chapters port performance and port...

79
CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITY 5.1 Performance of Indian Ports 5.2 Measurement of Port Performance 5.3 Rank Variability of Major Ports in terms of Port Performance 5.4 Conclusions 143

Upload: others

Post on 22-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

CHAPTERS

PORT PERFORMANCE AND PORT PRODUCTIVITY

5.1 Performance of Indian Ports

5.2 Measurement of Port Performance

5.3 Rank Variability of Major Ports in terms of Port

Performance

5.4 Conclusions

143

Page 2: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

5.1 Performance of Indian Ports

The seaports of the developing countries are going through a process of

rejuvenation and change in recent years triggered by the competition among the nations

to capture the world market, by the introduction of sophisticated cargo handling

techniques and innovations in the shipping vessels. The organisational set up and the

work climate in the ports are also undergoing phenomenal changes. Studies on ports in

India have not captured the impact of these changes on the performance of Indian ports.

Most of these studies have been in the form of reports or inquiries undertaken by

committees appointed to review some specific aspects of port activities. These reports are

mostly technical in nature dealing with specific issues and rarely look into the entire

process of port functioning. In this context, an assessment of the performance of major

Indian ports during the 1990s has been attempted in this chapter. An attempt has been

made to assess performance and productivity among the Indian major ports, both in terms

of physical and financial indicators. It must be admitted at the onset that this exercise has

limitations of covering only some indicators of port performance. Nevertheless, both

intra-port and inter-port comparisons and contrasts do indicate the changes in

performance among the major Indian ports. Performance or productivity of a port is a

function of the interplay of a number of variables and is not a matter of chance. Newer

ports perform better than older ports. This hypothesis has been put to test in this chapter.

5.1.1 The Port as a link in the transport chain

A port is essentially the point a~ which sea-borne cargo is transferred from one

mode of transport to another. On the seaward side, the port is concerned with a flow of

ships, which bring in cargo for discharge, and load cargo aggregated at the port and then

depart to deliver at different destinations. On the land ward side cargo is brought by road

or by inland water transport to the port and is transferred into ships and vice-versa. In

order that the entire operation should be smooth, both aspects of the port operation must

be efficient. Between land transport and sea transport lie the storage and handling

facilities of a port and a degree of efficiency must be attained if the whole port is to

operate as an efficient unit.

144

Page 3: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Origin

Sea voyage

The Transport Chain

Fig . 5.1

Hinterland transport

Port of discharge

Port of loading

Hinterland transport Destination

Page 4: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

LAYOUT OF THE PORT FIG. 7.1

I . - [-----··- -- --------~

_. •• 'U _.., .,,. • J • ., 'lo<:' .. ,. ~

······r

. ~·:· .. ~1;:: .. :: -:~:.:.~;~:::· ~I-·-~~~-~-~ .. , • .. ··· :- A"• ...... ',.. ....... ... . .. ~ ...... ,_,. . ,.., ,_,.~.' ~ - · ............. ..

• ~- ) ... · ···--··~~-· tl' ,., A.,..,; ~· .. ,'t'll• ~-~ "' . ....... ~'t··t 1 (t .·~• ' "'"' ' •·• ··l'..>J .>1 o o!N·~' .-;-.., ,..,, ,r o;!( h', ""

• • • ,. ;:. ~-,, .. ,,,·~ n. ,1'"" · ···~-.., r ,.

i A

i

\~ I / f<·l 'J- , . ~1 ............

\

~ ~~WMER

-=J I __ j

·----···i

I i I ·---·- ---·-·-·1

I

~ I i I

Page 5: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

mechanised boats today. The third stage development was commissioned recently at

a cost of Rs. 4.54 crore to accommodate 34 more trawlers.

• Slipway: The unique feature of the fishing harbour is the construction of a modem

slipway. The slipway provides six repair tracks facilitating repairs to six trawlers or

12 boats at a time. It can accommodate the trawlers with LOA of 30 mtrs., beam of

7 mtrs. and draft of 3.5 mtrs. This is the only one kind on the eastern coast of India

offering full-fledged repairing facilities to the different crafts engaged in modem

fishing.

• Dry Dock: The dry dock with the length of 65.4 mtrs., breadth of 21.6 mtrs. and

depth of 6 mtrs. was constructed in February 1990 to cater to the repairs of trawlers.

Today, the fishing harbour has transformed itself into a most modem buzzling

harbour with 24 hectares of tranquil water basin and infrastructure facilities.

7.1 Planned Development of the Port

In the First five-year Plan (1951-56), four alongside berths were constructed and

cargo-handling facilities were improved. During the Second Five Year Plan (1956-61 ),

two oil berths were commissioned to meet the requirements of Hindustan Petroleum

Corporation (Caltex Oil Refinery), procurement of port euipment and laying of BG

railway tracks were undertaken.

The third Five-Year Plan (1961-66), Animal Plans (1966-69) and the Fourth

Five-Year Plan (1969-74), witnessed significant growth of the Port. During this period,

two west ore berths for export of iron ore and mechanised iron ore handling plant

facilities were provided. In addition two more multipurpose berths to handle bulk a)

break-bulk cargo and b) a specialised fertiliser berth for Coromandel Fertilisers Ltd. to

import fertiliser raw materials were commissioned. Construction of warehouses and

storage sheds, reclamation of land and development of open storage area, construction

of fly-over bridge, construction of administrative office building, procurement of

forklift trucks and 150 tonne floating crane (Bheema) were undertaken.

During the Fifth Plan period ( 197 4-78), the most prestigious and the deepest

Outer Harbour was commissioned in 1976 at a cost of Rs. 110 crores to accommodate

large size vessels upto 1,50,000 DWT for export of iron ore to Japan. The Iron Ore

248

Page 6: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

handling facilities were augmented and a modem Mechanical Ore Handling Complex

came into existence in place of an ore handling plant. This period also saw the

procurement of tugs and one dredger of 4,000 TPH capacity and 6110 tonne electric

wharf crane. During the Annual Plan ( 1978-80) port railway system was improved and

additional floor in transit shed and construction of storage shed was undertaken.

In the Sixth Five Year Plan (1980-85), an Off-shore Tanker Terminal (OSTT) in

the Outer Harbour was commissioned in 1985 for accommodating large crude carriers

of size 1,50,000 DWT with direct discharge facility to the refinery at 5500 TPH. An Oil

Mooring was also developed in the Outer Harbour to accommodate deep draft tankers.

A General-Cum-Bulk Cargo Berth to accommodate vessels of 65,000 DWT was also

commissioned in the Outer Harbour in 1985 and a warehouse of 15,000 tonne capacity

near GCB was constructed.

During the Seventh Five-Year Plan (1985-90), the oil terminal in the outer

harbour was commissioned. High capacity tugs, electrical cranes, mobile cranes, locos

etc. were procured. Development of stacking areas and railway lines were undertaken.

During the Annual Plans (1990-92), two quay berths (W. Q-2 and W. Q-3) were

constructed by dismantling old jetties. The port railway system was developed and high

capacity tugs were procured.

During the Eighth Five Year Plan (1992-97), several development programmes

were undertaken with an investment of Rs. 197 crores. This period saw the development

of stacking space, development of roads and construction of two multipurpose berths in

inner harbour (W. Q. 1. and E. Q. 7). Office buildings came up in the dock area; an

integrated sports complex and an institute for port and dockworkers were setup.

Activities like deepening of outer and inner harbour, widening of entrance channel,

procurement of higher capacity locos and cranes, computerisation of port operations and

upgradation of communication facilities were undertaken.

249

Page 7: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.1

Plan-wise investment at Visakhapatnam and other Major Ports

Plans Visakhapatnam All Ports

Rs. in crores Rs. in crores

First Five Year Plan (1951-56) 1.36 26.32

Second Five Year Plan (1956-61) 4.31 45.50

Third Five Year Plan (1961-66) 9.07 92.95

Annual plans ( 1966-67, 67-68 and 68-69) 6.54 88.82

Fourth Five Year Plan (1969-74) 62.6 265.16

Fifuth Five Year Plan (1974-78) 55.8 359.35

Annual Plans (1978-80) 7.40 101.20

Sixth Five Year Plan (1980-85) 57.34 568.15

Seventh Five Year Plan (1985-90) 56.81 1273.39

Annual Plans (1990-91 and 91-92) 42.43

Eighth Five Year Plans ( 1992-97) 197.00 1884.13

Ninth Five Year Plan (proposed) (1997- 1178.00

2002)

Source: The Lmk- Global Trade and Freight Review- "VIsakhapatnam Port­

Excellence an on-going Quest" -Special Issue, Vol. III. No.4, 1998.

Ninth Plan Outlay

Vishakhapatnam Port Trust (VPT) has proposed an outlay of Rs. 1,180 crore for

various development activities that it hopes to undertake during the Ninth Plan period,

to achieve a target of handling 45 million tonnes of cargo by the end of the year 2001-

02. Some of the projects that are to be carried out during the Plan period include an

exclusive jetty for unloading liquefied natural/petroleum gas at a cost of Rs. 24.12

crores; a deep draft multipurpose berth in the outer harbour to handle 60,000 DWT

ships (Rs. 41.27 crores); four additional multipurpose berths in the inner harbour- two

by VPT and two on BOT (build, operate, transfer) basis, for receiving vessels of 35,000

DWT (Rs. 120 crores).

250

Page 8: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The Plan also envisages modernisation of the cargo transfer system by procuring

14 higher capacity electric wharf cranes and a number of mobile cranes, forklift trucks,

top lift trucks, a bucket wheel reclaimer and two 50-tonne Ballard pull tugs from

Hindustan Shipyard Limited. Some infrastructural development programmes like

revamping the port rail system, overbridges, roads etc. would also be taken up during

the period. The Port railway system would be developed at an estimated cost of Rs. 75

lakh and road system with about Rs. 50-60 crore by the end of the Plan period. Also, the

second railway line would be laid for usage of general cargo berth

7.2 Hinterland and Transport Links

It can be seen from Table 7.2, that out of a total cargo traffic of 34.25 million

tonnes, 6.7 million tonnes does not require land transport leaving 27.55 million tonnes

to be transferred by land. Out of this, 18.27 million tonnes forming 66.3 percent is

moved by railways, and 5.61 million tonnes forming 20.4 percent is moved by pipiline,

leaving only 3.67 million tonnes of cargo forming 13.3 percent for road movement.

Even out of this, the cargo of Coromondal Fertilisers which is 0.79 million tonnes is

moved on a short dedicated road. Therefore road based cargo for/from outstations is

only 2.88 million tonnes.

Table 7.2

Distribution of cargo on different modes reaching Visakhapatnam Port

(In '000 tonnes)

Cargo 1996-97 Quantity

Total Quantity Quantity by Other

Quantity by by Road Modes

Railways I. Export A. Dry Bulk Iron Ore 5740 5740 Other Ores 110 110 Thermal Coal 3710 3710 Alumina 466 466 Soyabean Extract 188 188 Foodgrains 129 129

251

Page 9: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Cargo 1996-97 Quantity

Total Quantity Quantity by Other

Quantity by by Road Modes

Railways Iron ore pellets 271 271 Feldspar, Illeminite 60 60 Cement Clinker, !bentonite B. Liquid Bulk Petroleum and POL 613 613 products Molasses, Ethyl Alcohol 215 150 65 C. Break Bulk Pig Iron 487 487 Iron and Steel 900 900 Other Miscellaneous 285 - 285 D. Containers 111 - 111 Total Export 13285 11751 921 613 II. Import A. Dry Bulk Fertiliser and raw materials 1390 360 1030 Coking Coal and Coke 5315 5315 Other Miscellaneous 638 - 638 B. Liquid Bulk Petroleum and Products 6222 730 492 5000 Caustic Soda 111 111 Phosphoric Acid/ Ammonia 347 347 C. Break Bulk Total 184 184 D. Containers 56 56 Total Import 14263 6516 2747 5000 E. Transshipment 6700 - 5613 Grand Total (I+II) 34248 18267 3668

.. Source: Perspective Plan for Indian Port Sector- VIsion 2020'- Part IV, By RITES,

MOST (GOI), January 1998.

7.3.1 Roads

The POL products are transferred to tank farms of oil companies through

pipeline from where it is moved by railways and roadways. The fertiliser raw materials

are moved by dedicated roadway to the fertiliser factory, which is close to the port. Port

roads to the National Highway No. 5 link the refinery and the fertiliser plant. All the

252

Page 10: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

berths (twelve) have proper roads laid close to the berths. These roads combine near the

port gate and independently join the link to NH-5 from the northern side. The Outer

Harbour has a separate road access through the Visakhapatnam Town. The Port Trust

has about 50 km of roads varying in widths from 3.6 metres to 9.0 metres. An important

feature of this port is that since it is criss crossed by several railway systems, these

roads have to cross them at several locations. The port has therefore constructed several

Rail Over Bridges and a subway so that the road traffic can move smoothly. There is

also a major river bridge to cross Megadrigedda.

7 .3.2 Railways

The Port railway system consists basically of a broad gauge section with 64 km

of track which handles all traffic to and from the Indian Railways and a narrow gauge

section with a track length of 9 km meant purely for internal movement of manganese

ore from the stockyards to the two quay berths. The main linkage of the railway system

to the hinterland of the port is through the main Chennai-Howrah line. Visakhapatnam

has the most extensive railway system and it links all berths, storages, workshops etc.

Separate sidings are provided for cargoes like iron and steel, foodgrains, minor ores,

fertilisers etc.

The iron ore trains from Bailadilla-Kiriburu mmes through South Eastern

Railway reach the Ore Exchange Yard. From there they go to the tippling yard and the

empties come back to Ore Exchange yard, where the rakes are gathered for return to

mines. All other trains reach the R and D yard. Fro~ here the coking coal and the

thermal coal trains go to the Visakhapatnam Steel Plant through the southwestern

boundary of the port. Thermal coal trains are linked to the mines through main Chennai­

Howrah line of the Indian Railways.

For alumina and caustic soda, a separate NALCO yard is provided which is

linked to the Rand D yard. The oil cargo reaching the storages of HPCL and IOC have

their own loading/unloading sidings and are linked to the Chennai-Howrah line through

the R and D yard.

253

Page 11: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Broadly, the ports of Madras, Bombay, Paradip and Kandla are considered ports

in competition to Visakhapatnam. The competition between Visakhapatnam and Madras

Port over the movement of cargo through Railway can be considered via these routes :

• Waltair- Vijayawada- Madras

• Waltair- Guntur- Guntakal-Madras; and

• Waltair-Vijaywada-Kazipet

• Dronachalarn- Guntakal - Madras routes.

For marking off, the hinterland between Visakhapatnam and Calcutta route has

been considered less important because of Paradip Port coming in between. Rather the

Waltair-Jharsuguda-Titlagarh- Calcutta route has been considered. The possibility of

competition between Visakhapatnam and Calcutta Ports is temporary because the

economic hinterland of Paradip Port is yet to be exploited by it. Once Paradip Port is

suitably linked to its economic hinterland, the point equidistant from Visakhapatnam

and Calcutta Ports will fall in the economic hinterland of Paradip Port. In case of

Visakhapatnam and Bombay Ports, five railway routes have been considered. These

routes are:

1. Waltair- Secunderabad-Poona-Bombay;

2. Waltair-Secunderabad-Marmad-Bombay;

3. Waltair-Kazipet-Wardha-Marmad-Bombay;

4. Waltair-Raipur-Nagpur-Manmad-Bombay;and

5. Waltair-Jharsuguda-Katni-Bomb~y routes.

In so far as Visakhapatnam and Mormugao Ports are concerned, the possibility

of direct competition is very little. The equidistant points between the Visakhapatnam

and Mormugao Ports fall near Gaupalli station on the Waltair-Guntur-Guntakal­

Mormugao routes (644 Krns. away from the Visakhapatnam Port) and Balanagar station

on the Waltiar-Khazipet-Dronachalam-Mormugao route (778 Krns. from the

Visakhapatnam Port)? As both these points fall in the economic hinterland of Madras

Port, the chances of direct competition between Visakhapatnam and Murmugao Ports

"Traffic Analysis and Forecast -Master Plan Study(l986-2002A.D.)- Visakhapatnam Port", Volume II, , IPA, New Delhi, June 1988

254

Page 12: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

are remote. The railway distance between Visakhapatnam and Kandla Ports and

Visakhapatnam Cochin ports have not been considered because the Visakhapatnam Port

is not likely to face any competition from either Kandla or Cochin Port.

