chemical and construction input industry development
TRANSCRIPT
Chemical and Construction Input
Industry Development Institute
Project Profile on the Establishment of
Cement Tiles
Information Technology and Technical Service
Directorate
Technical Service Team
Addis Ababa
Table of Contents
1. Executive Summary ................................................................................ 1
2. Product Description and Application ................................................... 1
3. Market Study, Plant Capacity and Production Program ................... 2
3.1 Market Study ....................................................................................................... 2
3.1.1 Present Demand and Supply ....................................................................... 2
3.1.2 Projected Demand ....................................................................................... 3
3.1.3 Pricing and Distribution .............................................................................. 4
3.2 Plant Capacity ..................................................................................................... 5
3.3 Production Program ............................................................................................ 6
4. Raw Materials and Utilities ................................................................... 6
4.1 Availability and Source of Raw Materials .......................................................... 6
4.2 Annual Requirement and Cost of Raw Materials and Utilities ........................... 6
5. Location and Site .................................................................................... 7
6. Technology and Engineering ................................................................. 8
6.1 Production Process .............................................................................................. 8
6.2 Machinery and Equipment ................................................................................ 10
6.3 Civil Engineering Cost ...................................................................................... 11
7. Human Resource and Training Requirement ................................... 11
7.1 Human Resource ............................................................................................... 11
7.2 Training Requirement ....................................................................................... 12
8. Financial Analysis ................................................................................. 12
8.1 Underlying Assumption .................................................................................... 12
8.2 Investment ......................................................................................................... 13
8.3 Production Costs ............................................................................................... 14
8.4 Financial Evaluation ......................................................................................... 14
9. Economic and Social Benefit and Justification.................................. 15
ANNEXES ................................................................................................... 17
1
1. Executive Summary
This profile envisages the opportunity of establishing cement tile manufacturing plant
especially for domestic consumption.
The present demand for the product is estimated at 1.19 million m2 per annum.
The plant will have a capacity of producing 55,000m2 of cement tiles per annum. The
machinery and equipments required are mixer moulds and press and they can be supplied
from both local and foreign sources. The cost of machinery & equipment is estimated at
Birr 2.8 million.
The unit will generate employment opportunities for 16 people.
The total investment cost including working capital is about of Birr 5.1 million. The net
present value (NPV) of the project is Birr 596,158 at annual discount rate of 18% and the
internal rate of return (IRR) is 21.3%.
2. Product Description and Application
Cement tiles are wall & floor tiles made from of cement together with sand, gravel &
optionally adding marble chips to the ingredient. The process of manufacturing is called
the “LENOBE” process, which at present is used in many factories. Equipments used to
produce are rubber moulds, vibrators, mixers and other items. The installation can be
made mobile. Tiles of various sizes can be produced. The most common ones rage from
surface sizes of 20 cm x 20 cm to 60cm x 40 cm having thickness in the rage of 1 to 3
cm.
2
3. Market Study, Plant Capacity and Production Program
3.1 Market Study
3.1.1 Present Demand and Supply
Cement tiles are not imported from abroad. The demand for cement tiles are supplied by
local private & public cement tiles manufacturing units. According to the Central
Statistics Authority publications, the annual production of cement tiles for the last five
years ranges between
Table 1: Local Production of Cement Tiles
Eth Year SQ M
1994 221,801
1995 395,916
1996 245,696
1997 485,868
1998 953,011
1999 465,779
2000 287,257
2001 112,616
2002 199,092
2003 413,731 Source: The CSA data
The demand for cement tiles is directly related to the increasing demand for housing
needs and demand of new construction. Thus, for the purpose of estimating present
demand, it was necessary to project the demand for housing and work backwards to
arrive at a corresponding demand.
3
3.1.2 Projected Demand
Time Trend Analysis
The future demand is projected using the linear projection formula. This formula assumes
that the current rapid growth in the demand of cement tiles will continues to rise in the
coming years as well.
The model summary is shown below in fig 1.1
Fig. 1
Trend Analysis Model Summary
The model summary shows that the demand project is reduced to 0.212 million square
meters in 2004 E.C. from 0.331 million square meters in 2018 E.C.
