jamie Chen

Open MI test builder

CIINT-181Jamie Chen

Open smoke test builder

CIINT-184Jamie Chen

Open unit test code coverage

CIINT-185Jamie Chen

Open Prune code from pyon, coi-services, and CEI coverage reports for code not included in running R2 product

CIINT-187Jamie Chen

Open Move egg repository off Amoeba to Operation supported VM

CIINT-188Jamie Chen

Open Integrate Common Data Model technology into builds and for developers

CIINT-189Jamie Chen

Open Troubleshoot bigcouch

CIINT-191Jonathan Newbrough

Open Upgrade dependency eggs in pyon and COI

CIINT-192Jonathan Newbrough

Open rsyslog and elastic search

CIINT-193Jonathan Newbrough

Open int test code coverage

CIINT-194Jonathan Newbrough

Open Use Stress testing framework to test out full running system on EC2 and Nimbus clouds

CIINT-195Jonathan Newbrough

Open Gumstix Analysis

 

 

Page 14: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 14 41

System Engineering and Architecture Subsystem: 23 tasks, 12 In Progress, 0 Resolved

Jira Key Task Status Task Title

SYSENG-160Stephen Henrie

In Progress Bring the AgentDefinition and AgentInstance resource types to readiness for R2C3

SYSENG-161Stephen Henrie

In Progress Bring the ConversationType, Conversation and ConversationRole resources types to readiness for R2C2

SYSENG-173Maurice Manning

In Progress Bring the DataSet resource type to readiness for R2C2

SYSENG-177Maurice Manning

In Progress Bring the Stream, StreamDefinition, StreamTopology resource types to readiness for R2C2

SYSENG-191Maurice Manning

In Progress Dataset Coverage service operations

SYSENG-193Michael Meisinger

In Progress Align DM resource types with UX attributes

SYSENG-194Michael Meisinger

In Progress Align SA resource types with UX attributes

SYSENG-195Michael Meisinger

In Progress Align EOI resource types with UX attributes

SYSENG-196Michael Meisinger

In Progress Align COI resource types with UX attributes

SYSENG-197Michael Meisinger

In Progress Align CEI resource types with UX attributes

SYSENG-198Michael Meisinger

In Progress Align AS resource types with UX attributes

SYSENG-207Michael Meisinger

In Progress Embedded platform technology decisions

SYSENG-134Stephen Henrie

Open Bring the Agent Management service to to readiness for R2C3

SYSENG-135Stephen Henrie

Open Bring the Conversation Management service to to readiness for R2C2

SYSENG-148Maurice Manning

Open Bring the CDM Validation service to to readiness for R2C3

SYSENG-199Stephen Henrie

Open Bring the Commitment and Negotiation resource types to readiness for R2C2

SYSENG-200Maurice Manning

Open Bring the Deployment resource type to readiness for R2C2

SYSENG-201Maurice Manning

Open Bring the Observatory, SubSite, PlatformSite, InstrumentSite resource types and Site base type to readiness for R2C2

Page 15: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 15 41

SYSENG-204Maurice Manning

Open Bring the Frame of Reference UI concept to readiness for R2C2

SYSENG-206Maurice Manning

Open Bring the Platform Agent architecture design to readiness for implementation

SYSENG-208Michael Meisinger

Open Embedded platform capability container

SYSENG-209Stephen Henrie

Open Design UI interactions toolchain from UI database to UI

SYSENG-210Stephen Henrie

Open Design framework from search and results from UI

 

 

User Experience Subsystem: 33 tasks, 2 In Progress, 5 Resolved Resolved Tasks: ( 0 Fixed, 0 Won't Fix, 0 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 2 Dropped-No Impact, 0 Dropped-May

Impact, 3 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CIUX-277susanne jul

Resolved ( Dropped-NoImpact)

Requirements and Product Alignment

CIUX-295Todd Boteler

Resolved ( Work Remains) User Notification and Event Subscription Development (6)

CIUX-301susanne jul

Resolved ( Dropped-NoImpact)

External Engagement Platform Development

CIUX-303Todd Boteler

Resolved ( Work Remains) Allow users to customize and personalize their display (9)

CIUX-343Todd Boteler

Resolved ( Work Remains) Status Page Template (4)

CIUX-275Carolanne Fisher

Open Information Model and Resource Attribute Alignment

CIUX-276susanne jul

Open User Vocabulary - testing

CIUX-283Carolanne Fisher

Open Core Interaction Specification (2)

CIUX-284Carolanne Fisher

Open CI Operator Screens (8)

CIUX-285Carolanne Fisher

Open User Vocabulary - Core Resources (3)

Page 16: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 16 41

CIUX-340Todd Boteler

Open Display Tooltips (2)

CIUX-341Todd Boteler

Open Basic Error Handling (2)

CIUX-342Todd Boteler

Open Pixel perfect graphic treatment (3)

CIUX-293Todd Boteler

In Progress Facepage Development

CIUX-336Todd Boteler

In Progress Left hand navigation bar (1)

CIUX-324Carolanne Fisher

Open Demo Presentation Preparation

CIUX-325susanne jul

Open Demo Presentation Preparation

CIUX-326Todd Boteler

Open Demo Presentation Preparation

CIUX-327Carolanne Fisher

Open Dashboard & Related Resources (6)

CIUX-328Carolanne Fisher

Open Extended Marine Resources (7)

CIUX-329Carolanne Fisher

Open User Vocabulary - Marine Resources (7)

CIUX-330Carolanne Fisher

Open User Vocabulary - CI Operator (8)

CIUX-331Carolanne Fisher

Open Enhanced Usability (9)

