che451_chemical process design and economics

Upload: daniel-grabovsky

Post on 10-Oct-2015

111 views

Category:

Documents


1 download

DESCRIPTION

Gives you understanding on Process design and economics as a chemical Engineer

TRANSCRIPT

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    1/99

    i

    KWAME NKRUMAH UNIVERSITY OF SCIENCE AND

    TECHNOLOGY, KUMASI

    INSTITUTE OF DISTANCE LEARNING

    CHE 451

    Chemical Process Design & Economics

    (Credits: 4)

    Benjamin Afotey, PhD

    Chemical Engineering Department

    August, 2014

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    2/99

    ii

    Course IntroductionDesign is the synthesis of ideas to achieve a desired goal (product). The designer starts with

    an idea and proceeds to develop several alternative designs that he evaluates and finallysettles on the one that satisfies his objective (goal).

    The search for alternative designs is important to the economic viability of the design project.CHE 451 is a fourth year core course offered in first semester in BSc. Chemical Engineering.

    Course OverviewMethodology of the Design Process: Constraints on a Design Problem; Fixed/Rigidconstraints, Less rigid constraints, The design process; Design objectives, Data collection,

    Generation of possible designs,Selection, Chemical manufacturing processes, Continuous

    and batch processes, Organization of a chemical engineering design project.

    Codes and Standards, Design Factors, Variable & Mathematical Representation of DesignProblems: Codes and standards, Design factors, Systems of units, Mathematical

    representation of the design problem, Selection of design variables. Optimization and Batch

    Production Process: Introduction, Simple models, Multiple variable systems, Methods ofanalysis, Other optimization methods, Batch production process.

    Process Synthesis: Introduction, Raw materials and chemical reactions, Summary of process

    design heuristics, Heuristics in equipment design. Process Simulation: Introduction, Processsimulator, Types of process simulation, Units operation solvers, Uncertainty and sensitivity

    issues. Flow sheeting, Piping and Instrumentation: Introduction, Piping & instrumentation

    diagrams, Valve selection, Pumps, Classification of pumps, Factors to consider in pump

    selection, Centrifugal pumps, Effective characteristics curves, Design parameters of

    centrifugal pumps, Operating point, Choice of rotational speed,. Process Economics: Costestimation, Cash flow for industrial operation, Factors affecting investment and production

    costs, Capital investment, Estimation of capital investment, Types of capital cost estimates,cost indices, Methods of estimating capital investment, Turnover ratio, Estimation of total

    product cost, Break-even point. Process Economics: Depreciation and profitability analysis,

    Service life, Salvage value, Present value, Methods for determining depreciation,Profitability standards, Basis for evaluating project profitability, Mathematical methods for

    profitability evaluation, Rate of return on investment, Discounted cash flow, Capitalized cost,

    Pay-back time, Sensitivity analysis.

    Course ObjectiveThe following is the main course Objective

    1. To enable students understand and acknowledge the importance of economic analysis

    in chemical process design, by way of efficiently maximizing profit.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    3/99

    iii

    Course OutlineThe course outline is divided into eight units. Each of the eight units is broken into subtopics.

    Each unit addresses one or more of the course objectives.

    Unit 1: Methodology of the Design Process

    Unit 2: Codes and Standards, Design Factors, Variable &Mathematical Representation ofDesign Problems

    Unit 3: Optimization and Batch Production Process

    Unit 4: Process Synthesis

    Unit 5: Process SimulationUnit 6: Flow Sheeting, Piping and Instrumentation

    Unit 7: Process Economics: Cost Estimation

    Unit 8: Process Economics: Depreciation and Profitability Analysis

    GradingContinuous Assessment: 30%

    End of Semester Examination: 70%

    Reading List/Recommendation Textbooks/Websites/CDs1. Plant Design and Economics for Chemical Engineers: By Peters and Timmerhaus

    2. Coulson & Richardsons Chemical Engineering Design: By Sinnot, Volume 6

    Course Writer

    Dr. Benjamin Afotey received his BSc. Degree in Chemical Engineering in 2000 at KwameNkrumah University of Science and Technology, Kumasi. He received his MSc. and PhD

    Degrees at the University of Texas, Arlington, and U.S.A in 2003 and 2008 respectively.

    He worked with the Texas Commission on Environmental Quality, U.S.A between 2008 and

    2009 and joined the Chemical Engineering Department in 2010.

    AcknowledgementI wish to thank the Almighty God for His guidance throughout the write up. I would also like

    to thank my colleagues who provided encouragement of any kind. Finally, I acknowledge the

    effort of my Teaching Assistant who contributed in a way to the successful completion of thematerial.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    4/99

    iv

    TABLE OF CONTENT1.0 METHODOLOGY OF THE DESIGN PROCESS 1

    SESSION 1-1 : 1

    1-1.1 Introduction 1

    1-1.2.Constraint on a Design Problem 11-1.2.1 Fixed/Rigid constraint 1

    1-1.2.2 Less rigid constraint 11-1.3 The Design Process 2

    1-1.3.1 The design objective 3

    1-1.3.2 Data collection 41-1.3.3 Generation of possible designs 4

    1-1.3.4 Selection 5

    1-1.4 Chemical Manufacturing Processes 5

    1-1.5 Continuous and Batch Processes 71-1.5.1 Choice of continuous verses Batch processes 7

    1-1.5.2 Organization of a chemical engineering design project 72.0 CODES AND STANDARDS, DESIGN FACTORS, VARIABLE &MATHEMATICAL REPRESENTATION OF DESIGN PROBLEMS 11

    SESSION 2-1 11

    2-1.1 Codes and Standards 112-1.2 Factors of Safety 12

    2-1.3 System of Units 13

    2-1.4 Mathematical Representation of the Design Problem 13

    2-1.5 Selection of Design Variables 183.0 OPTIMIZATION AND BATCH PRODUCTION PROCESS 20

    SEESION 3-1 20

    3-1.1 Introduction 203-1.2 Simple Methods 21

    3-1.3 Multiple Variable Systems 22

    3-1.4 Methods of Analysis 23

    3-1.5 Other Optimization Methods 24

    3-1.6 Batch Production Process 24

    4-0 PROCESS SYNTHESIS 26

    SESSION 4-1 26

    4-1.1Introduction 264-1.2 Raw Materials and Chemical Reactions 264-1.3 Summary of Process Design Heuristics 34

    4-1.4 Heuristics in Equipment Design 345.0 PROCESS SIMULATION 38SESSION 5-1 38

    5-1.1 Introduction 38

    5-1.2 Process Simulator 395-1.3 Types of Process Simulation 39

    5-1.4 Unit Operation Solvers 40

    5-1.5 Uncertainty and Sensitivity Issues 40

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    5/99

    v

    6.0 FLOW SHEETING, PIPING AND INSTRUMENTATION 42

    SESSION 6-1 426-1.1 Introduction 42

    6-1.2 Piping and Instrumentation Diagrams 43

    6-1.3 Valve Selection 44

    6-1.3.1 Gate valves 456-1.3.2 Globe valves 46

    SESSION 6-2 466-2.1 Introduction of Pumps 46

    6-2.2 Classification of Pumps 46

    6-2.3 Factors to Consider in Pump Selection 476-2.4 Centrifugal Pumps 48

    6-2.4.1 Effective characteristics curves 48

    6-2.4.2 Design parameters of centrifugal pumps 49

    6-2.4.3 Operating point 496-2.4.4 Q/H Curve versus Technical choices 51

    6-2.4.5 Choice of rotation speed 526-2.4.6 Suction Conditions: Concept of NPSH 537.0 PROCESS ECONOMICS: COST ESIMATION 57

    SESSION 7-1 57

    7-1.1 Cost Estimation 577-1.2 Cash Flow for Industrial Operations 58

    7-1.3 Factors affecting Investment and Production Costs 59

    7-1.4 Capital Investment 59

    7-1.5 Estimation of Capital Investment 617-1.5.1 Introduction 61

    7-1.5.2 Types of capital cost estimates 61

    7-1.5.3 Cost indexes 627-1.5.4 Methods for estimating capital investment 63

    7-1.5.4.1 Power factor applied to plant-capacity ratio 63

    7-1.5.4.2 Detailed item estimate 667-1.5.4.3 Other Methods for Estimating Equipment or Capital Investment 67

    7-1.5.5 Turn-over ratio 68

    SESSION 7-2 68

    7-2.1 Estimation of Total Product Cost 687-2.2 Break-even Point 70

    8.0 PROCESS ECONOMICS: DEPRECIATION AND PROFITABILITY ANALYSIS 75

    SESSION 8-1 75

    8-1.1 Depreciation 758-1.2 Service Life 76

    8-1.3 Salvage Value 768-1.4 Present Value 76

    8-1.5 Methods for Determining Depreciation 77

    8-1.5.1 Straight-line method 778-1.5.2 Decliningbalance ( or fixed percentage) method 77