In all, therefore, ten railway routes linking Visakhapatnam Port to the other

Major Indian Ports (in this case Madras, Bombay, Paradip and Calcutta) from which it

is likely to face competition have been considered and points equidistant from the

Visakhapatnam Port and these Ports marked off. Calculation regarding the marking off

these points is presented in the Table 7.43

Based on the Railway links and economic advantages available for the use of

this mode of transport, the hinterland for the Visakhapatnam Port has been determined

(Refer Table 7.3). The spatial extent of this economic advantage zone consists of 36

districts spreading over four states as given below.

Ibid.

255

Page 13: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.3

Hinterland Demarcation of Visakhapatnam port by Railway Connection

State/District

Andhra Pradesh 19. Ganjam

1. Srikakulam 20. Phulbani

2. Viziangram 21. Kalahandi

3. Visakhapatnam 22. Bolangir

4. East Godavari 23. Sambalpur

5. West Godavari Madhya Pradesh

6. Krishna 24. Raigarh

7. Guntur 25. Raipur

8. Kurnool 26. Bastar

9. Mahabubnagar 27. Durg

10. Nalgonda 28. Bilaspur

11. Hyderabad 29. Jabalpur

12. Medak 30. Shadol

13. Nizamabad 31. Mandla

14. Adilabad 32. Seoni

15. Karimnagar 3 3. Balaghat

16. Warangal Maharashtra

17. Khammam 34. Chandrapur

Orissa 35. Nagpur

18. Koraput 36. Bhandra

Source: Traffic Analysis and Forecast, Volume II, Master Plan Study(1986

2002A.D.)- Visakhapatnam Port, IPA, New Delhi, June 1988.

256

Page 14: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.4

Points equi-distant from the Visakhapatnam Port and the nearest Indian Major Ports on various Railway Routes

Hinterland boundary point on the railway Other Major Port Total chargeable distance in Chargeable rail Other nearest line nearest to the Kms. By rail between distance in Km from Major Port

boundary point Visakhapatnam and other Visakhapatnam Port Major Port

I. 7 Kms South of Tenali on the Vijawada Madras 780 390 390 Madras Section 2. I Km. West ofChelimation on the Guntur Madras 1250 625 625 Guntakal Section 3. II Kms. South ofTimarpur on the Madras 1518 759 759 Secunderabad- Dronachalam- Guntakal Section 4. 5 Kms West of Sharkarpali on the Bombay 1504 752 752 Secunderabad Poona Section 5. Akanapet Station on the Secunderabad- Bombay 1586 793 793 Manmad Section 6. 6 Kms South of Tadali on the Kazipet Bombay 1698 849 849 Wardha Section 7. 4 Kms. South ofNagpur on the Nagpur- Bombay 1668 834 834 Wardha Section 8. I 0 Kms. South-West of Gosalpur on the Bombay 2038 1019 1019 Bilaspur Kantni- Jabalpur Section 9. 5 Kms. South of Lapanga on the Titlagarh- Calcutta 1070 535 535 Jharsuguda Section I 0. 2 Kms. North of Golanthra on the Waltair Paradip* 562 281 281 Cuttack Section

• The rml distance between Cuttack and Parad1p has been taken as 96 Kms.

Source: Traffic Analysis and Forecast, Volume II, Master Plan Study(1986-2002A.D.)- Visakhapatnam Port, IPA, New Delhi, June 1988

Page 15: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Based on the definition and extent of hinterland explained earlier, the immediate

and primary hinterland for incoming and outgoing traffic for Visakhapatnam Port will

comprise of the State of Andhra Pradesh. The district mentioned above of Orissa,

Madhya Pradesh and Maharashtra will form the secondary and economic hinterland.

Though, it is true that some of the items originating from Andhra Pradesh are presently

exported through Madras and Bombay ports, they will come back once full scale

container handling facilities are available at Visakhapatnam Port. The Port is better

known for its efficiency now, and will certainly have an economic advantage over the/

neighbouring ports once the infrastructural facilities are developed.

7.3.3 Pipelines

The Port has major pipelines to serve the import of crude and import/export of

POL products - the main oil berth is located at the Outer Harbour. This is linked by

pipeline through the Lova garden area to the HPCL refinery loacted within the port

area. Recently an LPG berth was commissioned at the Outer Harbour which is linked to

HPCL storage area by a pipeline. All the pipelines in the port connect to storage within

the port area. From this storage the cargo moves by road or rail. There is a proposal to

have a long distance pipeline for POL products linking Visakhapatnam to Vijaywada.

7.3 Extent of the Hinterland

The hinterland of Visakhapatnam Port has been determined by taking into

account

the commodity composition of traffic available,

the changes in the traffic pattern that will arise once industrialisation matures in its

hinterland,

consequential changes which will ultimately take place at the point of origin and

destination of cargo passing through the port due to technological development and

expansion in transport linkages and finally,

• the impact of competing ports.

258

Page 16: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Based on these criteria, the delineated hinterland of Vishakhapatnam is fairly large.

It covers Bailadilla iron-ore mines in Madhya Pradesh as well as sources of thermal coal

and alumina in Orissa. Coking coal is imported through this port to serve

Visakhapatnam, Bhilai and Durgapur Steel Plants. However, the liquid cargo is mostly

for the refinery located in the port area itself and for the areas close to the port. All the

origins/destinations of major cargo are well connected through railways. In order to

transport other break-bulk cargo like grains, fertiliser etc., good road system exists

within the port and outside through its link to NH-5.

Since the major quantum of cargo handled at Visakhapatnam is rail borne, great

emphasis has been given to analyse the rail transport linking the port and its hinterland.

This is because bulk commodities account for major portion of the port's traffic for

which rail transport is regarded as the most suitable mode of transport for their

movement over long distances.

Port and hinterlands are interactive, both have an effect on each other but the

success and future of a port is the product of its hinterland. An agriculturally and

industrially rich hinterland lying close to the port is an additional favourable factor for

port development. In this context, first, a comprehensive study of Visakhapatnam

District is essential to assess the present and future growth of the port. The VEPZ also

falls in the immediate or primary hinterland of the Visakhapatnam port. The extended

hinterland of the port crosses state boundaries and covers adjoining states of Orissa,

Madhya Pradesh, Karnataka and Maharashtra.

7.3.1 Immediate/Primary hinterland of Vishakhapatnam Port (Vishakhapatnam

District)

The district has a population of 3 2. 72 lakhs as per 1991 census, which

constitutes 4.95 percent of the population of the State. The density of population of the

district is 294 per sq. km. The district has a working force of 12.89 lakhs constituting

about 38.92 percent of the population besides 10.05 lakhs marginal workers. According

to 1991 census, there are 12.63 lakh literates in the district forming 3 8.49 percent of the

total population of the district, male literates constitute 62.15 percent and female

literates (37.84 percent).

259

Page 17: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

• Resources:

Agricultural Resources

Agriculture is the main occupation of around 70 percent of the households.

Though Viaskhapatnam is industrially developing, the rural areas continue to be

backward due to lack of adequate irrigation facilities. The important crops grown in the

district are paddy, ragi, sugarcane, groundnut, vegetables and fruits and chilies.

According to the statistics available cultivated area and annual production in

tonnes is as follows:

Table 7.5

Agriculture in Vishakhapatnam District (1991)

Item Area in hectares Annual production in tonnes Paddy 85,150 183000 Ragi 32,792 38000 Sugarcane 24,458 1637000 Groundnut 29,980 37000 Vegetable and Fruits 36259 NA Chillies 5669 15000

Source: Industnal Scenar10 of Vtsakhapatnam Dtstnct, The Vtsakhapatnam Estate

Industrialists' Association, Silver Jubilee Celebrations, 6th December 1997,

Visakhapatnam.

Quite a good number of agro based industries have come up in the district. Still

there is vast scope for establishing these types of industries in the district.

Live Stock Resources

Visakhapatnam district has a total live stock population of 12.26 lakhs and 22.77

lakh poultry population respectively. As per the statistics available, the breakup of live

stock population is as follows:

260

Page 18: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.6

Livestock Resources in Visakhapatnam District (1991)

Live Stock Population in Lakhs

Cattle (white) 4.59

Buffaloes 4.21

Sheep 1.84

Goats 2.39

Pigs 0.90

Source: Industnal Scenano of V1sakhapatnam D1stnct, The V1sakhapatnam Estate

Industrialists' Association, silver Jubilee Celebrations, 6 th December 1997,

Visakhapatnam.

There are no organised units for the manufacture of leather goods even though

tiny leather based units are existing. There is scope for establishment of a couple of

units for the manufacturing of leather goods. Scope exists for establishment of

bonemeal factories, meat processing units and one or two tanneries.

Marine Resources

The district has the advantage of having a long coastline of about 160 km, which

helped development of salt, and marine based industries. Salt fields are concentrated at

Bhimunipatnam, Karasa, Balacheruvu, Vada Cheepurupalli and Pudimadaka villages.

Since salt fields are abundant, there is scope for establishment of few iodised salt

manufacturing units. Huge quantities of prawns and fish catch helped setting up of

eleven large and medium scale industries besides twenty in small scale.

Forest Resources

About 41.8 percent of the total geographical area of the district ( 4.67 lakh

hectares) is covered under forests. The major forest produce are timber (6,537 hectares),

fuel and bamboo (1.48 lakh hectares), while minor produce are tamarind, myrobalan,

ginger, turmeric, shekakai, honey, soap nuts etc. Coffee plantation is also being

encouraged in the agency area in about 7,225 hectares. The Girijan Cooperative

261

Page 19: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Corporation is the main agency that is collecting many of the forest produce in the

agency areas.

Mineral Resources

The district is mostly covered with hilly terrain and has huge deposits of

limestone and bauxite. Due to the establishment of the Visakhapatnam Steel Plant, 15

industries for the manufacture of Cement based on slag available with the plant have

been encouraged by the district administration, out of which 12 have already been

established excluding the Andhra Cement Company and 3 are under implementation. In

addition to these, about 6 units in Visakhapatnam district, 4 units in Vizainagram

district, and 4 in Srikakulam district have come up on their own.

• Industries

Large and Medium Scale Industries

53 Large and Medium Scale Industries are existing in the district. Out of this,

there are 7 industries in the Public Sector, 5 in Cooperative Sector and 41 in Private

Sector. The total investment in these industries adds upto Rs.9324.53 crores. There are

46573 persons employed in these industries.

The Public Sector units include the prestigious Visakhapatnam Steel Plant, The

Hindustan Shipyard, Hindustan Zinc Ltd., Hindustan Petroleum Corporation and the B.

H. P. V. Ltd. The units in Cooperative sector are four sugar factories at Dariapudi,

Anakapalli, Govada, and Tummapala. The other one is the Visakha Cooperative Dairy.

Among the units in Private sector, 11 are engaged in the processing of f\'Iarine products,

the L. G. Polymers (India) Ltd., Pragathi Fertilisers Ltd., Coastal Chemicals Ltd.,

Oxygen and Acetylene Gas manufacturing units, The Andhra Petro Chemicals, Essar

Gujarat Ltd., Dairy Units, Coke briquettes and also a Korean joint venture

manufacturing fish, meat and paste.

Besides the above, 24 Large and Medium scale industries are in advanced stage

of implementation among the units awaiting implementation. There are also 15098

Small Scale Industrial units in the district. There are 140593 persons employed in these

industries. Total investments in SSI unit's amount to 11571.52lakhs.

262

Page 20: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Ancillary Industries

There are 5, 716 small scale industrial units in the district. Efforts are still going

on to encourage some more ancillary/downstream industries to come to the

Visakhapatnam Steel Plant.

Small Scale Industries

The Agro and Food processing industry has shown dominance in the region due

to the fact that the region is basically such as Modern Rice Mills, Sea food processing,

Bakery, Pulse grinding, Confectionery, Masala Grinding Pickles, Papad making,

descicated coconut, coir fibre extraction, cashew processing are the important agro-food

processing units in the districts. The other industries in this region comprise of

Engineering industries, Glass and Ceramic products, Chemical products, leather and

leather products, electrical and electronic items, hosiery products, automobile spares,

agriculture implements etc. The breakup of SSI industries is as under:

Table 7.7

Small Scale Industries in Visakhapatnam District (as on 30/4/1997)

Category of Number of Number of Investment in Industry Units Persons Employed Rs. Lakhs Agro based 1427 2110.62 13842

Forest based 3675 850.38 30081

Mineral based 498 1132.42 10414

Textile based 234 352.42 5514

Engg. Based 5047 3031.36 35722

Chemical based 656 1598.62 3737

Live Stock based 378 178.41 3552

Building materials 251 353.39 5287

Other industries 2932 1963.56 30444

Total 15098 11571.52 140593

Source: Industnal Scenano of V1sakhapatnam D1stnct, The V1sakhapatnam Estate

Industrialists' Association, silver Jubilee Celebrations, 6 th December 1997,

Visakhapatnam.

263

Page 21: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

• Infrastructure:

The infrastructure facilities already created in the Industrial Estates/Industrial

Development Areas in and around Visakhapatnam attracted quite a good number of

industries. Only about 95 plots/sheds are still available for allotment to the SSI units

coming up. As such the A. P. I. I. C. Ltd. Has already taken action to procure about

3500 acres of land near Parrawada to cater to the needs of industries. Since

Visakhapatnam is an ideal location for starting industries with its existing facilities like

Port, Rail, Road and Air links the following mega projects are likely to come up near

Parawada in this district.

Indorama Synthetics - PTA Project

Mahindra and Mahindra- Tractors assembling project

Proton Cars Project

Hinduja Power Plant

NTPC Thermal Projects

The implementation of the above mega projects will g1ve tremendous

encouragement to more upstream and downstream industries. As such the Industries

Department is planning to identify sites for the development of new industrial area in

the surrounding areas of Parawada, to cater to the needs of Small Scale Industries.

Besides the above about 1800 units are being encouraged every year under tiny and

small- scale sector with an addition of 10 percent every year.

By making full use of the resources like production of cashew, pineapple,

mangoes, other agricultural produce, live stock, marine products, mineral deposits there

is vast scope of development of resource based industries.

• Industrial Estates and Industrial Development Areas in the Immediate

Hinterland of the Port

To assess the extent of the industrial activity in the primary hinterland of the port,

a glance at the following data is useful. As on 31. 03. 1994, the number of factories

registered under Factories Act in the Visakhapatnam district was around 558,

employing about 50982 workers. Though not all the factories have direct export and

264

Page 22: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

import potential but most of them were ancillary to port-based industries like

manufacture of machinery and equipment, manufacture of non-metallic mineral

products, repair of capital goods etc. These are industries, which have developed in the

hinterland because ofthe existence of port, and other port-related industries.

The Andhra Pradesh Industrial Infrastructure Corporation has so far established

seven Industrial Estates at Visakhapatnam, Gajuwaka, Pedagantyada, Anakapalli,

Paderu and Chinthapalli. An Autonagar, an assisted Private Industrial estate and an

Engineering Entrepreneurs Industrial Estates are among them which are developed near

Bharat Heavy Plates and Vessels Ltd., Visakhapatnam. One Industrial development

Area with A, B, C and D Blocks is also developed in close proximity to the above area,

and another in Pedagantyada.

