CHILDRENS FINANCE IMPROVEMENT PROJECT
Project Lead Display Week
Project Start Date
WBS Category TASK START END Status
1 CONTROCC & Provider Portal - Go-live 1st April 2020 -
1.1 Define Project Governance established Thu 25/07/19 Thu 25/07/19 Complete
1.2 Define Project Group meetings established Wed 14/08/19 Wed 14/08/19 Complete
1.3 Define
Meetings with Governance, Oracle Cloud
team, CDS to raise awareness of project
and identify inter-dependencies
1.4 DefineMeeting with OCC/LL to agree
implementation timeframes
1.5 DefineDo we need to refresh the UAT as it's not
been refreshed in 2 years
1.6 DefineDo we want a Report what we are and are
not using in our config.
1.7 DefineDo we need to use actuals/visits – barnet
use but KENT don’t
1.8 DefineContract docs demo to be arranged by
colin and simon
1.9 DefineWe need to decide whether to use Actions
in Portal
1.10 DefineDecisions about the skin must be made by
mid-July
1.11 Define
Anthony to have conversation with M RE
Payment request form & Service request
form
1.12 DefineBring in someone from the Childrens
Improvement hub into the project
1.13 DefineAwaiting implementation plan from OCC -
expected by end of May 2019
1.14 DefineGet team structures and process/how to
guides from KENT
1.15 Define Establish a formal relationship with Kent
1.16 DefineSend email to get current spec. for In
house batch fileThu 15/08/19 In progress
1.17 Define
Review docs sent by KENT. Agree
which guides belong to which team
and have them review in
preparation.
Mon 19/08/19 In progress
1.18 Define Mod 74 configuration Thu 15/08/19 In progress
1.18.1 Define
G to find out if there is a field in ContrOCC
to enter the totally amount you wish to
spend with a supplier
Thu 15/08/19 In progress
1.18.2 Define
G to find out the ‘naming convention’ for
POs in ContrOCC because this needs to be
distinct from My Resources and OHMs
Thu 15/08/19 In progress
1.18.3 Define
Anthony to email Dean Cooke to get the
original but now out of date Mod 74, which
won’t be that different from the new one.
Thu 15/08/19 Complete
![Page 2: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/2.jpg)
1.19 Define
Speak with DC (adults) to understand what
suppliers are used by what parts of the org.
For what spend types - data cleansing
exercise
Thu 15/08/19 Not started
1.20 Define
Speak with SS RE supplier engagagement,
on-boarding and the role of the brokerage
team preparedness for go-live
Fri 30/08/19 In progress
1.21 DefineGet calendar of supplier engagement from
V and PBThu 15/08/19 Tue 03/09/19 In progress
1.22 Define
Enagagement with N to get the org. ready
for go-live, include engaging with
Maidstone
Wed 21/08/19 In progress
1.23 DefineSend Contract Type and Service Level Type
lists to AWed 14/08/19 Wed 14/08/19 Complete
1.24 DesignCost Code requirements - consult with
Finance Thu 22/08/19 In progress
1.25 DesignCost Code requirements - consult with
Accounts Payable Thu 22/08/19 In progress
1.26 DesignCost Code requirements - consult with
Service Thu 22/08/19 In progress
1.27 Design
Update team names and budget tray
names to match the cost centres on
ContrOCC
Thu 22/08/19 In progress
1.28 Design
reviewing the budgetary approval in
ContrOCC to ensure managers have the
correct approval set up
Thu 22/08/19 In progress
1.29 Design Cost code hierarchy signed off by CSLT/CLT
1.30 Design
Review external payment types/ list to
decide recommendations for including on
Controcc e.g. include housing payment etc
1.31 DesignConsultation with service on what
payments are included in Controcc
1.32 DesignDecision on what payments are included in
Controcc - CLST?
1.33 Design Cost Code testing (including reporting)
1.34 DesignControcc reporting requirements decided
with Finance
1.35 DesignConfirm service levels and budgets
assigned to these levels
1.36 DesignConfigure service levels and budgets
assigned (not just placements)Thu 22/08/19 In progress
1.37 DesignReview of Cost Code testing (including
reporting)
1.38 Design Planning, addressing snagging issues
1.39 DesignProcess - Creation of new/change Nominal
codes in either CONTROCC or Oracle
1.40 Design
Monthly reconciliation of cost centres to
ensure CONTROCC and Myresouces
remain aligned. Extract of chart of
accounts from both systems and person
responsible for reviewing and reconciling
the two systems
In progress
1.41 DesignProcess - How is an Accrual created in
Finance/P&L
![Page 3: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/3.jpg)
1.42 DesignHow does data map and batch between
CONTROCC & ORACLE
1.43 DesignConfigure service levels and budgets
assigned
1.44 DesignConfirm service levels and budgets
assigned to these levels
1.45 DesignControcc reporting requirements decided
with Finance
1.46 DesignCost Code data structure, including the
ability to create the right reports
1.47 Design Process Proof of delivery/ consumption
1.48 Design Process How are goods delivered
1.49 Design Process How/Who buys goods
1.50 Design Process Finance Monthly reconcilliation
1.51 Design Process Payment of invoices
1.52 Design
Confirm systems model for
Placements External on Framework
- including PO, Invoice and supplier
detail data flows
1.53 Design
Confirm systems model for
Placements External not on
Framework - including PO, Invoice
and supplier detail data flows
1.54 Design
Confirm systems model for
Placements internal - including PO,
Invoice and supplier detail data
flows
1.55 Design
Confirm systems model for Non
Placement - including PO, Invoice
and supplier detail data flows
1.56 Design Treatment of VAT In progress
1.56.1 DesignG and A to meet with AS and M to
understand how we currently process VAT Fri 27/09/19 Complete
1.57 Deploy
Provider Portal functional Go-Live - soft
launch of Portal to providers (selected
providers and phased approach)
1.58 DeployFeedback from internal staff and Providers
on Go-Live
1.59 Deploy Test, reviews and tweaks to configuration
1.60 Deploy Feedback from service and finance
1.61 DeployHandover to CPH as BAU - define roles and
