characterizing the post-dredge surface: comparison of in-situ (pre-dredge) and post-dredge grab...
TRANSCRIPT
Characterizing the Post-Dredge Surface:Comparison of In-Situ (Pre-dredge) and
Post-Dredge Grab Samples at Three Sites in the Willamette River, Portland Harbor, Oregon
Michelle HollisPort of Portland
& James McMillanPortland District
Laura Inouye, Washington Department of EcologyJonathan Freedman, US Environmental Protection Agency, Region
10
PurposeCompare concentrations from pre-dredge
core samples and post-dredge grab samples at 3 sites
Examine contributions to post-dredge surface (PDS) chemistry based on site conditions
Use findings to inform risk-based regulatory decision making for dredging projects in the Portland Harbor
PDS
Dredge Prism
PDS
BEFORE AFTER
ProblemCore samples measure the pre-dredge conditionThe in-situ core sample characterizing the PDS is often
used in regulatory decision makingBUT, in-situ PDS samples don’t account for:
Post-dredge Surface (PDS)
current
fallback &physical mixing from dredging
deposition
side slopesloughing
mixing frommarine traffic
current mixing
Fallback from the dredge Physical mixing during dredging Side-slope sloughing Current mixing within the dredge
area
Deposition during/after dredging Mixing caused by natural
processes and marine traffic
(After ERDC, 2008 The Four Rs of Environmental Dredging: Resuspension, Release, Residual, and Risk [TR-08-4])
Regulatory Review of Post-Dredge Surface Regulatory agencies want to know what’s being
dredged AND what will be exposed after dredgingRegulatory concerns regarding:
Endangered speciesState water quality parameters (sediment-water
column interface)State anti-degradation policies
(i.e., exposed surface >> dredge prism = BAD)State and federal permits may require:
Monitoring after dredgingPhysical isolation of the PDS
Placement of a clean sand cover Natural infill (of cleaner sediment)
MethodsCompared concentrations of chemicals of concern:
PDS
BEFORE DREDGING
Dredge Prism
In-situ core sample
(pre-dredge estimate)
AFTER DREDGING
PDS
Post-dredge grab samples (of the actual post-dredge surface)
Methods (cont.)Examined factors contributing to PDS chemistry:
Post-dredge Surface (PDS)
current
fallback &physical mixing from dredging
deposition
side slopesloughing
mixing frommarine traffic
current mixing
(After ERDC, 2008 The Four Rs of Environmental Dredging: Resuspension, Release, Residual, and Risk [TR-08-4])
Portland Harbor Sites (3)
PORTLAND, OR
VANCOUVER, WA
Columbia R.
Willamette R.
PoP T5Willamette
FNC – PO Bar
N
2 4 60miles
PoP T2
Post Office Bar
Willamette R. FNCPost Office Bar
PORTLAND, OR
VANCOUVER, WA
Columbia R.
Willam
ette R.
Willamette R. FNC – PO BarN
2 4 60miles
DETAILS• Location: Willamette River, RM 2.1-2.4• Volume: 52,300 cy• Depth: Dredged to -40 feet CRD
(plus 2 feet advanced maintenance) • Disposal: Upland, West Hayden Is.
Placement Site • Project completed in Sept./Oct.
2011
73.2
80.483.8-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
Downstream End (RM 2.1) Upstream End (RM 2.3)
ZINC: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge
Feb. 2009 mudline
In-situ dredge prism core sample(PRE-dredge)
68.9226
156
In-situ PDS core sample(PRE-dredge)
8987.1
77.2DredgePrism
Zinc SL = 130 ppm
VC-02 VC-04
VC-06
Zinc Concentrations
Sample
PRE-DREDGE (Core) Zinc Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS
Average 84.4 79.1 150.3 130 ppm
73.2
80.483.8-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
BC-01 BC-02 BC-03BC-04 BC-05
Downstream End (RM 2.1) Upstream End (RM 2.3)
ZINC: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge; 2011 post-dredge
Feb. 2009 mudline
Oct. 2011 PDS
In-situ dredge prism core sample(PRE-dredge)
68.9226
156
91 10396 97 112
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
8987.1
77.2DredgePrism
Zinc SL = 130 ppm
VC-02 VC-04
VC-06
Zinc Concentrations
Sample
PRE-DREDGE (Core)POST-DREDGE