The Corporation has taken up expansion programme of the Industrial Estates

and proposes to expand the existing Industrial Development Areas. Visakhapatnam for

50 acres, exten3ion of the Industrial Development Areas at Gurrampalem for 200 acres,

Aganampudi for 250 acres and Autonagar at Narsipatnam (8 acres), Chodavaram (50

acres) besides land (200 acres) for Petro Chemical Complex at Vada Cheepurupalli.

• Visakhapatnam Export Processing Zone (VEPZ)

The Government of India has set up an Export Processing Zone 4 at

Visakhapatnam in March 1989 encouraged by the overall performance of the

functioning of EPZs. Visakhapatnam being a major growth centre on the East Coast

with an impressive array of heavy engineering industries including an integrated steel

plant, a fertiliser factory and commercial infrastructure like banking, insurance and port

facilities was considered relevant for the establishment of the EPZ.

In order to meet the requirements of export oriented industries the

Visakhapatnam Export Processing Zone was set up at a strategic location very close to

Export Processing Zones constitute an important element of export promotion policy in developing countries and thus it is considered as an effective instrument for promotion of exports and thereby earn foreign exchange. An export Processing Zone is a separate enclave for setting up of industries for manufacture of products exclusively for exports. The first EPZ in India was established in Kandla in Gujarat State in 1965, which also happens to be the first in Asia. A decade later another EPZ came up at Mumbai, followed by four more in 1983 at Chennai, Cochin, Falta and NOIDA respectively. The Seventh one is set up in Visakhapatnam. Thus, in all there are seven EPZs in India as in 2000.

265

Page 23: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

the Duvada railway Station where excellent infrastructural and communication facilities

are provided. It also has in house customs/excise facilities. Visakhapatnam was chosen

for establishing the Export Processing Zone because

1. It is an important port on the East Coast of India

11. It is one of the fastest growing cities oflndia and Asia

iii. It is well connected to the rest of the world

iv. It is close to an important industrial belt of Andhra Pradesh.

An extent of 360.51 acres of land was acquired in Duvada village,

Visakhapatnam district through the Government of A. P. Out of this, 163.0 acres were

developed in the Phase - I at an estimated cost of Rs. 20.0 crores. Various facilities are

provided to set up Export Oriented Industrial Units in the Zone. The most important of

them are the basic infrastructure facilities, supportive services and utilities necessary for

the units. These may be summarised as follows:

Land : Developed plots are made available on lease basis for a period of 15 years to

begin with and renewable thereafter. The sizes of these developed plots are of varying

sizes ranging from half acre and above and the lease rent charged is Rs. 16/- per sq. mtr.

per annum with a concession of 75 percent, 50 percent and 25 percent in the first,

second and third years respectively.

Ready-built Area : Built-up area is also available in the SDF building in a modular

form. Units of sizes ranging from 467 sq. mtr. To 1100 sq. mtr. are available on lease

basis for a period of 5 years and renewable thereafter. The lease rent charged is Rs.

300/- per sq. mtr. Per annum with a concession of 50 percent, 40 percent and 25 percent

in the first, second and third years respectively.

Power : A 33 KV sub-station is exclusively functioning for the zone units. The Central

and State Governments meet the infrastructure cost of providing power. The unit­

holders will have to pay the actual consumption charges only. Hence, power to any

extent can be supplied to the units in VEPZ.

Water : Provision has been made to supply water to the units in VEPZ by sinking

infiltration wells in Meghadrigedda reservoir in addition to 4 nos. borewells in the zone

premises.

266

Page 24: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Utilities : Apart from the basic infrastructure facilities, common utilities such as

telephone and telex connections are also provided. A 100-lines telephone exchange is

installed in the Zone to provide telephone connections to the units on out-of-turn

priority basis.

Banking : Essential supportive such as banking, postal and telecom services, canteen

etc., are also provided.

Custom Facilities : A Customs Wing forms part of the Zone administration. As such,

all customs and central excise clearances required by the unit are provided within the

zone premises. Hence, no separate registration with Central Excise is required for

obtaining CT 3 Forms etc.

Port Facilities : Visakhapatnam Port, one of the major Ports in the country is equipped

with most modern berthing, handling and storage facilities. Facilities for safe anchorage

of ship upto 50,000 DWT and regular feeder service in container traffic to all major

Ports in the world are available. ·

Single Window System : In addition to the above, a unique Single Window System is

in operation m VEPZ to guide and assist entrepreneurs m obtaining

permissions/clearances from various agencies. Once the application for setting up the

unit is received in VEPZ, the Single Window System takes care of all the requirements

of the unit by helping and assisting them in obtaining permissions/clearances from

various government agencies etc. Hence, the unit-holders need not go around different

offices for permissions/clearances and, thus, can save lot of time.

Incentives/Concessions offered : The present economic policy of the Government lays

greater stress on export-oriented industries. Both the Central and State Government are

offering a wide range of incentives/concessions made available to the units in VEPZ.

Incentives from Government oflndia:

• Total exemption from Custom Duty on both capital goods and raw materials and no

Import License is required for imports under OGL.

• Full reimbursement of Central Excise Duty on capital goods and manufactured

items. Besides, full reimbursement of Central Sales Tax is permitted on supplies

made by the DT A units.

• Tax Holiday on profits earned by the units for a period of 5 years.

267

Page 25: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

• Foreign investment permitted upto 100 percent equity and full and free repatriation

of profits allowed after payment of taxes.

• Liberal sanction of foreign exchange including blanket permits for business visits

abroad.

• Eligible for DT A sale to the extent of 25 percent of production in value terms .

• Incentives from the Government of Andhra Pradesh :

• Investment Subsidy- Investment Subsidy of 20 percent of the fixed capital invested

subject to a maximum of Rs. 20 lakhs.

• Sales Tax- Sales Tax Deferment Limited to 135 percent of fixed capital investment

in a period of 14 years.

• Exemption of SSI Units- SSI units are granted Sales Tax Holiday for a period of 15

years subject to a maximum of Rs. 35 lakhs or the total fixed capital investment,

whichever is less.

• Power Tariff- Rebate of 25 percent on power bills (both demand and energy) for a

period of three years from the date of commencement of commercial production

subject to a maximum of Rs. 50 lakhs in the case of medium and large, and Rs. 30

lakhs in the case of small and tiny sector.

7.3.2 The extended hinterland

An attempt has been made to establish the extended hinterland of the

Visakhapatnam port comprising of the States of Madhya Pradesh, Orissa and

Maharashtra which form the primary and economic hinterland for the port of

Visakhapatnam.

268

Page 26: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.8

Extended Hinterland Districts ofVisakhapatnam Port Area and Population (1991)

State Districts Area Population District H.Q. (in sq. (1991 Km.) Census)

Andhra Srikakulam 5387 2321126 Srikakulam Pradesh

Viziangram 6539 2110993 Viziangram

Visakhapatnam 11161 3285092 Visakhapatnam

East Godavari 10440 4541222 Kakinda

West Godavari 7780 3517568 Eluru

Krishna 8734 3698833 Machilli patnam

Guntur 11377 4106999 Guntur

Kurnool 18799 2973024 Kurnool

Mahabubnagar 18419 3077050 Mahabubnagar

Nalgonda 14242 2852092 Nalgonda

Hyderabad 217 3145939 Hyderabad

Medak 9865 2269800 Sangareddy

Nizamabad 7969 2037621 Nizamabad

Adilabad 10133 2082479 Adilabad

Karimnagar 11824 3037486 Karimnagar

Warangal 12875 2818832 Warangal

Khammam 15866 2215809 Khammam

Orissa Koraput 27020 3012546 Koraput

Ganjam 12527 3158764 Chhatrapur

Phulbani 11070 863903 Phulbani

Kalahandi 11835 1600385 Bhawanipatna

Bolangir 8903 1707753 Bolangir

Sambalpur 17570 2697153 Sambalpur

269

Page 27: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

State Districts Area Population District H.Q. (in sq. (1991 Km.) Census)

Madhya Raigarh 12924 2697153 Raigarh Pradesh

Raipur 21258 3908042 Raipur

Bas tar 39114 2271314 Jagdalpur

Durg 8537 2397134 Durg

Bilaspur 19897 3793566 Bilaspur

Jabal pur 10160 2649962 Jabal pur

Shadol 14028 1743869 Shadol

Mandla 12269 1291263 Mandl a

Seoni 8758 1000831 Seoni

Balaghat 9229 1365870 Balaghat

Maharashtra · Chandrapur 10490 1771994 Chandrapur

Nagpur 9931 3287139 Nagpur

Bhandra 9213 2107629 Bhandra

Total 4633310 93420226

3287263

Percentage to 14 percent 11 percent Total of India

Source: Traffic Analysis and Forecast, Volume II, Master Plan Study, Penod: 1986-

2002 A.D. Visakhapatnam Port, VPT, June 1988, IPA, New Delhi.

7.4 Growth of Port Traffic

A review of the cargo throughput and its composition during the past 45 years

suggest how Visakhapatnam port blossomed from a mono-commodity port in 1933 into

a multi-commodity port with a variegated cargo mix. An interesting observation is how

Visakhapatnam always exceeded the targets set by the Ministry, much ahead of

schedule, on almost every occasion:

270

Page 28: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.9

Traffic Growth at Visakhaptnam Port -Target and Actual (1988-1996)

Year Target Actual cargo Date of realisation of the throughput target

1988-89 15.50 20.37 17.1.1989

1989-90 18.95 21.12 2.3.1990

1990-91 19.20 19.42 27.3.1991

1991-92 19.84 21.52 5.3.1992

1992-93 20.83 22.77 4.3.1993

1993-94 21.67 25.60 12.2.1994

1994-95 24.00 30.03 3.2.1995

1995-96 29.90 32.81 1.3.1996 Sl (Note. Year ends on 31 March for every year)

Source: Perspective Plan For Visakhapatnarn Port, 1996-2020, Research and Planning

Department, Visakhapatnarn Port Trust, VPT.

The cargo throughput at the port recorded a phenomenal growth from 0.8

million tonnes in 1950-51 to 34.5 million tonnes in 1996-97. In the decade of 70's,

Visakhapatnam's annual growth rate of traffic was over 10 percent while in the next

decade, it rose to about 13 percent in 1984-85. In the present decade, it is around 11

percent. From 21.5m tonnes in 1991-92, the volume of cargo increased to 34.5 m tonnes

during 1996-97, when it was adjudged as the 'premier port of the country'.

Table 7.10

Traffic Growth Rate (Commodity-wise) at Visakhapatnam Port (1951-1997)

Commodity Traffic in Million Tonnes 1991-92 1996-97

Iron Ore 6.2 5.7 POL 6.4 13.4 Fertiliser and Raw 1.4 1.3 Materials Coal (Coking and 5.6 8.9 thermal) Others 1.9 5.2 Total 21.5 34.5

Source: Art1cle by Y. Jayanth1, 'Plans and Perspectives Of V1sakhapatnam Port w1th reference to Modernisation and Development', October 1997

271

Page 29: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The growth rate in cargo throughput, particularly during the past few years was

spectacular, owing to the setting up of the first port-based Steel plant of the country

(VSP) and rapid industrialisation of the service area. Traditionally, Visakhapatnam port

has been providing dedicated facilities for various ores, fertiliser, fertiliser raw

materials, petroleum crude, POL products etc. Very recently, the port has started

handling containers though of a modest volume. In 1996-97, out of a total throughput of

34.50 m tonnes, 5.70 m tonnes comprised of iron-ore and other ores. 3.71 m tonnes of

thermal coal, 1.3 m tonnes of fertiliser and fertiliser raw materials, 1.39 m tonnes of pig

iron and iron and steel products. A study of the composition of the cargo throughput

shows that mineral oil (crude and petroleum products) under the category of liquid bulk

accounts for more than 3 7 percent of the total cargo throughput. A recent addition to

this cargo is import of LPG. The dry bulk category consists of iron-ore, coking coal,

thermal coal, fertilisers, foodgrains and other bulk cargo like manganese ore, alumina,

limestone, scrap etc .. This group accounts for 54 percent of the total cargo throughput.

The break-bulk though small in volume, comprise of several heterogeneous

merchandise. At present, this accounts for 6 percent of the total cargo throughput and

the major thrust of growth is anticipated in this category.

Table 7.11

Traffic Growth Rate (1950-51 to 1996-97)

Year Growth Rate Year Growth Rate

1950-51 1987-88 2.23

1960-61 34.32 1988-89 32.54

1970-71 35.50 1989-90 3.66

1980-81 87.55 1990-91 - 8.03

1981-82 8.61 1991-92 10.82

1982-83 -7.09 1992-93 5.78

1983-84 -3.27 1993-94 12.43

1984-85 12.14 1994-95 17.32

1985-86 43.58 1995-96 9.28

1986-87 - 5.51 1996-97 5.12

Source: Basic Port Statistics Of India, 1997-98, Transport Research Wmg, MOST, GOI, New Delhi.

272

Page 30: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The total cargo traffic growth rate is extremely fluctuating, 1982-83, 1983-84,

1986-87 and 1990-91 are the years which recorded negative growth rate, where total

traffic figures fell compared to the corresponding previous years. But from 1991-92, the

trend has always been positive, but fluctuating from 5.12 percent (96-97) to 17.32

percent (94-95). This table, however, gives an average picture of Cargo growth rate.

Individual commodity-wise, the picture is more interesting (Refer to Table

3.4c). For POL and products growth rate is most fluctuating from 1950-51 to 1990-91.

While it increased at 2.~3 percent from 1950-51 to 1960-61, and 94.58 percent from

1960-61 to 1970-71, it dropped to 72.38 percent in the next decade, i.e., 1970-71 to

1980-81. The decade of 1980s witnessed variations in POL traffic growth and this trend

became steady only after 1991-92.

This fluctuating growth rate was true for other commodities as well, like

fertiliser, fertiliser raw materials, iron-ore and foodgrains. Coal, however, maintained a

more or less steady positive growth rate, ranging from 5 percent · 17 percent annual

average growth rates in the 90's. As regards, container traffic, Visakhapatnam has less

number of containers as compared to other types of cargo but in recent years stress is

being given to developing a container terminal.

The port was opened for sea-going traffic in 1933 and during the first year of its

operation the traffic was only 1.29 lakh tonnes. The export/import traffic has steadily

grown year to year and the above table indicates the general growth of the traffic. It is

evident that the Bulk cargo exports account for about 43 percent and bulk imports- 45

percent.

Due to rapid industrialisation and economic growth in the hinterland of the port

and the developmental activity undertaken by the Port Trust, like extra berths,

development of stockyards, connected railway infrastructure - all are efforts to work in

unison for movement of smooth traffic flow. In the decade of the 1990s, traffic has gone

up from 21.5 m tonnes (1991-92) to 35m tonnes (1996-97), an increase of about 14m

tonnes. In other words, the growth of the traffic during the last 6 years is about 60

percent.

One of the major factors that contributed for this outstanding performance is the

Port's locational advantage with its naturally sheltered waters with deep draft. The port

273

Page 31: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

is the main economic outlet for the States of Madhya Pradesh, Bihar, Orissa, Uttar

Pradesh and Andhra Pradesh. Secondly, it is well connected to its hinterland by a

national highway and owns, operates and maintains 228 kms of railway networks,

acting as a terminal for South Eastern Railways. Also, the location of core sector

industries in the Primary and Secondary Service areas have stimulated traffic growth in

the past decades.

7.5 Performance of the Port

Performance of Visakhapatnam port has been gauged on the basis of following

indicators:

• Average Berth Occupancy (percent)

Berth occupancy is a measure of the facility utilisation of a port. The gross berth

occupancy is considered to be more useful and is generally adopted. According to the

UNCTAD rule, the berth occupancy should be 70 percent for a berth group of 6 berths

or more. The overall berth occupancy of the Visakhapatnam port is given in the table

above. Over the years, the percentage has increased, crossing the 70 percent mark (in

the 1990s) which indicates inefficiency due to congestion and other factors.

