41 MD,ENGINEERS INDIA LIMITED
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-68-0021
Page 1 of 3
Project: Job No.:
Document No.: Rev. No.:
Document Title:
SR. NO,
CHECK/ CONTROL POINTS Tick Mark
as per Legend
1 GENERAL
a Drawing number is as per approved DCI
b Electronic file number is as per approved DCI
c Draughting is as per design requirements
d North line/ orientation as per input data
e Notes comply with Job Specifications and General Notes
f Field notes for specific instructions/ scope of work defined
g Layout of grids and spacing/ dimensions/ equipment location, support, orientation etc. as per input data
h Referenced Drawings specified
i Referenced Standards specified
.1 If not adequately clear in General Notes, grade of concrete and grade of reinforcement bars specified
k Bill of materials furnished (for the detailed portion)
1 Necessary internal co-ordination done with relevant departments as per requirements
m Resolution/ incorporation of comments received
2 FOUNDATIONS
a Coordinates/ location is as per input data, suction side & discharge side (for pump foundations) as per layout drawing
b Referenced level and elevations specified are as per approved General Civil/ Architectural drawings/ Piping GAD (viz. NGL/ FGL/ HPP)
c Elevation/ depth of foundation bottom furnished
d Fouling with surrounding foundations/ services cleared
e Any extra cover for rebar required and specified
f Any extra minimum cement content required and specified
g Thickness, projection and grade of lean concrete specified
Anchor bolt location and orientation specified
Adequacy of foundation depth checked to accommodate anchor bolt assemblies
J Anchor bolt description (as per standard) specified
k Depth of pockets specified
1 Minimum cover on anchor bolts/ pockets checked
m
n
Fouling between anchor bolt assembly and pedestal rebar checked
Grout thickness specified
o Reinforcement provided as per design/ codal requirements
Format No. 8-00-0001-F1 Rev. 0
Copyright EIL — All rights reserved
Page 20858 of 22455
mad ENGINEERS Ogui tVe--E; INDIA LIMITED
,rtfia Undert*.)1
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-.68-0021
Page 2 of 3
SR. NO,
CHECK/ CONTROL POINTS Tick Mark
as per Legend
p Links and ties detailed
q Dowel lengths for column rebars staggered and specified
r Depth of machine foundations with respect to building foundations checked
s Separation detail for machine foundations and pouring sequence given .
t Requirement of water bars at construction joints for liquid retaining
structures furnished
u Requirement of protective painting
v Field note for sequence of construction, if adjoining foundations are at different level
w
For pump foundations, following field note shall compulsorily be added in foundation drawings: "The pump discharge nozzle is facing towards North/East/West/South". (appropriate direction shall be selected as per layout drawing, in case discharge is upwards, direction of suction nozzle shall be specified)
3 SUPER STRUCTURE Reinforced Cement Concrete
a Layout is as per approved Piping GAD/ Architectural drawings
b Requirement of expansion/ separation joints checked
c Anchor bolt location and orientation specified
d Anchor bolt description (as per standard) specified
e Pockets for bolts located/oriented and specified
f Depth of pockets/ length of bolts in RCC members checked
g Minimum cover on anchor bolts/ pockets checked
h Fouling between anchor bolt assembly and rebar checked
i Grout thickness specified
j Reinforcement provided as per design/ codal requirements
k Cut-outs as per requirement provided with edge protection
1 Slope has been provided over RCC roof
m Curb around all openings
n Insert plates & pipe sleeves provided wherever required
o Extra reinforcement around cut-outs & openings
p Dowel bars for lap length & anchorage length
q Nominal links in column, stin-ups for beams & their arrangement
4 SUPER STRUCTURE Structural steel
a Layout is as per approved Piping GAD/ input drawings
b Requirement of expansion/ separation joints checked
c Bolting details for equipments specified
d Member sizing and connection details furnished
e Grating/ chequered plate requirements with supporting members furnished
f Welding requirements furnished
g Fire-proofing requirements furnished
Format No. 8-00-0001-F1 Rev. 0
Copyright EIL — All rights reserved
Page 20859 of 22455
31 ENGINEERS ligat INDIA LIMITED rtA,PRI, r;,:, 04 ,rea. Undertak.g,
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-68-0021
Page 3 of 3
SR. NO.