2
)
XX
YYXXb
and
xbya
where
bXaY
4
Table 2: Cement Tile projection using trend analysis
Year Forecast
(m2)
2004 331,447.93
2005 322,969.98
2006 314,492.02
2007 306,014.06
2008 297,536.10
2009 289,058.15
2010 280,580.19
2011 272,102.23
2012 263,624.27
2013 255,146.32
2014 246,668.36
2015 238,190.40
2016 229,712.44
2017 221,234.48
2018 212,756.53
However, the demand projection doesn’t show the real market scenario as the market was
suppressed by local supply of cement tiles. Hence, the major demand drivers are the real
GDP growth of the country. The country has registered a double digit growth of real
GDP. Accordingly, cement tile demand shall be estimated to grow at 10% each year
which is a conservative approach. Therefore, the projection is estimated as shown below
in fig.2.The demand is estimated to be 0.6 million square meter in 2025 E.C.
5
Table 2: Demand Projection of Cement Tiles
2004 325,265
2005 294,351
2006 295,912
2007 336,237
2008 366,409
2009 355,998
2010 362,760
2011 377,810
2012 395,827
2013 408,937
2014 418,293
2015 431,998
2016 447,230
2017 462,503
2018 477,171
2019 492,183
2020 508,439
2021 525,256
2022 542,421
2023 560,003
2024 578,226
2025 597,156
3.1.3 Pricing and Distribution
The average production price of cement tile per m2 in the year 1998 eth cal was Birr
39.89, according to CSA data. The current price is about Birr 75. Deducting 29% for
distributors’ margin of the cement tiles proposed in this project are expected to sell at
Birr 60 per m2.
3.2 Plant Capacity
A small scale plant having an annual production capacity of 55,000 m2 is more
appropriate. It is believed that the product will have adequate local market.
6
It is considered that the plant will operate single shift 275 days a year subtracting the
Sundays, National holidays (amounting to 65 days a year) and stoppages for maintenance
etc. Working in two or three shifts a day is possible to increase the supply.
3.3 Production Program
The plant will be made to start operation at 75% of its capacity during the first year.
Production will be made to rise to 85% of its capacity in the second year, and to full
capacity (100%) in the third year. It is assumed that full scale production will be
maintained starting from third year up to the fifteenth year.
As the plant is new and is equipped with new machinery production build-up is made to
start at reduced capacity and gradually rise to full capacity. This lower production level at
the initial stage is to develop substantial market outlets for the product. Machinery
operators will also get enough time to develop the required skills and experience.
4. Raw Materials and Utilities
4.1 Availability and Source of Raw Materials
Raw materials used by the plant are of local and foreign origin. Local raw materials are
sand, cement (grey), gravel and marble chips. Foreign materials include resins and
lubricants. The principal raw materials together with annual requirements and costs are
given in Table 2.
4.2 Annual Requirement and Cost of Raw Materials and Utilities
An auxiliary material required by the plant consists of pigment, resins and packing
material. The quantity required for each material and costs incurred annually are
indicated in Table 3.
7
Table 2: Raw and Auxiliary Material Requirements at Full Capacity
No Item Qty
(tons)
Birr (in ‘000)
F. C L. C Total
1. Sand 843 - 110 110
2. Grey cement 477 - 458 458
3. Aggregate 1488 - 230.64 230.64
4. Marble chips 162 - 32 32
5. Pigments 10 278 - 278
6. Resins 7 75.6 - 75.6
7. packing material - 30 30
Total - 353.6 860.64 1214.24
The pigments are used to give different colours to the product, while the resins are used
to stick together the different layers of the tile and finally give compactness to the
product.
The pigments are used to give different colours to the product, while the resins are used
to stick together the different layers of the tile and finally give compactness to the
product.
Table 3: Annual Utilities Requirements (at full capacity)
No. Items Annual Consumption Cost in Birr
F.C L.C Total
1. Electricity 123750 Kwh - 68062.5 68062.5
2. Water 4500m3 11925.0 11925.0
3. Lubricants Lump sum 1,000.0 1000.0
4 Consumable ” 2000.00 2000.0
Total 1,000.00 81987.5 82987.5
5. Location and Site
Cement product manufacturing plant has to be located in towns that have abundant raw
material of sand /aggregate and demand for modern houses. The cement roof tile has to
start manufacturing in major towns like Bahir Dar.
8
6. Technology and Engineering
6.1 Production Process
The production of cement tiles (wall and floor type) use rubber moulds and vibrating
tables. The different materials such as sand, grey cement, aggregates (gravel) and marble
chips are assumed to be ready at the site of the plant. Aggregate and sand preparations are
not assumed to be part of the activity of this plant.
The ready made raw materials together with water are mixed in the right proportion by a
mixer and measured amounts are poured into the flexible moulds. This is done manually
for the purpose of this study. However, mixing and pouring can be done automatically.