    8-1.5.3 Other methods for determining depreciation 78

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    6/99

    vi

    SESSION 8-2 82

    8-2.1 Profitability Analysis 828-2.2 Profitability Standards 82

    8-2.3 Basis for Evaluating Project Profitability 83

    8-2.4 Mathematical Methods for Profitability Evaluation 84

    8-2.4.1 Rate of return on investment 848-2.4.2 Discounted cash flow 86

    8-2.4.3 Capitalized cost 888-2.4.4 Payout period (or Pay-back time) 90

    8-2.4.5 Sensitivity Analysis 91

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    7/99

    vii

    LIST OF FIGURESFigure 1-1.1 Design Constraints 2

    Figure 1-1.2 The Design Process 3

    Figure 1-1.3 Anatomy of a Chemical Process 5

    Figure 1-1.4 The Structure of a Chemical Engineering Project 8Figure 1-1.5 Project Organisation 9

    Figure 3-1.1 Effect of Constraints on the Optimum of a Function 23Figure 3-1.2 Yield as a Function of Reactor Temperature and Pressure 24

    Figure 6-1.1 Flow-sheet of Simplified Nitric Acid Production Process 42

    Figure 6-1.2 Polymer Production Diagram 43Figure 6-1.3 Commonly used Valves 45

    Figure 6-2.1 Approximate Range of Operation for the Three Main Types of Pump 48

    Figure 6-2.2 Basic Curves Characterizing a Centrifugal Pump 49

    Figure 6-2.3 Curve Characteristic of the System 50Figure 6-2.4 Variation of Operating Point by means of a Valve 50

    Figure 6-2.5 Variation in Specific Speed versus the Type of Impeller used 51Figure 6-2.6 Different Types of Characteristic Curves 52Figure 6-2.7 Variation in the Operating Point versus the Rotation Speed 53

    Figure 7-1.1 Cash Flow for an Overall Industrial Operation 58

    Figure 7-2.1 Cost Involved in Total Product Cost for a Typical Chemical Process Plant 70Figure 7-2.2 Break-even Chart for Chemical Processing Plant 71

    Figure 7-2.3: Project Cash Flow Diagram 72

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    8/99

    viii

    LIST OF TABLES

    Table 6-2.1 Main Types of Pumps 47Table 7-1.1: Cost indexes as Annual Averages 63

    Table 7-1.2 Typical Exponents for Equipment Cost vs. Capacity 64

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    9/99

    1

    UNIT 1METHODOLOGY OF THE DESIGN PROCESS

    IntroductionThis unit discusses the methodology of the design process and its application to thedesign of chemical manufacturing processes.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Explain chemical process design2. Distinguish between fixed and less rigid constraints3. Know what constitutes the design process4. List the basic components of a chemical manufacturing process

    SESSION 1-1 In this session we shall discuss what a chemical process design is,

    the constraints of the design problem, the components of the chemical manufacturing

    process and the difference between a continuous and a batch process.

    1-1.1 Introduction: Design is the synthesis of ideas to achieve a desired goal (product).

    The designer starts with an idea and proceeds to develop several alternative designs that

    he evaluates and finally settles on the one that satisfies his objective (goal).

    The search for alternatives: this step becomes necessary because the designer will be

    constrained by several factors.

    1-1.2 Constraints on a Design Problem

    1-1.2.1 Fixed/Rigid constraints: these are constraints the designer must live with outside

    his influence. E.g. physical laws, government regulations and standards. The fixed

    constraints define the outer boundary of all possible designs.

    1-1.2.2 Less rigid constraints: these are constraints the designer can manipulate inorder

    to arrive at the best design. E.g. materrials of construction, time. These are interrnal

    constraints over which the designer has some control.

    In summarry we have the following diagramatic sketch.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    10/99

    2

    Figure 1-1.1: Design Constraints

    1-1.3 The Design Process

    The design process can be shown in schematic form in Figure 1-1.2.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    11/99

    3

    Figure 1-1.2: The Design Process

    The diagram shows the design process as an iterative procedure because as the design

    proceeds the designer will be looking for information and ideas to refine the design.

    1-1.3.1 The Design objective

    In the particular case of a chemical process plant, the objective/goal is to satisfy the

    public need for a product. In large commercial organizations, this need is identified by

    the sales/ marketing department. Before starting to work, the designer should obtain

    complete information/background on the need for the product and its application

    areas/uses.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    12/99

    4

    1-1.3.2 Data collection

    To proceed with the design, the designer must assemble all the relevant facts and data

    required. For process design, the information should include process alternatives,

    equipment performances, physical property data. In large design companies, they have

    in house manuals containing all the process know how on which the design is based

    and preferred methods and data for the frequently used design procedures.

    1-1.3.3 Generation of possible designs

    At this stage the designer must come up with all possible solutions for analysis,

    evaluation and selection. To do this, he must rely on his own experience or that of others,

    using tried or tested methods.

    Chemical engineering projects can be divided into 3 types:

    1. Modification, additions to existing plant often undertaken by the plant design

    group.

    2. New production capacity to meet growing sales demand, and the sale of

    established processes by contractors. Repetition of existing designs, with only

    minor design changes.

    3. New processes, developed from laboratory research, through pilot plant, to a

    commercial process. Here most of the unit operations and process equipment willuse established designs.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    13/99

    5

    1-1.3.4 Selection

    The selection process can follow the following screening stages:

    Possible designs (credible)within the external constraints

    Plausible designs (feasible)- within the internal constraints

    Probable designslikely candidates

    Best designs (optimum)judged the best solution to the problem

    To select the best design from the probable designs, detailed design work and costing will

    be necessary.

    1-1.4 Chemical Manufacturing ProcessesThe basic components of a typical chemical process can be shown using the block

    diagram below.

    Figure 1-1.3: Anatomy of a Chemical Process

    Each block represents a stage in the overall process for producing a product from the raw

    materials. Each stage is a collection of equipment required to accomplish a defined task.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    14/99

    6

    Stage 1: Raw Material Storage

    Unless the raw materials are supplied as intermediate products from a neighboring plant,

    storage space is needed to hold several days or months supply. Types of storage required

    will depend on the nature of the raw materials, and the methods of delivery.

    Stage 2: Feed Preparation

    Some purification of the raw materials will be necessary to render them in a form

    required for feed to the reaction stage.

    Stage 3: Reactor

    In the reactor the raw materials are brought together under conditions that promote the

    production of the desired product. However by-products and unwanted compounds/

    impurities will also be formed.

    Stage 4: Product Separation

    After the reactor, the products and by-products are separated from any unreacted

    material. If in sufficient quantity, the unreacted material will be recycled to either the

    reactor directly or to the feed purification and preparation stage.

    Stage 5: Purification

    Before sale, the main product is purified to meet product specification. If the by-product

    is also produced in sufficiently large quantities, it must also be purified for sale.

    Stage 6: Product Storage

    Provision for product packaging and transport will be required. Besides some inventory

    of finished product must be held to match production with sales

    Ancillary Process

    In addition to the main process stages/ units, provision will have to be made for the

    supply of utility services, process water, cooling water, compressed air, steam. Facilities

    are required for maintenance, firefighting, offices, laboratories and accommodation.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    15/99

    7

    1-1.5 Continuous and Batch Processes

    Continuous processes are designed to operate 24 hours a day, 7 days a week, throughout

    the year (365 days). However down time is allowed for maintenance and process catalyst

    regeneration.

    Plant attainment: this is the percentage of the available hours in a year that the plant

    operates. This is usually 90-95%.

    1-1.5.1 Choice of continuous versus batch production

    The choice will not be clear - cut, however one can use as a guide the following rules:

    Continuous

    1. Production rate greater than 5*106 kg/h (5000tonnes/h)

    2. Single product

    3. No severe fouling

    4. Good catalyst life

    5. Proven process design

    6. Established market

    7. Cost can be reduced

    8. Less laborBatch

    1. Production rate less than 5*106 kg/h (5000tonnes/h)

    2. A range of products or product specifications

    3. Severe fouling

    4. Short catalyst life

    5. New product

    6. Uncertain design

    1-1.5.2 Organization of a chemical engineering design project

    The design work required in the engineering of a chemical manufacturing process plant

    can be divided into two broad phases:

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    16/99

    8

    Phase 1.Process Design

    This covers the steps from the initial selection of the process to be used, through to the

    issuing of the process flow-sheets; and includes the selection, specification, and chemical

    engineering design of equipment. In any organization, this phase is handled by the

    process design group composed of chemical engineers. The group is also responsible for

    the preparation of piping and instrumentation diagrams.

    Organization of a project group is shown in Figure 1-1.4 below.

    Figure 1-1.4: The Structure of a Chemical Engineering Project

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    17/99

    9

    Phase 2. The detailed mechanical design of equipment; the structural, civil and electrical

    design; specification and design of ancillary services. Other specialist groups will be

    responsible for cost estimation, and the purchase and procurement of equipment and

    materials.

    The sequence of steps in the design, construction and start up of a chemical process plant

    is shown diagrammatically in Figure 1-1.5.

    .