CHECK/ CONTROL POINTS Tick Mark
as per Legend
h Requirement of removable floor/ handrails checked
i Requirement of grouting holes in base plates specified
j Vertical & Horizontal bracings provided as per piping clearance
k Splicing location has been proposed/ suggested
I Approach staircase/ ladder provided with proper landing at entry point
m Toe plate around openings
n Stiffness/ diaphragm plates have been suitably provided
o Vertical clearance below monorail beam checked
P Capacity of monorail specified & structurally stable cantilever projection given
Drawing issued through DCIM (Document Control Index Module)
Date: Name & Signature
Legend :
✓ : Check carried out and found OK ✓ NA : Check carried out and found not applicable
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Page 20860 of 22455
EQUIPMENT LAYOUT DFCU BLOCK (AREA 125A)
B224-EPCC07-LT-125-PP-DW-0001
CIVIL
B224
LAYOUT AND DETAILS
FOR FOUNDATION OF 125-LZ-1922 - SH 2
MIXED BED EXCHANGERS (125-V-01A & 125-V-01B)
B224-EPCC07-LT-125-CV-DW-3206
B224-EPCC07-LT-125-CV-DW-3206
B224-EPCC07-LT-125-CV-DW-3206
16.10.2021
1:100
1 OF 1
01
PHT
PSK/SMK
YSB/AKB
DFCH
ISSUED FOR REVIEW00 16.10.2021
PLANT
NORTH
N
DETAIL
-
01
(SCALE 1:20)
GENERAL NOTES AND LEGENDS FOR CONCRETE WORK
B224-EPCC07-LT-125-CV-DW-0001
F
E
G
H
C
B
A
D
G
F
E
D
C
B
A
H
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 6 7 8 9 10 11 12
DWG. NO.
5
A1
SCH. DATE OF SUBMISSION
STATEMENT OF SUB:
FINAL FOR CODE-1
ISSUED FOR
DOCUMENT STATUS
SIGN:
(USE TICK MARK)
DATE:
AS BUILT
1st 2nd
R
3rd
VPTL NO.:
DRG. CATEGORY:
I
EIL REVIEW/APPROVAL
CODE:
DEPT:
CHK BY:
APP BY:
DATE
EPC/LSTK
OWNER
DRG. NO.:
REVISE THIS DRG. USING CAD SYSTEM ONLY
PWO NO.:
CAD
PROJECT:
TITLE:
DRNDATE CHECKED
SCALE
DRN BY:
APPROVED
SH.
PMC :
REV.
REV.
DESCRIPTION
SUB-CONTRACTOR:
ENGINEERING
NAME DISCIPLINE SIGN. DATE
INFORMATION
CONSTRUCTION REVIEW
AS BUILT
FILE:
DRAWING NO. DRAWING TITLE REV
REFERENCE DOCUMENTS / DRAWINGS
CODE 1 - NO COMMENTS
PROCEED WITH MANUFACTURE / FABRICATION/
CONSTRUCTION AS PER THE DOCUMENT.
CODE 2 - PROCEED WITH MANUFACTURE
/ FABRICATION / CONSTRUCTION AS PER THE
COMMENTED DOCUMENT. REVISED DOCUMENT REQUIRED.
CODE 3 - DOCUMENT DOES NOT CONFORM
TO BASIC REQUIREMENTS AS MARKED.
RESUBMIT FOR REVIEW.
R - DOCUMENT IS RETAINED FOR RECORDS.
PROCEED WITH MANUFACTURE / FABRICATION
V-VOID
CONTRACTOR:
EPCC 07 PACKAGE - DUAL FEED CRACKER BLOCK FOR RAJASTHAN
HPCL RAJASTHAN REFINERY LIMITED
L&T Hydrocarbon Engineering
REFINERY PROJECT (RRP) OF M/S HRRL, BARMER, RAJASTHAN, INDIA
(A Govt. of India Undertaking)
ALL RIGHTS RESERVED
THIS DOCUMENT IS DEVELOPED BY LTHE AND INFORMATION CONTAINED IS PROPERTY OF HPCL RAJASTHAN REFINERY LTD. IT SHALL NOT
BE USED FOR ANY PURPOSE OTHER THAN FOR WHICH IT WAS SUPPLIED. CONFIDENTIAL
– NOT TO DISCLOSE WITHOUT AUTHORIZATION
A1
0°
90°
270°
180°
℄ OF 125-V-01A
℄ OF 125-V-01A
PILE LAYOUT
03 NOS. 500∅ (10M)
BCIS PILES @ PCD=2848
-
A
℄ OF 125-V-01A & B
SECTION
-
A
50
(TYP)
75
300
(TYP)
(SCALE 1:50)
16-T16
3-T12
(SIDE FACE R/F)
EL+97.500 (BOF)
EL+100.000 (HPP)
EL+100.300 (TOG)
T16@150 C/C (T)
(B/W)
LEGEND :
500 DIA BCIS PILE 10M
NOTES:
1. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS &
CO-ORDINATES ARE IN METERS UNLESS NOTED OTHERWISE.