CIUX-333Carolanne Fisher

Open Specifications Database refactoring

CIUX-334Todd Boteler

Open Integrate Service API for Instrument Device (1)

CIUX-335Todd Boteler

Open Facepage Development for generic resources (1)

CIUX-337Todd Boteler

Open Integrate with Extended Service APIs

CIUX-338Todd Boteler

Open Interactions supporting facepages (2)

CIUX-339Todd Boteler

Open Filemaker Pro to Interaction resources (2)

CIUX-344

Page 17: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 17 41

Martin Locker Open Complete Icon Set (3)

CIUX-346susanne jul

Open Specifications Database refactoring

CIUX-349susanne jul

Open Internal Alignment

CIUX-350Carolanne Fisher

Open Internal Alignment

 

 

CI CyberPop Subsystem: 466 tasks, 1 In Progress, 169 Resolved Resolved Tasks: ( 165 Fixed, 5 Won't Fix, 1 Duplicate, 0 Incomplete, 0 Cannot Reproduce, 0 Dropped-No Impact, 0

Dropped-May Impact, 0 Work Remains, 0 Mistaken Entry )

Jira Key Task Status Task Title

CPOP-42Teresa V. Allen

Closed Dell R510 and Dell 810 servers

CPOP-286Teresa V. Allen

Closed Purchase Copper cabling

CPOP-75brian dunne

Resolved ( Fixed) Install Cisco 4500 switch for Portland

CPOP-76brian dunne

Resolved ( Fixed) Arista 7124SX

CPOP-79brian dunne

Resolved ( Fixed) R810 servers for Portland

CPOP-83brian dunne

Resolved ( Fixed) Portland R810 servers - create new subnet

CPOP-84Bahadir Gul

Resolved ( Fixed) Portland R810 servers - reinstall ESXi

CPOP-85Bahadir Gul

Resolved ( Fixed) Portland R810 servers - creation of VSphere

CPOP-86Mark James

Resolved ( Fixed) Portland R810 servers - IP allocation

CPOP-87Bahadir Gul

Resolved ( Fixed) Portland R810 servers - Ubuntu installations

CPOP-88Bahadir Gul

Resolved ( Fixed) Portland R810 servers - create Compellent storage for VMWare

Page 18: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 18 41

CPOP-90Daniel Wei

Resolved ( Fixed) Portland R810 servers - Configure ION apps

CPOP-91Daniel Wei

Resolved ( Fixed) Portland R810 servers - incorporate sflow

CPOP-93Adam Brust

Resolved ( Duplicate) Add Tripwire production configuration files to monitor for changes

CPOP-96brian dunne

Resolved ( Fixed) Power Calculations for PIttock & Seattle

CPOP-237Mark James

Resolved ( Won't Fix) Purchase Cisco ASA 5510

CPOP-238Mark James

Resolved ( Won't Fix) Install Cisco ASA 5510

CPOP-239Mark James

Resolved ( Fixed) Cable Cisco ASA 5510

CPOP-240Mark James

Resolved ( Won't Fix) Configure S/W Cisco ASA 5510

CPOP-241Mark James

Resolved ( Fixed) Test Cisco ASA 5510

CPOP-242Mark James

Resolved ( Fixed) Document Cisco ASA 5510

CPOP-243Unassigned

Resolved ( Fixed) Purchase Cisco 4500

CPOP-244brian dunne

Resolved ( Fixed) Install Cisco 4500

CPOP-245brian dunne

Resolved ( Fixed) Cable Cisco 4500

CPOP-249Rod Cressey

Resolved ( Fixed) Purchase Dell R810 Servers

CPOP-250Rod Cressey

Resolved ( Fixed) Install Dell R810 Servers

CPOP-251Rod Cressey

Resolved ( Fixed) Cable Dell R810 Servers

CPOP-252Rod Cressey

Resolved ( Fixed) Configure S/W Dell R810 Servers

CPOP-253Rod Cressey

Resolved ( Fixed) Test Dell R810 Servers

CPOP-254Rod Cressey

Resolved ( Fixed) Document Dell R810 Servers

CPOP-267

Page 19: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 19 41

Rod Cressey Resolved ( Fixed) Purchase Dell R410 Servers

CPOP-268Rod Cressey

Resolved ( Fixed) Install Dell R410 Servers

CPOP-269Rod Cressey

Resolved ( Fixed) Cable Dell R410 Servers

CPOP-270Rod Cressey

Resolved ( Fixed) Configure S/W Dell R410 Servers

CPOP-271Rod Cressey

Resolved ( Fixed) Test Dell R410 Servers

CPOP-272Rod Cressey

Resolved ( Fixed) Document Dell R410 Servers

CPOP-279Mark James

Resolved ( Fixed) Purchase Racks

CPOP-280brian dunne

Resolved ( Fixed) Install Racks

CPOP-281brian dunne

Resolved ( Fixed) Cable Racks

CPOP-282Mark James

Resolved ( Fixed) Purchase Shelves

CPOP-283Mark James

Resolved ( Fixed) Install Shelves

CPOP-284Teresa V. Allen

Resolved ( Fixed) Purchase Fiber cabling

CPOP-285brian dunne

Resolved ( Fixed) Install Fiber cabling

CPOP-287brian dunne

Resolved ( Fixed) Install Copper cabling

CPOP-288Teresa V. Allen

Resolved ( Fixed) Purchase Environmental Sensors

CPOP-294Teresa V. Allen

Resolved ( Fixed) Purchase Mergepoint KVM (Large Site)