Each mould containing the measured mix is made to travel the length of the vibrating
table for about one minute.
Allowing the concrete mix in the rubber mould to travel along, the vibrating table has the
advantage of eliminating air bubbles and water veins. In addition to this, the mix is
pressed with tiles press. This will create an exceptionally high compactness of the
aggregates and the cement in the mix.
After a period varying from one to two hours, a second and thicker layer of concrete is
added to the first, and the moulds are vibrated again. The result of the vibrations is a
perfect compaction and firm hold between the two layers. The tile hardens in the mould
and is then demoulded on the following day without the need of any demoulding
products. The concrete then dries in controlled conditions of temperature and humidity.
It is to be noted that during preparation of mix, pigments are added to give different
colours to the product.
Alternative technologies:
1. Using manual brick making machine
The machine imparts a compressive effort of not less than 3/Nmm2 on 4% cement-
stabilized laterite blocks to achieve a strength of not less than 1.6 N/mm2 which is
9
suitable and adequate for cost-effective bungalows. The machine is light-weight and can
readily be transported and used at sites especially in rural areas.
2. Fibre Concrete Roofing Tiles (Mador Tiles)
The production capacity is 600 to 700 bricks per an eight hour working day. Two bricks
are produced in one operation and the standard size of the product is 190 x 140 x 100
(mm) size. During the production and use of cement-stabilized bricks and blocks, great
economy is achieved because less cement than would normally be required in sandcrete
blocks is used. However, in the production of burnt bricks and blocks, the machine
produces unstabilized bricks which are then burnt in clamp kilns. An appropriate level of
technology is applied in the construction of clamp kilns using unskilled and semi-skilled
labour with the advantage of utilizing communal self help spirit of the rural areas.
10
3. Electrohydraulic Brick making Machine
With the desire to improve on and mechanize the brick production process, developed an
electro hydraulic brick making machine which produces two bricks in one single
operation. Due to its semi-automatic nature, the machine allows for mass production of
bricks to meet the high demand required on sites over short periods. This is in addition to
ensuring.
6.2 Machinery and Equipment
Machinery and equipments required by cement tile plant consists of a mixer, tile press,
vibrating tables, rubber moulds and fork lift trucks. The complete list of machinery and
equipment together with costs are shown in table 5.
Table 4: Machinery and Equipments
No
Item
Qty
(Pcs)
Cost (‘000 Birr)
F.C L.C Total
1. Vibrating Tables 2 90 - 90
2. Rubber Moulds 4500 1412 - 1412
3 Mixers 2 105 - 105
4. Tile press 1 316 - 316
5. Fork lift Trucks 2 600 - 600
6. Pallets 20 20
Sub-Total - 2,523 20 2543
freight, insurance,
Inland Transportation,
Bank charges, etc.
- - 254 254
Grand Total - 2,523 274 2797
Supplier Address
Contact person: Rachel Lei
Ningbo Hualong Machinery Factory
ShenXiShan JiShiGang Town,Yinzhou District,Ningbo,ZheJiang,China
Ning Bo China (Mainland) 315172
Tel: 86-574-88003997
Fax: 86-574-88000985
11
6.3 Civil Engineering Cost
Land requirement by the plant including provision for open space is estimated at 1200
m2. Land lease price is Birr 72000. For building, an ordinary shed of corrugated iron
sheet walling and ceiling is envisaged. The floor will be reinforced concrete, having a
strong foundation. Part of the building will be used to allow storage of the product to dry
properly. Open storage is also used for the already dried product and ready for dispatch.
The total building area estimated is 600 m2.at the unit cost (per m
2) of Birr 2000;
therefore, the total cost estimate of building will be Birr 1,200,000.
Land value is estimated at the rate of Birr 206 per m2. Thus, the total payment for land
holding will be birr 12,000.
7. Human Resource and Training Requirement
7.1 Human Resource
Table 5: Human Resource Requirement
No
Description
Qty. Monthly Annual
(No) Salary
Cost
(Birr)
A. Administration
1 Plant Manager 1 4500 54,000
2 Secretary 1 850 10,200
3 Accountant 1 1200 14,400
4 Sales man 1 1200 14,400
5 Clerk 1 750 9,000
6 General Service 3 300 10,800
B. Production
1 Technician 1 1500 18,000
2 Semi Skilled workers 3 850 30,600
3 Unskilled Workers 4 450 21,600
183,000
Benefits (20%) 36,600
Grand Total 219,600
12
7.2 Training Requirement
On job training can be provided curing and after the construction period. Birr 25,000 is
allotted in working capital to finance training.