2. HIGH POINT OF PAVING (HPP) ELEVATION +100.000 CORRESPONDS
TO REDUCED LEVEL(RL) 107.650 ABOVE MEAN SEA LEVEL (MSL)
3. ONLY FIGURED DIMENSIONS SHALL BE FOLLOWED. DIMENSIONS
SHALL NOT BE SCALED.
4. ALL DIMENSIONS ARE SYMMETRICAL ABOUT CENTER LINE UNO.
5. ALL REINFORCING BARS ARE EQUALLY SPACED UNO.
6. FOR GENERAL NOTES FOR CONCRETE WORKS, REFER TO DWG NO.
B224-EPCC07-LT-125-CV-DW-0001.
7. FOR TEST PILE LOCATION, REFER TO STD. DWG. NO.
B224-EPCC07-LT-125-CV-DW-0013.
8. FOR DETAILS OF PILES, REFER TO STD. DWG. NO.
B224-EPCC07-LT-125-CV-DW-5091 "STANDARD DRAWING FOR
DETAILS OF PILES (WORKING PILE)".
9. CONSTRUCTION JOINT SHALL BE ROUGHENED UNIFORMLY TO EXPOSE THE
AGGREGATE AND PROPERLY CLEANED FROM LAITANCE, LOOSE PARTICLES OF
AGGREGATE & DAMAGED CONCRETE SURFACE PRIOR TO PLACEMENT OF
FRESH CONCRETE.
10. REINFORCEMENT SHALL BE ADJUSTED TO CLEAR THE POCKETS OR EMBEDDED
PARTS ETC. HOWEVER IN NO CASE ANY REBAR SHALL BE CUT WITHOUT
PERMISSION OF ENGINEER-IN-CHARGE.
11. FOR SURFACE PROTECTION REFER TO CLAUSE 1.1.2 OF EIL SPECIFICATION
B224-000-81-41-SP-0001.
12. FOR STD REINFORCEMENT DETAILS, REFER TO DWG NO.
B224-EPCC07-LT-125-CV-DW-0003.
13. FOR ANCHOR BOLT STD DETAILS, REFER TO DWG NO.
B224-EPCC07-LT-125-CV-DW-0004.
14. THIS DRAWINGS SHALL BE READ IN CONJUNCTION WITH
B224-EPCC07-LT-125-CV-DW-3205.
15. THICKNESS & TYPE OF TILING TO BE USED SHALL BE AS PER VENDOR
REQUIREMENT & AS PER EIL STANDARD NO. 7-65-0310.
GA DRAWINGS OF MIXED BED EXCHANGERS VESSEL
B224-EPCC07-LT-MEP-PO92804-GA-7011
DESIGN CALCULATION FOR FOUNDATION OF 125-LZ-1922
B224-EPCC07-LT-125-CV-CL-0575
SCHEDULE OF BCIS PILE SAFE LOAD CAPACITIES
DIA
(mm)
10500
LEGEND
40
SAFE CAPACITY (MT)
15 4.5
COMPRESSION TENSION LATERAL
(*) PILE LENGTH BELOW PILE CUT-OFF LEVEL-L (M)
PILE
LENGTH (*)
TYPE
-
PILE NOS. REMARK
ITEM
TOTAL NO.
OF PILES
PILE CUT-OFF
ELEVATION
EL+97.600
TABLE FOR PILE CUTOFF ELEVATION
PILE LENGTH
LENGTH (*)
(*) PILE LENGTH IS MEASURED BELOW PILE CUT-OFF LEVEL.
DIA
ELEVATION (**)
EL+91.100
(**) REFER NOTE-19 OF STD. DWG. NO. B224-EPCC07-LT-125-CV-DW-5091 AS REFERRED IN NOTE-8 OF THIS DWG.
LINER TERMINATION
06
03125-V-01A 500∅ 10M
SUB TOTAL OF PILE
125-V-01A-001 TO 003
50
50
300
100
APPROXIMATE QUANTITIES
CONCRETE
PCC (M5)
CONCRETE (M35)
REINFORCEMENT
T8
T16
TOTAL
M30 (TYPE-A)
2.10 cu.m
22.00 cu.m
0.45 MT
12 NOS.
ANCHOR BOLT
1.20 MT
1.85 MT
T12 0.20 MT
SPECIAL EXECUTION NOTES:
REFERENCE SHALL BE MADE TO PILE & PILE CAP LAYOUT TO
IDENTIFY DEEPER FOUNDATION IF ANY AROUND THIS EQUIPMENT.