Table 7.12

Average Berth Occupancy at Visakhapatnam Port (1980- 1996)

(In%)

Year Berth Occupancy Year Berth Occupancy

1980-81 55.81 1989-90 77.90

1981-82 58.83 1990-91 81.90

1982-83 53.59 1991-92 91.00

1983-84 58.94 1992-93 87.5

1984-85 63.99 1993-94 92.7

1985-86 69.69 1994-95

1986-87 54.47 1995-96

1987-88 56.90 1996-97

1988-89 63.30 ..

Source: Baste Port Statlstlcs Oflndta, 1997-98, Transport Research Wmg, MOST, GOI, New Delhi.

274

Page 32: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Average Output per Ship Berth Day (Tonnes)

Average output per ship berth day figs. Are given commodity-wise as rate of

handling differs with various types of cargo. For eg. it is maximum for liquid bulk (POL

and products) and less for break bulk and minimum for containers (See table above).

The (total) average output per ship berth day however is increasing which is a positive

trend showing the output per day is on the rise for a ship at berth at Viazg port (5688

tonnes in 1993-94 to 6553 tonnes in 96-97). The output per berth day of this port in case

of certain bulk commodities is high compared to other similar ports.

Table 7.13

Average Output per Ship Berth Day (commodity-wise) at Visakhapatnam Port

(1980-1986)

Type 1980-81 1981-82 1982-83 1983-84 1984-85 1985-86

Foodgrain 543 572 922 778 395 461

Fertilisers 464 518 912 898 510 329

Iron-ore 17976 44856 36840 21120 20925 9552

General 632 666 669 650 432 415 Cargo Oil 5132 6029 4761 3994 3847 6490 (mineral)

.. Source: Basic Port Statistics Oflndia, 1997-98, Transport Research Wmg, MOST, GOI,

New Delhi.

Table 7.14

Average Output per Ship Berth Day (cargo category-wise) at

Visakhapatnam Port (1986-1997)

Type 1986-87 1993-94 1994-95 1995-96 1996-97

Dry Bulk 403 19724 19854 42281 4143

Liquid Bulk 769 14570 14844 19903 19306

Break Bulk 17869 1431 1321 1173 1633

Containers 638 1073 1432 1095 1601

Total 7621 5688 6089 5341 6553 ..

Source: Compiled from Basic Port Statistics, MOST, GOI.

275

Page 33: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

• Percentage of Idle Time at Berth to Time at Working Berth

The above table shows a healthy trend. For all categories of cargo, percent of

idle time at berth is on the decline, which is nodoubt impressive. This shows nothing

but less wastage of time when a ship is at berth. More time utilisation or less of idle

time shows efficiency of the port.

Table 7.15

Percentage of idle time at berth to time at working berth at

Visakhapatnam Port (1993-1997)

Type 1993-9~ 1994-95 1995-96 1996-97

Container 21 18 17.98 15.78

Break-Bulk 27 24 21.20 18.62

Dry Bulk 28 21.5 23.88 19.61

Liquid Bulk 35 32 31.08 29.68

All Types 26 23 24.22 24.54

Source: Compiled from Basic Port Statistics, MOST, GOI.

• Average Turn Round Time (Days)

By definition, Average TRT (days) shows the total time ship spent by a ship

after reaching sandhead, proceeding towards the harbour, pre-berthing detention, if any,

time at berth, return passage to sandhead after loading/unloading. TR T entails the total

time for all these activities. Any delay in any of these activities due to any reason may

cause ship delay, thus increasing the TRT. More the TRT, less the efficiency of the port

and vice-versa. From the Table 7.16, it is evident that Average TRT for all types of

cargo in Visakhapatnam port is fluctuating from year to year so there is no fixed trend.

This indicator shows the overall performance of any port. Faster TRT, means faster

disposal of cargo indicating better performance. Compared to 1995-96, TRT has

improved in 1996-97 for all categories of cargo.

276

Page 34: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.16

Average turn around time at Visakhapatnam Port (1993-1997)

Type 1993-94 1994-95 1995-96 1996-97

Container 1.8 2.6 2.79 2.32

Break-Bulk 8.4 8.7 I 0.11 6.84

Dry Bulk 7.05 6.65 11.56 8.79

Liquid Bulk 2.5 2.2 3.09 2.96

All Types 6.0 5.6 7.78 5.73

Source: Compiled from Basic Port Statistics, MOST, GOI.

• Number of Vessels

If number of vessels by any standard is an indication of how a port is performing

then Visakhapatnam port's performance is easy to judge from the table below:

Table 7.17

Number of vessels at Visakhapatnam Port (1975- 1998)

Year No. of Year No. of Year No. of vessels vessels vessels

1975-76 547 1983-84 579 1991-92 870

1976-77 529 1984-85 625 1992-93 951

1977-78 458 1985-86 754 1993-94 1043

1978-79 492 1986-87 642 1994-95 1209

1979-80 564 1987-88 1995-96 1390

1980-81 563 1988-89 699 1996-97 1471

1981-82 557 1989-90 788 1997-98 1529

1982-83 589 1990-91 813

Source: Compiled from Basic Port Statistics, MOST, GOI.

Efficient financial management is important for all public undertaking including

ports. A sound financial management would enable a port administration to keep all

port facilities at a high technical and operating level and to render efficient and

277

Page 35: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

economically viable services to its users. 5 Visakhapatnam port has passed through a

precarious financial position with deficits reaching menacing proportions since the

commissioning of outer harbour in 1976-77. Deficits in such menacing proportions

result in colossal waste of limited national resources. But the port has come of that

situation successfully and today can claim itself to be in a financially comfortable

position.

• Operating Ratio (in percent) and Operating Surplus (crores)

The operating ratio figures show operating expenditure to operating income as a

percentage. Lower the share of operating expenditure, better is the financial condition of

the port as it indicates that the port concerned spends less out of its operating income

over the reporting period. Visakhapatnam's financial performance is improving

compared to 1991-92 (operating ratio 72.63 percent). Operating surplus gives the actual

surplus figures which show a consistent rise - no doubt a healthy sign for a port.

Table 7.18

Operating Ratio and Operating Surplus at Visakhapatnam Port (1984-1997)

Year Operating Operating Year Operating Operating Ratio Surplus Ratio Surplus

(percent) (crores) (percent) (crores) 1984-85 68.01 19.08 1991-92 72.63 36.93

1985-86 66.64 23.05 1992-93 64.76 57.75

1986-87 69.68 23.66 1993-94 61.04 70.50

1987-88 76.87 18.73 1994-95 62.35 78.71

1988-89 67.87 34.47 1995-96 60.17 97.18

1989-90 57.00 52.65 1996-97 61.41 104.55

1990-91 68.15 37.67

Source: MaJor Ports Of India: A profile: 1991-1998, Indian Ports AssociatiOn, New

Delhi.

Y. Gouthama Rao, Financial Management in Public Undertaings.

278

Page 36: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Human Resource Productivity

It is interesting to note that the importance of 'Human Resource' has been

recognised. Productivity or performance level of a port can be improved by better

training (mainly technical) of manpower and also by encouraging the workforce by

introducing work oriented incentives. Basic economic principle recognises that labour is

one of the factors of production along with land, capital and entrepreneurship or

organisation. With mechanisation, productivity improves replacing labour intensive

technology with capital intensive ones. But, even then importance of manpower exists,

not in terms of quantity or number but in terms of quality. By proper training,

productivity of labour increases by improving the quality of manpower. It is to fulfill

this particular aim that the 'Port Technical Institute' at Visakhapatnam port under the

VPT was established in the late 70's. The principal objective is to train the employees

and apprentices selected by the port.

The principal objective is to train the employees and apprentices selected by the

port. The aims of the training programmes would be as under:

to improve the skills and efficiency of the worker;

to help the worker to understand the working environment and appreciate the

importance of the work;

to widen the horizon of understanding and comprehension;

to inculcate greater sense of identification with work and the organisation in the

worker;

to generate. a sense of participation in the worker;

to break the traditional ideas imbibed in the mind of the worker and imbibed in him

a scientific approach and outlook.

to expose the worker to the technological advances in the field of his work;

to make the worker a better worker.

Techniques for Determining Training Needs : The following 11 Techniques can be

used for determining training needs. They include observations, management requests,

interviews, group conferences, job or activity analysis, questionnaires surveys, tests or

279

Page 37: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

examinations, merit or performance ratings, personnel records, business and production

reports, long-range organisational planning.

Year

1977-78

1978-79

1979-80

1980-81

1981-82

1982-83

1983-84

1984-85

1985-86

1986-87

1987-88

1988-89

1989-90

1990-91

1991-92

1992-93

1993-94

1994-95

1995-96

1996-97

1997-98

Table 7.19

Employees trained at Port Technical Institute -

Visakhapatnam Port (1977- 1998)

Officers Supervisions Ministerial

17 36

13 112

35 104

26 200

55 ' 66

134 119

106 178 81

118 166 146

450 195 100

170 185 121

40 116 252

255 69 266

377 189 216

408 400 147

412 686 187

317 612 432

828 615 313

413 545 405

516 344 468

187 266 350 ..

Source: Port Trammg Institute, VPT

280

Workers

709

826

667

422

290

233

191

182

112

245

472

324

446

337

152

141

322

304

931

1375

1528

Page 38: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.20

Sample training programme conducted at Port Technical Institute­

Visakhapatnam (1997-98)

Title of the course Number of Number of Batches Participants

Refresher Courses For Electricians 4 40

Refresher Courses For Fitters 4 77

Cleanliness of the Deck on the Dredger 2 31

Quality Circles Review Classes 20 858

Coordination between Deck and Engine 3 46

Room Personnel

Supervisory Development Programme 3 78

Health Awareness 7 127

Training Programme On Sanitation 6 109

Personal Computer 6 76

Capsule Course for Non-fired CISF 2 60

Personnel

Serangs and Tug Master Gr.II 1 7

Disciplinary Proceedings and Domestic 1 20

Enquiries

Two Days need based seminar for Woman 1 20

Employees

Source. Port Trammg Institute, VPT, 1998

281

Page 39: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Part II - Visakhapatnam Port : Information from the Field Study

7.6 Current Problems, Corrective Measures and Growth Prospect

To discuss the issues relating to current problems and prospect of this bulk port,

a field survey was undertaken at Visakhapatnam Port, in August, 1998. An open-ended

questionnaire was prepared keeping in mind the target group (Users, Management and

Unions) for conducting in depth interviews. Accordingly, three sets of questionnaires

were administered to the three identified groups, associated with port functioning. Wide

cross-sections of people were interviewed mainly from the user side, as it is the port

user who actually has the final say in choosing a port of call. Going by the logic that

traffic in a port is dependent upon consumers/user's choice, a port has to satisfy its

customers or users in order to attract traffic and remain competitive. In other words, in

economic terms, the port sector is a buyer's market, where the port user is the buyer and

seller is the port authority offering services to be availed of. The current problems of the

port were assessed from the users as well as from the port's point of view. The port

management, in spite of good intentions, fails to achieve much as it has serious

limitations within which it has to work. Since a port has different activities, the

problems are of various dimensions. Corrective measures to tackle such problems and

future growth prospects of the port were the common issues discussed with all

interviewees. Last, but not the least, the port workers, who are an integral part of proper

port functioning, were taken into consideration. The contribution of the training

.institute, one of its kind in Visakhapatnam Port, which claims to have positively

changed the attitude of port workers through various training programmes, was also

assessed. In this regard, the Director of Port Training Institute (PTI) was interviewed.

Moreover, opinion of the Worker's Union was noted which represented the viewpoint

of the port workers, on different aspects of port functioning.

It is important at this juncture to mention the relevance of this qualitative survey

undertaken at Visakhapatnam Port. Data analysis, literature survey, document scanning,

etc. - all are tools, which do throw light on various aspects of port functioning but

certain gaps still exist which need proper explanation. To compliment the documented

material, a need was felt for a qualitative survey over and above a quantitative analysis.

282

Page 40: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

It should be admitted at the outset that the opinions expressed on different aspects of

port functioning are those of a few selected port users'. Since, opinions within Unions

and Management might differ, interviewees were selected with utmost caution after a

background study so that a true unbiased picture emerged out of the survey. It must be

mentioned in this context that except on few vital issues, like Gangavaram, opinions

differed from person to person. Care has been taken to respect individual viewpoints but

even then some issues might have remained unexplained.

The rationale for the selection of interviewees has been as follows:

Port Users- Defined as those who have been using the services of the port for more

than fifteen years (active both in pre and post liberalisation phase) in various capacities

included Stevedores, C & F agents, exporters, importers, etc. Also attempt had been

made to contact those users who have been the Trustees of the Viaskhapatnam Port and

knowledgeable enough to comment on various issues concerning the port especially in

the present fast changing maritime world scenario.

Port Management - Key persons at all hierarchical levels and from vanous

departments of the port management such as Chairman - in charge, Deputy Director

Planning, Traffic Manager and Manager (Operations) - were selected for the

interviews.

Port Unions- The oldest and numerically the most powerful Union was contacted. The

General Secretary was interviewed with regard to issues concerning labour. Also at

random a few dock and port workers were asked a few basic questions on labour

welfare issues, port functioning and rel~ted problems.

Interview was conducted to cover the following aspects of training of

manpower, port performance, user opinion, union opinion, port problems, corrective

measures and future growth prospect.

7.6.1 Training

Training of manpower has been one strong point in Visakhaptnam port. It boasts

of a unique port training institute, one of its kind in the country which has made

cardinal contribution towards training of port persons in various categories, from

administrative to technical. Port Training Institute (PTI) was established in 1977 in a

283

Page 41: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

single room with one assistant to the Director. Over the years PTI has grown and today

owns a separate building to conduct its round the year training programmes. Though

meant basically for the Visakhapatnam port employees and workers, it hosts training

programmes for employees of other ports as well as for the staff of the Ministry of

Surface Transport. The employees are given 'in-service training' in this Institute

through the 'bottom-up' approach. The demand for such programmes comes from the

employees who feel the need of the training assistance. Therefore, an area where

training is needed is first identified along with those in need of the training. In the

second stage an appropriate training programme is formulated and the resource persons

identified from other ports or from the two national institutes, viz. NIPM, (Chennai) and

IIPM (Calcutta). Similarly, such programmes for vari<?us other areas of cargo handling

and port related activities are fixed and a year calendar is prepared which is then

circulated to different sections of the port. Employees interested in such programmes

send their consent two months in advance so that proper co-ordination is possible.

During the training, besides free food and accessories such as bags, no other incentive,

(cash or otherwise) is provided except a citation of their participation at the end of the

programme as a token of recognition. But if any worker loses monetarily on account of

attending the programme, instead of continuing with their regular duty (like piece rate

emoluments earned by cargo and shore handling workers over and above their fixed

salary) -they are compensated. At the end of the training, the attending workers prepare

an evaluation report, highlighting their individual viewpoints. These are taken care of

by the PTI so as ~o organise future programmes on such lines, which would be more to

the satisfaction of the employees. The whole process, therefore, is scientifically framed

with the ultimate objective to benefit the port.

One important point to note is that there is no parameter to measure whether

labour productivity has improved with such training programmes. Indirectly, however,

it may be said that if total cargo throughput of the port has increased significantly over

time, then labour or manpower being an important component of port functioning must

have improved its performance too. But qualitatively, impact of training programmes

has been positive mainly in terms of the 'attitude' of the workers. It is through the

training programmes that they are educated to accept changed circumstances of port

284

Page 42: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

operations over time like mechanization, computerization, etc. They are enlightened on

the fact that all these changes are aids to facilitate faster and efficient performance and

not to replace human resources. Workers are also made to realize that the port is a

multi-functioning operational system and entire cargo handling process is like one chain

and any disruption at any time would halt the entire process and the port would suffer.