8. Financial Analysis
8.1 Underlying Assumption
The financial analysis of milk powder producing plant is based on the data provided in
the preceding chapters and the following assumptions.
A. Construction and Finance
Box 1: Construction and Finance
Construction period 1 years
Source of finance 40% equity and 60% loan
Tax holidays 2 years
Bank interest rate 12%
Discount for cash flow 18%
Value of land Based on lease rate of ANRS
Spare Parts, Repair & Maintenance 3% of fixed investment
B. Depreciation
Box 2: Depreciation
Building 5%
Machinery and equipment 10%
Office furniture 10%
Vehicles 20%
Pre-production (amortization) 20%
13
C. Working Capital (Minimum Days of Coverage)
Box 3: Working Capital
Raw Material-Local 30 days
Raw Material-Foreign 120 days
Factory Supplies in Stock 30 days
Spare Parts in Stock and Maintenance 30 days
Work in Progress 10 days
Finished Products 15 days
Accounts Receivable 30 days
Cash in Hand 30 days
Accounts Payable 30 days
8.2 Investment
The total initial investment and working capital at full capacity are shown in Table 7
below.
Table 6: Production Costs
Total Initial Investment
Item Cost Land 3,600.00
Building and civil works 1,200,000.00
Office equipment 50,000.00
Vehicles 250,000.00
Plant machinery & equipment 2,797,000.00
Total Fixed Investment 4,300,600.00
Pre production capital expenditure 215,030.00
Total Initial Investment 4,515,630.00
Working capital at full capacity 633,956.14
Total 5,149,586.14
*Pre-production capital expenditure includes - all expenses for pre-
investment studies, consultancy fee during construction and expenses for
company‘s establishment, project administration expenses, commission
expenses, preproduction marketing and interest expenses during
construction.
14
8.3 Production Costs
The total production cost at full capacity operation is estimated at Birr 2.45 million as
detailed in Table 8 below.
Table 7: Production Costs
Total Production Cost at Full Capacity
Items Cost
1. Raw materials 1,214,240.00
2. Utilities 82,987.50
3. Wages and Salaries 219,600.00
4. Spares and Maintenance 129,018.00
Factory costs 1,645,845.50
5. Depreciation 437,706.00
6. Financial costs 370,770.20
Total Production Cost 2,454,321.70
8.4 Financial Evaluation
I. Profitability
The project is profitable starting from the first year of operation. During the first year
Gross Profit/Sales equals 0.66% and then steady increases to reach 41.60% at the 8th
year
and then after. Likewise, Net Profit after Tax/Sales rises from 0.66% to 29.12%; Return
on Investment from 16.82% to 18.66% and Return on Equity from 0.80% to 46.66%.
II. Breakeven Analysis
The project wills break-even at 30.82% of capacity.
III. Payback Period
The project will payback at the 4th
year of operation.
IV. Simple Rate of Return
The simple rate of return is 18.5%.
15
V. Internal Rate of Return and Net Present Value
The internal rate of return is 21.3% and the NPV at 18% annual discounting rate is Birr
596,158.
VI. Sensitivity Analysis
The project will remain profitable during the first year even if the input prices increase up
to 15 %.
9. Economic and Social Benefit and Justification
Based on the foregoing presentation and analysis, we can learn that the proposed project
possesses wide range of benefits that complement the financial feasibility obtained
earlier. In general the envisaged project promotes the socio-economic goals and
objectives stated in the strategic plan of the Amhara National Regional State. These
benefits are listed as follows
A. Profit Generation
The project is found to be financially viable and earns a net profit of about Birr 7.5
million within the project life. Such result induces the project promoters to reinvest the
profit which, therefore, increases the investment magnitude in the region.
B. Tax Revenue
In the project life under consideration, the region will collect Birr 2.9 million from
corporate tax payment alone (i.e. excluding income tax, sales tax and VAT). Such result
create additional fund for the regional government that will be used in expanding social
and other basic services in the region
C. Import Substitution and Foreign Exchange Saving
That is, based on the projected figure we learn that in the project life an estimated amount
of Birr 31.6 million worth of import will be saved as a result of the proposed project. This
will create room for saving hard currency to be allocated on other vital and strategic
sectors
16
D. Employment and Income Generation
The proposed project is expected to create employment opportunity to several citizens of
the country. That is, it will provide permanent employment to 16 professionals as well as
support staffs..