    Figure 1-1.5: Project Organization

    Project manager; a chemical engineer by training is responsible for the coordination of

    the project.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    18/99

    10

    SELF ASSESSMENT 1-1

    (a) Distinguish between Fixed and less rigid constraints

    (b) List the components of a basic chemical manufacturing process and in just two

    sentences explain the importance of each in the manufacturing process.

    (c) In a tabular form, list six differences between a continuous process and a batch

    process.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    19/99

    11

    UNIT 2CODES AND STANDARDS, DESIGN FACTORS, VARIABLE &

    MATHEMATICAL REPRESENTATION OF DESIGN PROBLEMS

    IntroductionThis unit discusses the codes & standards, design factors and variables and mathematicalrepresentation of the design problems.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Distinguish between codes and standards2. Understand the importance of design factors as a margin of safety

    in meeting design specifications3. Appreciate the importance of mathematical representation of the

    design problem

    SESSION 2-1 In this session we shall study the difference between codes and standards,

    design factors and their relation to equipment safety and the mathematical representation

    of the design problem.

    2-1.1 Codes and Standards

    The terms CODE and STANDARD are used interchangeably, though CODE should be

    reserved for a code of practices. That is a recommended design or operating procedure.STANDARD on the other hand refers to preferred sizes, eg. pipes, composition etc.

    In modern engineering practice we have standards and codes that cover various functions

    e.g

    1. Materials, properties and composition

    2. Testing procedures for performance, composition and quality

    3. Preferred sizes, eg tubes, plates, sections

    4. Design methods, inspection, fabrication

    5. Codes of practice, for plant operation and safety

    All developed countries have national organizations responsible for the issue and

    maintenance of standards for the manufacturing industries and for the protection of

    consumers.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    20/99

    12

    In the U.K:; British Standards Institution

    In the U.S; National Bureau of Standards

    They are responsible for coordinating information on standards. Standards are issued by

    the Federal State and various commercial organizations. The major ones of interest to

    chemical engineers are:

    American National Standards Institute (ANSI)

    American Petroleum Institute (API)

    American Society for Testing Materials (ASTM)

    American Society of Mechanical Engineers (ASME)

    International Organization for Standardisation (ISO) coordinates the publication of

    International Standards.

    In Ghana, there is no national standards organization to coordinate local standards for

    industries. However there are national standard organizations with standards for the

    protection of consumers eg. Standards Boards, Food and Drug Administration (FDA),

    and the Environmental Protection Agency (EPA).

    Equipment manufactures work together to produce standardized designs and size ranges

    for commonly used items; electric motors, pumps, pipes, and pipe fittings.

    2-1.2 Factors of Safety (Design Factors)

    Design is an inexact act; errors and uncertainties can arise in the design data available

    and in the approximations necessary in the design calculations. To meet design

    specifications, factors are included to give a margin of safety in the design so that the

    equipment will not fail to perform satisfactorily, and that it will operate safely.

    e.g. in a mechanical and structural design, the magnitude of design factors used to allow

    for uncertainties in material properties, design methods fabrication and operating loads

    are well established. In process design, design factors are used to give tolerances in the

    design e.g. process stream average flows calculated from material balances are often

    increased by a factor of 10%, to give some flexibility in process operation. This factor

    then sets the maximum flows for equipment, instrumentation and piping design.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    21/99

    13

    2-1.3 System of Units

    Chemical engineering uses a diversity of units from American and British engineering

    Systems, CGS (grain, centimeter, second)

    MKS( kilogram, meter, seconds)

    English and Americanpound mass (lb), foot, second or hours, pound force.

    If working in S. I units is preferred, data expressed in the American and British

    engineering systems can be converted to S.I units. Conversions factors are available in

    the literature.

    2-1.4 Mathematical Representation of the Design Problem

    A process unit e.g. distillation unit in a chemical process plant performs some operation

    on the inlet material stream to produce the desired outlet stream.

    Inlet stream Outlet stream

    In the design of such a unit, the design calculations model the operation of the unit. Thus

    the flow of materials is replaced by flow of information into the unit and flow of derivedinformation out of the unit.

    Input Output

    Information Information

    Process

    Unit

    Calculationmethod

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    22/99

    14

    Information flows are the values of the variables which are involved in the design.

    Example:

    Input stream Output stream

    variables variables

    Flow rate same as the input variables.

    Composition

    Temperature

    Pressure

    Enthalpy

    Composition, temperature, pressure are called intensive variables, i.e. independent

    of quantity of material flow (flow rate)(Nv).

    The constraints on the design will place restrictions on the possible values that

    these variables can take; for example the values of some of the variables will be

    fixed directly by process specification. The values of other variables will be

    determined by design relationships arising from constraints.

    Some of the design relationships will be in the form of explicit mathematicalequations (design equations): such as those arising from material and energy

    balances, thermodynamic relationships, and equipment performance parameters.

    Other relationships will be less precise such as those arising from the use of

    standards and preferred sizes and safety considerations (Nr).

    The difference between the number of variables in the design and the number of

    design relationships is called the number of degrees of freedom.

    If Nvthe number of possible variables in a design problem

    Nrthe number of design relationships

    Nd = NvNr

    Nd = number of degrees of freedom

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    23/99

    15

    Case 1.

    If Nv=Nr implies Nd = 0; this implies that there is only one unique solution to the

    problem. The problem is not a true design problem and no optimization is possible.

    Case 2

    Nv is less than Nr, Nd is less than 0; this implies that the problem is over defined, and

    only the trivial solution is possible.

    Case 3

    Nv >Nr, Nd > 0; implies there is an infinite number of possible solutions. However for a

    practical problem, there will be only a limited number of feasible solutions. Nd represents

    the number of variables which the designer must assign values to solve the problem.

    EXAMPLE 2-1.1: Consider a single phase stream (liquid/vapour) containing C

    components.

    Input OutputProcess Unit

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    24/99

    16

    Note

    (1) The sum of the mass/mol fractions equal 1.

    (2) The enthalpy is a function of stream composition, temperature and pressure.

    Therefore, Degrees of Freedom, Nd = NvNr =(C+4)(2) = C+2

    Specifying C+2 variables completely defines the stream.

    EXAMPLE 2-1.2: Flash distillation / Equilibrium distillation

    In this process unit, a feed is passed into a still (fractionating column), where part is

    vaporized, and the vapour remaining in contact with the liquid. The mixture of vapor and

    liquid leaves the still and is separated so that the vapour is in equilibrium with the liquid.

    Where, F= Stream flow rate, P= pressure, T=temperature, xi= concentration of

    component i, q = heat input.

    Surfixes, 1= inlet; 2=outlet vapor; 3 =outlet liquid

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    25/99

    17

    Note: 1. given the temperature and pressure, the concentration of any component in the

    vapor phase can be obtained from the concentration in the liquid phase ( v-l-e data)

    2. An equilibrium separation implies that the outlet streams and the still are the

    same pressure and temperature.

    This implies that P2 = P (1) T2 = T (3)

    P3 = P (2) T3 = T (4)

    Gives 4 equations.Degrees of freedomNd(No of degrees of freedom)=Nv - Nr= (3C + 9) - (2C + 5) = C + 4

    Though the total degrees of freedom calculated is (C+4), some of the variables will be

    fixed by the process conditions and will not be free for the designer to select as design

    variables. For example: the flash distillation unit will normally be one unit in a process

    system and the feed composition and feed conditions will be fixed by the upstream

    process. Hence defining the feed, fixes (C+2) variables and the designer is left with,

    (C+4)-(C+2) = 2

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    26/99

    18

    2-1.5 Selection of Design Variables

    To solve a design problem, the designer has to decide which variables are to be chosen as

    design variables, i.e the ones he can manipulate to produce the best design. This choice is

    crucial to enable the simplification of the calculations.

    Example: Flash distillation problem in the previous example.

    For a binary mixture, C=2; this implies Nd=C+4=6

    If the feed stream flow, composition, temperature, pressure are fixed by upstream

    conditions, then the number of design variables is Nd=6-(C+2)=6-4=2. This implies, the

    designer is free to select 2 variables from the remaining variables to proceed with the

    calculation of the outlet stream composition and flows.

    Scenerio 1

    Suppose you select the still pressure implies for a binary system, vapour-liquid

    equilibrium (V-L-e) relationship is determined, and one outlet stream flow rate, then the

    outlet compositions can be calculated by the simultaneous solution of mass-balance and

    (v-l-e) relations.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    27/99

    19

    Scenerio 2

    If you select the still pressure and the liquid outlet stream composition, then the

    simultaneous solution of the mass balance and the v-l-e relationship will not be

    necessary. Following the procedure below, one can calculate the stream compositions.

    1. Specify P determines the v-l-e curve from experimental data

    2. Knowing the outlet liquid composition, the outlet vapor composition can be

    calculated from the v-l-e.

    3. Knowing the feed and outlet compositions, and the feed flow rate, the outlet

    stream flows can be calculated from a material balance.

    4. An enthalpy balance gives the heat input required.

    SELF ASSESSMENT 2-1

    (a) List 3 American organizations responsible for coordinating information on standards.