Each one's sincere participation is pertinent to the smooth functioning of the port

system. This concept has gained ground among the employees over the last 1 0 years.

PTI, therefore, performs a three-fold duty, viz. skill development, knowledge

enrichment and finally changing the attitude of those who undergo training.

The 'quality circle' concept is yet another instance of the 'bottom-up' approach.

There are 51 such 'quality circles', in different departments, each consisting of 15-20

members who voluntarily participate and meet once a week to identify daily problems.

After the problems are listed out, they prioritise them and find possible solutions. To

give it a final shape, once a month a meeting with the Steering Committee (the

Chairman of the port heads the committee) is arranged by the PTI where they discuss

the problems with 'cause and ef~ect' approach. Through 'quality circle', the workers

can have direct access to the management to discuss work-related problems. PTI here

acts as the facilitator or coordinator of such meetings. 'Quality circle' is a method of

involving each worker's active participation in the cargo handling activity of the port,

which is multi-functionary and complicated.

Not all ports have such training institutes and devices of workers' participation

like 'quality circle'. For example, Kandla, one of the premier ports, does not have any

such training programmes or institute. But its cargo traffic remains unaffected; rather it

has progressively grown over the years. Therefore, it cannot be said with certainty that

training improves labour productivity which inturn positively affects cargo traffic. How

does one explain such an anomaly? With Kandla's example, one can apparently

conclude that human resource training has nothing to do with cargo throughput at a

port. A port can prosper without such human resource training. But it is really not the

case. The catch here is the cargo mix of a particular port. Visakhapatnam handles a

variety of cargo, predominant being bulk cargo - both dry and liquid. For efficient

handling of such cargo, proper training of manpower is essential. Whereas, Kandla

285

Page 43: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

handles predominantly liquid bulk (POL and products) where involvement of

manpower is minimum, as the whole process of cargo transfer is rather simple and

mechanical. Therefore, keeping in view the cargo-mix of a port, human resource

management needs to be planned. Some ports need them urgently, some do not, to that

extent. Visakhapatnam and Kandla represent the two extremes of this scale.

It has been widely recognised that incentives do boost up the labour spirit. To

encourage the workforce, productivity-linked bonus, piece rate/incentive payments,

merit certificates and citations as recognition for good work, etc. are given at

Visakhapatnam port. In fact the port has worked on this aspect and has a definite policy

on 'incentive scheme'. One must remember here that incentive scheme for each

individual port is different, as no two ports are the same as regards type of cargo,

natural location, mechanization status, etc.

7.6.2 Port performance evaluation

There are several practical instances of excellent port performance which have

been discussed in here. In case of Visakhapatnam port, no major plan after

implementation proved to be redundant. This is mainly because of the judicious

decisions taken by the Port Authority at the right time. An example of this is the

aftermath of outer harbour construction. The port ran into financial crisis in 1983, when

the annual loss was Rs. 3.5 crores. To make the situation worse, there was no cargo

traffic at all during 1985-87 at the Outer Harbour which was designed to handle 4

million tonnes. This was because ch;:trges of handling at the Outer Harbour were fixed

at higher rates than the Inner Harbour with the intention of recovering the cost. It was

envisaged that deeper draft and modem handling facilities at Outer Harbour would

attract traffic and reduce congestion at the Inner Harbour. But the economic

consideration was perhaps underestimated. Unexpectedly, the outer harbour with a huge

investment remained unutilized, while the Inner Harbour faced traffic congestion. This

was, however, only for a short period. In 1988, the authorities sensed the pulse of the

trade. The handling rates at the Outer Harbour were brought at par with the Inner

Harbour. Within no time traffic picked up so much so that the return on investment was

realised within 4 years and the Outer Harbour designed to handle 4 lakh tonne, was

286

Page 44: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

handling 1.22 million tonnes. Before construction, the internal rate of return (IRR)

calculated based on experience was 12 percent. But within 6 years, post construction

IRR was as high as 25 percent.

Another case is that of iron ore exports. Initially MMTC - the canalising agent

was expected to export 8 million tonnes of iron ore via Visakhapatnam port. Following

worldwide recession of iron and steel, iron ore exports dropped and Visakhapatnam port

lost a substantial volume of iron ore traffic as well. Essar' s pellets plant near the port is

now using the iron ore berth for moving iron pellets to Hazira by coastal movement.

Yet another instance of an appropriate step at an appropriate time is the abolition

of DLB levy on cargoes. Within one year, cargo throughput increased by 5 million

tonnes (from 15 to 20 million tonnes) eroding the loss caused by levy abolition.

Visakhapatnam port, therefore, has always acted according. to the situation. As

Visakhapatnam has less of a containerized general cargo, the threat of losing traffic to

other competing ports is less too. This is because, being a predominantly bulk cargo

port, it has dedicated cargo like POL (Refinery is at the hinterland - HPCL), Fertilizer

(Coromandel Fertilizer), iron ore and alumina which in future would hardly move to

other ports. Keeping this in mind, the rates are hiked varying from 50 percent to 100

percent -- higher for dedicated cargoes and minimum or no hike for general cargo which

is sensitive to hike in rate. This is yet another example of Visakhapatnam's practical

strategy.

Port capacity can be augmented by two methods. Firstly, optimum utilisation of

the current capacity by better equipment facility, proper manpower training etc.. and

secondly, a more obvious capacity addition in the form of new berths or may be a new

port altogether to handle extra traffic. In a resource crunch state like India, the first

option should be worked out first before embarking on massive irifrastructure

investment so that more traffic can be handled on existing ports. As far as capacity

augmentation in Visakhapatnam is concerned, it has almost reached a saturation point.

Action has already been taken for the construction of 4 berths in the Inner Harbour and

2 berths in the Outer Harbours. No further extension of berth is possible in future as

both waterfront and back-up land to install mechanised facility is limited. To optimise

the existing port capacity, 2 grab loaders and higher capacity cranes have been

287

Page 45: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

sanctioned, which would increase cargo handling capacity by another 5 to 6 million

tonnes. The port to handle other cargo when not in use can use captive berth of

Coromandel Fertilizer. By accommodating one oil berth in the Inner Harbour through

some structural adjustment and marginal investment, another additional 2 to 3 million

tonnes of cargo can be handled.

To increase port capacity means either construction of another harbour or

satellite port. The deciding factor would be economic viability to embark on such

projects. The estimated construction cost of outer to outer harbour is Rs. 2500 crores but

it is quite uncertain whether it would attract sufficient cargo traffic to cover the cost.

Here lies the dilemma. Moreover, Gangavaram's position has to be assessed before

launching such a costly project. Gangavaram's status is still somewhat uncertain, as it

has been notified as a state port and not a satellite port to Visakhapatnam. But one thing

is certain, privatization would be necessary, be it a new port or extension of berthing

capacity at the present port of Visakhapatnam. To solve most of the present ailments

and to run the port on commercial and corporate lines, privatization is perhaps the

answer. Social objectives like guaranteed employment opportunity cannot over ride

interests of international trade. There is overstaffing at Visakhapatnam like any other

port and retrenchment of labour by half would put the port on a healthier path. At

present, Visakhapatnam port (including DLB) has 13,000 workers to handle 36 million

tonnes. In Gangavaram, as per the plans, 22 million tonnes of cargo will be handled by

only 11,00 people as it will handle would be a modern mechanized port in tune with the

present demands. Privatization would also reduce hug~ demurrage losses (Rs. 645

million in 1995 for all major ports) which would ultimately benefit the nation as a

whole. IRR for projects offered for private participation has been calculated at 20

percent-24 percent under the BOT principle, but since the privatization guidelines are

not clearly spelled out, the investor is still not confident in investing in massive port

projects. Today, Visakhapatnam has the dual objectives of optimisation and

modernization and is trying to maintain its position as a premier port of the country.

Traffic projection till 2020 AD has been done for Visakhapatnam. But a point of

caution has to be noted here. Traffic may be diverted if any port comes up as a

competitor in the hinterland. In case of Visakhapatnam port, Gangavaram in the south

288

Page 46: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

and Dhamra (Orissa) in the north might pose such a threat in future. Kakinada, the state

port is, however, in no way a competitor for Visakhapatnam's cargo traffic. Similar is

the case with Krishnapatnam. Since Gangavaram and Dhamra are 'green field sites'

today, their influence has not been taken into consideration for traffic projection.

Moreover, change in international scenario may affect cargo trade in certain

commodities. These are certain limitations in traffic projection.

A 1 7 -member team constitutes the Board of Trustees, which has representation

from the management, union, stevedores, clearing agents and major users. The

Chairman of the Port heads the Port Trust Board. This board finally approves any

project after carefully studying the project proposal. One major yardstick of project

viability is the internal rate of return. More the IRR, better it is for the port. The other

consideration is the positive increase in delegated financial power for the individual

Port Trusts from 1996. Previously, for taking up any project proposal costing more than

Rs. 5 crores, prior sanction was necessary. Now, Visakhapatnam Port Trust Board can

sanction up to Rs. 50 crore for any modernization process and Rs. 100 crores for

replacement projects.

7.6.3 Opinion of users'

The opinions of several port users have been crystallised in this section.

Visakhapatnam has congestion problems and TRT of vessels is high, more specifically

the PBD component of TRT is more. In other words, vessels wait in queues for berth,

but once they get a berth, cargo discharging is fast. So, vessels prefer to wait for days

rather than go to other neighbouring ports. The bunching of vessels, as port officials

say, is beyond their control and is not a regular feature. This is because of the random

arrival pattern of vessels over which the port has no control. Investigations revealed that

if the importers/shippers or agents plan the correct timing for chartering vessels in

advance, then vessel queuing may be avoided to some extent. Today, this co-ordination

among the user agencies on one side and the port authority on the other is sadly

missing, causing unnecessary delay and thereby loss of time and money. For measuring

the loss due to pre-berthing detention of vessels, the standing charges of the vessels are

to be estimated which varies from Rs. 3 lakhs to Rs. 8 lakhs depending on the size and

289

Page 47: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

type ofthe ship. It sounds quite illogical that a Rs. 150 crore ship should wait for a berth

worth 45 to 50 crore. It should rather be the other way round. A berth should wait for

the ship and not ship for a berth, which is the case now

It has been widely agreed that today there does exist a shortage of berths.

Capacity wise, Visakhapatnam has reached a plateau stage. Extension of berthing

facility is not feasible because of natural limitations. In an attempt to acquire more

water front area, the port authority decided to shift the fishil').g harbour from its present

location to Bheemunipatnam. Though the idea was good, but its practical application

was difficult, as implementing the proposal was not easy. Besides, dealing with the

resistance put up by the local fishermen, the port had the responsibility to rehabilitate

them, which is not a simple task.

Capacity-wise too, Visakhapatnam is saturated and over-utilized. All possible

measures of increasing productivity, so as to reduce the cost of handling have already

been tried. For instance, cranes have been provided with matching slings, whereby

productivity increases. Earlier, a 10 tonne crane had 3 tonne slings. By a simple

innovative method of replacing the 3 tonne sling by large size sling, productivity of that

particular crane nearly tripled. Similarly, a lot of time was earlier wasted in transferring

railroute cargo because of lack of proper sidings. Now, by simply constructing sidings

at appropriate locations the railway wagons are loaded or unloaded without difficulties.

Another example is shifting the maintenance staff quarters and building a stockyard

behind the berth, which was 10 kms away. This made cargo loading/unloading

convenient. Again gang strength was reduced without any negative effect on cargo

handling. Such adjustments in machinery and port planning have improved present port

productivity.

As future traffic projections show, Visakhapatnam has to augment its capacity.

Since the present port capacity is already over-stretched and dusty cargoes have to be

shifted from Visakhapatnam, the only alternative seems to be the idea of a satellite port.

Gangavaram is a possible location but only if it has required draft, back-up space and

infrastructurallinks.

Privatisation is picking up in Visakhapatnam port, but privatisation in isolation

is of no use. For privatisation policies to be successful, certain things are important.

290

Page 48: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Firstly, the guidelines should be very clear, as the investor must be aware of his duties

and be confident of the returns on his investment. Secondly, regulatory mechanism by

various authorities should be reduced to the minimum and the private investor be

allowed to charge according to his own wish. Thirdly, manpower strength would be

reduced as this would relieve the port of its cost burden on account of salaries and

wages. Visakhapatnam's cargo is more or less assured, as it is dedicated bulk cargo like

coal, iron-ore, POL etc.

Visakhapatnam does have a bright prospect for containerization only if it caters

more to general cargo, in future. Bulk cargo hardly gets unitized or containerised.

Therefore, if the cargo mix changes in future, Visakhapatnam might have substantial

container traffic, posing competition to Chennai.

Certain advantages make Visakhapatnam a frequent port of call like peaceful

labour situation, fast disposal of cargo once the vessel is berthed, quick customs

• clearance within a few hours etc. Emphasis today should be on modernisation and

capacity augmentation backed by proper prior planning. A little planning and co­

ordination among the port users and the port authorities can solve a lot of the problems

faced by a user today. A good planner should foresee problems and know his

limitations. Visakhapatnam port should follow this in order to remain one of the

important ports of the country.

7.6.4 Unions

The opinion of the port workers organised into unions is important to understand

the complete picture of the Visakhapatnam port. There are 13 registered unions in

Visakhapatnam port of which five are most prominent. The first union, which was

formed in 1936, three years after the Visakhapatnam port started its operation is called

Visakhapatnam Harbour and Port Workers Union, affiliated to AITUC. The next union

came up only in 1964. Visakhapatnam Harbour and Port Workers Union is heavily

tipped on the dockside as about 65 percent of the dockworkers are members of this

union. i.e. about 13,000 workers. 3,000 workers are from the port side. Besides these,

there exists a large section of unorganised labour force who are engaged as private

291

Page 49: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

contract labour in various cargo handling activities. 90 percent of this category of

workers are registered with this union, adding to a total strength of 4,000.

The most important function of the Workers Union has been to look after the

interests of the workers and the management and maintain a cordial and healthy relation

between the two. The union believes in the overall prosperity of the port, as it would

benefit them too. The union voices the demands of the workers like wage revision,

welfare benefits, revision of incentives, promotional policy, etc. and raise the problems

of the workers to the management. Strikes are the last option that they opt for to express

their unhappiness and the unions resort to it only when all other methods of negotiations

fail. Before going on strikes, all other avenues are explored for convincing the

management. This stems from the realisation that if the workers go on strike, it is the

port as a whole, which suffers. Strikes, therefore, are not frequent in Visakhapatnam

port. This is evident from the fact that the last strike in which they participated was in

1984, which was an all India strike lasting for 26 days.

The union feels it is accountable to the management for its actions. If there is

laxity on the part of workers, they should be held responsible. But, if on the other hand,

they work well, workers should be rewarded as a mark of recognition and

encouragement. If the management feels concerned and looks into the interests of the

workers, it is not a social obligation rather they do it for self-interest. To get the work

done properly and on time, workers should be satisfied, because it is they who actually

work. This philosophy of the management is well understood by the union, but what is

commendable is that in Visakhapatnam port, the Union does not take undue ad~antage

of this situation and make unreasonable demands, which are absolutely unacceptable to

the management, though this happens in other ports. The Union claims it never preaches

the workers to compromise on work. The workers are advised to do their work well and

the union would take care of their demands. The union has a positive constructive

approach and adopts the philosophy of hard work.

Among the achievements, which the union claims, the most noteworthy is the

pay hike in 1986 and wage fixation of the private contract workers which made them at

par with the regular workers. The Union fought the case for the workers who were

working in the ore-handling plant for twenty years and yet were getting less pay than

292

Page 50: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

regular workers. The demand was raised in the Dock Labour Board to regularize those

2000 workers. A further demand has been put forward for other benefits like leave,

medical facility etc. This is a major achievement in the history of port union movement.