E. Pro Environment Project
The proposed production process is environment friendly.
F. Diversification
The project accelerates industrialization and diversification of the economy.
17
ANNEXES
1
Annex 1: Total Net Working Capital Requirements (in Birr)
CONSTRUCTION PRODUCTION
Year 1 Year 2 1 2 3 4
Capacity Utilization (%) 0 0 75% 85% 100% 100%
1. Total Inventory 0 0 756,557 857,432 1,008,743 1,008,743
Raw Materials in Stock- Total 0 0 310,595 352,008 414,127 414,127
Raw Material-Local 0 0 28,931 32,788 38,575 38,575
Raw Material-Foreign 0 0 281,664 319,219 375,552 375,552
Factory Supplies in Stock 0 0 1,642 1,861 2,190 2,190
Spare Parts in Stock and Maintenance 0 0 10,556 11,963 14,075 14,075
Work in Progress 0 0 41,056 46,531 54,742 54,742
Finished Products 0 0 82,113 93,061 109,484 109,484
2. Accounts Receivable 0 0 270,000 306,000 360,000 360,000
3. Cash in Hand 0 0 18,510 20,978 24,680 24,680
CURRENT ASSETS 0 0 734,473 832,402 979,297 979,297
4. Current Liabilities 0 0 270,000 306,000 360,000 360,000
Accounts Payable 0 0 270,000 306,000 360,000 360,000
TOTAL NET WORKING CAPITAL REQUIREMENTS 0 0 464,473 526,402 619,297 619,297
INCREASE IN NET WORKING CAPITAL 0 0 464,473 61,930 92,895 0
2
Annex 1: Total Net Working Capital Requirements (in Birr) (continued)
PRODUCTION
5 6 7 8 9 10
Capacity Utilization (%) 100% 100% 100% 100% 100% 100%
1. Total Inventory 1,008,743 1,008,743 1,008,743 1,008,743 1,008,743 1,008,743
Raw Materials in Stock-Total 414,127 414,127 414,127 414,127 414,127 414,127
Raw Material-Local 38,575 38,575 38,575 38,575 38,575 38,575
Raw Material-Foreign 375,552 375,552 375,552 375,552 375,552 375,552
Factory Supplies in Stock 2,190 2,190 2,190 2,190 2,190 2,190
Spare Parts in Stock and Maintenance 14,075 14,075 14,075 14,075 14,075 14,075
Work in Progress 54,742 54,742 54,742 54,742 54,742 54,742
Finished Products 109,484 109,484 109,484 109,484 109,484 109,484
2. Accounts Receivable 360,000 360,000 360,000 360,000 360,000 360,000
3. Cash in Hand 24,680 24,680 24,680 24,680 24,680 24,680
CURRENT ASSETS 979,297 979,297 979,297 979,297 979,297 979,297
4. Current Liabilities 360,000 360,000 360,000 360,000 360,000 360,000
Accounts Payable 360,000 360,000 360,000 360,000 360,000 360,000
TOTAL NET WORKING CAPITAL REQUIREMENTS 619,297 619,297 619,297 619,297 619,297 619,297
INCREASE IN NET WORKING CAPITAL 0 0 0 0 0 0
3
Annex 2: Cash Flow Statement (in Birr)
CONSTRUCTION PRODUCTION
Year 1 Year 2 1 2 3 4
TOTAL CASH INFLOW 2,257,815 2,877,112 2,745,000 2,841,000 3,354,000 3,300,000
1. Inflow Funds 2,257,815 2,877,112 270,000 36,000 54,000 0
Total Equity 903,126 1,150,845 0 0 0 0
Total Long Term Loan 1,354,689 1,726,267 0 0 0 0
Total Short Term Finances 0 0 270,000 36,000 54,000 0
2. Inflow Operation 0 0 2,475,000 2,805,000 3,300,000 3,300,000
Sales Revenue 0 0 2,475,000 2,805,000 3,300,000 3,300,000
Interest on Securities 0 0 0 0 0 0
3. Other Income 0 0 0 0 0 0
TOTAL CASH OUTFLOW 2,257,815 2,257,815 2,695,553 2,267,320 2,788,428 2,598,400
4. Increase In Fixed Assets 2,257,815 2,257,815 0 0 0 0
Fixed Investments 2,150,300 2,150,300 0 0 0 0
Pre-production Expenditures 107,515 107,515 0 0 0 0
5. Increase in Current Assets 0 0 734,473 97,930 146,895 0