    (b) List 3 national standard organizations with standards for the protection of consumers.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    28/99

    20

    UNIT 3OPTIMIZATION AND BATCH PRODUCTION PROCESS

    Introduction

    This unit discusses batch production processes and the importance of optimization.

    Learning ObjectivesAfter reading this unit, you should:

    1. Appreciate the importance of optimization in plant design2. Understand the process of batch production

    SESSION 3-1 In this session we shall discuss the steps involved in optimizing the design

    of a chemical process plant. Further, we shall

    3-1.1 Introduction

    Optimizing the design of a chemical process plant is a foreboding task. This can be

    achieved by subdividing the plant into subunits and optimizing each subunit. However

    this does not result in the optimal design of the whole plant because the optimization of

    each subunit is at the expense of the other.

    The general procedure for optimizing process units and equipment design:

    Step1: the first step is to clearly define the objective. i.e the criteria to be used for

    measuring the performance of the system. For a chemical process plant, the overall

    objective is tomaximize profit.

    This overall objective can be broken down into sub objectives such as; minimize

    operating cost, minimize capital investment, maximize yield of the product, reduce labour

    requirements, reduce maintenance, operate safely.

    Step 2: the second step is to determine the objective function; the system of equations

    and other relationships, which relate the objectives with the variables to be manipulated

    to optimize the function.

    Step 3: this step is to find values of the variables that give the optimum value of objective

    function i.e maximum or minimum. The best technique to be used will depend on the

    complexity of the system and the type of mathematical model used to represent it.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    29/99

    21

    3-1.2 Simple Models

    If the objective function can be expressed as a function of one variable (single degree of

    freedom), the function can be differentiated or plotted to find the maximum or minimum.

    This situation arises only for exceptional cases. In most practical situations, the numbers

    of variables exceed the number of relationships.

    Example of a simple model: Determine the optimum proportions for a closed cylindrical

    container.

    D

    L

    The surface area A in terms of the dimensions is:

    ( )

    VV4VLabove(2)inDngsubstituti

    VD

    VDD

    D

    4V

    zerotoequationabovethesetweDoptimumthefinding

    (3)DD

    4V

    (D)fatingdifferenti

    2

    D

    D

    4Vf(D)

    haveweD,variableoneoftermsinfunctionobjectivethegres

    (2)D

    4VLL

    4

    DV

    have,we(V)volumegivenafor

    (1)2

    DLDLD,fisfunctionobjectivethe

    DDLDDLA

    3

    2

    2

    2

    2

    31

    32

    31

    '

    22

    44

    440

    ,

    ;

    sinexp

    242

    =

    =

    =

    ==+

    +

    =

    +

    =

    =

    =

    +=

    +=

    +=

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    30/99

    22

    For a cylindrical container, the minimum surface area to enclose a given volume is

    obtained when the length (height) is made equal to the diameter.

    In practice, when the cost is the objective function; L=2D; this is because the cost must

    include that of forming the vessel, making the joints in addition to the cost of the

    material.

    3-1.3 Multiple Variable Systems

    The general optimization problem can be represented mathematically as:

    variablesthearevvvvandfunctionobjectivefwhere

    vvvvff

    n

    n

    ,.......,,

    ),.......,,(

    321

    321

    =

    In a design situation, there will be constraints on the possible values of the objective

    function due to constraints on the variables.

    - Equality constraints are expressed by equations of the form

    0),.......,,( 321 == nmm vvvv

    - Inequality constraints are expressed by equations of the form

    pnpp Pvvvv = ),.......,,( 321

    Optimization of the problem involves finding values for the variables nvvvv ,.......,, 321

    that will optimize the objective function ( i.e give maximum or minimum values within

    the constraints).

    3-1.4 Methods of Analysis:

    a. Analytical method: objective functions can be expressed as a mathematical function;

    use the methods of calculations to find maximum or minimum values.

    - For practical situations where the values of the variables are subject to constraints,

    the optimum of the constrained objective function will not necessarily occur

    where the partial derivatives of the objective function are zero.

    e.g.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    31/99

    23

    Figure 3-1.1: Effect of Constraints on the Optimum of a Function

    - The method of Lagranges undetermined multipliers is a useful analytical

    technique for dealing with problems that have equality constraints (fixed designvalues).

    b. Search Methods: Relationships between variables and constraints that arise in

    practical design problems are such that analytical methods are not feasible; hence the use

    of search methods.

    For single variable problems where the objective function is unimodal, the simplest

    approach is to calculate the value of the objective function at uniformly spaced values of

    the variable until a maximum or minimum is obtained.

    Figure 3-1.2 Yield as a Function of Reactor Temperature and Pressure

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    32/99

    24

    3-1.5 Other Optimization Methods

    - Linear programming; a technique used when the objective function and constraints can

    be expressed as a linear function of the variables.

    - Dynamic programming; used for the optimization of large systems.

    3-1.6 Batch Production Process

    - Productive period: this is the period when product is being produced

    - Nonproductive period; this is the period when the product is discharged and

    equipment prepared for the next batch.

    - Total batch time: productive period + nonproductive period

    - The rate of production is determined by the total batch time as follows:

    Batches per year = 8760 x Plant attainment

    Total batch time (batch cycle time)

    Annual production rate = (quantities produced per batch)x(batches per year)

    Cost per unit of production= annual cost of production

    Annual production rate

    SELF ASSESSMENT 3-1

    A rectangular tank with a square base is constructed from 5 mm steel plates. If thecapacity required is eight cubic meters. Determine the optimum dimensions if the tank

    has a closed top.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    33/99

    25

    UNIT 4PROCESS SYNTHESIS

    IntroductionThis unit discusses the synthesis of chemical processes.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Explain process synthesis2. Define and explain heuristics

    SESSION 4-1 In this session we shall discuss process synthesis and the importance of

    heuristics in chemical process optimization.

    4-1.1 Introduction: process synthesis aims at the optimization of the logical structure of

    a chemical process; specifically the sequence of steps; reaction, separation (distillation,

    extraction etc), the source and destination of recycle streams.

    The logical structure of a chemical process: Given the following;

    - Raw materials, required products, allowed byproducts, a set of unit operations for

    consideration, cost factors for materials and unit operations required to generate

    and rank in order of preference and feasible chemical plant flow sheets.

    Approach 1. Combinatorial algorithms are used to find all feasible flow sheets contained

    in a toolkit of raw materials and operating steps. The flow sheets are then reviewed and

    optimized based on performance, economic and safety criteria.

    Approach 2. Heuristic rules based on experiences that are used for the selection and

    positioning of processing operations as flow sheets are assembled.

    4-1.2 Raw Materials and Chemical Reactions

    Heuristic 1: select raw materials and chemical reactions to avoid or reduce the

    handling and storage ofhazardous and toxic chemicals.e.x. Manufacture of ethylene glycol

    (2)OHCHHOCHOHOHC

    (1)OHCOHC

    ++

    ++

    22242

    42242 21

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    34/99

    26

    - Both reactions are extremely exothermic, therefore they need to be controlled

    carefully. Such processes are designed with two reaction steps with storage of the

    intermediate, to enable continuous production, even when maintenance problems

    shut down the first reaction operation.

    Alternative to the 2-step example process:

    1. Use chlorine and caustic in a single reaction step, to avoid the intermediate:

    NaClOHCHHOCHaqNaOHClCHCH 2)(2 22222 +++=

    2. Use the 2-step reaction with the following modifications:

    - As ethylene-oxide is formed, react it with carbon dioxide to form ethylene

    carbonate, a much less active intermediate that can be stored safely. This can then

    be hydrolysed to form the required ethylene glycol product

    2222343

    343242

    42242 21

    COOHCHHOCHOHOHC

    OHCCOOHC

    OHCOHC

    ++

    +

    ++

    Heuristic 2: Distribution of Chemicals

    Use an excess of one chemical reactant in a reaction to completely consume a second

    valuable, toxic or hazardous reactant.

    e.x. use an excess of ethylene in the production of Dichloroethane.

    C2H4

    Cl C2H4Cl2 +C2H4

    C2H4

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    35/99

    27

    Heuristic 3: when nearly pure products are required, eliminate the inert species before

    the reaction operations, when the separations are easily accomplished, or when the

    catalyst is adversely affected by the inert.

    Heuristic 4: introduce liquid or vapour purge streams to provide exit for species that;

    - Enter the process as impurities in the feed

    - Produced by irreversible side reactions

    e.x. Ammonia, NH3 synthesis loop

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    36/99

    28

    Heuristic 5: Do not purge valuable species or species that are toxic and hazardous, even

    in small concentrations

    - Add separators to recover valuable species

    - Add reactors to eliminate toxic and hazardous species

    e.g. catalytic converter in car exhaust

    Heuristic 6: For competing series or parallel reactions, adjust temperature, pressure, and

    catalyst to obtain high yields of desired products. In the initial distribution of chemicals,

    assume that these conditions can be satisfied; obtain kinetic data, and check this

    assumption before developing a base-case design.

    e.x. Manufacture of alkyl-chloride

    HClClCHCHCHClClCHClCHCH

    kk

    Cl

    HClClCHCHCHClCHCHCH

    2

    k

    +=

    ++=+=

    223

    3

    2

    222321

    Dichloropropane dichloropropene

    This is a series/parallel reaction;

    - for each reaction, obtainR

    EKH oR ,,

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    37/99

    29

    For each reaction, obtain kinetic data and examine the dependency of reaction rate on

    temperature; implies RTE

    oekk

    =

    Since for multiple reactions, high temperature favors the reaction of higher activation

    energy and vice versa.