CPOP-298Teresa V. Allen

Resolved ( Fixed) Purchase PDUs

CPOP-300brian dunne

Resolved ( Fixed) Cable PDUs

CPOP-311Rod Cressey

Resolved ( Fixed) Install Configure Network

CPOP-312Rod Cressey

Resolved ( Fixed) Cable Configure Network

Page 20: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 20 41

CPOP-313Rod Cressey

Resolved ( Fixed) Configure S/W Configure Network

CPOP-321Rod Cressey

Resolved ( Fixed) Document Implementation

CPOP-350Mark James

Resolved ( Fixed) Purchase Cisco ASA 5510

CPOP-351Mark James

Resolved ( Fixed) Install Cisco ASA 5510

CPOP-352Mark James

Resolved ( Fixed) Cable Cisco ASA 5510

CPOP-353Mark James

Resolved ( Won't Fix) Configure S/W Cisco ASA 5510

CPOP-354Mark James

Resolved ( Fixed) Test Cisco ASA 5510

CPOP-355Mark James

Resolved ( Fixed) Document Cisco ASA 5510

CPOP-356Unassigned

Resolved ( Fixed) Purchase Cisco 4500

CPOP-357brian dunne

Resolved ( Fixed) Install Cisco 4500

CPOP-362Rod Cressey

Resolved ( Fixed) Purchase Dell R810 Servers

CPOP-363Rod Cressey

Resolved ( Fixed) Install Dell R810 Servers

CPOP-364Rod Cressey

Resolved ( Fixed) Cable Dell R810 Servers

CPOP-365Rod Cressey

Resolved ( Fixed) Configure S/W Dell R810 Servers

CPOP-366Rod Cressey

Resolved ( Fixed) Test Dell R810 Servers

CPOP-367Rod Cressey

Resolved ( Fixed) Document Dell R810 Servers

CPOP-380Rod Cressey

Resolved ( Fixed) Purchase Dell R410 Servers

CPOP-381Rod Cressey

Resolved ( Fixed) Install Dell R410 Servers

CPOP-382Rod Cressey

Resolved ( Fixed) Cable Dell R410 Servers

CPOP-383

Page 21: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 21 41

Rod Cressey Resolved ( Fixed) Configure S/W Dell R410 Servers

CPOP-384Rod Cressey

Resolved ( Fixed) Test Dell R410 Servers

CPOP-385Rod Cressey

Resolved ( Fixed) Document Dell R410 Servers

CPOP-392Mark James

Resolved ( Fixed) Purchase Racks

CPOP-393brian dunne

Resolved ( Fixed) Install Racks

CPOP-394brian dunne

Resolved ( Fixed) Cable Racks

CPOP-395Mark James

Resolved ( Fixed) Purchase Shelves

CPOP-396Mark James

Resolved ( Fixed) Install Shelves

CPOP-397Teresa V. Allen

Resolved ( Fixed) Purchase Fiber cabling

CPOP-398brian dunne

Resolved ( Fixed) Install Fiber cabling

CPOP-399Teresa V. Allen

Resolved ( Fixed) Purchase Copper cabling

CPOP-400brian dunne

Resolved ( Fixed) Install Copper cabling

CPOP-401Teresa V. Allen

Resolved ( Fixed) Purchase Environmental Sensors

CPOP-403brian dunne

Resolved ( Fixed) Cable Environmental Sensors

CPOP-407Teresa V. Allen

Resolved ( Fixed) Purchase Mergepoint KVM (Large Site)

CPOP-411Teresa V. Allen

Resolved ( Fixed) Purchase PDUs

CPOP-413brian dunne

Resolved ( Fixed) Cable PDUs

CPOP-424Rod Cressey

Resolved ( Fixed) Install Configure Network

CPOP-425Rod Cressey

Resolved ( Fixed) Cable Configure Network

CPOP-426Rod Cressey

Resolved ( Fixed) Configure S/W Configure Network

Page 22: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 22 41

CPOP-463Mark James

Resolved ( Fixed) Purchase Racks

CPOP-464brian dunne

Resolved ( Fixed) Install WHOI Rack

CPOP-465brian dunne

Resolved ( Fixed) Cable Racks

CPOP-466Mark James

Resolved ( Fixed) Purchase Shelves

CPOP-467Mark James

Resolved ( Fixed) Install Shelves

CPOP-468Teresa V. Allen

Resolved ( Fixed) Purchase Copper cabling

CPOP-469brian dunne

Resolved ( Fixed) Install WHOI Rack copper cabling

CPOP-470brian dunne

Resolved ( Fixed) Cable Copper cabling

CPOP-471Teresa V. Allen

Resolved ( Fixed) Purchase Mergepoint KVM (Small Site)