6. Operating Costs 0 0 1,140,128 1,286,183 1,505,266 1,505,266
7. Corporate Tax Paid 0 0 0 0 314,680 333,166
8. Interest Paid 0 0 820,952 369,715 308,096 246,476
9.Loan Repayments 0 0 0 513,493 513,493 513,493
10.Dividends Paid 0 0 0 0 0 0
Surplus (Deficit) 0 619,297 49,447 573,680 565,572 701,600
Cumulative Cash Balance 0 619,297 668,744 1,242,424 1,807,995 2,509,595
4
Annex 2: Cash Flow Statement (in Birr): Continued
PRODUCTION
5 6 7 8 9 10
TOTAL CASH INFLOW 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
1. Inflow Funds 0 0 0 0 0 0
Total Equity 0 0 0 0 0 0
Total Long Term Loan 0 0 0 0 0 0
Total Short Term Finances 0 0 0 0 0 0
2. Inflow Operation 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
Sales Revenue 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
Interest on Securities 0 0 0 0 0 0
3. Other Income 0 0 0 0 0 0
TOTAL CASH OUTFLOW 2,555,267 2,540,035 2,496,902 1,940,276 1,940,276 1,940,276
4. Increase In Fixed Assets 0 0 0 0 0 0
Fixed Investments 0 0 0 0 0 0
Pre-production Expenditures 0 0 0 0 0 0
5. Increase in Current Assets 0 0 0 0 0 0
6. Operating Costs 1,505,266 1,505,266 1,505,266 1,505,266 1,505,266 1,505,266
7. Corporate Tax Paid 351,651 398,039 416,525 435,010 435,010 435,010
8. Interest Paid 184,857 123,238 61,619 0 0 0
9. Loan Repayments 513,493 513,493 513,493 0 0 0
10. Dividends Paid 0 0 0 0 0 0
Surplus (Deficit) 744,733 759,965 803,098 1,359,724 1,359,724 1,359,724
Cumulative Cash Balance 3,254,328 4,014,293 4,817,391 6,177,115 7,536,839 8,896,563
5
Annex 3: DISCOUNTED CASH FLOW-TOTAL CAPITAL INVESTED
CONSTRUCTION PRODUCTION
Year 1 Year 2 1 2 3 4
TOTAL CASH INFLOW 0 0 2,475,000 2,805,000 3,300,000 3,300,000
1. Inflow Operation 0 0 2,475,000 2,805,000 3,300,000 3,300,000
Sales Revenue 0 0 2,475,000 2,805,000 3,300,000 3,300,000
Interest on Securities 0 0 0 0 0 0
2. Other Income 0 0 0 0 0 0
TOTAL CASH OUTFLOW 2,257,815 2,257,815 1,604,601 1,348,113 1,912,840 1,838,431
3. Increase in Fixed Assets 2,257,815 2,257,815 0 0 0 0
Fixed Investments 2,150,300 2,150,300 0 0 0 0
Pre-production Expenditures 107,515 107,515 0 0 0 0
4. Increase in Net Working Capital 0 0 464,473 61,930 92,895 0
5. Operating Costs 0 0 1,140,128 1,286,183 1,505,266 1,505,266
6. Corporate Tax Paid 0 0 0 0 314,680 333,166
NET CASH FLOW -2,257,815 -2,257,815 870,399 1,456,887 1,387,160 1,461,569
CUMULATIVE NET CASH FLOW -2,257,815 -4,515,630 -3,645,231 -2,188,344 -801,184 660,385
Net Present Value (at 18%) -2,257,815 -1,913,403 625,107 886,707 715,482 638,865
Cumulative Net present Value -2,257,815 -4,171,218 -3,546,110 -2,659,404 -1,943,922 -1,305,057
6
Annex 3: DISCOUNTED CASH FLOW-TOTAL CAPITAL INVESTED (Continued)
PRODUCTION
5 6 7 8 9 10
TOTAL CASH INFLOW 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
1. Inflow Operation 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
Sales Revenue 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000 3,300,000
Interest on Securities 0 0 0 0 0 0
2. Other Income 0 0 0 0 0 0
TOTAL CASH OUTFLOW 1,856,917 1,903,304 1,921,790 1,940,276 1,940,276 1,940,276
3. Increase in Fixed Assets 0 0 0 0 0 0
Fixed Investments 0 0 0 0 0 0
Pre-production Expenditures 0 0 0 0 0 0
4. Increase in Net Working Capital 0 0 0 0 0 0