    Heuristic 7: for reversible reactions, consider conducting them in a separation device

    capable of removing products, and hence driving the reaction to the right.

    e.g. manufacture of ethyl-acetate (ethyl ethanoate) using reactive distillation

    Conventionally, this will call for the reaction:

    EtOH + HOAc EtOAc +H2O

    followed by separation of products using a sequence of separation of towers, using areactive distillation:

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    38/99

    30

    Heuristic 8: Separations : separate liquid mixtures using distillation, stripping towers

    and liquid-liquid extractors.

    Heuristic 9: attempt to condense vapour mixtures with cooling water, then use heuristic

    8.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    39/99

    31

    Heuristic 10: Heat Transfer in reactors: to remove highly exothermic heat of reaction,

    consider the use of excess reactant, an inert diliuent.

    Heuristic 11: For less exothermic heat of reaction, circulate reactor fluid to an external

    cooler, or use a jacketed vessel or cooling coils.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    40/99

    32

    Heuristic 12: Pumping and Compression: To increase the pressure of a stream, pump a

    liquid rather than compress a gas: i.e condense a vapor as long as refrigeration ( and

    compression) is not needed before pumping.

    Instead of:

    Compressors have large capital cost and consume a lot of power.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    41/99

    33

    4-1.3 Summary of Process Design Heuristics

    The discussion focused on the following:

    - understanding the importance of selecting reaction paths that do not involve toxic

    or hazardous chemicals.

    - Be able to distribute the chemicals in a process flowsheet, to account for the

    presence of inert species, to purge species that would otherwise build up to

    unacceptable concentrations, to achieve a high selectivity of the desired products.

    - Apply heuristics in in selecting separation processes to separate liquids, vapours,

    and vapour-liquid mixtures.

    - Understand the advantages of pumping a liquid rather than compressing a vapor.

    4-1.4 Heuristics in Equipment Design

    1. Equipment Size

    Need information on the required throughput to determine vessel size

    - General guidelines for vessel size

    o Height: 2-10 m

    o L/D: 2-5m

    - Towers/ Columns

    o

    Height: 2-50mo L/D: 2-30m

    Note: Do not specify units outside these ranges

    2. Heat Exchangers

    Several kinds are used

    - Area: 10-1000m2

    - For shell and tube (tubular)

    o Tube diameter: 1-2 cm

    o Tube length: 2-6m

    o Shell diameter:0.3-1m

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    42/99

    34

    - Plate and frame

    Newer technology- thin, gasketed plates separate hot and cold fluids.

    Advantage: more compact and very efficient

    3. Heat transfer considerations

    - Minimum temperature approach: for fluids 10oC and for refrigerants, 5

    oC

    - Cooling water in: 30oC; Cooling water out: 45

    oC

    - Equipment heat transfer(overall) coefficient in decreasing order of magnitude

    Reboiler>Condenser>Liquid-to-Liquid>gas-to-gas

    - Heat Exchangers:tlm < 100oC

    4. Towers/ Columns

    Tower operating pressure is usually determined by the temperature of condensing

    medium or maximum allowable reboiler temperature

    Sequencing multiple towers: typically

    - Do easy separation first and leave difficult ones for last

    - If relative volatilities of all species are close , remove one-by-one from overhead

    - When volatilities are close but feed concentrations vary, remove high

    concentrations first. Distillation operating conditions

    - Economically reflux ratio is typically 1.2-1.5 times Lmin

    - Optimum number of theoretical trays trays is typically 2 times Nmin

    - Find Nmin from Fenske-Underwood equation

    Tower design

    - Tray spacing are typically 20-24

    - Pressure drop typically 0.1psi per tray

    - Tray efficiencies: 60-90% for gas absorption and stripping

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    43/99

    35

    5. Process Conditions: General Guidelines

    (a) High Pressure

    To achieve a high pressure in a process:

    - For a liquid use a pump; for a vapour first condense it and pump it into an

    evaporatior

    - For a gas compression; P/Po

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    44/99

    36

    (c) Low Temperature

    Operate at low temperature to achieve the following:

    o Slow reaction rate

    o Prevent thermal sensitive species from degradation

    o Change thermodynamics

    Achieve a high temperature in a process by the following means:

    o Using a heat exchanger with the following fluids( cold steam)

    Cooling tower water

    Chilled water

    Active refrigeration

    SELF ASSESMENT 4-1

    In the manufacture of ethylene glycol, a two step reaction process is used; the first step isthe formation of the intermediate ethylene oxide which can be stored, followed by itshydrolysis to form the ethylene glycol. Since both reactions are extremely exothermicand explosive, show with balanced chemical equations a safer two step approach after theinitial production of ethylene oxide.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    45/99

    37

    UNIT 5PROCESS SIMULATION

    IntroductionThis unit discusses the simulation of a chemical process.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Explain what process simulation is.2. Identify the types of process simulations

    SESSION 5-1 In this session we shall discuss the importance of process simulations, the

    various types of simulations available and the importance of mathematical models in

    process simulation.

    5-1.1 Introduction

    - Process simulation is the act of representing some aspects of the real world by

    numbers or symbols that may be easily manipulated to facilitate their study.

    - The important step in process simulation is the representation of that aspect of the

    real world to be studied in terms of a mathematical model.

    - With respect to chemical engineering, the real world is a chemical process

    described by a process flow sheet. Therefore process simulation is used to solve

    problems related to the process flow sheet, i.e process design, process analysis,

    process control etc.

    - The mathematical model that simulates an aspect of the process needs an

    appropriate method of solution.

    - A process simulation is a computer program developed to solve the model and

    study its behavior by manipulating the model parameters.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    46/99

    38

    5-1.2 Process Simulator

    Computational package that enables predictions of the process behavior

    Inputs for the package are:

    Basic engineering relationships such as:

    - Mass and energy balances

    - Phase and chemical equilibrium

    - Flowsheet topography

    Uses are:

    - For design of new plants

    - Increase profitability in existing plants

    - Run many possible cases

    - Sensitivity studies, and optimization

    Accuracy depends on the use of

    - Reliable thermodynamic and property data

    - Realistic operating conditions

    - Rigorous equipment models

    5-1.3 Types of Process Simulation

    There are several commercial packages. E.g Aspen Plus, Chemcad, Hysis Pro/II.Common features of all these are:

    1. Database of hundredsthousands( a large number) of compounds

    2. A parameter library to compute /estimate properties of these compounds

    3. Flowsheet builder- graphical interface that enables units to be defined and

    connected.

    4. Thermo Solver; computes phase equilibrium and thermodynamic properties given

    the database

    5. Unit operations Solver: short cut and rigorous solvers for equipment

    6. Overall flowsheet solver; mathematical convergence of the flowsheet

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    47/99

    39

    5-1.4 Unit Operations Solvers; e.g Reactors

    - specifies the reaction stoichiometry, temperature, pressure and conversion

    - when the reaction is equilibrium limited, specifies the stoichiometry , the approach to

    equilibrium and equilibrium constants

    - for the reaction involved, specifies the kinetic expression, reactor type and enables the

    reactor size calculation.

    - distillation columns

    - Uses the Feuske, Underwood methods to provide a good initial guess for subsequent

    calculations

    - for rigorous plate-by-plate approach, it solves simultaneously, material and energy

    balance equations, and VLE relations for each plate.

    5-1.5. Uncertainty and Sensitivity Issues

    It is important to be able to quantify the uncertainty of results:

    - Determine the probability of accuracy of results

    - Determine what part of results obtained is most likely to be incorrect, and

    estimate error range

    - Sensitivity issues; in cost estimation and profitability studies, estimate the

    sensitivity of the results to variations in capital cost, operating cost etc.Other causes of uncertainty of results using a simulator.

    - Thermo model used

    - Physical properties data

    - Convergence tolerance

    - Simulation method ( simulator)

    Because there are disturbing variations between different process simulators using

    the same models.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    48/99

    40

    - What can we do?

    o Estimate uncertainties by performing simulations using a range of

    parameters, different models.

    o Determine the sensitivity of results

    o Use statistical methods to design experiments over ranges of parameters

    and the results will provide confidence limits

    o Ultimately, final designs should be tested on pilot studies.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    49/99

    41

    UNIT 6FLOW SHEETING, PIPING AND INSTRUMENTATION

    IntroductionThis unit discusses flow sheeting, piping and instrumentation in chemical process design.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Appreciate the importance of flow sheet in chemical process design2. Understand why instrumentation in plant design is critical3. Acknowledge the processes involved in valves and pumps selection

    SESSION 6-1 In this session we shall study the essence of flow sheets in process design.