ACCORDINGLY DEEPER FOUNDATION SHALL BE EXECUTED FIRST TO
AVOID ANY SCOURING OF SOIL BELOW PILE CAP.
GROUT 1.75 sq.m
ANCHOR BOLT
GROUT
3-T8 (STIRRUPS)
EL+100.300 (TOG)
PROJ.
T8@150
100
50
50
(TYP)
ISOLATION JOINT
(SCALE 1:50)
002
003
T16@150 C/C (B)
(B/W)
LEAN CONCRETE
SMK YSB/AKBPHT
001
0°
90°
270°
180°
℄ OF 125-V-01B
℄ OF 125-V-01B
PILE LAYOUT
03 NOS. 500∅ (10M)
BCIS PILES @ PCD=2848
-
A
(SCALE 1:50)
005
006
004
℄ OF 125-V-01A
0°
90°
270°
180°
℄ OF 125-V-01B
0°
90°
270°
180°
℄
O
F
P
E
D
E
S
T
A
L
3875
= =
1605
= =
℄ OF 125-V-01A\PEDESTAL
2-A-M30-N2-525
@ 2848 BCD
STRADDLE CENTER LINE
6
0
°
℄
O
F
P
E
D
E
S
T
A
L
℄
O
F
P
E
D
E
S
T
A
L
3875
= =
1605
= =
℄
O
F
P
E
D
E
S
T
A
L
℄ OF 125-V-01B
6
0
°
HOLD-1
PILE CAP PLAN
(SCALE 1:50)
PILE CAP PLAN
(SCALE 1:50)
(SCALE 1:25)
PEDESTAL REBAR
STIRRUPS
T8@150 C/C
(TYP)
16-T16
600
600
(SCALE 1:25)
ANCHOR BOLT DETAILS
(FOR ORIENTATION OF PEDESTAL REFER PILECAP PLAN)
180
= =
600
= =
600
= =
℄ OF PEDESTAL
℄ OF PEDESTAL
125-V-01B 500∅ 10M 125-V-01B-004 TO 006 03 EL+97.600 EL+91.100
2-A-M30-N2-525
HOLD-1
-
A
℄ OF BOLT/PEDESTAL ℄ OF PEDESTAL
300
1800
700
2500
30 THK
GROUT
01
-
℄ OF PEDESTAL
KEY-PLAN
PLANT
NORTH
N
SS-15
(DFCU)
SRR-9A
(DFCU) SRR-9B
SS-16
THIS AREA
HOLD LIST :
1. ANCHOR BOLT PROJECTION
℄ OF 125-NPIT-01
℄ OF 125-NPIT-01
2-A-M30-N2-525
@ 2848 BCD
℄ OF 125-V-01A
0°
90°
270°
180°
℄ OF 125-V-01A
T16@150 C/C (T)
T16@150 C/C (T)
T16@150 C/C (B)
T16@150 C/C (B)
℄ OF 125-V-01B
0°
90°
270°
180°
℄ OF 125-V-01B
T16@150 C/C (T)
T16@150 C/C (T)
T16@150 C/C (B)
T16@150 C/C (B)
REINFORCEMENT ARRANGEMENT REINFORCEMENT ARRANGEMENT
℄ OF 125-V-01A ℄ OF 125-V-01B
℄ OF 125-V-01A
N 3076.406
E 8312.950
E 8316.950
℄ OF 125-V-01B
N 3076.406
LAYOUT FOR 125-V-01A & B
6
0
°
HOLD-1
2. EXTENT OF ACID PROOFING TILING IN PLAN.
(2600 X 2500 HOS.)