CPOP-475Teresa V. Allen

Resolved ( Fixed) Purchase UPS

CPOP-476brian dunne

Resolved ( Fixed) Install WHOI Rack UPS

CPOP-477brian dunne

Resolved ( Fixed) Cable UPS

CPOP-480Teresa V. Allen

Resolved ( Fixed) Purchase PDUs

CPOP-482brian dunne

Resolved ( Fixed) Cable PDUs

CPOP-494Rod Cressey

Resolved ( Fixed) Install Configure Network

CPOP-495Rod Cressey

Resolved ( Fixed) Cable Configure Network

CPOP-496Rod Cressey

Resolved ( Fixed) Configure S/W Configure Network

CPOP-539Mark James

Resolved ( Fixed) Purchase Cisco ASA 5510

CPOP-540Mark James

Resolved ( Fixed) Install Cisco ASA 5510

CPOP-541

Page 23: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 23 41

Mark James Resolved ( Fixed) Cable Cisco ASA 5510

CPOP-542Mark James

Resolved ( Won't Fix) Configure S/W Cisco ASA 5510

CPOP-543Mark James

Resolved ( Fixed) Test Cisco ASA 5510

CPOP-544Mark James

Resolved ( Fixed) Document Cisco ASA 5510

CPOP-551Rod Cressey

Resolved ( Fixed) Purchase Dell R810 Servers

CPOP-575Teresa V. Allen

Resolved ( Fixed) Purchase VMWare ESXI Enterprise

CPOP-576Mark James

Resolved ( Fixed) Install VMWare ESXI Enterprise

CPOP-577Mark James

Resolved ( Fixed) Cable VMWare ESXI Enterprise

CPOP-578Mark James

Resolved ( Fixed) Configure S/W VMWare ESXI Enterprise

CPOP-579Mark James

Resolved ( Fixed) Test VMWare ESXI Enterprise

CPOP-581Teresa V. Allen

Resolved ( Fixed) Purchase VMWare vCenter

CPOP-582Mark James

Resolved ( Fixed) Install VMWare vCenter

CPOP-583Mark James

Resolved ( Fixed) Cable VMWare vCenter

CPOP-584Mark James

Resolved ( Fixed) Configure S/W VMWare vCenter

CPOP-585Mark James

Resolved ( Fixed) Test VMWare vCenter

CPOP-587Teresa V. Allen

Resolved ( Fixed) Purchase Cisco Nexus 1000v

CPOP-589Mark James

Resolved ( Fixed) Cable Cisco Nexus 1000v

CPOP-594Bahadir Gul

Resolved ( Fixed) Install Microsoft SQL Server

CPOP-595Bahadir Gul

Resolved ( Fixed) Cable Microsoft SQL Server

CPOP-596Bahadir Gul

Resolved ( Fixed) Configure S/W Microsoft SQL Server

Page 24: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 24 41

CPOP-597Bahadir Gul

Resolved ( Fixed) Test Microsoft SQL Server

CPOP-599Mark James

Resolved ( Fixed) Purchase Racks

CPOP-600brian dunne

Resolved ( Fixed) Install Racks

CPOP-601brian dunne

Resolved ( Fixed) Cable Racks

CPOP-602Mark James

Resolved ( Fixed) Purchase Shelves

CPOP-603Mark James

Resolved ( Fixed) Install Shelves

CPOP-604Teresa V. Allen

Resolved ( Fixed) Purchase Fiber cabling

CPOP-605brian dunne

Resolved ( Fixed) Install Fiber cabling

CPOP-606brian dunne

Resolved ( Fixed) Cable Fiber cabling

CPOP-607Teresa V. Allen

Resolved ( Fixed) Purchase Copper cabling

CPOP-608brian dunne

Resolved ( Fixed) Install Copper cabling

CPOP-609brian dunne

Resolved ( Fixed) Cable Copper cabling

CPOP-610Teresa V. Allen

Resolved ( Fixed) Purchase Environmental Sensors

CPOP-612brian dunne

Resolved ( Fixed) Cable Environmental Sensors

CPOP-616Teresa V. Allen

Resolved ( Fixed) Purchase Mergepoint KVM (Large Site)