5. Operating Costs 1,505,266 1,505,266 1,505,266 1,505,266 1,505,266 1,505,266
6. Corporate Tax Paid 351,651 398,039 416,525 435,010 435,010 435,010
NET CASH FLOW 1,443,083 1,396,696 1,378,210 1,359,724 1,359,724 1,359,724
CUMULATIVE NET CASH FLOW 2,103,468 3,500,164 4,878,374 6,238,098 7,597,822 8,957,546
Net Present Value (at 18%) 534,564 438,458 366,656 306,558 259,795 220,165
Cumulative Net present Value -770,493 -332,036 34,621 341,179 600,974 821,139
Net Present Value (at 18%) 821,139.00
Internal Rate of Return 22.5%
7
Annex 4: NET INCOME STATEMENT ( in Birr)
PRODUCTION
1 2 3 4 5
Capacity Utilization (%) 75% 85% 100% 100% 100%
1. Total Income 2475000 2805000 3300000 3300000 3300000
Sales Revenue 2475000 2805000 3300000 3300000 3300000
Other Income 0 0 0 0 0
2. Less Variable Cost 1052437 1192762 1403250 1403250 1403250
VARIABLE MARGIN 1422563 1612238 1896750 1896750 1896750
(In % of Total Income) 57 57 57 57 57
3. Less Fixed Costs 525397 531127 539722 539722 539722
OPERATIONAL MARGIN 897166 1081111 1357028 1357028 1357028
(In % of Total Income) 36 39 41 41 41
4. Less Cost of Finance 820952 369715 308096 246476 184857
5. GROSS PROFIT 76214 711396 1048933 1110552 1172171
6. Income (Corporate) Tax 0 0 314680 333166 351651
7. NET PROFIT 76214 711396 734253 777386 820520
RATIOS (%)
Gross Profit/Sales 3.08% 25.36% 31.79% 33.65% 35.52%
Net Profit After Tax/Sales 3.08% 25.36% 22.25% 23.56% 24.86%
Return on Investment 18.02% 21.44% 20.30% 19.94% 19.58%
Return on Equity 3.71% 34.64% 35.75% 37.85% 39.95%
8
Annex 4: NET INCOME STATEMENT (in Birr): Continued
PRODUCTION
6 7 8 9 10
Capacity Utilization (%) 100% 100% 100% 100% 100%
1. Total Income 3300000 3300000 3300000 3300000 3300000
Sales Revenue 3300000 3300000 3300000 3300000 3300000
Other Income 0 0 0 0 0
2. Less Variable Cost 1403250 1403250 1403250 1403250 1403250
VARIABLE MARGIN 1896750 1896750 1896750 1896750 1896750
(In % of Total Income) 57 57 57 57 57
3. Less Fixed Costs 446716 446716 446716 446716 446716
OPERATIONAL MARGIN 1450034 1450034 1450034 1450034 1450034
(In % of Total Income) 44 44 44 44 44
4. Less Cost of Finance 123238 61619 0 0 0
5. GROSS PROFIT 1326796 1388415 1450034 1450034 1450034
6. Income (Corporate) Tax 398039 416525 435010 435010 435010
7. NET PROFIT 928757 971891 1015024 1015024 1015024
RATIOS (%)
Gross Profit/Sales 40.21% 42.07% 43.94% 43.94% 43.94%
Net Profit After Tax/Sales 28.14% 29.45% 30.76% 30.76% 30.76%
Return on Investment 20.49% 20.13% 19.77% 19.77% 19.77%
Return on Equity 45.22% 47.32% 49.42% 49.42% 49.42%
9
Annex 5: Projected Balance Sheet (in Birr)
CONSTRUCTION PRODUCTION
Year 1 Year 2 1 2 3 4
TOTAL ASSETS 2,257,815 5,134,927 5,481,141 5,715,044 5,989,804 6,253,698
1. Total Current Assets 0 619,297 1,403,217 2,074,826 2,787,292 3,488,892
Inventory on Materials and Supplies 0 0 322,793 365,832 430,391 430,391
Work in Progress 0 0 41,056 46,531 54,742 54,742
Finished Products in Stock 0 0 82,113 93,061 109,484 109,484
Accounts Receivable 0 0 270,000 306,000 360,000 360,000
Cash in Hand 0 0 18,510 20,978 24,680 24,680
Cash Surplus, Finance Available 0 619,297 668,744 1,242,424 1,807,995 2,509,595
Securities 0 0 0 0 0 0
2. Total Fixed Assets, Net of Depreciation 2,257,815 4,515,630 4,077,924 3,640,218 3,202,512 2,764,806