(Grab) Zinc Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS
Oct. 2011
Average 84.4 79.1 150.3 99.8 130 ppm
73.2
80.483.8-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
BC-01 BC-02BC-03 BC-04 BC-05
Downstream End (RM 2.1) Upstream End (RM 2.3)
ZINC: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge; 2011 & 2012 post-dredge
Feb. 2009 mudline
Oct. 2011 PDS
In-situ dredge prism core sample(PRE-dredge)
68.9226
156
91 10396 97 112
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
Apr. 2012 surface 8875 98
86 88
8987.1
77.2DredgePrism
Zinc Concentrations
Sample
PRE-DREDGE (Core)POST-DREDGE
(Grab) Zinc Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS
Oct. 2011
Apr. 2012
Average 84.4 79.1 150.3 99.8 87 130 ppm
Zinc SL = 130 ppm
VC-02 VC-04
VC-06
<7.2
<12<12-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
Downstream End (RM 2.1) Upstream End (RM 2.3)
PCBs: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge
Feb. 2009 mudline
Oct. 2011 PDS
In-situ dredge prism core sample(PRE-dredge)
<7.4154
79
In-situ PDS core sample(PRE-dredge)
<1256
<12DredgePrism
PCBs SL = 60 ppb
VC-02 VC-04
VC-06
PCBs Concentrations
Sample
PRE-DREDGE (Core) PCB Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS
Average 22.7 ND 78.9 60 ppb
<7.2
<12<12-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
BC-01 BC-02BC-03 BC-04 BC-05
Downstream End (RM 2.1) Upstream End (RM 2.3)
PCBs: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge; 2011 post-dredge
Feb. 2009 mudline
Oct. 2011 PDS
In-situ dredge prism core sample(PRE-dredge)
<7.4154
79
16 <9.8<9.6 <10 39
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
<1256
<12DredgePrism
PCBs SL = 60 ppb
VC-02 VC-04
VC-06
PCBs Concentrations
Sample
PRE-DREDGE (Core)POST-DREDGE
(Grab) PCB Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS Oct. 2011
Average 22.7 ND 78.9 13.9 60 ppb
<7.2
<12<12-36
-32
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD) VC-05
VC-01 VC-03
BC-01 BC-02BC-03 BC-04 BC-05
Downstream End (RM 2.1) Upstream End (RM 2.3)
PCBs: WILLAMETTE R., POST OFFICE BAR – 2009 pre-dredge; 2011 & 2012 post-dredge
Feb. 2009 mudline
Oct. 2011 PDS
In-situ dredge prism core sample(PRE-dredge)
<7.4154
79
16 <9.8<9.6 <10 39
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
Apr. 2012 surface <9.7<9.9 <9.8
<9.7 <9.7
<1256
<12DredgePrism
PCBs Concentrations
Sample
PRE-DREDGE (Core)POST-DREDGE
(Grab) PCB Screening
LevelDredge Prism
Sloughing Material
In-Situ PDS Oct. 2011
Apr. 2012
Average 22.7 ND 78.9 13.9 ND 60 ppb
PCBs SL = 60 ppb
VC-02 VC-04
VC-06
Port of PortlandTerminal 2, Berth 205
DETAILS• Location: Willamette River, RM 10 • Volume: ~10,000 cy (project total 12,424 cy)• Depth: Dredged to -37 feet CRD
(plus 2 feet overdepth allowance) • Disposal: Upland, West Hayden Island
Placement Site • Project completed in July/Aug. 2008
PORTLAND, OR
VANCOUVER, WAColumbia R.
Willam
ette R.
N
2 4 60miles
Port of PortlandTerminal 2
DEHP: PORT OF PORTLAND, TERMINAL 2 – January 2008 pre-dredge
-29
-38
-26
-27
-36
-35
-34
-33
-32
-31
-30
-37
-28
Dep
th (f
eet C
RD)
Downstream Upstream
Aug. 2008 PDS
DEHP SL = 220 ppb
-39
C-5
130 240
C-3
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
DredgePrism
Jan. 2008 mudline
100 (dredge prism
composite)
DEHP Concentrations
Sample
PRE-DREDGE (Core)
DEHP Screening Level
Dredge Prism
In-Situ PDS
Result 100 240 220 ppb
DEHP: PORT OF PORTLAND, TERMINAL 2 – January 2008 pre-dredge; August 2008 post-dredge
-29
-38
-26
-27
-36
-35
-34
-33
-32
-31
-30
-37
-28
Dep
th (f
eet C
RD)
Downstream Upstream
Aug. 2008 PDS
DEHP SL = 220 ppb
-39
100
C-5
130 240
C-3
DEHP Concentrations
Sample
PRE-DREDGE (Core)
POST-DREDGE (Grab)
DEHP Screening Level
Dredge Prism
In-Situ PDS August 2008
Result 100 240 100 220 ppb
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
DredgePrism
Jan. 2008 mudline
100 (dredge prism
composite)
PORTLAND, OR
VANCOUVER, WA
Columbia R.