CPOP-620Teresa V. Allen

Resolved ( Fixed) Purchase PDUs

CPOP-622brian dunne

Resolved ( Fixed) Cable PDUs

CPOP-633Rod Cressey

Resolved ( Fixed) Install Configure Network

CPOP-634Rod Cressey

Resolved ( Fixed) Cable Configure Network

CPOP-635

Page 25: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 25 41

Rod Cressey Resolved ( Fixed) Configure S/W Configure Network

CPOP-649Mark James

Resolved ( Fixed) Cisco MoN

CPOP-651Mark James

Resolved ( Fixed) BOM ECR

CPOP-652brian dunne

Resolved ( Fixed) Cable Cisco 4500

CPOP-694Mark James

Resolved ( Fixed) Purchase Cisco 3560X switch for Seattle Distribution Point

CPOP-695brian dunne

Resolved ( Fixed) Install Cisco 3560X switch for Seattle Distribution Point

CPOP-696brian dunne

Resolved ( Fixed) Cable Cisco 3560X switch for Seattle Distribution Point

CPOP-697brian dunne

Resolved ( Fixed) Test Cisco 3560X switch for Seattle Distribution Point

CPOP-698brian dunne

Resolved ( Fixed) Document Cisco 3560X switch for Seattle Distribution Point

CPOP-699Mark James

Resolved ( Fixed) Purchase Cisco 3560X switch for Chicago Distribution Point

CPOP-700brian dunne

Resolved ( Fixed) Install Cisco 3560X switch for Chicago Distribution Point

CPOP-701brian dunne

Resolved ( Fixed) Cable Cisco 3560X switch for Chicago Distribution Point

CPOP-702brian dunne

Resolved ( Fixed) Test Cisco 3560X switch for Chicago Distribution Point

CPOP-703brian dunne

Resolved ( Fixed) Document Cisco 3560X switch for Chicago Distribution Point

CPOP-704Mark James

Resolved ( Fixed) Puchase Cisco 3560X switch for Portland Acquisition Point

CPOP-705brian dunne

Resolved ( Fixed) Install Cisco 3560X switch for Portland Acquisition Point

CPOP-706brian dunne

Resolved ( Fixed) Cable Cisco 3560X switch for Portland Acquisition Point

CPOP-707brian dunne

Resolved ( Fixed) Test Cisco 3560X switch for Portland Acquisition Point

CPOP-708brian dunne

Resolved ( Fixed) Document Cisco 3560X switch for Portland Acquisition Point

CPOP-709Mark James

Resolved ( Fixed) Purchase Cisco 3560X switch for WHOI Acquisition Point

Page 26: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 26 41

CPOP-710brian dunne

Resolved ( Fixed) Install WHOI Cisco 3560X switch

CPOP-711brian dunne

Resolved ( Fixed) Cable WHOI Cisco 3560X switch

CPOP-712brian dunne

Resolved ( Fixed) Test WHOI Cisco 3560X switch

CPOP-713brian dunne

Resolved ( Fixed) Document WHOI Cisco 3560X switch

CPOP-586Bahadir Gul

In Progress Document Portland VMWare Infrastructure

CPOP-213Paul Dean

Open Purchase Chicago A10 - AX2500

CPOP-214Rod Cressey

Open Install A10 - AX2500

CPOP-215Rod Cressey

Open Cable A10 - AX2500

CPOP-216Rod Cressey

Open Configure S/W A10 - AX2500

CPOP-217Rod Cressey

Open Test A10 - AX2500

CPOP-218Rod Cressey

Open Document A10 - AX2500

CPOP-219Paul Dean

Open Purchase Chicago Palo Alto 2050 Firewall

CPOP-220Rod Cressey

Open Install Palo Alto 2050 Firewall

CPOP-221Rod Cressey

Open Cable Palo Alto 2050 Firewall

CPOP-222Rod Cressey

Open Configure S/W Palo Alto 2050 Firewall

CPOP-223Rod Cressey

Open Test Palo Alto 2050 Firewall

CPOP-224Rod Cressey

Open Document Palo Alto 2050 Firewall

CPOP-225Paul Dean

Open Purchase Chicago Palo Alto 500 switch

CPOP-226Rod Cressey

Open Install Palo Alto 500 VPN switch

CPOP-227

Page 27: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 27 41

Rod Cressey Open Cable Palo Alto 500 switch

CPOP-228Rod Cressey

Open Configure S/W Palo Alto 500 switch

CPOP-229Rod Cressey

Open Test Palo Alto 500 switch

CPOP-230Rod Cressey

Open Document Palo Alto 500 switch

CPOP-231Paul Dean

Open Purchase Chicago Infoblox 550A

CPOP-232Rod Cressey

Open Install Infoblox 550A

CPOP-233Rod Cressey

Open Cable Infoblox 550A

CPOP-234Rod Cressey

Open Configure S/W Infoblox 550A

CPOP-235Rod Cressey

Open Test Infoblox 550A

CPOP-236Rod Cressey

Open Document Infoblox 550A

CPOP-246brian dunne

Open Configure S/W Cisco 4500

CPOP-247brian dunne

Open Test Cisco 4500

CPOP-248brian dunne

Open Document Cisco 4500

CPOP-255Paul Dean

Open Purchase Chicago Dell R810 servers (4) (128GB)

CPOP-256Rod Cressey

Open Install Dell R810 server (128GB)

CPOP-257Rod Cressey

Open Cable Dell R810 server (128GB)

CPOP-258Rod Cressey

Open Configure S/W Dell R810 server (128GB)

CPOP-259Rod Cressey

Open Test Dell R810 server (128GB)

CPOP-260Rod Cressey

Open Document Dell R810 server (128GB)

CPOP-261Paul Dean

Open Purchase Chicago Dell R610 Server

Page 28: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 28 41

CPOP-262Rod Cressey

Open Install Dell R610 Servers

CPOP-263Rod Cressey

Open Cable Dell R610 Servers

CPOP-264Rod Cressey

Open Configure S/W Dell R610 Servers

CPOP-265Rod Cressey

Open Test Dell R610 Servers

CPOP-266Rod Cressey

Open Document Dell R610 Servers

CPOP-273Paul Dean

Open Purchase Chicago Compellent Storage

CPOP-274Rod Cressey

Open Install Compellent Storage

CPOP-275Rod Cressey

Open Cable Compellent Storage

CPOP-276Rod Cressey

Open Configure S/W Compellent Storage

CPOP-277Rod Cressey

Open Test Compellent Storage

CPOP-278Rod Cressey

Open Document Compellent Storage

CPOP-289brian dunne

Open Install Environmental Sensors

CPOP-290brian dunne

Open Cable Environmental Sensors

CPOP-291brian dunne

Open Configure S/W Environmental Sensors

CPOP-292brian dunne

Open Test Environmental Sensors

CPOP-293brian dunne

Open Document Environmental Sensors

CPOP-295Rod Cressey

Open Install Mergepoint KVM (Large Site)