There is yet another example, which substantiates the fact that the Union looks

into the interests of the management as well. In 1986, the Visakhapatnam Dock Labour

Board was in a financial crunch and one possible solution was retrenching the

manpower. At that time, thermal coal wagons were handled manually by a gang of 16

workers. The Union intervened and convinced the workers and reduced the gang

strength to 10 thereby reducing the manning scale by 6 per gang. As a result, the cost of

handling was reduced. The union introduced interchangeability of work for optimal

utilisation of manpower by work adjustments. Workers released from one form of work

were engaged somewhere else. This was the turning point in the history of

Visakhapatnam Dock Labour Board and today it is one of the richest and a pioneer

organisation. The Union takes the credit for this turning point in the history of the Dock

Labour Board.

Among the failures of the union, the most disturbing factor has been the decline

in the morale of trade union leaders. The philosophy of trade unionism has undergone

drastic change so much so that today there exist only trade and no union as one leader

subtly remarked. Most of the senior leaders are not port employees but paid by the

unions. Moreover, inter-union rivalry is another unfortunate factor, which hinders the

strength of the union movement. Yet another factor is the division of trade union

workers on communal lines rather than on the basis of work. The union strongly feels

that these hindrances have put limitations on the functioning of the union.

Union opinion on modernisation of the port is positive. They believe that the

gain of modernisation would acquire to them also and that port modernisation is for the

betterment of the nation. At the same time, modernisation, automation must not lead to

retrenchment of labour or forced retirement of workers. Interchangeability or alternative

employment opportunity should be offered in such a case. The union raised an

interesting issue here. Machines not always work faster and efficiently. For example, at

the ore handling plant at Visakhapatnam, it has been proved surprisingly that manual

handling of ore is faster than mechanical handling. This is however, nothing but a

293

Page 51: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

manifestation of the improper maintenance and inefficiency of the plant, which faces

frequent equipment breakdown.

The Union's opinion on privatisation is critical. They insist that privatisation is

nothing new. It existed since long time as the exporters, importers, stevedore, Clearing

and Forwarding and Steamer agents, are all private parties on whom trade depends.

Private owners sometimes own equipment too. One of the major objectives of

privatisation however, is bringing in private investment for development of port

infrastructure. The union strongly stands by the opinion that privatisation should not be

adopted for the sake of privatisation as it is considered fashionable today to go 'private'.

But, a port should encourage privatisation only when it is absolutely necessary. In case

of Visakhapatnam, when the port is fulfilling its targets, earning profits and is running

efficiently, the need for private participation does not arise. The union feels that

Gangavaram should develop as a satellite port to Visakhapatnam port and should not be

declared as a private or state port as both the latter have their respective disadvantages.

The fate of Kakinada over all these years as a state port is not quite encouraging. The

union feels that from employment perspective, Gangavaram would not be ideal as it

would develop as a mechanical modem port involving less labour. Visakhapatnam

would lose a substantial cargo to Gangavaram but this would pose no problem if it is an

extension of the former port. But the counter argument is that Visakhapatnam does not

have enough funds to develop Gangavaram on its own. So, if developed in the private

sector in a green field area, the ills of restrictive practices is not likely to affect the new

port.

7.6.5 Problems faced by the port

Port problems have been summarised here after discussions were held with all

interviewees.

• Perhaps the single most important problem faced at Visakhapatnam port today is

that of port congestion. The port facilities are not adequate to handle the unexpected

increase in cargo traffic volume, especially in the last 10 years. In the 80s, a few

extra berths were constructed in the Inner Harbour, open land were converted into

stockyard, rail sidings were built, Outer Harbour was constructed. All these

294

Page 52: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

developments attracted so much cargo that the port capacity created for next 15

years were consumed within 5 years! Cargo traffic increased beyond expectation,

surpassing all capacity arrangements. The net result was congestion at the port.

• The problem is expected to grow more acute in future as more industrial activity and

increase in population in the hinterland is expected, which would mean more cargo

traffic for Visakhapatnam port to handle.

• The port has certain limitations like channel and draft restriction, scarcity of

waterfront, etc. Keeping all these in mind, commensurate with increased traffic, port

capacity has to be augmented. This is precisely the need of the hour. A ship waiting

for a berth at Visakhapatnam port costs the nation a fortune Rs. 3 lakh to Rs. 8 lakh

per day, depending on the 'size and type of ship.

• The bunching of vessels is unavoidable as individual port users have different self­

interest, which would never match with each other. Since the ultimate aim of a port

user is to saw time and money, by calling at Visakhapatnam, he is comparatively

better off than any other east coast port. Other possible choices are ruled out like

Chennai which is congested, Ennore- is only a green field site today, Paradip --once

completes its coal loading terminal may ease the pressure of thermal coal handling

at Visakhapatnam. Moreover, Visakhapatnam has dedicated bulk cargo like coking

coal, POL, iron-ore, fertiliser, etc. which hardly can move away. In addition, it is a

peaceful port with no labour trouble. Visakhapatnam as a frequent port of call on the

east coast is therefore justified.

• It was widely agreed upon that the expansion facilities at the present port are

limited. The logical option seems to go for a satellite port at Gangavaram. The

proposal for Gangavaram, still a green field site today was put up 1 0 years back.

Due to indecision on the status of the port, it is still lying idle. This delay in

implementation of the port would prove costly because of huge cost escalation.

There is a need to develop Gangavaram immediately.

• Another problem that the port face is delay in project approval and thereby cost

escalation. The proposal for LPG berth at Outer Harbour was delayed at the

Ministry level by one year. This delay resulted in 25 percent extra cost. Moreover,

faster the implementation of projects, more economic cycles can be adjusted within

295

Page 53: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

the same time frame which would lead to more trade. More trade means more cargo

traffic for the port to handle and the port prospers.

• After the liberalisation of the economy in the 1990s, the trade pattern changed.

Indian ports should modernise so as to remain competitive in the international

maritime scenario. The Indian ports should upgrade themselves to international

standards so that the multinationals invest and automatically traffic flow will

increase as a natural process. Matching infrastructure facilities should be created

and the government's intervention should be reduced to a minimum. The ports

should be allowed to exercise their autonomy in financial and policy matters so that

delay caused in seeking Central Government's approval can be avoided. Unlike in

the past, today hinterland is not captive. If a port does not perform well, cargo

moves to another port following purely economic considerations. This threat would

make the ports perform tothe best of their ability.

• The reason for slow containerization at Visakhapatnam is the lack of sufficient

general cargo traffic that can be containerised. It is expected that if modern

container facilities were developed at Visakhapatnam port, then container traffic

would automatically flow in. Ports should develop facilities, following which

industries and ancillary activities would automatically follow. There is a

misconception that if a satellite port comes up, then the traffic of the original port

suffers. No two ports should develop close to each other, as they would have

overlapping hinterland and eat into other's traffic. But this is an apparent fear. In

Germany Bremen and Bremer Haven are just 45 kms. apart and both the ports are

prosperous and performing well. There is similar example in Holland where

Rotterdam and Amsterdam are only 40 kms. distant.

• So, to combat the problems of port congestion, lack of infrastructural facilities,

unnecessary delays in project implementation etc. the approach should be practical

and quick. The planners must have a vision and be aware of the problems too.

Solutions should be implemented fast. Governmental intervention should be

minimum, allowing the ports to act apace according to their requirements. One

should learn from past experiences and keep abreast with latest information from the

outside world. The basic philosophy should be understood by all - if trade prospers

296

Page 54: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

due to faster circulation of economic cycles, then port flourishes and the nation as a

whole benefit. If, there is delay, we lose on two counts- demurrage on ship side and

cost escalation on project side. In both the cases, port suffers and the burden

ultimately percolates down to each single user. Port functioning is just like a chain,

and any break or delay in the process, disturbs the whole linkage. Any corrective

measure undertaken should, therefore be cost effective and time saving. Future

projections are necessary to plan. Without proper planning, there are chances of

either under utilisation or over utilisation of port capacity.

7.6.6 Corrective measures

What could be the possible corrective measures to combat the present problems

that the port faces today? Answer to this question varied from one person to the other.

Summarising all, the following discussion is revealing. As a bulk cargo port,

Visakhapatnam is perhaps the best possible choice on the east coast because it has

natural protection, comparitively less labour related problems and a flourishing

industrial hinterland. Yet, Visakhapatnam faces port congestion and needs extra berths.

At present, there is a sanction for the construction of 4 berths in the Inner Harbour and

two berths in the Outer Harbour. Any further extension of berthing facility at the port is

not possible. The port is already running on over capacity (134 percent capacity

utilisation). The only alternative solution seems to develop Gangavaram port.

Gangavaram port is still on conception stage, as there has been unnecessary

shunting between the state and the centre as to the status of the port. Political indecision

is one of the reasons causing unnecessary delay. Gangavaram port is expected to handle

all the dirty and dusty cargo of Visakhapatnam port. This is of utmost importance as the

city of Visakhapatnam is suffering from extreme air pollution. The conveyor belt

carrying iron-ore passes right across the town. The pollution problem has urged the

citizens of Visakhapatnam to appeal to the port authority and VUDA to undertake some

measure so as to curb further pollution. Some people have shifted to safer places like

Srikakulam, a few kms away. Since the port is adjoining the Visakhapatnam City,

certain considerations have to be looked into so that the city can also grow as the port

prospers. It is an excellent idea to shift thermal coal, coking coal, etc.--the dusty cargoes

297

Page 55: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

to Gangavaram-which can infact be an extension of Visakhapatnam port. Moreover, the

entire belt from Visakhapatnam to Kakinada port- can be developed as an 'industrial

corridor'. With several industries taking advantage of common infrastructure and port

facility. Gangavaram therefore, can act as a catalyst in the development of this future

industrial hinterland.

Besides increasing capacity, in the form of berths or a separate satellite port,

certain considerations can be made by the present port authority to encourage the port

users without much investment or policy changes. What is needed is a corporate

attitude. For example, privatisation can be introduced in equipment supply and

maintenance. By this, the port can have access to modern equipment and machines and

at the same time be relieved from the responsibility of maintenance. The port users

often complain of poor maintenance of equipment and also that machine is out-dated.

Productivity levels would surely then improve under the present circumstances if the

Port go.es for equipment and machine privatisation. Even tugs can be hired from the

private parties. If computerised, 'single window' operation is introduced in the ports,

paper work and time can both be saved. Since, individual ports toady can take

investment decisions upto Rs. 50 crores for modernisation process and Rs. 100 crores

for replacement project without Central Government intervention, this power should be

exercised to the maximum. It is important to note here that Visakhapatnam port, which

had a surplus of Rs.73 crores in 1999, has its own funds. This surplus has to be

judiciously used to bring overall improvement in port productivity. Privatisation has to

be encouraged wherever needed to usher in healthy competition. Visakhapatnam has a

good work culture compared to other ports like Calcutta or Paradip on the east coast. It

has the advantage of being a natural port backed by a resourceful well-connected

hinterland and has excellent labour-management relations. It is also generating a

financial surplus. Though the port faces some problems, it has grown over the years and

today it meets its cargo throughput targets before deadlines.

298

Page 56: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

7.6.7. Containerisation

Visakhapatnam has no specialised container terminal and has very little

container traffic. It is predominantly a bulk port and the container traffic generated in

the hinterland (like tobacco) passes through the Chennai port which has specialised

container-handling facility. Through Visakhapatnam, aluminium ingots, reefer cargo

like shrimps and other marine products are moved out in containers. At present,

container vessels are berthed at multi-purpose berths in the absence of dedicated

container terminal at Visakhapatnam.

Though the port has plans to install modern container handling facility to

facilitate better handling of container traffic, nothing has come up as yet. Since the

earnings from container traffic are comparatively low as compared to bulk, the port is

not too keen to invest substantially in developing a full-fledged container terminal.

Chennai is already a successful container port with matching infrastructure and

developing Visakhapatnam into one might not be a profitable proposition. But, to

remain in trade, some container traffic atleast that meant for the hinterland of the port,

has to be handled. The port users are willing to engage their own labour who are trained

to handle containers and who could perhaps also support the port workers. There is no

dearth of land for staking the containers and the hinterland has potential for container

traffic. What is needed therefore is matching container facility at the Visakhapatnam

port. Realisation of investment/cost for developing modern container terminal would be

easy since freight charges for handling containers are more compared to bulk.

Moreover, manpower needed would be minimum as the facilities would be mostly

mechanised and automated. Raw material for power projects are imported today in

containers. From Visakhapatnam to Kakinada - the entire stretch would house a few

new power projects, which would need import of raw material. Therefore, container

traffic has a somewhat bright future in Visakhapatnam. If only, it is well equipped to

handle so. At present, however there is no plan underway for a dedicated container

terminal.

299

Page 57: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

7.6.8 Future growth prospect of the port

An assessment has been made here of the future growth prospects of the port

based on primary sources and personal interviews.

The cargo throughput from the Port by 2020 is anticipated to reach 140 million

tonnes. To enable efficient and smooth transfer of this cargo, it is assumed that the port

capacity has to be enhanced to 148 million tonnes per annum by that time. The Port

capacity primarily consists of the 'Berth Capacity' which means the berth, the cargo

transfer system, the storage and the transportation facilities. There are also several other

supporting and auxiliary services (road and rail network, functional structures, water,

electricity, etc.) which together form the Port capacity.

The first task is to estimate the number of berths that would be required to meet

the demand. The berth requirements depend on

1. the nature of cargo

u. the parcel size

u1. the cargo transfer system and

IV. the berth occupancy

In order to benefit from the economies of scale, deployment of large size ships is

envisaged in case of cargo with substantial volume and where deep draft facility is

provided. Accordingly, corresponding parcel size (the quantity/volume of cargo

intended for loading or unloading at the Port) is assumed. It is proposed to take full

advantage of the developments in port technology and install cargo transfer systems,

which use the 'state-of-art' technology. Thus, it is assumed that the output rates will be

much higher than at present, particularly in case of crude, dry bulk cargo (mechanised)

and container cargo. It is also assumed that the cargo transfer systems will be fully

mechanised and automated in case of liquid bulk, dry bulk and containerised cargo,

wherever the cargo volumes are sizable and the economics permits.

It may be mentioned that care has been taken to ensure that the assumed output

rates are reasonable and attainable. It is necessary to mention that the rates assumed are

those, which one port or the other has achieved. With the induction of better technology

300

Page 58: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

and improvisation of the systems, these rates are bound to be higher by 2020 - a time

span of25 years from now.

Development Options for the Port

In view of the position explained, the port is left with two options :

1. to explore the scope to expand the Port in and around its present

location, or

u. to identify possible new suitable locations, as near as possible to the

present location.

The first option does not seem either possible or advantageous. Presently, the

Indian Navy, Coast Guards, Hindustan Shipyard and the Department of Agriculture

utilise some of the waterfront of the Port. One way is to release this area for commercial

shipping. In addition, an Outer Harbour to the Outer Harbour may be built for additional

water-front. These propositions involve either dislocation of established institutions of

national importance or huge investment. Apart from the inconvenience, their relocation

would entail enormous costs. Similarly, converting the fishing harbour for commercial

shipping and construction of an Outer Harbour requires huge capital investment. Its

technical feasibility has to be studied. This option may still not be advantageous since,

the draft limitation continues in the case of Inner Harbour taking away

the competitive edge ofthe Port;

the single entrance channel to access the harbour still remains a threat

to commercial shipping at times of eventualities;

adding berths without the desired back up land area creates several

severe bottlenecks to the cargo operations;

the enormous capital investment may not be commensurate with the

development;

the staunch opposition from the established institutions of national

importance definitely delay and block the process; and

further, environmental degradation, may increase the public resentment

beyond the ability of the Port to contain it.