4000
(SCALE 1:100)
4000
(NTS)
-
A
SURFACE PROTECTION
(NOTE-11)
WELL COMPACTED
SOIL
63THK ACID PROOF TILING
(REFER NOTE-15)
BOLT DIA
M30
REBAR AROUND ANCHOR BOLT
(MM)
REQUIRED
2-T16
REBAR
PROVIDED
3-T16
REBAR
REMARKS
OK
(NOTE-13)
R340
HOLD-2
6
0
°
FOR DETAILS REFER DRG NO
B224-EPCC07-LT-125-CV-DW-3205-SH 01
KERB LINE
3
0
°
120°
3
0
°
120°
41 MD,ENGINEERS INDIA LIMITED
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-68-0021
Page 1 of 3
Project: Job No.:
Document No.: Rev. No.:
Document Title:
SR. NO,
CHECK/ CONTROL POINTS Tick Mark
as per Legend
1 GENERAL
a Drawing number is as per approved DCI
b Electronic file number is as per approved DCI
c Draughting is as per design requirements
d North line/ orientation as per input data
e Notes comply with Job Specifications and General Notes
f Field notes for specific instructions/ scope of work defined
g Layout of grids and spacing/ dimensions/ equipment location, support, orientation etc. as per input data
h Referenced Drawings specified
i Referenced Standards specified
.1 If not adequately clear in General Notes, grade of concrete and grade of reinforcement bars specified
k Bill of materials furnished (for the detailed portion)
1 Necessary internal co-ordination done with relevant departments as per requirements
m Resolution/ incorporation of comments received
2 FOUNDATIONS
a Coordinates/ location is as per input data, suction side & discharge side (for pump foundations) as per layout drawing
b Referenced level and elevations specified are as per approved General Civil/ Architectural drawings/ Piping GAD (viz. NGL/ FGL/ HPP)
c Elevation/ depth of foundation bottom furnished
d Fouling with surrounding foundations/ services cleared
e Any extra cover for rebar required and specified
f Any extra minimum cement content required and specified
g Thickness, projection and grade of lean concrete specified
Anchor bolt location and orientation specified
Adequacy of foundation depth checked to accommodate anchor bolt assemblies
J Anchor bolt description (as per standard) specified
k Depth of pockets specified
1 Minimum cover on anchor bolts/ pockets checked
m
n
Fouling between anchor bolt assembly and pedestal rebar checked
Grout thickness specified
o Reinforcement provided as per design/ codal requirements
Format No. 8-00-0001-F1 Rev. 0
Copyright EIL — All rights reserved
Page 20858 of 22455
mad ENGINEERS Ogui tVe--E; INDIA LIMITED
,rtfia Undert*.)1
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-.68-0021
Page 2 of 3
SR. NO,
CHECK/ CONTROL POINTS Tick Mark
as per Legend
p Links and ties detailed
q Dowel lengths for column rebars staggered and specified
r Depth of machine foundations with respect to building foundations checked
s Separation detail for machine foundations and pouring sequence given .
t Requirement of water bars at construction joints for liquid retaining
structures furnished
u Requirement of protective painting
v Field note for sequence of construction, if adjoining foundations are at different level
w
For pump foundations, following field note shall compulsorily be added in foundation drawings: "The pump discharge nozzle is facing towards North/East/West/South". (appropriate direction shall be selected as per layout drawing, in case discharge is upwards, direction of suction nozzle shall be specified)
3 SUPER STRUCTURE Reinforced Cement Concrete
a Layout is as per approved Piping GAD/ Architectural drawings
b Requirement of expansion/ separation joints checked
c Anchor bolt location and orientation specified
d Anchor bolt description (as per standard) specified
e Pockets for bolts located/oriented and specified
f Depth of pockets/ length of bolts in RCC members checked
g Minimum cover on anchor bolts/ pockets checked
h Fouling between anchor bolt assembly and rebar checked
i Grout thickness specified
j Reinforcement provided as per design/ codal requirements
k Cut-outs as per requirement provided with edge protection
1 Slope has been provided over RCC roof
m Curb around all openings
n Insert plates & pipe sleeves provided wherever required
o Extra reinforcement around cut-outs & openings
p Dowel bars for lap length & anchorage length
q Nominal links in column, stin-ups for beams & their arrangement
4 SUPER STRUCTURE Structural steel
a Layout is as per approved Piping GAD/ input drawings
b Requirement of expansion/ separation joints checked
c Bolting details for equipments specified
d Member sizing and connection details furnished
e Grating/ chequered plate requirements with supporting members furnished
f Welding requirements furnished
g Fire-proofing requirements furnished
Format No. 8-00-0001-F1 Rev. 0
Copyright EIL — All rights reserved
Page 20859 of 22455
31 ENGINEERS ligat INDIA LIMITED rtA,PRI, r;,:, 04 ,rea. Undertak.g,
CHECK LIST FOR PREPARATION OF
STRUCTURAL DRAWING
ANNEXURE-15 OF 6-68-0021
Page 3 of 3
SR. NO.
CHECK/ CONTROL POINTS Tick Mark
as per Legend
h Requirement of removable floor/ handrails checked
i Requirement of grouting holes in base plates specified
j Vertical & Horizontal bracings provided as per piping clearance
k Splicing location has been proposed/ suggested
I Approach staircase/ ladder provided with proper landing at entry point
m Toe plate around openings
n Stiffness/ diaphragm plates have been suitably provided
o Vertical clearance below monorail beam checked
P Capacity of monorail specified & structurally stable cantilever projection given
Drawing issued through DCIM (Document Control Index Module)
Date: Name & Signature
Legend :
✓ : Check carried out and found OK ✓ NA : Check carried out and found not applicable
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved