choice of architecture : 1 photo-injector 3 lil sections: 1 for compression and 2 for acceleration
DESCRIPTION
K. steerer. position monitor. Laser. profile monitor. RF pulse compression. 2 x 45 MW. beam dump. 10. 20. 25. 25. quadrupoles. 17 MV/m acceleration. 17 MV/m acceleration. 15 MV/m compression. rf gun cavity. focusing coils. LIL sections. RF deflector. spect. magnet. - PowerPoint PPT PresentationTRANSCRIPT
CTF3-CLEX meeting June 12, 2006 page 1
choice of architecture :• 1 photo-injector• 3 LIL sections: 1 for compression and 2 for
acceleration• 1 beamline with diagnostics (leading to 2-beam
teststand)
Probe beam status and scheduleJanuary 2006
15 MV/mcompression
17 MV/macceleration
17 MV/macceleration
LIL sections
beam dump
focusing coils
K
quadrupoles
Laser RF pulse compression
2 x 45 MW
10 20 25 25
profile monitor
position monitor
steerer
rf gun cavity spect. magnetRF deflector
C A L I F E S
CTF3-CLEX meeting June 12, 2006 page 2
RF gun status
R. RouxJuly, 7th 2006
1. Drawings, overview
2. What is under way?
3. Open questions, ask for info
4. Problems, risks
CTF3-CLEX meeting June 12, 2006 page 3
1. Studies finished
2. Drawings finished
3. List of components:
- gun with a measurement loop
- 2 tapered waveguides
- 2 LIL flanges
- 2 solenoids
- 1 steerer
- vacuum chamber (tubes, valve, bellow)
- 2 gauges
- 1 ionic pump
- 1 pneumatic valve
- 1 translation trolley for the preparation
chamber (additional request from CERN)
- NEG coating on the vacuum chamber
(agreed with CERN people)
1. Overview
solenoids
RF input
steerer valve
photocathode
vacuum pump
CTF3-CLEX meeting June 12, 2006 page 4
2. What’s under way?
• Gun: new supplier, the coupler cell should arrive between 17th-21th July
if everything OK, order the rest of the gun, all pieces in September
then, RF measurements, mechanical adjustments and brazing at LAL
(thanks to Eric Chevallay for the 316LN stainless steel, we will soon refunded)
• Magnetism: coils and steerer are ordered, should arrive in the beginning of September
power supplies will be bought by CERN (offer of R. Losito)
• Vacuum: gauges and valve are received, ionic pump at the end of July
power supply will be bought by CERN (offer of R. Losito)
• Mechanics: vacuum chamber and supports are under construction in LAL workshop
it should be finished in September but risks of overlap with PHIN gun
machining PHIN gun has the priority !
CTF3-CLEX meeting June 12, 2006 page 5
3. Open questions, ask for info
• Girder: if we can reuse the LIL 2300 mm girder, we need the drawings open question: RF gun assembly on girder at LAL or at CERN ?
• Cabling: Who does the cabling between the photo-injector and the racks?-cables for solenoids and steerer (electric and cooling)-cable for RF loop-cables for gauges and power supply-on which side of the linac set the connectors of the solenoids?
• Possible overlap between the solenoid connectors and RF network pumps? (happened on PHIN, solenoids sent back to the supplier to modify connectors)
• Cooling: tuning cooling loop from frozen water (20°C) the gun will be mechanically deformed in such a way thatthe right tuning frequency achieved at 30°C
CTF3-CLEX meeting June 12, 2006 page 6
3. Problems, risks
- New supplier for the gun, if not good delay
- Money: 70 k€ received this year
not enough to order the power supplies and gun cooling loop
I hope to get the totality of the required budget next year in March
But up to now,RF gun construction proceeds well
CTF3-CLEX meeting June 12, 2006 page 7
Signal taken from the Drive Beam Laser
2 main distinct tasks:1. extraction & manipulation of laser beam (windowing, x4
frequency multiplication, doubling of the pulse frequency 1.5 3 GHz)
2. transport of the laser beam over 80 m as far as the photo-cathode
Subcontractor : LILM (Laser Matter Interaction Lab) from CEA-Saclay
Study of the 2 tasks till the end of 2006
mechanical design and realization follow-up by Dapnia
Pb : delay of the DB laser 1st tests with real laser will be very late
Laser system
CTF3-CLEX meeting June 12, 2006 page 8
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 9
Beam dynamics
calculations nearly complete ...
single bunch is fine
multibunch operationdue to beam-loading, bunch charge should be linearly reduced to meet energy & phase requirements (1% and 1deg)Qb < 5nC/N
still to be done:
• effect of laser spot misalignment
• estimation of the emittance measurement accuracy
CTF3-CLEX meeting June 12, 2006 page 10
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 11
Califes Drawings
Drawings nearly complete ...
