![Page 1: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/1.jpg)
Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail
10 January 2018
![Page 2: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/2.jpg)
Agenda
2
1. Scheme Background
2. Brief Outline of the Scheme
3. Chesterton Bridge
4. Jetty
5. Bridge and Jetty Construction
6. Newmarket Road Underpass
7. Environmental
8. Planning Conditions
9. Time-table
10.Questions
![Page 3: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/3.jpg)
Scheme Background
3
![Page 4: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/4.jpg)
Brief outline of the scheme
4
• 1400m footpath / cycleway.• 44m footbridge lifted over river Cam.• New underpass under A1134 installed in
weekend closure.• Footpath ‘jetty’ in river under rail bridge. • Service diversions.• Culverts. • Contractor design elements
A1134
Cambridge FC
Abandoned Railway
Footbridge
Jetty
![Page 5: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/5.jpg)
Chesterton Bridge
5
River Cam –Looking West
Looking south on line of new footbridge
![Page 6: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/6.jpg)
Chesterton Bridge
6
River Cam Footbridge - 44m span circa 150 tonnes
![Page 7: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/7.jpg)
Chesterton Bridge
7
Lift arrangement based on AIP drawings
![Page 8: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/8.jpg)
Chesterton Bridge and Jetty
8
Existing Jetty
Looking south
footpath route
Route of footpath
![Page 9: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/9.jpg)
Jetty
9
![Page 10: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/10.jpg)
Bridge and Jetty Construction
10
![Page 11: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/11.jpg)
Newmarket Road Underpass
11
A1134 Newmarket road – looking West
A1134 Newmarket road – looking East
![Page 12: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/12.jpg)
Newmarket Road Underpass
12
![Page 13: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/13.jpg)
Underpass Construction
13
![Page 14: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/14.jpg)
Environmental
14
Carillion as a company pride themselves on their knowledge and in house ability together with our supply chain to construct projects that offer the minimum disruption to the local resident and also to the environment as a whole. We achieve this by mitigation the following potential risk to the Environment.
• Noise• Dust• Vibration• Light• Working hours
Stage one:
FaunaEcological surveys will be carried out to identify the presence of protected animals and birds. Once the results of these are known, mitigation will be put in place to provide protection. With regard to birds, all trees will be felled / trimmed outside of the nesting season.
FloraSurvey will be carried out prior to works to identify any areas of protected grassland that can be translocated. Also, with the area being in a flood plain, a survey will be carried out to ensure that the levels of the newly created footpath will not affect the overall capacity of the flood plain.
WaterwaysColdhams Brook runs directly though the works and will need diverting where it flows into The River Cam, any works that are carried out on the waterway will be done with the utmost care to ensure that no pollution of the waterway happens.
![Page 15: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/15.jpg)
Planning Conditions
15
During Phase 1 Carillion will assist Cambs Council in discharging numerous Planning Conditions, most of these conditions are put in place to ensure that the works are constructed so as not to disrupt the environment and those living and visiting the area during the works and to ensure that the final finished project is fit for the future.
![Page 16: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/16.jpg)
8. Indicative time-table
16
Jan Feb Mar Apr May June July Oct Sept Nov
Enabling works
Bridge construction
Bridge delivery to site
Bridge lift
Preparatory works for underpass
Build underpass
Install underpass
![Page 17: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/17.jpg)
8. Contract Programme
17
Completion Date Stage 2 : Approx March 2019
Overall Construction Period : Approx 12 months
![Page 18: Chesterton/Abbey Foot and Cycle Bridge and Chisholm Trail · Agenda 2 1. Scheme Background 2. Brief Outline of the Scheme 3. Chesterton Bridge 4. Jetty 5. Bridge and Jetty Construction](https://reader031.vdocuments.us/reader031/viewer/2022022718/5c5b712a09d3f259368bb0dd/html5/thumbnails/18.jpg)
12. Questions
18
QUESTIONS?