Fixed Investment 0 2,150,300 4,300,600 4,300,600 4,300,600 4,300,600
Construction in Progress 2,150,300 2,150,300 0 0 0 0
Pre-Production Expenditure 107,515 215,030 215,030 215,030 215,030 215,030
Less Accumulated Depreciation 0 0 437,706 875,412 1,313,118 1,750,824
3. Accumulated Losses Brought Forward 0 0 0 0 0 0
4. Loss in Current Year 0 0 0 0 0 0
TOTAL LIABILITIES 2,257,815 5,134,927 5,481,141 5,715,044 5,989,804 6,253,698
5. Total Current Liabilities 0 0 270,000 306,000 360,000 360,000
Accounts Payable 0 0 270,000 306,000 360,000 360,000
Bank Overdraft 0 0 0 0 0 0
6. Total Long-term Debt 1,354,689 3,080,956 3,080,956 2,567,463 2,053,971 1,540,478
Loan A 1,354,689 3,080,956 3,080,956 2,567,463 2,053,971 1,540,478
Loan B 0 0 0 0 0 0
7. Total Equity Capital 903,126 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971
Ordinary Capital 903,126 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971
Preference Capital 0 0 0 0 0 0
Subsidies 0 0 0 0 0 0
8. Reserves, Retained Profits Brought Forward 0 0 0 76,214 787,610 1,521,863
9.Net Profit After Tax 0 0 76,214 711,396 734,253 777,386
Dividends Payable 0 0 0 0 0 0
Retained Profits 0 0 76,214 711,396 734,253 777,386
10
Annex 5: Projected Balance Sheet (in Birr): Continued
PRODUCTION
5 6 7 8 9 10
TOTAL ASSETS 6,560,725 6,975,990 7,434,388 8,449,412 9,464,436 10,479,460
1. Total Current Assets 4,233,625 4,993,590 5,796,688 7,156,412 8,516,136 9,875,860
Inventory on Materials and Supplies 430,391 430,391 430,391 430,391 430,391 430,391
Work in Progress 54,742 54,742 54,742 54,742 54,742 54,742
Finished Products in Stock 109,484 109,484 109,484 109,484 109,484 109,484
Accounts Receivable 360,000 360,000 360,000 360,000 360,000 360,000
Cash in Hand 24,680 24,680 24,680 24,680 24,680 24,680
Cash Surplus, Finance Available 3,254,328 4,014,293 4,817,391 6,177,115 7,536,839 8,896,563
Securities 0 0 0 0 0 0
2. Total Fixed Assets, Net of Depreciation 2,327,100 1,982,400 1,637,700 1,293,000 948,300 603,600
Fixed Investment 4,300,600 4,300,600 4,300,600 4,300,600 4,300,600 4,300,600
Construction in Progress 0 0 0 0 0 0
Pre-Production Expenditure 215,030 215,030 215,030 215,030 215,030 215,030
Less Accumulated Depreciation 2,188,530 2,533,230 2,877,930 3,222,630 3,567,330 3,912,030
3. Accumulated Losses Brought Forward 0 0 0 0 0 0
4. Loss in Current Year 0 0 0 0 0 0
TOTAL LIABILITIES 6,560,725 6,975,990 7,434,388 8,449,412 9,464,436 10,479,460
5. Total Current Liabilities 360,000 360,000 360,000 360,000 360,000 360,000
Accounts Payable 360,000 360,000 360,000 360,000 360,000 360,000
Bank Overdraft 0 0 0 0 0 0
6. Total Long-term Debt 1,026,985 513,493 0 0 0 0
Loan A 1,026,985 513,493 0 0 0 0
Loan B 0 0 0 0 0 0
7. Total Equity Capital 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971
Ordinary Capital 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971 2,053,971
Preference Capital 0 0 0 0 0 0
Subsidies 0 0 0 0 0 0
8. Reserves, Retained Profits Brought Forward 2,299,249 3,119,769 4,048,526 5,020,417 6,035,441 7,050,465
9. Net Profit After Tax 820,520 928,757 971,891 1,015,024 1,015,024 1,015,024
Dividends Payable 0 0 0 0 0 0
Retained Profits 820,520 928,757 971,891 1,015,024 1,015,024 1,015,024