301

Page 59: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The 1st proposition is not advantageous to the Port. Thus, the second option

seems feasible and advantageous. A cursory study of the coast to the north and south of

the Port suggests that expansion of the Port to the south side will be preferable since the

access to the expanding industry will be more and the required land area could be

acquired, more easily. At the same time, it is easier to link the selected locations with

the national rail and road network. The Master Plan of the port identified suggests

'Gangavaram', near the 'Steel Plant' as a satellite harbour. In recent times,

'Mutyalammapalem', a place further south to 'Gangavaram', was under consideration

by some private investors. As such, these two locations are referred as the probable

locations for considerations. It is expected that satellite ports would

• relieve the port from the present pressure with diversion of thermal and coking coal;

berths now handling those cargo will be available for other cargo.

• provide a competitive edge to the Port through economies of scale on account of

deep draft provisions;

enable a systematic redistribution of service facilities for their optimum utilisation;

elimination of transportation bottlenecks to lower transportation cost to users;

easy linkage to the national rail and road network;

easing the pressure on the urban road and rail transportation systems;

improved environment at the present Port thereby mitigating the public resentment;

adequate land at economical cost;

promoting regional development arresting shift in natural cargo flows;

Discourage the growth of small sized cost-ineffective Port facilities;

uninterrupted service even if an outlet is closed due to unforeseen eventualities;

greater maneuverability to navy at time of war; and

scope to expand the Port facilities further and beyond 2020 .

Thus, opening one or two or more satellite harbours, in a phased manner and

extending the present Port limits, depending on the requirements from time to time, will

be the right solution to meet the demand of the anticipated cargo throughput for Port

servtces

302

Page 60: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The following distribution of berths has been suggested:

Table 7.21

Suggested berth distribution at Visakhapatnam Port

Cargo Type Existing Oulet- I Outlet -11, Total Port (Gangavaram) (Mutyalammapalem)

Dry bulk 4 11 15

Break bulk 9 9

Steel 6 6 products Container 8 8

Liquid bulk 3 8 11

Passenger 1 1 berth Berth for 1 1 explosives Total 25 17 9 51

Source: Article by Y. Jayanth1 from VPT.

Based on this allocation by 2020, a restructuring of the berth configuration at the

present Port is suggested as under :

• 3 Deep Draft Container Berths for 5th Generation Container Ships-( depending on

the container traffic generation)

• •

• •

1 Crude Oil Jetty for 1,50,000 DWT Tankers (OSTT)

1 Jetty for LPG Carriers of 20,000 DWT and LNG Carriers of 80,000 DWT (LPG

Jetty)

1 Mooring Berth for Transshipment (NOM)- ( may not be required now with the

setting up of the FSO terminal at sandhead)

1 Fertliser Berth (FB)

1 Alumina Berth (WQ. 5)

1 Berth for Export of Oilseed Extracts (EQ-6)

1 Iron Pellet Berth

1 Passenger/Luxury Cruise Berth (OR1/0R2)

9 Break-bulk Berths (EQ1 to EQ5, 7, WQ- 2, 3, 4)

5 Container Berths (Extended N. Arm)

303

Page 61: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The first pre-requisite of establishing the new harbours will be the creation of a

sheltered, tranquil water basin for berthing the ships. It is suggested that a water basin

of about 400 hectares may be envisaged at Gangavaram for the bulk. Similarly, a water

basin of about 450 hectares may be built to accommodate tankers. To build these

satellite harbours and to construct the additional berths, a minimum of 1600 hectares at

the first outlet and 1200 hectares at the second outlet will be required. Acquiring land

more than the minimum is desirable and there can be no norms for this purpose. The

next step, is to estimate the facilities associated with the berth system. These are the

cargo transfer system, the storage (covered and open) space and the facilities for the two

modes of cargo transport.

For this purpose, five types of cargo transfer systems are visualised as under:

• The conventional wharf/mobile crane system with supporting ground fleet in case of

break-bulk;

• The fully automated and mechanised system with ship loader/grab/marine unloader

and conveyors, etc., for dry bulk;

• The conventional-cum-semi mechanised system for minor bulk and steel produces;

• The marine arms and pipelines for liquid bulk; and

• Quay Gantry Cranes, RMGs and RTGs, etc., as in full-fledged container terminals,

for containers.

Today, the situation is different. The policy of economic reforms and liberalisation

opened the gates for international exchange and free flow of state-of-art technology and

expertise. The general environ is conducive to radical experiments and endeavour for

better performance. It is believed whatever may be the general environ, the internal

developments of the industry itself propel the change. The most significant factors,

which may provide the impetus for the changes, are:

Privatisation;

Multimodal transport and

Electronic Data Interchange (EDI).

While the last two are in different stages of implementation, much progress have

been achieved with regard to private sector participation.

304

Page 62: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Part III- Visakhapatnam : A Port City

"A port-city is an urban settlement which has a set of specific characteristics

derived from the maritime functions of exchange, enterprise and transport that, firstly,

set the settlement apart from its surrounding region and, secondly, determine the

physical, economic and social configuration of the settlement............ When a city

outgrows by the port it is no longer a port-city. Its port may remain important to it; but

if its character changes ..... then it moves beyond the port-city stage."- Dr. Frank Broeze,

Professor Peter Reeves and Kenneth McPherson. 6

7.7 Development of the Port Town

The metamorphosis of Visakhapatnam which was once a small & sleepy

fisherman's village into an industrial beehive toady, is not an event that occurred

overnight. The driving force behind this transformation is undoubtedly the

"Visakhapatnam Port'. Strategically located on the East Coast, the Port has been

playing a catalyst role for rapid industrialisation of the hinterland.

The first reliable census of the town was taken in 1881 when the town recorded

30,291 persons. The first two decades of the last century recorded a moderate rate of

increase while the following two decades were marked by quite a slow rate of growth.

But during the subsequent fifty years, a rapid increase has been noticed on account of

the various developments. In 1971, the city's population was about 3.5 lakhs which

increased to 5.65 lakh and 7.52lakh in 1981 and 1991 respectively. The large numbers

of immigrants and increased birth rate have been important in the growth of population.

The development of the port is perhaps the stimulus behind the growth of the town. See

Map 7.2- "The Port City-Visakhapatnam".

6 Frank Broeze, Peter Reeves and Kenneth Me Pherson in ' Port Cities in the Indian Ocean Region: 1815-1939: Functional and methodological issues', Paper for the 2 nd International Conference on Indian Ocean Studies held in Perth, Western Australia, 5-12 December, 1984.

305

Page 63: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

VISAKHAPATNAM PORT CITY FIG. 7.2

Page 64: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table 7.22

The chronology of major events in the history of the town

1068 Visakhapatnam referred to in an inscription.

1650 The settlement of a branch of the East Indian Company.

1803 Visakhapatnam became a Collectorate.

1858 Miniciapal Board started.

1893 Madras-Waltair Railway line opened.

1910 Madras-Waltair-Calcutta Railway line opened.

1923 King George Hospital established.

1931 Andhra University shifted to Waltair.

1932 Completion ofVisakhapatnam-Raipur Railway line.

1941 Opening of Hindustan Shipyard.

1942 I. N. S. Circars (Naval Base) commissioned.

1943 Bombing ofthe Harbour in World War II.

1946 Commencement of Civil Aerodrome and Civil Offices.

1947 Independence.

1948 'Jala Usha' the first ship was launched.

1957 Caltex Oil Refinery commissioned.

1962 Constitution of the Town Planning Trust.

1964 Constitution of the Port Trust.

1966 Ore Handling Plant in the Port started.

1967 Coromandal Fertilisers commissioned.

1967 Bharat Heavy Plate and vessels Limited started.

1967 Hindustan Polymers started.

1967 Graving Dry Dock Project started.

1968 "Kalvari" the first sub-marine of the Indian Navy cruised into the harbour.

Source: Visakha Mahanagar, Comprehensive Development Plan, 1969-1986, Town

Planning Trust, Visakhapatnam.

306

Page 65: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Broadly speaking, four geographical zones may be recognised in the town : the

Inner Zone, Middle Zone, Outer zone and the Suburban Zone. The Inner zone is

characterised by fully built-up areas with old type of architecture. It covers the older

part of the town south of the Sand Hill. The Middle Zone shows a transitional character

between the fully built-up Inner Zone and the partly built-up Outer Zone. The Outer

Zone of the town is extensive, covering the Waltair, Alipuram and the Port areas. The

suburban zone has not yet developed as an integrated unit in the town. The external

transport system is confined to three roads coming from Bhimunipatnam, Vijaynagram

and Ankapalli. The Coastal Railway and Vijaynagaram-Raipur railway are the only

direct railway links. The port provides proper facilities for overseas and coastal

relations. The air transport is insignificant. The condition of the essential services like

water supply, drainage and conservancy, is not satisfactory. In the absence of a

perennial source for water supply, the city faces a serious problem.

7.8 Port led Industrialisation

Visakhapatnam is a multi-functional port town. Although the establishment of

industries in Visakhapatnam city dates back to the seventeenth century, the present

industrial landscape has been shaped only after the establishment of the Visakhapatnam

Port. According to a report on the Visakhapatnam Municipalit/, the East India

Company established the first factory in Visakhapatnam town in the year 1682 to

produce some consumer goods. No large scale units were established during the next

two centuries. The only large and medium scale industry established in the district prior

to the establishment of the Port was Chittivalasa Jute Mills ( 1926) and Etikoppaka Co­

operative Sugar and Agricultural factory (1933).

The commissioning of Visaskhapatnam as a mono-commodity Port, with three

berths was the starting point of the industrial development of the region. Most of the

capital-based industries have sprung up only after the commissioning of Visakhapatnam

Port. The industries like Hindustan Shipyard, Hindustan Petroleum Corporation,

Hindustan Zinc, Bharat Heavy Plates and Vessels Ltd., Coromandal Fertilizers Ltd. and

Jayanthi, Y., "Role ofViaskhapatnam Port in the Industrial Development", VPT, 23. 3. 1996.

307

Page 66: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

the latest in the list, the first port-based integrated Steel Plant (VSP), - all owe their birth

to Visakhapatnam port.

The first phase of industrialisation of the city began after the Second World

War, with the setting up of Hindustan Shipyard in 1946- the first ship building yard of

the country. This shipbuilding unit has further led to the installation of many ancillary

industries connected with Shipbuilding. When the need to set up a grass-root refinery in

the hinterland was identified in the early fifties, the natural choice of location was

Visakhapatnam - the prime reason being the vicinity of a natural harbour with deep

water. Accordingly, Caltex Oil Refinery with an annual refinery capacity of 1.5 million

tonnes per annum was established way back. in 1957. In order to cater to the

requirement of this refinery, the Port constructed 2 Specialised Oil Berths, OR-I and

OR-2, during 1957-58, connecting the berths directly to the storage tanks of the

refinery.

The period of 1967-70, marked the beginning of rapid industrialisation of the

city. Industries like BHPV, Coromandal Fertilisers Ltd., Hindustan Zinc have been

attracted to Viaskhaptnam, primarily because of the Port and the facility it offers. The

Port responded to this industrial activity ofthe region by upgrading and augmenting the

cargo handling facilities. It also provided immense employment opportunities for the

citizens in and around the city. The number of persons employed by the Port directly

increased from 5000 in 1964, to 15,000 in 1993-94. In addition to this, the existence of

fishing harbour, ancillary industries to the basic & heavy industries mentioned above,

also helped in promoting the employment opportunities in this region. Industries like

ship building, oil refinery, fertiliser factory, Zinc smelter plant, Bharat Heavy Plates

& Vessels industries, Export Processing Zone (VEPZ) & the first integrated steel plant

vow their birth at the city to the Port. The large scale industries employ more than 80

percent of the industrial workers of the town and have kept the place distinctively on the

industrial map of the country. The small scale industries employ 18 percent of industrial

workers of Visakhapatnam. The newly developed small scale industries show a marked

influence of modernity while the old ones are in poor state of progress. The condition of

Cottage industries is the worst.

308

Page 67: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The Visakhapatnam city's economic structure is chiefly guided by the public

investment by the Government at various levels and the con-committed development on

account of the public sector undertakings and private enterprises to some extent. The

Visakhapatnam Port undoubtedly catalysed the development ofVisakhapatnam city and

was responsible for the establishment of major public sector undertakings like

Hindustan Shipyard, HPCL, BHPV, HZL and of late the Steel Plant complex. Private

undertakings like Coromandal Fertilisers, Hindustan Polymers etc., large and medium

industries were also established.

7.9 Changes in Land-use

To assess the functional topography of the port town, a land-use pattern is of

great relevance.

7.9.1 Land-use in 1970

From the Table 7.23 the general pattern of urban land use in 1970 at

Visakhapatnam is clear. The industrial use of the land was quite significant.

Proportionately the area under residences was not as important considering the size of

the population. The roads covered only 5.5 percent of the total area which was below

the average. Due to tidal swamp and newly extended areas in the municipal limit ,the

percentage of vacant land was very high (42 percent).

309

Page 68: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Land-uses

Residential

Commercial Public Offices Industrial Recreational Educational Hospitals Railways Roadways Agriculture Hills & Geddas Vacant Total

Table 7.23

Land Use Pattern in Visakhapatnam, 1970

Total area 4684 hectares,

Built-up area 2052 hectares

Area in percent to the percent of the built hectares total area up area

854.2 18.00 41.90

34.3 0.70 1.80 42.0 1.00 2.00

514.0 11.00 24.60 29.5 0.60 1.50 104.7 2.30 5.20 117.1 2.60 6.00 100.0 2.20 5.00 252.0 5.50 12.0 27.5 0.60

631.1 13.50 1971.5 42.00 4684 100 100

Source: Urban Morphology, Chap V, Vtsakhapatnam Port Town, Dr. V.S. Knshna

Memorial Library, Andhra University, Visakhapatnam.

The growth of the port as well the industrial base of the city led to the

development of its hinterland and changes in the land use. Viaskhapatnam Development

Area and its vicinity today termed as Visakhapatnam Metropolitan Region (VMR.)

consists of Visakhapatnam city, Anakapalli, Vizainagaram, Gajuwaka, Bheemili towns

and 287 rural settlements comprising an area of 1721 Sq. Kms. The VMR is set for

increased economic activity due to the establishment of major industrial complexes in

the city and its environs. The main focus in the region is on Visakhapatnam Urban

Agglomeration which contains the major share of the region's population and economic

activities; including large number of large and medium industries like Hindustan

Shipyard, HPCL, HZL, Hindustan Polymers with their activities central around the port.

The steel Plant complex in the immediate vicinity of the city with its huge investment,

is the unique feature of this region. The Eastern Naval Command, Naval Dock Yard and

the Divisional Headquarters of S. E. Railway, Andhra University accompanied by

310

Page 69: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

scores small scale industries, business, trade and commerce have contributed to the fast

growth of Visakhapatnam Urban Region.

7.9.2 Land-use in 1990

The topography and the transport network converging on the port area are the

major structuring elements in the evolution of land use pattern in the Visakhapatnam

urban area. The land under different land uses in the city is as follows :

Table 7.24

Land-use pattern in 1990

Description Extent in Extent in Percentage Percent to Hectares acres contiguous built

up area (11330 acres)

Residential 1803.92 4464.58 23.43 39.40

Commercial 105.09 259.69 1.36 2.29

Industrial 633.33 1565.03 8.23 13.81

Public and semi 528.06 1304.89 6.86 12.01

public utilities

Recreational 117.13 289.43 1.52 2.55

Transportation

a. Roads 387.66 957.94 5.03 8.45

b. Railways 110.94 249.43 1.32 2.20

c. Port 2934.39 7250.43 38.11 Port area not calculated

Agricultural 0.45 1.12 0.01

Hills/Forests 385.52 5.00 3.91

Water bodies 71.50 176.68 0.93 1.56

Vacant land 632.01 1562.75 8.21 13.82

Total area 19027.48 19027.48 100.00 100.00

Note: Bmlt-up area (11330 acres).excludmg Port Areas, Defense Areas,

Air Port area etc.

Source: Visakhapatnam City, Zonal Development Plan- Synopsis, VUDA Report, 1991.