CPOP-296Paul Dean

Open Purchase Chicago Keyboard

CPOP-297Rod Cressey

Open Install Keyboard

CPOP-299

Page 29: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 29 41

brian dunne Open Install PDUs

CPOP-301brian dunne

Open Configure S/W PDUs

CPOP-302brian dunne

Open Test PDUs

CPOP-310Rod Cressey

Open Configure Network

CPOP-314Rod Cressey

Open Test Configure Network

CPOP-315Rod Cressey

Open Document Configure Network

CPOP-316Rod Cressey

Open Build VMs

CPOP-317Rod Cressey

Open Test Build VMs

CPOP-318Rod Cressey

Open Document Build VMs

CPOP-319Rod Cressey

Open Test Environment

CPOP-320Rod Cressey

Open Document Test Environment

CPOP-322Rod Cressey

Open Prepare artifacts

CPOP-323Rod Cressey

Open Schedule IOC

CPOP-324Rod Cressey

Open Conduct IOC

CPOP-325Rod Cressey

Open IOC Report

CPOP-326Paul Dean

Open Purchase Seattle A10 - AX2500

CPOP-327Rod Cressey

Open Install A10 - AX2500

CPOP-328Rod Cressey

Open Cable A10 - AX2500

CPOP-329Rod Cressey

Open Configure S/W A10 - AX2500

CPOP-330Rod Cressey

Open Test A10 - AX2500

Page 30: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 30 41

CPOP-331Rod Cressey

Open Document A10 - AX2500

CPOP-332Paul Dean

Open Purchase Seattle Palo Alto 2050 Firewall

CPOP-333Rod Cressey

Open Install Palo Alto 2050 Firewall

CPOP-334Rod Cressey

Open Cable Palo Alto 2050 Firewall

CPOP-335Rod Cressey

Open Configure S/W Palo Alto 2050 Firewall

CPOP-336Rod Cressey

Open Test Palo Alto 2050 Firewall

CPOP-337Rod Cressey

Open Document Palo Alto 2050 Firewall

CPOP-338Kelly Tucker

Open Purchase Seattle Palo Alto 500 switch

CPOP-339Rod Cressey

Open Install Palo Alto 500 switch

CPOP-340Rod Cressey

Open Cable Palo Alto 500 switch

CPOP-341Rod Cressey

Open Configure S/W Palo Alto 500 switch

CPOP-342Rod Cressey

Open Test Palo Alto 500 switch

CPOP-343Rod Cressey

Open Document Palo Alto 500 switch

CPOP-344Paul Dean

Open Purchase Seattle Infoblox 550A

CPOP-345Rod Cressey

Open Install Infoblox 550A

CPOP-346Rod Cressey

Open Cable Infoblox 550A

CPOP-347Rod Cressey

Open Configure S/W Infoblox 550A

CPOP-348Rod Cressey

Open Test Infoblox 550A

CPOP-349Rod Cressey

Open Document Infoblox 550A

CPOP-358

Page 31: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 31 41

brian dunne Open Cable Cisco 4500

CPOP-359brian dunne

Open Configure S/W Cisco 4500

CPOP-360brian dunne

Open Test Cisco 4500

CPOP-361brian dunne

Open Document Cisco 4500

CPOP-368Rod Cressey

Open Purchase Seattle Dell R810 servers (4) (128GB)

CPOP-369Rod Cressey

Open Install Dell R810 server (128GB)

CPOP-370Rod Cressey

Open Cable Dell R810 server (128GB)

CPOP-371Rod Cressey

Open Configure S/W Dell R810 server (128GB)

CPOP-372Rod Cressey

Open Test Dell R810 server (128GB)

CPOP-373Rod Cressey

Open Document Dell R810 server (128GB)

CPOP-374Rod Cressey

Open Purchase Seattle Dell R610 Server

CPOP-375Rod Cressey

Open Install Dell R610 Servers

CPOP-376Rod Cressey

Open Cable Dell R610 Servers

CPOP-377Rod Cressey

Open Configure S/W Dell R610 Servers

CPOP-378Rod Cressey

Open Test Dell R610 Servers

CPOP-379Rod Cressey

Open Document Dell R610 Servers

CPOP-386Rod Cressey

Open Purchase Seattle Compellent Storage

CPOP-387Rod Cressey

Open Install Compellent Storage

CPOP-388Rod Cressey

Open Cable Compellent Storage

CPOP-389Rod Cressey

Open Configure S/W Compellent Storage

Page 32: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 32 41

CPOP-390Rod Cressey

Open Test Compellent Storage

CPOP-391Rod Cressey

Open Document Compellent Storage

CPOP-402brian dunne

Open Install Environmental Sensors

CPOP-404brian dunne

Open Configure S/W Environmental Sensors

CPOP-405brian dunne

Open Test Environmental Sensors

CPOP-406brian dunne

Open Document Environmental Sensors

CPOP-408Rod Cressey

Open Install Mergepoint KVM (Large Site)

CPOP-409Rod Cressey

Open Purchase Seattle Keyboard

CPOP-410Rod Cressey

Open Install Keyboard

CPOP-412brian dunne

Open Install PDUs

CPOP-414brian dunne

Open Configure S/W PDUs

CPOP-415brian dunne

Open Test PDUs

CPOP-423Rod Cressey

Open Configure Network

CPOP-427Rod Cressey

Open Test Configure Network

CPOP-428Rod Cressey

Open Document Configure Network

CPOP-429Rod Cressey

Open Build VMs

CPOP-430Rod Cressey

Open Test Build VMs

CPOP-431Rod Cressey

Open Document Build VMs

CPOP-432Rod Cressey

Open Test Environment

CPOP-433

Page 33: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 33 41

Rod Cressey Open Document Test Environment

CPOP-434Rod Cressey

Open Document Implementation

CPOP-435Rod Cressey

Open Prepare artifacts

CPOP-436Rod Cressey

Open Schedule IOC

CPOP-437Rod Cressey

Open Conduct IOC

CPOP-438Rod Cressey

Open IOC Report

CPOP-439Paul Dean

Open Purchase WHOI Palo Alto 500 switch

CPOP-440Rod Cressey

Open Install WHOI Palo Alto 500 switch

CPOP-441Rod Cressey

Open Cable WHOI Palo Alto 500 switch

CPOP-442Rod Cressey

Open Configure WHOI Palo Alto 500 switch

CPOP-443Rod Cressey

Open Test WHOI Palo Alto 500 switch

CPOP-444Rod Cressey

Open Document WHOI Palo Alto 500 switch

CPOP-445Paul Dean

Open Purchase WHOI Infoblox 550A

CPOP-446Rod Cressey

Open Install WHOI Infoblox 550A

CPOP-447Rod Cressey

Open Cable WHOI Infoblox 550A

CPOP-448Rod Cressey

Open Configure WHOI S/W Infoblox 550A

CPOP-449Rod Cressey

Open Test WHOI Infoblox 550A

CPOP-450Rod Cressey

Open Document WHOI Infoblox 550A

CPOP-451Paul Dean

Open Purchase WHOI Dell R810 servers (2) (128GB)