    We shall also look at piping and instrumentation diagram and the types of valves used in

    a process plant design.

    6-1.1 Introduction

    Industrial equipment are always arranged and interconnected in a certain fashion. The

    process flow sheet gives a pictorial representation of the various equipment selected to

    carry out the process. The process flow sheet always convey information on the operating

    conditions, stream flow-rates and composition. The information included in a typical

    flow sheet is either essential or optional. An example flow sheet is shown in Figure 6-1.1

    Figure 6-1.1: Flow-sheet of Simplified Nitric Acid Production Process

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    50/99

    42

    The essential information included in the flow-sheet are;

    1. Stream composition, either:

    The flow-rate of each individual component, kg/h, which is preferred, or

    The stream composition as a weight fraction.

    2. Total stream flow-rate, kg/h.

    3. Stream temperature, degrees Celsius preferred.

    4. Nominal operating pressure (the required operating pressure).

    Optional information

    1. Molar percentages composition.

    2. Physical property data, mean values for the stream, such as:

    Density

    Viscosity

    3. Stream name, a brief, one or two-word, description of the nature of the stream

    4. Stream enthalpy, kJ/h.

    Figure 1 below shows the information included in a polymer production process.

    6-1.2 Piping and Instrumentation Diagram (P&ID)The piping and instrumentation diagram shows the engineering details of the equipment,

    instruments, piping, valves and fittings; and their arrangement.

    Figure 6-1.2: Polymer Production Diagram

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    51/99

    43

    In the polymer production flow sheet above, all the following information should be

    included in the P&ID:

    1. All process equipment identified by an equipment number. The equipment should be

    drawn roughly in proportion, and the location of nozzles shown.

    2. All pipes, identified by a line number. The pipe size and material of construction

    should be shown. The material may be included as part of the line identification number.

    3. All valves control and block valves, with an identification number. The type and size

    should be shown. The type may be shown by the symbol used for the valve or included in

    the code used for the valve number.

    4. Ancillary fittings that are part of the piping system, such as inline sight-glasses,

    strainers and steam traps; with an identification number.

    5. Pumps, identified by a suitable code number.

    6. All control loops and instruments, with an identification number.

    For simple processes, the utility (service) lines can be shown on the P and I diagram.

    For complex processes, separate diagrams should be used to show the service lines, so the

    information can be shown clearly, without cluttering up the diagram. The service

    connections to each unit should, however, be shown on the P and I diagram.

    6-1.3 Valve Selection

    Control of flow in lines and provision for isolation of equipment when needed are

    accomplished with valves. Depending on primary function, valves are classified as:

    1. Shut-off valves (block valves), whose purpose is to close off the flow.

    2. Control valves, both manual and automatic, used to regulate flow.

    Figure 6-3 shows the valves commonly encountered in industry.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    52/99

    44

    Figure 6-1.3: Commonly used Valves

    The main types of valves used are:

    Gate Figure 6-1.3a

    Plug Figure 6-1.3b

    Ball Figure 6-1.3c

    Globe Figure 6-1.3d

    Diaphragm Figure 6-1.3e

    6-1.3.1 Gate valves

    In gate valves, the flow is straight through and is regulated by raising or lowering the

    gate. The majority of valves in the plant are of this type. In the wide open position they

    cause little pressure drop.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    53/99

    45

    6-1.3.2 Globe valves

    In globe valves, the flow changes direction and results in appreciable friction even in the

    wide open position. This kind of valve is essential when tight shutoff is needed,

    particularly of gas flow.

    The ball and plug valves are also frequently used for the purpose of flow shutoff.

    Butterfly valves are often used for the control of gas and vapor flows. Automatic control

    valves are basically globe valves with special trim design.

    SESSION 6-2: In this session we shall discuss the classification of pumps and factors to

    consider in pump selection.

    6-2.1 Introduction of Pumps

    They are mechanical devices used to increase the energy of a liquid stream flowing in a

    closed conduit or pipe. This energy may be used to increase the velocity (move the fluid),

    the pressure or the elevation of the fluid.

    6-2.2 Classification of PumpsPumps are generally classified into two main categories namely:

    Centrifugal pumps

    Positive displacement pumps

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    54/99

    46

    Table 6-2.1: Main Types of Pumps

    Category Types Structure

    Centrifugal Single-stage

    Multi-stage

    Volute

    Diffuser

    Regenerative

    Vertical

    Hellico-centrifugal

    Axial flow

    Positive

    displacement

    Rotary Gear

    Screw

    Vane

    Reciprocating Piston

    Diaphragm

    Plunger

    There are many subgroups of pumps as indicated in Table 6-2.1.

    6-2.3 Factors to Consider in Pump Selection

    Capacity (flow rate in m3

    /h)

    The pressure head that is generated by the pump

    The type of liquid pumped (its viscosity and vapour pressure under inlet

    conditions)

    An initial selection is generally made based on the first two criteria mentioned, i.e. the

    capacity and the pressure generated.

    The centrifugal pump is often the only possible choice for high capacities whereas

    positive displacement pumps are better suited to generating high pressure heads.

    Other criteria such as the viscosity of the liquid can modify this initial choice. A positive

    displacement pump is generally recommended to pump liquids with a viscosity higher

    than 2000 cP. Figure 6-2.1shows the approximate range of operation generally covered

    by the main types of pump mentioned above.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    55/99

    47

    Figure 6-2.1: Approximate Range of Operation for the Three Main Types of Pump

    6-2.4 Centrifugal Pumps

    Basically consists of an impeller equipped with radial vanes rotating inside a shell called

    the pump casing. It works by the transfer of centrifugal force of the rotating impeller into

    kinetic energy of the liquid. This energy is then converted into pressure when the fluid

    velocity decreases.

    6-2.4.1 Effective characteristic curves

    A centrifugal pump is characterized by 4 basic curves, all of which are expressed versus

    the flow rate as shown in Figure 6-2.2.

    A. The head generated

    B. The mechanical/hydraulic conversion efficiency

    C. The mechanical power input consumed at the shaft

    D. The pump suction capacity or NPSH.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    56/99

    48

    Figure 6-2.2: Basic Curves Characterizing a Centrifugal Pump.

    6-2.4.2 Design parameters of centrifugal pumps

    - The rotation speed

    - The number of impellers

    - The impeller diameter

    - The impeller design

    6-2.4.3 Operating point

    The pressure head HA required by the installation is represented by the system curve

    versus flow rate, Q. It is the sum of the static and dynamic heads of the installation as

    shown in Figure 6-2.3. The static heads are independent of the flow rate and include

    differences in height and pressure between the unit inlet and outlet. The dynamic heads

    correspond to pressure drops and are proportional to the square of the flow rate.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    57/99

    49

    Figure 6-2.3: Curve Characteristic of the System.

    A centrifugal pump adjusts itself on an operating point B, corresponding to the

    intersection between the Q/H curve of the pump and the HA curve of the system (Figure

    6-2.4). A variation in the operating point (and therefore in the flow rate and the head) can

    be obtained by a physical modification in the pump, but also by modifying its speed or

    the system curve, usually by means of a valve.

    Figure 6-2.4: Variation of Operating Point by means of a Valve.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    58/99

    50

    6-2.4.4 Q/H Curve versus Technical Choices

    1. Basic choices; concept of specific speed

    The number Nq, called the specific speed, allows all centrifugal pumps to be compared

    with one another. It is calculated from the following expression:

    43

    60H

    QNNq =

    With:

    N = rotational speed in rpm

    Q= flow rate the best efficiency in m3/h (through one eye if double-suction impeller)

    H= head in m generated at the best efficiency (for one stage)

    For the same specific speed, the hydraulic designs will be similar on varying scales. The

    choice of Nq is a major parameter in impeller hydraulic design (Figure 6-2.5). The

    specific speed also considerably influences the best efficiency achievable by a pump. If

    high pressure is required, a compromise will have to be found between a reasonable

    number of stages and an acceptable number efficiency.

    Figure 6-2.5: Variation in Specific Speed versus the Type of Impeller used.

    2. Choice of Design: Concept of Q/H Curve Slope

    For a given hydraulic choice, the different design parameters, in particular the number of

    vanes can modify the curve shape downward, flat or bell-shaped (Figure 6-2.6). These

    curves should be considered according to the requirements of the resisting network. Bell-

    shaped curves in particular, should be avoided for pumps that have to work in parallel

    (risk of instability).

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    59/99

    51

    Figure 6-2.6: Different Types of Characteristic Curves

    6-2.4.5 Choice of Rotation Speed

    The rotation speed is a dominant parameter for the characteristic curve of a centrifugal

    pump. Figure 6-2.7 shows how the operating point varies with speed. The flow rate varies

    linearly with speed:

    1

    212N

    NQQ =

    The head generated varies with the square of the speed:

    2

    1

    212

    =

    N

    NHH

    As a result, the power absorbed varies with the cube of the speed

    3

    1

    212

    =

    N

    NPP

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    60/99

    52

    Figure 6-2.7: Variation in the Operating Point versus the Rotation Speed.