Willam
ette R.
Port of PortlandTerminal 5
N
2 4 60miles
Port of PortlandTerminal 5, Berth 501
DETAILS• Location: Willamette River, RM 1-2• Volume: 12,246 cy (project total 25,000 cy)• Depth: Dredged to -43 feet CRD
(plus 3 feet overdepth allowance) • Disposal: Upland, West Hayden Island
Placement Site • Project completed in July/Aug. 2010
ZINC: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 PDS
Zinc SL = 130 ppm
-46
C-7
177
126
C-12
74
85
268
197
C-6
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
DredgePrism
Zinc Concentrations
Sample
PRE-DREDGE (Core) Zinc Screening
LevelDredge Prism In-Situ PDSAverage 156 153 130 ppm
ZINC: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge; 2010 post-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 PDS
Zinc SL = 130 ppm
-46
98167 116
C-7
177
126
C-12
74
85
268
197
C-6
C-7C-12 C-6
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
DredgePrism
Zinc Concentrations
Sample
PRE-DREDGE (Core) POST-DREDGE (Grab) Zinc Screening
LevelDredge Prism In-Situ PDS July 2010Average 156 153 127 130 ppm
ZINC: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge; 2010 & 2011 post-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 PDS
Zinc SL = 130 ppm
-46
98167 116
Aug. 2011 surface
C-7
177
126
C-12
74
85
268
197
C-6
C-7
160
C-12
93C-6
120
Zinc Concentrations
Sample
PRE-DREDGE (Core) POST-DREDGE (Grab) Zinc Screening
LevelDredge Prism In-Situ PDS July 2010 Aug. 2011Average 156 153 127 124 130 ppm
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
DredgePrism
PCBs: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 surface
PCBs SL = 60 ppb
-46
C-7
34
47
410
38
C-6C-12
<3.9
22
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
DredgePrism
PCBs Data Summary
Sample
PRE-DREDGE (Core) PCB Screening
LevelDredge Prism In-Situ PDS
Average 149 36 60 ppb
PCBs: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge; 2010 post-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 surface
PCBs SL = 60 ppb
-46
2825.337
C-7
34
47
410
38
C-6C-12
<3.9
22
C-7C-12 C-6
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
DredgePrism
PCBs Data Summary
Sample
PRE-DREDGE (Core) POST-DREDGE (Grab) PCB Screening
LevelDredge Prism In-Situ PDS July 2010
Average 149 36 30 60 ppb
PCBs: PORT OF PORTLAND, TERMINAL 5 – 2008 pre-dredge; 2010 & 2011 post-dredge
-36
-45
-33
-34
-43
-42
-41
-40
-39
-38
-37
-44
-35
Dep
th (f
eet C
RD)
Downstream Upstream
Jun. 2007 mudline
July 2010 surface
PCBs SL = 60 ppb
-46
2825.337
Aug. 2011 surface
C-7
34
47
410
38
C-6C-12
<3.9
22
C-7
<3.8
C-12
<3.9C-6
9.6
PCBs Data Summary
Sample
PRE-DREDGE (Core) POST-DREDGE (Grab) PCB Screening
LevelDredge Prism In-Situ PDS July 2010
Aug. 2011
Average 149 36 30 4.0 60 ppb
In-situ dredge prism core sample(PRE-dredge)
In-situ PDS core sample(PRE-dredge)
Surface grab sample(POST-dredge)
DredgePrism
What might account for differences between in-situ cores and PDS grabs?Fallback is a realityMixing happens: physical mixing during
dredgingnatural river processes, marine traffic
Side slope sloughingKnown rates of deposition: 4” to 6” year
accumulation
PDS
Regulatory requirements for the PDS(based on pre-dredge core sampling)BEFORE DREDGINGBioassays on pre-dredge core samplesBenthic invertebrate studyAFTER DREDGINGPDS sediment samplingMonitored natural recovery
Additional sediment samplingBathymetric surveysAdditional benthic invertebrate studies
OR
OVERDREDGE and cover with sand
ConclusionsThe in-situ PDS core sample generally over-
predicted the post-dredge condition Depending on site conditions and patterns of
contamination, the in-situ PDS sample may under-predict the post-dredge condition
When available, consider historic information and knowledge of site conditions to help predict PDS chemistry and potentially reduce sampling burden:
CPDS = ƒ[cin-situ core, cDP(mixed&fallback), cside slope, cdeposition]
ConclusionsAgencies and the regulated community should use these findings to inform risk-based regulatory decision making for dredging projects in the Portland Harbor
Future WorkExamine additional paired in-situ core and PDS grab samples to improve risk-based decision making in the Portland Harbor
Questions?