CPOP-452Rod Cressey

Open Install WHOI Dell R810 servers (2) (128GB)

Page 34: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 34 41

CPOP-453Rod Cressey

Open Cable WHOI Dell R810 server (2) (128GB)

CPOP-454Rod Cressey

Open Configure WHOI S/W Dell R810 servers (2) (128GB)

CPOP-455Rod Cressey

Open Test WHOI Dell R810 servers (2) (128GB)

CPOP-456Rod Cressey

Open Document WHOI Dell R810 servers (2) (128GB)

CPOP-457Paul Dean

Open Purchase WHOI Dell R410 Server

CPOP-458Rod Cressey

Open Install WHOI Dell R410 Server

CPOP-459Rod Cressey

Open Cable WHOI Dell R410 Server

CPOP-460Rod Cressey

Open Configure WHOI S/W Dell R410 Server

CPOP-461Rod Cressey

Open Test WHOI Dell R410 Server

CPOP-462Rod Cressey

Open Document WHOI Dell R410 Server

CPOP-472Rod Cressey

Open Install Mergepoint KVM (Small Site)

CPOP-473Paul Dean

Open Purchase WHOI Keyboard

CPOP-474Rod Cressey

Open Install WHOI Keyboard

CPOP-478brian dunne

Open Configure S/W UPS

CPOP-479brian dunne

Open Test UPS

CPOP-481brian dunne

Open Install PDUs

CPOP-483brian dunne

Open Configure S/W PDUs

CPOP-484brian dunne

Open Test PDUs

CPOP-485brian dunne

Open Document PDUs

CPOP-493

Page 35: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 35 41

Rod Cressey Open Configure Network

CPOP-497Rod Cressey

Open Test Configure Network

CPOP-498Rod Cressey

Open Document Configure Network

CPOP-499Rod Cressey

Open Build VMs

CPOP-500Rod Cressey

Open Test Build VMs

CPOP-501Rod Cressey

Open Document Build VMs

CPOP-502Rod Cressey

Open Test Environment

CPOP-503Rod Cressey

Open Document Test Environment

CPOP-504Rod Cressey

Open Document Implementation

CPOP-505Rod Cressey

Open Prepare artifacts

CPOP-506Rod Cressey

Open Schedule IOC

CPOP-507Rod Cressey

Open Conduct IOC

CPOP-508Rod Cressey

Open IOC Report

CPOP-509Paul Dean

Open Purchase Portland A10 - AX2500

CPOP-510Rod Cressey

Open Install A10 - AX2500

CPOP-511Rod Cressey

Open Cable A10 - AX2500

CPOP-512Rod Cressey

Open Configure S/W A10 - AX2500

CPOP-513Rod Cressey

Open Test A10 - AX2500

CPOP-514Rod Cressey

Open Document A10 - AX2500

CPOP-515Paul Dean

Open Purchase Portland Palo Alto 2050 Firewall

Page 36: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 36 41

CPOP-516Rod Cressey

Open Install Palo Alto 2050 Firewall

CPOP-517Rod Cressey

Open Cable Palo Alto 2050 Firewall

CPOP-518Rod Cressey

Open Configure S/W Palo Alto 2050 Firewall

CPOP-519Rod Cressey

Open Test Palo Alto 2050 Firewall

CPOP-520Rod Cressey

Open Document Palo Alto 2050 Firewall

CPOP-521Paul Dean

Open Purchase Portland Palo Alto 500 switch

CPOP-522Rod Cressey

Open Install Palo Alto 500 switch

CPOP-523Rod Cressey

Open Cable Palo Alto 500 switch

CPOP-524Rod Cressey

Open Configure S/W Palo Alto 500 switch

CPOP-525Rod Cressey

Open Test Palo Alto 500 switch

CPOP-526Rod Cressey

Open Document Palo Alto 500 switch

CPOP-527Paul Dean

Open Purchase Portland Infoblox 1050

CPOP-528Rod Cressey

Open Install Infoblox 1050

CPOP-529Rod Cressey

Open Cable Infoblox 1050

CPOP-530Rod Cressey

Open Configure S/W Infoblox 1050

CPOP-531Rod Cressey

Open Test Infoblox 1050

CPOP-532Rod Cressey

Open Document Infoblox 1050

CPOP-533Paul Dean

Open Purchase Portland Infoblox 550A

CPOP-534Rod Cressey

Open Install Infoblox 550A

CPOP-535

Page 37: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 37 41

Rod Cressey Open Cable Infoblox 550A

CPOP-536Rod Cressey

Open Configure S/W Infoblox 550A

CPOP-537Rod Cressey

Open Test Infoblox 550A

CPOP-538Rod Cressey

Open Document Infoblox 550A

CPOP-545Paul Dean

Open Purchase Portland RSA Appliance

CPOP-546Rod Cressey

Open Install RSA Appliance

CPOP-547Rod Cressey

Open Cable RSA Appliance

CPOP-548Rod Cressey

Open Configure S/W RSA Appliance

CPOP-549Rod Cressey

Open Test RSA Appliance

CPOP-550Rod Cressey

Open Document RSA Appliance

CPOP-552Rod Cressey

Open Install Dell R810 Servers

CPOP-553Rod Cressey

Open Cable Dell R810 Servers

CPOP-554Rod Cressey

Open Configure S/W Dell R810 Servers

CPOP-555Rod Cressey

Open Test Dell R810 Servers

CPOP-556Rod Cressey

Open Document Dell R810 Servers

CPOP-557Rod Cressey

Open Purchase Portland Dell R810 servers (4) (128GB)