    6-2.4.6 Suction Conditions: Concept of NPSHVapour pressure

    For a given temperature, each liquid has a specific boiling pressure, called the vapour

    pressure Tv. if the pressure at one point in the liquid becomes less than T v, the liquid

    vaporizes instantly.

    Cavitation

    The lowest static pressure inside a centrifugal pump is located at the impeller inlet. If

    vaporization begins at this point, the liquid will be repressurized nearby downstream. The

    bubbles formed condense by collapsing suddenly, most often near a wall. This very noisy

    phenomenon is called cavitation. The head generated by the pump and the absorbed

    power then drop, the vibrations and noise increase and erosion can be observed, mainly in

    the impeller, in the form of characteristic pits. If the pump is kept working under these

    conditions, permanent damage may occur.

    Required NPSH

    To prevent cavitation, the total liquid pressure at the inlet must be such that no

    vaporization can occur. The minimum value depends on the pump design

    Available NPSH

    It is the pressure available to force a given flow through the suction piping into the pump.

    This is a function of the system. It is easily calculated with the formula below.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    61/99

    53

    =

    + ( )

    EXAMPLE 6-1.1: Pressure drop calculation

    A pipeline connecting two tanks contains four standard elbows, a plug valve that is fully

    open and a gate valve that is half open. The line is commercial steel pipe, 25mm internal

    diameter, length120m. The properties of the fluid are: viscosity 0.99mNm-2s, density

    998kg/m3.Calculate the total pressure drop due to friction when the flow rate is 3500

    kg/h.

    SOLUTION 6-1.1

    Cross-sectional area of pipe = ( ) 2323 10491.010254

    m =

    Fluid velocity, u = sm/98.1998

    1

    10491.0

    1

    3600

    35003

    =

    Reynolds number, Re = ( )

    4

    3

    109.9

    102598.1998

    4105900,49 ==

    Absolute roughness commercial steel pipe = 0.046mm

    Relative roughness = 0018.01025

    046.03=

    , round to 0.002

    From friction factor chart, f = 0.0032

    Fitting/valve Number of velocity

    heads, K

    Equivalent

    pipe diameters

    Entry

    Elbows

    Globe valve, open

    Gate valve, open

    Exit

    0.5

    (0.84)

    6.0

    4.0

    1.0

    25

    (404)

    300

    200

    50

    Total 14.7 735

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    62/99

    54

    Method 1, velocity heads

    A velocity head mg

    u20.0

    8.92

    98.1

    2

    22

    =

    = of liquid,

    Head loss = 0.20 14.7 = 2.94m

    As pressure = 2.94 998 9.8 = 28,754 N/m2

    Friction loss in pipe,2

    98.1998

    1025

    1200032.08

    2

    3

    = fP

    = 240,388 N/m2

    Total pressure = 28,754 + 240,388 = 269,142 N/m2 = 270 kN/m2

    Method 2, equivalent pipe diameters

    Extra length of pipe to allow for miscellaneous losses

    = 735 25 10-3

    = 18.4 m

    So total length for P calculation = 120 + 18.4 m

    2

    98.1998

    1025

    1380032.08

    2

    3

    = fP

    = 277 kN/m2

    Note: the two methods will not give the same results. The method of velocity heads is the

    more fundamentally correct approach. But the use of equivalent diameters is easier to

    apply and sufficiently accurate for use in design calculations.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    63/99

    55

    SELF ASSESSMENT 6-1

    A process fluid is pumped from the bottom of one distillation column to another, using acentrifugal pump. The line is standard commercial steel pipe 75 mm internal diameter.From the column to the pump inlet the line is 25 m long and contains six standard elbowsand a fully open gate valve. From the pump outlet to the second column the line is 250 m

    long and contains ten standard elbows, four gate valves (operated fully open) and a flow-control valve. The fluid level in the first column is 4 m above the pump inlet. The feedpoint of the second column is 6 m above the pump inlet. The operating pressure in thefirst column is 1.05 bara and that of the second column 0.3 barg. Determine the operatingpoint on the pump characteristic curve when the flow is such that the pressure drop acrossthe control valve is 35 kN/m

    2. The physical properties of the fluid are: density 875 kg/m

    3,

    viscosity 1.46 mNm-2s.Pump characteristicFlow-rate, m3/h 0.0 18.2 27.3 36.3 45.4 54.5 63.6Head, m of liquid 32.0 31.4 30.8 29.0 26.5 23.2 18.3

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    64/99

    56

    UNIT 7PROCESS ECONOMICS: COST ESIMATION

    Introduction

    This unit discusses the estimation of capital investment, total product cost and thedetermination of breakeven point.

    Learning ObjectivesAfter reading this unit, you should be able to:

    1. Define total capital investment2. Apply the Marshall & Swift cost index and capacity ratio to estimate

    equipment cost3. Distinguish between fixed capital and working capital4. Define turnover ratio

    SESSION 7-1 In this session we shall discuss the estimation of capital investment.

    Further we shall discuss fixed capital investment, working capital, cost indices and turn-

    over ratio.

    7-1.1 Cost Estimation

    An acceptable plant design must present a process that is capable of operating under

    conditions which will yield a profit. Since net profit equals total income minus all

    expenses, it is essential that the chemical engineer be aware of the many different types

    of cost involved in manufacturing process. Capital must be allocated for direct plant

    expenses, such as those for raw materials, labor and equipment. Besides direct expenses,

    many other indirect expenses are incurred and these must be included if a complete

    analysis of the total cost is to be obtained. Examples of these indirect expenses are

    administrative salaries, product-distribution cost, and cost for interplant communications.

    A capital investment is required for any industrial process, and determination of the

    necessary investment is an important part of a plant-design project. The total investmentfor any process consist offixed-capital investment for physical equipment and facilities

    in the plant plus working capital which must be available to pay salaries, keep raw

    materials and products on hand and handle other special items requiring a direct cash

    outlay.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    65/99

    57

    Thus in an analysis of cost in industrial processes, capital investment costs,

    manufacturing costs, and general expenses including income taxes must be taken into

    consideration.

    7-1.2 Cash Flow for Industrial Operations

    Figure 7-1.1 shows the concept of cash flow for an overall industrial operation.

    Figure 7-1.1: Cash Flow for an Overall Industrial Operation.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    66/99

    58

    7-1.3 Factors affecting Investment and Production Costs

    Sources of equipment

    Price fluctuations

    Company policies

    Operating time and rate of production

    Governmental policies

    7-1.4 Capital Investment

    Before an industrial plant can be put into operation, a large sum of money must be

    supplied to purchase and install the necessary machinery and equipment. Land and

    service facilities must be obtained, and the plant must be erected complete with all

    piping, controls, and services. In addition it is necessary to have money available for the

    payment of expenses involved in the plant operation.

    - Fixed capital investment

    The capital needed to supply the needed manufacturing and plant facilities.

    - Working capital

    The capital necessary for the operation of the plant

    - Total capital investment = Fixed capital investment + Working capital

    - Fixed capital investment= Manufacturing fixed capital investment + Non-

    manufacturing fixed capital Investment.

    - Manufacturing fixed capital investment: the fixed capital necessary for the

    installed process equipment with all auxiliaries that are needed for complete

    process operation. These include expenses for piping, instruments, insulations,

    foundations, and site preparation.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    67/99

    59

    - Non- manufacturing fixed capital investment: the fixed capital required for

    construction overhead and for all plant components that are not directly related to

    the process operation. These plant components include the land, processing

    buildings, administrative and other offices, warehouses, laboratories,

    transportation, shipping and receiving facilities, utilities and waste disposal

    facilities, shops and other permanent parts of the plant.

    - Construction overhead cost: consists of field-office and supervision expenses,

    home-office expenses, engineering expenses, miscellaneous construction costs,

    contactors fees and contingencies. In most cases, construction overhead is

    proportioned between manufacturing and non-manufacturing fixed-capital

    investment.

    - Working capital: the working capital for an industrial plant consist of the total

    amount of money invested in

    o Raw materials and supplies carried in stock

    o Finished products in stock and semi-finished products in process of being

    manufactured

    o Accounts receivable

    o Cash kept on hand for monthly payment of operating expenses , such as

    salaries, wages, and raw materials purchases

    o Accounts payables

    o Taxes payables

    The ratio of working capital to total capital investment varies with different

    companies. Most chemical plants use an initial working capital of 10 to 20 percent

    of the total capital investment. It is 50% or more for companies producing

    products of seasonal demand because of the large inventories which must be

    maintained for appreciable period of time.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    68/99

    60

    7-1.5 Estimation of Capital Investment

    7-1.5.1 Introduction

    Of the many factors which contribute to poor estimates of capital investments, the most

    significant one is usually traceable to sizeable omissions of equipment, services, or

    auxiliary facilities rather than to gross errors in costing. A check list of items covering a

    new facility is an invaluable aid in making a complete estimation of the fixed capital

    investment. A typical list of items for estimating fixed capital investment is:

    Direct cost

    1. Purchased equipment; all equipments listed on a flow sheet

    2. Purchased-equipment installation

    3. Instrumentation and controls

    4. Piping

    5. Electrical equipment and materials

    6. Buildings(including services)

    7. Yard improvements

    8. Service facilities

    9. land

    Indirect cost1. Engineering and supervision

    2. Construction expenses

    3. Contractors fees

    4. Contingencies

    7-1.5.2 Types of capital cost estimates

    An estimate of the capital investment for a process may vary from a predesign estimate

    based on little information except the size of the proposed project to a detailed estimate

    prepared from complete drawings and specifications. The following five categories

    represent the accuracy range and designation normally used for design purposes:

    1. Order-of-magnitude estimate(ration estimate) based on similar previous cost data:

    probable accuracy of estimate over30 percent

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    69/99

    61

    2. Study estimate (factored estimate) based on knowledge of major items of

    equipment; probable accuracy of estimate up to30 percent

    3. Preliminary estimate (budget authorization estimate; scope estimate) based on

    sufficient data to permit the estimate to be budgeted; probable accuracy of

    estimate within20 percent.

