chp 2 production strategy pg 81
DESCRIPTION
zcdzaTRANSCRIPT
Case Problem: Production Strategy Managerial Report
MC506 Quantitative Methods for Managers - Start Date: July 1, 2003
Analyze the production problem at Better Fitness, Inc. and prepare a report for BFI's president presenting your findings and recommendations. Include (but donot limit your discussion to) a consideration of the following items:
1. The recommended number of BodyPlus 100 and BodyPlus 200 machines to produce.Let
BP100 = the number of BodyPlus 100 machines produced
BP200 = the number of BodyPlus 200 machines produced
Max 371BP100 + 461BP200s.t.
8BP100 + 12BP200 £ 600 hrs of machining
5BP100 + 10BP200 £ 450 hrs of painting and finishing time
2BP100 + 2BP200 £ 140 hrs of assembly, testing and packaging.
-0.25BP100 + .75BP200 ³ 0
BP100 , BP200 ³ 0
By Debbie St. George: Student #: 1086941
Optimal solution: BP100 = 50, BP200 = 50/3 or 16.667, profit = $26,233.33. See Management Science notes.
.
10
20
40
30
50
60
70
80
0 10 20 30 40 50 60 70 80 90 100Number of BodyPlus 100
Num
ber
of B
odyP
lus
200
Optimal Solution
BodyPlus 200 Requirement
Painting and Finishing
Assembly, Test, and Packaging
Machining and Welding
BP100
BP200
2. The effect on profits of the requirement that the number of units of the BodyPlus 200 produced must be at least 25% of the total production.If the requirement were reduced to at least 24% of total production, the new optimal solution is BP100 = 1425/28, BP200 = 225/14, with a total profit of $26,290.18; thus, total profits would increase by $56.85. In the short run the requirement reduces profits.
3. Where efforts should be expended in order to increase profits.Retain the constraint requiring that the number of units of the BodyPlus 200 produced be at least 25% of total production.Obtain additional machining and welding time to increase profits as the current optimal solution uses the current machining and welding time.
1. The recommended number of BodyPlus 100 and BodyPlus 200 machines to produce.
hrs of painting and finishing time
hrs of assembly, testing and packaging.
= $26,233.33. See Management Science notes.
Management Science Program - LINEAR PROGRAMMING PROBLEM
MAX 371BP100+461BP200
S.T.
1) 8BP100+12BP200<600 2) 5BP100+10BP200<450 3) 2BP100+2BP200<140 4) -0.25BP100+0.75BP200>0
OPTIMAL SOLUTION
Objective Function Value = 26233.333
Variable Value Reduced Costs -------------- --------------- ------------------
Constraint Slack/Surplus Dual Prices -------------- --------------- ------------------ 1 0.000 43.722 2 33.333 0.000 3 6.667 0.000 4 0.000 -84.889
OBJECTIVE COEFFICIENT RANGES
Variable Lower Limit Current Value Upper Limit ------------ --------------- --------------- --------------- BP100 307.333 371.000 No Upper Limit BP200 -1113.000 461.000 556.500
RIGHT HAND SIDE RANGES
Constraint Lower Limit Current Value Upper Limit ------------ --------------- --------------- --------------- 1 0.000 600.000 630.000 2 416.667 450.000 No Upper Limit 3 133.333 140.000 No Upper Limit 4 -7.500 0.000 15.000
or $26,233.33
BP100 50.000 0.000 BP200 16.667 0.000
Notes:
Department BP100 BP200Frame machining & welding time 4 hrs 5 hrs
Frame paint & finish 2 hrs 4 hrs
Press machining & welding time 2 hrs 3 hrs
Press paint & finish 1 hr 2 hrs
Pec-dec machining & welding time 2 hrs 2 hrs
Pec-dec paint & finish 2 hrs 2 hrs
Leg press machining & welding time 0 hrs 2 hrs
Leg press paint & finish 0 hrs 2 hrs
Assembly, testing and packaging 2 hrs 2 hrs
Production Time Requirements Totals for BP100 and BP200
Department BP100 BP200Machining & welding time 8 hrs * $20 = $160 12 hrs * $20 = $240Paint & finish 5 hrs * $15 = $75 10 hrs * $15 = $150Assembly, testing and packaging 2 hrs * $12 = $24 2 hrs * $12 = $ 24
15 hrs = $259 24 hrs = $414
Notes & constraints for next production period
8BP100 +5BP100 +2BP100 +
Suggested Price
BP100 $2,400 Frame 450 Press 300 Pec-dec 250 Assembly/Pack 50 Labor 259 $1,309
$1,091
Suggested Price
BP100 $3,500
Production Requirements for BP100 and BP200 Production Time
Frame 650 Press 400 Pec-dec 250 Leg press 200 Assembly/Pack 75 Labor 414 $1,989
$1,511 Max +371BP100
12BP200 £ 600 hrs of machining
10BP200 £ 450 hrs of painting and finishing time
2BP200 £ 140 hrs of assembly, testing and packaging.
Dealers 70% Price$1,680
$1,309 $371 Profit per unit for BP100
Dealers 70% Price$2,450
Production Requirements for BP100 and BP200 Production Time
$1,989 $461 Profit per unit for BP200
461BP200