CPOP-558Rod Cressey

Open Install Dell R810 server (128GB)

CPOP-559Rod Cressey

Open Cable Dell R810 server (128GB)

CPOP-560Rod Cressey

Open Configure S/W Dell R810 server (128GB)

CPOP-561Rod Cressey

Open Test Dell R810 server (128GB)

Page 38: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 38 41

CPOP-562Rod Cressey

Open Document Dell R810 server (128GB)

CPOP-563Rod Cressey

Open Purchase Portland Dell R610 Server

CPOP-564Rod Cressey

Open Install Dell R610 Servers

CPOP-565Rod Cressey

Open Cable Dell R610 Servers

CPOP-566Rod Cressey

Open Configure S/W Dell R610 Servers

CPOP-567Rod Cressey

Open Test Dell R610 Servers

CPOP-568Rod Cressey

Open Document Dell R610 Servers

CPOP-569Rod Cressey

Open Purchase Portland Compellent Storage

CPOP-570Rod Cressey

Open Install Compellent Storage

CPOP-571Rod Cressey

Open Cable Compellent Storage

CPOP-572Rod Cressey

Open Configure S/W Compellent Storage

CPOP-573Rod Cressey

Open Test Compellent Storage

CPOP-574Rod Cressey

Open Document Compellent Storage

CPOP-590Bahadir Gul

Open Install/Configure/Test Cisco Nexus 1000v for Portland VMware Infrastructure

CPOP-593Paul Dean

Open Purchase Portland Microsoft SQL Server

CPOP-611brian dunne

Open Install Environmental Sensors

CPOP-613brian dunne

Open Configure S/W Environmental Sensors

CPOP-614brian dunne

Open Test Environmental Sensors

CPOP-615brian dunne

Open Document Environmental Sensors

CPOP-617

Page 39: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 39 41

Rod Cressey Open Install Mergepoint KVM (Large Site)

CPOP-618Rod Cressey

Open Purchase Portland Keyboard

CPOP-619Rod Cressey

Open Install Keyboard

CPOP-621brian dunne

Open Install PDUs

CPOP-623brian dunne

Open Configure S/W PDUs

CPOP-624brian dunne

Open Test PDUs

CPOP-632Rod Cressey

Open Configure Network

CPOP-636Rod Cressey

Open Test Configure Network

CPOP-637Rod Cressey

Open Document Configure Network

CPOP-638Rod Cressey

Open Build VMs

CPOP-639Rod Cressey

Open Test Build VMs

CPOP-640Rod Cressey

Open Document Build VMs

CPOP-641Rod Cressey

Open Test Environment

CPOP-642Rod Cressey

Open Document Test Environment

CPOP-643Rod Cressey

Open Document Implementation

CPOP-644Rod Cressey

Open Prepare artifacts

CPOP-645Rod Cressey

Open Schedule IOC

CPOP-646Rod Cressey

Open Conduct IOC

CPOP-647Rod Cressey

Open IOC Report

CPOP-648Rod Cressey

Open Dell MoN

Page 40: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 40 41

CPOP-650Rod Cressey

Open Bird Rock MoN

CPOP-653brian dunne

Open Configure Cisco 4500 switch

CPOP-654brian dunne

Open Test Cisco 4500 switch

CPOP-655brian dunne

Open Document Cisco 4500 switch

CPOP-656Rod Cressey

Open Install Arista 7124SX switch for Portland

CPOP-657Rod Cressey

Open Cable Arista 7124SX switch for Portland

CPOP-658Rod Cressey

Open Configure Arista 7124SX switch for Portland

CPOP-659Rod Cressey

Open Test Arista 7124SX switch for Portland

CPOP-660Rod Cressey

Open Document Arista 7124SX switch for Portland

CPOP-667Paul Dean

Open Purchase WHOI Palo Alto 500 switch

CPOP-668Rod Cressey

Open Install WHOI Palo Alto 500 switch

CPOP-669Rod Cressey

Open Cable WHOI Palo Alto 500 switch

CPOP-670Rod Cressey

Open Configure WHOI Palo Alto 500 switch

CPOP-671Rod Cressey

Open Test WHOI Palo Alto 500 switch

CPOP-672Rod Cressey

Open Document WHOI Palo Alto 500 switch

CPOP-678Rod Cressey

Open Purchase Seattle Brocade Fiber Optic Switch

CPOP-679Rod Cressey

Open Install Brocade Fiber Optic Switch

CPOP-680Rod Cressey

Open Cable Brocade Fiber Optic Switch

CPOP-681Rod Cressey

Open Test Brocade Fiber Optic Switch

CPOP-682

Page 41: CI System Administration Subsystem: 3 tasks, 0 In Progress ... · 7/20/2012  · Bi-weekly Report on OOI CI Iteration Tasks for period of 2012.06.25 — 2012.07.20 (726 tasks) Page

Bi-weekly Report on OOI CI Iteration Tasksfor period of

2012.06.25 — 2012.07.20(726 tasks)

Page of 41 41

Rod Cressey Open Document Brocade Fiber Optic Switch

CPOP-683Paul Dean

Open Purchase Chicago Brocade Fiber Optic Switch

CPOP-684Rod Cressey

Open Install Brocade Fiber Optic Switch

CPOP-685Rod Cressey

Open Cable Brocade Fiber Optic Switch

CPOP-686Rod Cressey

Open Test Brocade Fiber Optic Switch

CPOP-687Rod Cressey

Open Document Brocade Fiber Optic Switch

CPOP-688Rod Cressey

Open Move 2 zNAS and fiber optic switch from San Diego Managment Point to Portland Acquisition Point