    4. Definitive estimate(project control estimate) based on almost complete data but

    before completion of drawings and specifications; probable accuracy of estimate

    within10 percent

    5. Detailed estimate (contractors estimate) based on complete engineering

    drawings, specifications and site surveys; probable accuracy of estimate within

    5 percent.

    7-1.5.3 Cost indexes

    Most cost data which are available for immediate use in a preliminary or predesign

    estimate are based on conditions at some time in the past. Because prices may change

    considerably with time due to changes in economic conditions, some methods must

    be used for updating cost data applicable at a past date to costs that are representative

    of conditions at a later time. This is done using a cost index.

    Acost index is hence an index value for a given point in time showing the cost ofanequipment or plant at that time relative to a certain base time.

    =

    obtainedwascostoriginaltimeatvalueindex

    timepresentatvalueindexcostOriginalcostesentPr

    Cost indexes can be used to give a general estimate, but no index can take into

    account all factors, such as special technological advancements or local conditions.

    The common indexes permit fairly accurate estimates if the time period involved is

    less than 10 years.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    70/99

    Some indexes are used fo

    labor, construction, mate

    The most common of the

    process-industry equipm

    the Nelson refinery const

    index. This is shown in T

    Table

    7-1.5.4 Methods for Estima

    7-1.5.4.1 Power factor appl

    ( )nn RCFeC =

    Where:

    R = size (or capacity) ratio o

    62

    r estimating equipment cost, others apply speci

    ials etc.

    se indexes are theMarshall and Swift all-indust

    nt indexes, the Engineering New-Record const

    ruction index and the Chemical Engineering pl

    ble 7-1.1.

    7-1.1: Cost indexes as Annual Averages

    ing Capital Investment

    ed to plant-capacity ratio:

    equipment=plaorequipmentoldofcapacity

    plaorequipmentnewofcapacity

    ically to

    ry and

    uction index,

    nt cost

    t

    t

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    71/99

    Fe = equipment cost index ra

    n = equipment size (or capac

    C = purchased cost of old eq

    Cn = purchased cost of new e

    Table 7-1.2 shows typical ex

    Table 7-1.2 Typi

    63

    tio=obwascostoriginaltimetheatvalueindex

    timepresentinvalueindex

    ity) exponent

    ipment

    quipment

    ponents for equipment cost vs. capacity

    al Exponents for Equipment Cost vs. Capaci

    tained

    ty

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    72/99

    64

    EXAMPLE 7-1.1

    If a process plant was erected in Kumasi at a fixed capital investment of $436,000 in

    1970, determine what the capital investment will be in 1975 for a similar process plant

    located near Dansoman in Accra with twice the process capacity but with an equal

    number of process equipment.

    SOLUTION 7-1.1

    ( )nn RCFeC =

    Where:

    R = size ( or capacity) ratio of equipment

    Fe = equipment cost index ratio

    n = equipment size exponent

    C = purchased cost of equipment in 1970

    Cn = cost of equipment in 1975

    From Table 7-1.1

    M & S index, 1970 =303,

    M & S index 1975 = 444,

    From Table 7-1.2

    Equipment size exponent, n = 0.6

    ( ) 378,968$2303

    444000,436

    6.0 ==nC

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    73/99

    65

    7-1.5.4.2 Detailed item estimate

    EXAMPLE 7-1.2

    Initial design work was done for a chemical plant to revamp the process in order to

    recover valuable product from an effluent gas stream. The gas will be scrubbed with a

    solvent in a packed column and the recovered product and solvent separated by

    distillation. The solvent will then be cooled and recycled. The major items of equipment

    required and their purchased costs in cedis are:

    Absorption column

    Column purchased cost = 19,800

    Cost of column packing = 6,786

    Recovery column

    Column purchased cost = 45,000

    Cost of 30 sieve trays = 8,670

    Reboiler

    Cost of reboiler = 7,600

    Condenser

    Purchased cost = 4,800

    Recycle solvent cooler

    Cost of cooler = 2,550Storage tank

    Cost of tank = 7,790

    The relevant component factors for this processing plant are;

    f1: equipment erection = 0.40

    f2: piping = 0.70

    f3: Instrumentation = 0.2

    f4: electrical = 0.10

    f10: design and engineering = 0.30

    f12: contingencies = 0.20

    Estimate the total capital investment for the project, if the working capital can be taken as

    10 % of the fixed capital cost.

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    74/99

    66

    SOLUTION 7-1.2

    Total capital investment, TCI = Fixed capital investment, FCI Working capital, WC

    Total purchased cost of equipment, PCE

    Absorption column = 19,800 + 6,786 = 26,586

    Recovery column = 45,000 + 8,670 = 53,670

    Reboiler = 7,600

    Condenser = 4,800

    Recycle solvent cooler = 2,550

    Solvent and product storage tank = 7,790

    Total purchased cost of major equipment = 102,996

    Equipment erection = 102,996 (0.4) = 41,198

    Piping cost = 103,996 (0.70) = 72,097

    Instrumentation cost = 102,996 (0.2) = 20,599

    Electrical = 102,996 (0.10) = 10,300

    Total physical plant cost (Direct cost) = 10,300 + 20,599 + 72,097 + 41,198 + 102,996

    = 247,190

    Indirect cost

    Design and engineering, f10 = 0.30 (247,190) = 74,157

    Contingencies = 0.20 (247,190) = 49,436Total indirect cost = 123,595

    Fixed capital investment (Direct cost + Indirect cost) = 247,190 + 123,595 = 370,785

    Working capital = 0.10 (370,785) = 37,079

    Total capital investment = 370,785 + 37,079 = 407,864

    7-1.5.4.3 Other Methods for Estimating Equipment or Capital Investment

    (i) Unit cost Estimate

    (ii) Percentage of delivered-equipment Cost

    (iii) Lang factors for approximation of capital Investment

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    75/99

    67

    7-1.5.5.Turnover Ratios:

    A rapid evaluation method suitable for order-of-magnitude estimates is known as the

    turnover ratio method.

    Turnover ratio is defined as the ratio of gross annual sales to the fixed capital

    investment

    tinvestimencapitalfixed

    salesannualgrosstioTurnoverra =

    Where the product of the annual production rate and the average selling price of the

    commodities produced is the gross annual sales figure.

    ratioTurnoverratioinvestmentorratioCapital

    1=

    Turnover ratio ranges between 0.2 to 5. For chemical industries, as a very rough rule of

    thumb, the ratio can be approximated to 1.

    SESSION 7-2: In this session we shall study the estimation of total product cost and

    determination of breakeven point.

    7-2.1 Estimation of Total Product Cost

    Manufacturing cost: all expenses directly connected with the manufacturing

    operation or the physical equipment of a process plant itself.

    There are 3 classifications of these expenses:

    Direct production cost: expenses directly associated with the

    manufacturing operation. E.g. expenses for raw materials ( including

    transportation, unloading)

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    76/99

    68

    Fixed charges: expenses that remains practically constant from year to

    year. Do not vary widely with changes in production rate. E.g. property

    taxes, insurance.

    Plant overhead cost: are for medical and hospital services; general plant

    maintenance and overhead; safety services; social security

    General Expenses:

    Administrative expenses

    Distribution and marketing expenses

    Research and development

    Financing expenses: extra costs involved in procuring the money

    necessary for the capital investment.

    Gross earnings expenses

    Total Product Cost= Manufacturing cost + General Expenses.

    Gross earnings (Gross Profit)= The total incomethe total product cost.

    Net annual earnings = Gross annual earningsincome taxes.

    Figure 7-2.1 shows the components constituting the estimation of total product cost

  • 5/20/2018 CHE451_Chemical Process Design and Economics

    77/99

    69

    Figure 7-2.1: Cost Involved in Total Product Cost for a Typical Chemical

    Process Plant

    7-2.2 Break-even Point

    (a) Break-even point occurs (or is the percentage of plant capacity) when the total

    annual product cost equals the total annual sales.

    i.e: Total Annual Product Co