chapter 7 the project schedule and budget copyright 2012 john wiley & sons, inc. 7-1

19
Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Upload: kristopher-manning

Post on 01-Jan-2016

220 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Chapter 7

The Project Schedule and Budget

Copyright 2012 John Wiley & Sons, Inc.7-1

Page 2: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Precedence Diagramming Method - PDM

Based on 4 fundamental relationships Finish-To-Start (FS) Start-To-Start (SS) Finish-To-Finish (FF) Start-To-Finish (SF)

7-2

Page 3: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

If people build safety into their estimates, then …

Why are projects still late?

7-3

Page 4: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Be Aware of Resource Loading

Resource loading

Over allocation

4

Page 5: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Resource Leveling

5

Page 6: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Benefits of Resource Leveling

6

Page 7: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Critical Chain Project Management (CCPM)

Introduced in 1997 in a book called Critical Chain by Eliyahu Goldratt

Based on his previous work called the Theory of Constraints

CCPM is based on the idea that people often inflate or add cushioning to their estimates to create a form of “safety” to compensate for uncertainty or risk because … Your work is dependent upon the work of someone else,

and you believe that starting your work will be delayed Your pessimism from previous experience where things

did not go as planned Your belief that the project sponsor or customer will cut

your project schedule or budget so you inflate your estimates to guard against this cut

7-7

Page 8: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

CCPM Assumptions

Begins by asking each person or team working on a task to provide an estimate that would have a 50% chance of being completed as planned

Instead of adding safety to each task, put that safety in the form of buffers where it is needed most

7-8

Page 9: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

A B C

D

E

10 Days 10 Days 10 Days 10 Days

10 Days

A B C E

D

5 Days 5 Days 5 Days 5 Days

5 Days

10

Project Schedule with Safety in Each Task

Critical Chain Project Schedule

2.5 Days

Buffers

The Critical Chain Project Schedule

7-9

Page 10: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Critical Chain Project Management

7-10

Page 11: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Developing the Project Budget

1.

2.

3.

4.

5.

7-11

Page 12: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Types of Costs and Benefits

Page 13: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Other Costs

7-13

Page 14: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Planning Cost Management

The project team uses expert judgment, analytical techniques, and meetings to develop the cost management plan

A cost management plan includes: Level of accuracy and units of measure Organizational procedure links Control thresholds Rules of performance measurement Reporting formats Process descriptions

Page 15: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Determining the Budget

Cost budgeting involves allocating the project cost estimate to individual work items over time

The WBS is a required input to the cost budgeting process since it defines the work items

Reserve analysis must occur

Page 16: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Figure 7-4. Surveyor Pro Project Cost Baseline

Page 17: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Project Management Software Tools

7-17

Page 18: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Finalizing the Project Schedule and Budget

7-18

Page 19: Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1

Copyright 2012 John Wiley & Sons, Inc.All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without

express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John

Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no

responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein.

7-19