311

Page 70: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

The Municipal area covers 77 sq.kms. (19027.48 acres.) due to the deletion of

zone in Dolphins' nose village which has been merged into Gajuwaka Municipality.

The extent merged in Gajuwaka Municipality area is 329 Acs. (1.33 sq.kms.).

Considering port swamp areas, defense, N.A.D., Air port etc., the contiguous built-up

area is 11330 acres. This area includes all the 37 detailed town planning scheme areas

and the industrial belt. Vacant land of about 1563 acres is still available for

development, out of which about 798 has already been committed for development by

various agencies like VUDA, Railways, Port etc. The density of population in the city

ranges from 30 to 473 persons per acres. The lowest density areas are the port and

extended areas while the highest density is registered in the old city area. The gross

residential density of the city is 40 persons per acre while it is 66 persons per acre when

calculated for the contiguous built-up area.

7.9.3 Changes in the land use pattern since 1970

There have been distinctive changes in the land use pattern of Visakhapatnam

from 1970 to 1990. The total area almost doubled in absolute terms, from 4684 hectares

in 1970 to 7700 hectares in 1990. The landuse pattern has also undergone changes as is

evident from the Tables 7.23 and 7.24.The total built-up area has doubled over the time

and a substantial area which was lying vacant (1971 hectare) has been included within

the built-up area in 1990. Excepting agriculture, all other types of activities have grown

over the years. In absolute terms, spatial extent has increased under all types of landuse

as in 1990. As a ratio to total area in the Visakhapatnam city, the Port has the lion's

share (38 percent), followed by area occupied by residential houses (23 percent). Not

only has proportion of land under agriculture declined, forested areas have also

registered a decline over the last two decades. It is interesting to note that proportion of

land under roadways have registered only a marginal increase while percentage of land

under railways has in fact gone down in relation to others.

7.10 Changes in Occupational Structure

The occupational structure of the city underwent changes as is evident from

1961 and 1991 data. The participation rate/ratio has declined marginally by about 2

percent from 1961 to 1991. (The proportion of total workers as percentage of total

312

Page 71: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

population is termed as work participation rate). This is because as urbanisation grows,

the non-working population like students, those engaged in household activities, retired

persons, beggars etc., also grow-putting pressure on the working age group. This is

reflected in the declining participation rates in growing metropolises. Important changes

in the occupational structure ofVisakhapatnam are the following:

• With the rapid pace of urbanisation, ratio of cultivators, agricultural labourers,

mining and quarrying and livestock population has declined.

• Though household industry has lost importance, proportion of industrial workers

has remained static over the years.

Proportion of workers in other services also has not changed .

The ratio of construction workers and those engaged in trade and commerce have

increased substantially. With more residential and public buildings coming up,

construction workers have flocked to the city in huge numbers. As the port has

prospered and the city has grown, trade and commerce have become the lifeline of

the metropolis and is infact an outcome of the successful export and import

activities of the port. A port generates trade and commerce and is only natural that a

prospering port will encourage a trade 'boom'. Visakhapatnam follows the general

rule as is evident from the Table 7.25

Table 7.25

Changes of occupational structure 1961 to 1991

Occupation 1961 1971 1981 1991 Worker Worker Worker Worker

Cultivators 318 1093 4942 2579 (0.15 %)

Agrl. Labour (1.70 %) (4.93 %) (1.67 %) 1460 (0.67 %)

Live Stock 5605 (2.56 %)

Mining & 2784 458 quarrymg (4.35 %) (0.21 %) Household 1268 1272 8172 1232 industry (1.98 %) (1.27 %) (5.28 %) (0.56 %) Industrial 9587 15753 31809 workers (14.97 %) (15.71%) (14.54 %)

313

Page 72: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Occupation 1961 1971 1981 1991 Worker Worker Worker Worker

Construction 2840 7483 16614

workers (4.45%) (7.46%) (7.60%)

Trade & 7211 13365 38309 commerce (11.27%) (13.33%) (17.52 %) Transport 14188 26169 143917 36611

(22.16%) (26.09%) (93.05%) (16.74%) Other services 25045 31298 86279

(39.12%) (31.21 %) (39.45%) Total 64016 100282 154668 218695 Participation (30.31 %) (27.59%) (26.03%) (28.99%) ratio

Note: Figures m bracket md1cate percentage of populatiOn m each category.

Source: Visakhapatnam City, Zonal Development Plan- Synopsis, VUDA Report,1991.

The industrialization over a period of time has changed the occupational

structure of the city from 1961 onwards significantly. The establishment of Steel Plant

complex near Visakhapatnam city may have also radically changed the occupation

structure of the Visakhapatnam city. The industrial working force of 31 ,809 are

employed in major and medium and small scale industries. There are 675 small scale

industrial units in the city and in its vicinity employing around 7000 workers. The city's

industrial employment is more than 32,000 with a capital investment ofRs. 7420 crores.

The Table 7.25 shows the changes in the occupational structure of the Visakhapatnam

city from 1961 to 1991.

a) Agriculture :

The agricultural activity marginally increased in 1971, because additional land was

included in the Municipal area which increased from 11.25 Sq. miles to 29.47 Sq. miles.

There was a decline of this sector between 1981 and 1991.

b) House Hold Industry:

The house hold industry registered a steep fall from 5.28 percent to 0.56 percent in

1991. This may be due to the classification of the workers adopted in 1981 and 1991 by

the Census Department. The industrial work force which registered 15.71 percent has

314

Page 73: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

come down to 14.54 percent, whereas by the absolute figure in 1971 it was 15753

while in 1991 the industrial work force 31809. The comparative analysis of 1981

figures cannot be presented in view of the 3 fold classification by the Census in 1981. It

can be seen that industrial work force has not increased in terms of the percentage share

in 1991.

c) Construction :

The share of construction workers was 4.45 percent in 1961,7.46 percent in 1971 and

it was 7.6 percent in 1991. No decline was registered in this sector.

d) Trade and Commerce :

The percentage share of this sector was 16.47 percent in 1991 while it was 13.33

percent in 1971 and 11.2 7 percent in 1961. There has been a gradual increase registered

in this sector.

e) Transport Sector:

In 1991 the transport sector employed 17.52 percent of total workers. When compared

to 1961, 1971 there has been a decline in the percentage share of transport sector

workers also.

f) Other Services :

Other services were significant in 1991 with 86,279 persons working in this sector

(39.45 percent). This sector has experienced a sharp increase since 1971. Though the

secondary sector i.e., manufacturing and construction workers shared 22.14 percent of

the workforce in the total economy (48423), other services have dominated the city's

functional pattern.

7.11 Simultaneous Growth of the Port and the City

The Visakhapatnam Port was declared as a major port in 1933. Since then,

traffic mainly bulk cargo increased manifold. The port activities and facilities too

increased over time like construction of berths, commissioning of ore handling plant in

315

Page 74: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

1965, commencement of night navigation in 1966. Commissioning of Outer harbour in

1976 and commissioning of multi-purpose berths recently (1995). As the Port grew,

Visakhapatnam town also grew along with the Port-both in terms of spatial extent and

population but of course not at the same pace. Population growth rate always had an

upward trend until the 1980s but in the last decade, the growth rate slowed down

compared to previous decades. One interesting feature to be noted is that during the

same decade (1980-90). Urban Agglomeration (UA) population growth rate was more

than the city's population growth rate. This was probably because of the huge land

acquisition scheme and the development of two major townships in the UA area. The

U A recorded population growth rate of 63 percent during 1971-81 and 7 5 percent

during the following decade (1981-91). See Table 7.26.

7.6 Conclusions

1. Visakhapatnam handles the widest range of cargo among all major ports of India

which makes it unique. First and foremost, it handles the widest range of cargo

among all major ports of India. Next,the sheer location of the Port - midway

between the two major ports of Calcutta- Haldia and Chennai on the east coast of

India. The vast mineral and industrial rich hinterland of the port stretching as far

as Madhya Pradesh and Uttar Pradesh in the north to Tamil Nadu in the south. In

addition, a fishing harbour and dry dock also functions. Today, Vishakhapatnan!

Port is preferred for trade especially in Eastern and South Eastern India.

2. Today, Visa~apatnam is characterised by the following features: Inner Harbour,

Outer Harbour, Mechanical Ore Handling Plant, Dry Dock, Fishing Harbour and

Slipway.

3. Based on this, the hinterland of Vishakhapatnam is fairly large. It covers

Bailadilla iron-ore mines in Madhya Pradesh as well as sources of thermal coal

and alumina in Orissa. Coking coal is imported through this port to serve

Visakhapatnam, Bhilai and Durgapur Steel Plants. However, the liquid cargo is

mostly for the refinery located in port area itself and for the areas close to the port

location. All the major cargo origins/destinations are well connected through

316

Page 75: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

Table No. 7.26

Growth of the Visakhapatnam Port and the City (1951-91)

Year Traffic in Traffic Million Growth

Density/ Sq. Population in Population Tonnes Rate

Km Lakhs Growth Rate

1950-51 1.14 1.08

1960-61 2.74 34.32 2.11

1970-71 8.73 35.50 3.55

1980-81 11.81 87.55 5.65

1990-91 19.42 2827 7.52 Source : Compiled from Bas1c Port Statistics and VUDA Report. NB: UA- Urabn Agglomeration

in%

68.50

93.70

60.40

33.00

Visakhapatnam City

Growth of Population No. of in Lakhs Household

City UA

1.08 1.08

2.11 2.11

3.55 3.63

5.65 6.04 I, 13,580

7.52 10.57 1,60,678

No. of Participation Residential Ratio

Houses

30.31

27.59

1,12,272 26.03

1,57,889 28.99

Page 76: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

railways. In order to transport other break-bulk cargo like grains, fertiliser's etc.,

good road system exists within the port and outside through its link to NH-5.

4. Based on the broad classification of the extent of hinterland, the immediate and

primary hinterland for incoming and outgoing traffic for Visakhapatnam Port will

comprise of the State of Andhra Pradesh The districts of the states of Orissa,

Madhya Pradesh and Maharashtra will form the secondary and economic

hinterland.

5. Traditionally, Visakhapatnam port has been providing dedicated facilities for

various ores, fertiliser, fertiliser raw materials, petroleum crude, POL products etc.

Very recently, the port has started handling containers though of a modest volume.

A recent addition to this cargo is import of LPG. The dry bulk category consists of

iron-ore, coking coal, thermal coal, fertilisers, foodgrains and other bulk cargo like

manganese ore, alumina, limestone, scrap etc.

6. Due to rapid industrialisation and economic growth in the hinterland of the port

the developmental activity undertaken by the Port Trust, particularly during the

last 10 years to meet the increased traffic, like extra berths, development of

stockyards, connected railway infrastructure- all are efforts to work in unison for

movement of smooth traffic flow.

7. Traffic may be diverted if any port comes up as a competitor in the hinterland of

Visakhapatnam port. In case of Visakhapatnam port, Gangavaram in the south and

Dhamra (Orissa) in the north might pose such a threat in future. Kakinada, the

state port is, however, in no way a competitor for Visakhapatnam's cargo traffic.

Similar is the case with Krishnapatnam. Since Gangavaram and Dhamra are

'green field sites' today, their influence has not been taken into consideration for

traffic projection. Moreover, change in international scenario may affect cargo

trade in certain commodities.

8. Capacity-wise Visakhapatnam is both saturated and over-utilized. Action has

already been taken for construction of 4 berths in the Inner Harbour and 2 berths

in the Outer Harbours. No further extension of berth is possible in future as both

waterfront and back-up land to install mechanised facility is limited. To optimise

the existing port capacity, 2 grab loaders and higher capacity cranes have been

317

Page 77: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

sanctioned, which would increase cargo handling capacity by another 5 to 6

million tonnes. In an attempt to acquire more water front area, the port authority

decided to shift the fishing harbour from its present location to Bheemunipatnam.

Though the idea was good, but its practical application was difficult, as

implementing the proposal was not an easy one. Besides, dealing with the

resistance put up by the local fishermen, the port had the responsibility to

rehabilitate them, which is not a simple task.

9. Perhaps the single most important problem faced at Visakhapatnam port today is

that of port congestion. The port facilities are not adequate to handle the

unexpected increase in cargo traffic volume, especially in the last 10 years. The

problem is expected to grow more acute in future as more industrial activity and

increase in population in the hinterland is expected, which would mean more

cargo traffic for Visakhapatnam port to handle. The port has certain limitations

like channel and draft restriction, scarcity of waterfront, etc. Keeping all these in

mind, commensurate with increased traffic, port capacity has to be augmented.

10. Despite the problem of waiting vessels, a port user prefers Visakhapatnam port

among all the ports on the East Coast. The reasons for the choice of

Visakhapatnam are that once at berth, cargo loading/unloading takes place very

fast reducing the overall TRT. Since the ultimate aim of a port user is to save time

and money, by calling at Visakhapatnam, he is comparatively better off than any

other East Coast port. Other possible choices are ruled out like Chennai which is

congested, Ennore- is only a green field site today, Paradip -once completes its

coal loading terminal may ease the pressure of thermal coal handling at

Visakhapatnam. Moreover, Visakhapatnam has dedicated bulk cargo like coking

coal, POL, iron-ore, fertiliser, etc. that hardly can move away. In addition, it is a

peaceful port with no labour trouble. Visakhapatnam as a frequent port of call on

the east coast is therefore justified.

11. Visakhapatnam has no specialised container terminal and has very little container

traffic. It is predominantly a bulk port and the container traffic generated in the

hinterland (like tobacco) passes through the Chennai port which has specialised

container-handling facility. Though the port has plans to install modern container

318

Page 78: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

handling facility to facilitate better handling of container traffic, nothing has come

up as yet. Since the earnings from container traffic are comparatively low as

compared to bulk, the port is not too keen to invest substantially in developing a

full-fledged container terminal.

12. The scenario at Visakhapatnam Port in the context of privatisation may be

different. The scope for large induction of private investment particularly for

building berths does not exist since the Port will be able to fund the feasible

expansion of its area. However, in case of Container Berths and equipment,

private participation may arise. Opening one or two or more satellite harbours, in a

phased manner and extending the present Port limits, depending on the

requirements from time to time, will be the right solution to meet the demand for

Port services from the anticipated cargo throughput.

13. Gangavaram port is still in the conception stage as there has been unnecessary

shunting between the state and the centre as to the status of the port. Political

indecision is causing unnecessary delay. Gangavaram port is expected to handle

all the dirty and dusty cargo of Visakhapatnam port. This is of utmost importance

as the city ofVisakhapatnam is suffering from extreme air pollution.

14. In case of the present Port, the scope for large induction of private investment

particularly for building berths may not be there since the Port will be able to fund

the feasible expansion of the Port. However, in case of Container Berths and

equipment, private participation may arise. The prominent feature may be leasing

the facilities for short periods rather than the BOT concept. As a result, the

dominance of the Port as an owner and operator is expected to continue though in

a modified and enlightened form. However, the position may be entirely different

in opening the new outlets as a part of its expansion programme. In this case, the

Port may contend with building the basic facilities leaving the construction of

berths, provision of cargo transfer system etc., and their operation to the private

investor for a longer period (say 25 to 30 years) on BOT or similar methods.

15. As has been discussed earlier, Vishakhapatnam town grew along with the port. As

traffic increased over time, more industries were set up in the vicinity of the port

which further led to the development of ancillary industries. Not all found place

319

Page 79: CHAPTERS PORT PERFORMANCE AND PORT PRODUCTIVITYshodhganga.inflibnet.ac.in/bitstream/10603/15155/13/14_chapter 5.pdfforklift trucks and 150 tonne floating crane (Bheema) were undertaken

within city limits. Population grew around these industrial nodes and

Vishakhapatnam became a bustling port city. Without hesitation, it may be safely

concluded that the city drew sustenance from the expanding port and similarly the

port prospered because of a growing hinterland and the city.

320