CTF3-CLEX meeting June 12, 2006 page 12
injector(LAL Orsay)
Injection beamline
laser beam
laser table
LIL sectioninput
BPM
screen
vacuumpump
CTF3-CLEX meeting June 12, 2006 page 13
inter-section
BPM
steerer
CTF3-CLEX meeting June 12, 2006 page 14
diagnostics beamline
screen
RF deflector QL3 Triplet Dipole Dumpvac. pump
total length (cathode plane to output valve) = 21.316 m
CTF3-CLEX meeting June 12, 2006 page 15
RF system
klystron, RF pulse compression, RF network : supplied by CERN
Modulator : includes• a high voltage pulsed power supply with negative polarity• three electromagnet power supplies• a filament heater power supply• an ion pump power supply• a hydraulic network• a X-ray shielding• a control-command system• some racks containing the materiel
offers from vendors received on 1st of July
realization time 12-14 months
vendor choice at end of July
CTF3-CLEX meeting June 12, 2006 page 16
RF network
Phase adjustment by length of waveguides
BOC Cavity (Pulse compression gain = 2,1)
Suppose 25 m waveguide, 8 flanges pairs
P
RF gun cavity
4.5 dB Splitter
3 dB Splitter4.5 dB
Splitter
15 MV/mCompression
17 MV/mAcceleration
43 MW
27,08 MW
9,4 MW 24.65 MW17.1 MW
A
W
W
17 MV/mAcceleration
SF6
= 90°
Klystron TH 2132
= 0 ° = 0 °
CO CO CO CO
P PP
P
P
P
P
CO+L CO+LCO+L
24.65 MW
CO
W
SF6
86,4 MW
76,3 MW
49,2 MW
22 MW
21.55 MW24.1 MW15 MW
7 MW
26,5 MW
CO
c
C0.5° precision0.5° stability± 20 ° tuning
Phase adjustment by length of waveguides
BOC Cavity (Pulse compression gain = 2,1)
Suppose 25 m waveguide, 8 flanges pairs
P
RF gun cavity
4.5 dB Splitter
3 dB Splitter4.5 dB
Splitter
15 MV/mCompression
17 MV/mAcceleration
43 MW
27,08 MW
9,4 MW 24.65 MW17.1 MW
A
W
W
17 MV/mAcceleration
SF6
= 90°
Klystron TH 2132
= 0 ° = 0 °
CO CO CO CO
P PP
P
P
P
P
CO+L CO+LCO+L
24.65 MW
CO
W
SF6
86,4 MW
76,3 MW
49,2 MW
22 MW
21.55 MW24.1 MW15 MW
7 MW
26,5 MW
CO
c
C0.5° precision0.5° stability± 20 ° tuning
defined in March 2006
1 power phase-shifter
has to be developed(fine tuning of thecompression section)
CTF3-CLEX meeting June 12, 2006 page 17
Phase-shifter
3 GHz scaling from a SLAC model at 11.4 GHz by Alexej Grudiev
sliding circular guide + mode converter
tolerances and mechanical studymade at Saclay
fabrication will start end of september
power tests at CERN
CTF3-CLEX meeting June 12, 2006 page 18
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 19
Vacuum adaptation and laser miror
Compression LIL section
Accelerating LIL section
Accelerating LIL section
Diagnostic lineRF Gun
Sector 1 Sector 2 Sector 3
IZ 120 IZ 120 IZ 120 IZ 120 IZ 120 IZ 120IZ 270 IZ 270
Vacuum
Vacuum system defined2 LIL sections tested under vacuum at Cern
• 3 valves
• 6 ion pumps for LIL sections
• 2 ion pumps for input and output beamlines
• power supplies, gauges
hardware providedby CERN
primarypumping group
CTF3-CLEX meeting June 12, 2006 page 20
steerer H+V solenoids earth field correction
quadrupoles dipole
5 2 x 17 3 x 2 3 1
order before August
CERN provision
CERN provision
call for tender (5) before August
CERN provision
delivery Nov 2006
- - delivery May 2007
-
Magnets
QL3 BHZ36
CTF3-CLEX meeting June 12, 2006 page 21
compression accélération accélération
RF gun
H V H V
solénoïde
VH VH H HV V
steerer steerer steerer steerer steerer
dipole
quadrupoles
solénoïde
quadrupoles quadrupoles
steerer
# of power supplies
type Intensity (A) Voltage (V)
Steerers 12 Bipolar ± 10 ± 5
Solenoids 2 Unipolar 120 20
Quadrupoles 3 Unipolar 200 10
Dipole 1Unipolar with
degauss capability100 20