responsibilities
1.62 Project Approvals Provide overview paper to CDS
1.63 Project Approvals CDS support requirements define and
agreed
1.64 Project Approvals CDS TAG Approval
1.65 Project Approvals New CDS provider engaged in Controcc
implementation
1.66 Project Approvals CSLT awareness raising of project
1.67 Project Approvals CSLT decision-making and sign-off
![Page 4: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/4.jpg)
1.68 Training Training needs analysis completed
1.69 TrainingProcess and guidance written and signed
off
1.70 Training Train business support (CPH only)
1.71 TrainingFeedback from service and finance on
system
1.72Communications &
Engagement Develop Comms and Engagement Plan
1.73Communications &
Engagement Implement Comms and Engagement Plan
1.74 [Task]
2 Children's Placement Process - Go-live XX XXX 2019
2.1 as-is process Map LAC change of placement Fri 30/08/19 Mon 30/09/19 Complete
2.2 as-is process Map Unknown LAC Mon 16/09/19 Mon 30/09/19 Complete
2.3 as-is process Map Emergency LAC Mon 16/09/19 Mon 30/09/19 Complete
2.4 as-is process
identify where the key decision points in
the process exist, especially if this is a
financial decision
Mon 16/09/19 Mon 30/09/19 Complete
2.5 to-be processbuild the to be process, including a
CRS workflow designFri 06/09/19 Fri 04/10/09 In progress
2.6 to-be process
to agree who is going to ensure
compliance, is this business support or
BIP&I chasing non-compliance
Mon 16/09/19 Fri 04/10/09 Not started
2.7 to-be process define emergency vs non-emergency Mon 16/09/19 Fri 04/10/09 Complete
2.8 to-be process Build workflow in CRS, to drive automation Mon 16/09/19 Fri 04/10/09 Not started
2.9 to-be processAgree new areas of responsibility for
business support Mon 16/09/19 Fri 04/10/09 Not started
2.10 to-be process define the post CONTROCC world for CPH Mon 16/09/19 Fri 04/10/09 Not started
2.11 Referal to care panel
1. SW Manager Record decision to refer to
care panel - detail what happens including
data fields
Not started
2.11.1 Referal to care panelDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.12 Referal to care panel
2. Social Worker Make case for taking child
into care - detail what happens including
data fields
Not started
2.12.1 Referal to care panelDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.13 Referal to care panel
3. SW Manager Quality assess Request to
Care Panel - detail what happens including
data fields
Not started
2.13.1 Referal to care panelDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.14 Referal to care panel
4. Care panel administrator Review
request for Care Panel agenda item - detail
what happens including data fields
Not started
2.14.1 Referal to care panelDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.15 Authorising search request5. Monday Care Panel review of meeting
structure & contentNot started
![Page 5: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/5.jpg)
2.15.1 Authorising search requestDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.16 Authorising search request6. Social Worker Search criteria and Pen
profileNot started
2.16.1 Authorising search requestDetail, RACI, define compliance & reporting
& SLA if appropriateNot started
2.17 Finding & buying 7. Perform search Not started
2.18 Finding & buyingProcess map & RACI In-house fostering
search processNot started
2.19 Finding & buyingProcess map & RACI External placements
search processIn progress
2.19.1 Finding & buyingAgree process of authorisation where cost
increases during searchIn progress
2.20 Finding & buying8. Placement duty officer Confirmation of
placementNot started
2.21 Finding & buying9. Placement duty officer Enter placement
detailsIn progress
2.21.1 Finding & buying Review PIFF and SPRF In progress
2.22 Payment processProcess map & RACI end of placement
processIn progress
2.23 Payment process Process map & RACI Invoice payment Not started
2.24 StructureEnsure correct complience and reporting is
in placeNot started
2.25 Structure
Ensure correct meetings are in place,
remove wasteful meetings from diaries and
provide a structure and content to
meetings that aligns to results
Not started
2.26 StructureDefine a clear escalation process for non-
compliance Not started
2.27 StructureDefine process to quality assure the work
of the placement's team Not started
2.28 StructureDefine process of annual reviews for
residential and semi-independent suppliers Not started
![Page 6: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/6.jpg)
Display Week 1
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
DAYS % DONEWORK
DAYS#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
-
0% 1
0% 1
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
#REF!
#REF!#REF! #REF! #REF!
#REF! #REF! #REF!
![Page 7: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/7.jpg)
0% -
0% -
0% -
0%
0%
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
![Page 8: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/8.jpg)
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
0% -
![Page 9: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/9.jpg)
0% -
0% -
0% -
0% -
0% -
0% -
0% -
-
22
11
11
11
23501
23495
23495
23495
23495
23495
0% -
-
0% -
-
0% -
-
0%
![Page 10: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/10.jpg)
0%
0%
0%
0%
0%
0%
-
0%
0%
0% -
0%
0% -
![Page 11: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/11.jpg)
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
![Page 12: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/12.jpg)
![Page 13: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/13.jpg)
![Page 14: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/14.jpg)
![Page 15: CHILDRENS FINANCE IMPROVEMENT PROJECT · 1.46 Design Cost Code data structure, including the ability to create the right reports 1.47 Design Process Proof of delivery/ consumption](https://reader034.vdocuments.us/reader034/viewer/2022050306/5f6ef19806b5f6683b2159ad/html5/thumbnails/15.jpg)