Earth field compensation
2 Unipolar 5 3
Power supplies requirements
Specifications of Power supplies have been done and conveyed to CERN
CTF3-CLEX meeting June 12, 2006 page 22
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 23
Measure Requirements chosen solutions
Current Resolution ≤ 1% Precision ≤ 3% Bandwidth > 250 MHz
Single shot, non destructive
BPM (after calibration)
Position Resolution ≤ 20µmPrecision ±100µmBandwidth >50 MHz
Range ±10 mmSingle shot, non destructive
BPMScreen + CCD camera
Profile Resolution ≤ 20µm Range 10x10mm Screen + CCD camera
Emittance Error < 20% Quad scan + Screen + CCD camera
Central energy
Resolution DP/P ≤1 %Precision ≤ 2% Bandwidth >250 MHz
Single shot 15° bending magnet + BPM
Energy spread
Resolution DP/P≤0.5%
Time resolution is desirable
15° bending magnet + Screen + CCD camera; possible future ...Streak Camera, segmented photomultiplier, segmented beam dump … for time resolution
BunchlengthResolution ≤0.5ps rms
Variation of bunch length along the train
Deflecting cavity + Screen + CCD camera; possible future ...RF pick-up (30-174 GHz) during operations
Diagnostics
CTF3-CLEX meeting June 12, 2006 page 24
CF40 rotating connectorand flange to be welded
Al2O3PTFE
SMAreceptacle
CF40 rotating connectorand flange to be welded
Al2O3PTFE
SMAreceptacle
BPMSpecifications : single bunch & multi-bunch operation (1-64 @ 3 GHz) 0.5 nC• coaxial reentrant cavity, original design from R. Bossard (CERN)• proposed and developed for TTF (M. Luong, C. Simon - DAPNIA)
prototype for technology validation : OK
pre-serie (2 units) : under fabrication
CTF3-CLEX meeting June 12, 2006 page 25
Beam profile monitors
3 profiler systems to different locations:injector output, behind the triplet, behind the dipole
2 main sub-systems:
1. the vacuum tank with devices (screen, actuator, viewport, lighting)
2. the optics system (lenses, CCD camera, filter wheel, shielding…)
Screen holder
Insertion mecanism
Tank study has started ...
CTF3-CLEX meeting June 12, 2006 page 26
TTF2 CTF3 SOLEIL
optics design (various magnifications) + CCD camera (with Cern MTV interface)
examples of optics design with different levels of integration
Califes : will start next September
Optics system
CTF3-CLEX meeting June 12, 2006 page 27
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 28
Beam
GraphiteLead
Polyéthylène500
Beam Dump
Derived from SOLEIL(100 MeV, 0.5 to 8 nC, 3 Hz)
Adaptation for CALIFES in progress (200 MeV, 1.5 A, 21 ns, 5 Hz)
CTF3-CLEX meeting June 12, 2006 page 29
41.6 m
22 m
CLEX building
CALIFES should fit into CLEX building ...
the last dipole could include 3 branches:
• straight to 2-beam teststand
• 15° to Beam Dump
• 30° to Instrumentation Test Beam
CTF3-CLEX meeting June 12, 2006 page 30
Time-schedule
CTF3-CLEX meeting June 12, 2006 page 31
Can we have a closed area for Califes ?
Which girders can we re-use from CERN ?
Who does the cabling between the Califes components and the racks ?
Alignment: studied by Michel Fontaine from Dapnia
who is the CERN contact person ?
Questions List
CTF3-CLEX meeting June 12, 2006 page 32
Flow (l/mn) Power (kW) Units Flow PowerStabilised water (30°)LIL sections 10 0.5 3 30 1.5deflecting section 1 0 0rf gun 1 0 0waveguides 1 0 0
Demineralised water (18-22°) 0 0sections solenoids 120 60 2 240 120quadrupoles 2 2 3 6 6dipole M45 7 8 1 7 8klystron collector & body 50 5 2 100 10klystron foc 20 5 2 40 10modulator 20 10 2 40 20rf gun solenoids 5 2 2 10 4
Total 473 179.5
Cooling needs